BOQ-RRCY
BOQ-RRCY
LOCATION
OWNER
SUBJECT
DATE
No.
A.
B.
F.
G.
H.
I.
ENGINEERING DESIGN FOR THE ELECTRICAL POW
BILL OF MATERIALS
November 12.2023
Item Description
GENERAL REQUIREMENTS
Mobilization
Bonds and Insurance
Permits for Upgrading
Temfacil
Water and Electricity Consumption
Admin/Management/Supervision Cost
As Built Plan
sub-total
CIVIL WORKS
Excavation Works
Sand Bedding
Construction of Hand Hole
Construction of Power House with Genset Pad
Back Filling
Hauling and Pullout of Debris
sub-total
ELECTRICAL WORKS
Mains and Submain distribution System
Miscellaneous(Mc Gill)
Pullboxes
Testing
Guardhouse
PP - 60AT/100AF, 3P, 400Vwith 12 Branches
Chapel
PP - 60AT/100AF, 3P, 400Vwith 12 Branches
Laundry
PP - 125AT/150AF, 3P, 400Vwith 22 Branches
Court
PP - 60AT/100AF, 3P, 400Vwith 18 Branches
Dietary
PP - 60AT/100AF, 3P, 400Vwith 18 Branches
Meter Centers
KwHR Meter and Meter Bases(GENERAL ELECTRIC)
Breaker gutter
Busbar Gutter
Current transformer 350/5A (RS PRO)
Substation Works
Supply of Labor for the installation of Substation Equip
i.e. Distribution Transformers, MV Cables, complete wi
testing and commissioning and necessary accessories
shown on drawings and as described on specifications
make the system operational.
Others:
Terminal lugs, accessories and consumables
Testing and Commissioning
ATS (SCHNEIDER)
1600A, 3-Pole, 400V in NEMA-3R Enclosure
Accessories (KUMWELL)
Ground Rod (Copper coated)
20mmФ x 3mm, Copper Accessories
LIGHTNING PROTECTION SYSTEM (KUMWELL)
Air terminal / Lightning Strike Pad
as per requirement
sub-total
SUBTOTAL FOR GENERAL REQUIREMENTS
SUBTOTAL FOR CIVIL WORKS
SUBTOTAL FOR ELECTRICAL WORKS
GRAND SUB TOTAL
OVERHEAD/CONSUMABLES/CONTINGENCIES - 12%
CONTRACTORS PROFIT - 8%
TAX - 5%
GRAND TOTAL
0.0499966651
0.066878655
Prepared and Submitted by:
NAME
POSITION
AA MODERN BUILDERS CONSTRUCTION CORP.
R SYSTEM OF THE REGIONAL REHABILITATION CENTER
1.00 lot
1.00 lot 120,000.00
1.00 lot 220,000.00
1.00 lot 100,000.00
1.00 lot 120,000.00
1.00 lot
1.00 lot
1.00 lot
1.00 lot 55,000.00
nos 175,000.00
1.00 lot 900,000.00
1.00 lot
1.00 lot
120.00 m 567.00
1.00 lot 10,200.00
281.00 m 459.00
1.00 lot 30,000.00
472.00 m 216.00
1.00 lot 25,000.00
107.00 m 155.25
1.00 lot 5,500.00
290.00 m 101.25
1.00 lot 7,000.00
175.00 m 67.50
1.00 lot 6,000.00
256.00 m 81.00
500.00 m 81.00
1,603.00 m 135.00
281.00 m 205.20
428.00 m 232.20
428.00 m 247.05
1,888.00 m 259.20
644.00 m 378.00
480.00 m 405.00
160.00 m 675.00
480.00 m 756.00
1.00 lot -
-
1.00 assy 303,750.00
1.00 no 29,700.00
1.00 no 64,800.00
1.00 no 101,250.00
1.00 no 22,950.00
1.00 no 64,800.00
1.00 no 81,000.00
1.00 no 22,950.00
1.00 no 64,800.00
1.00 no 101,250.00
5.00 no 85,050.00
1.00 no 28,350.00
1.00 no 28,350.00
1.00 no 64,800.00
1.00 no 42,400.00
1.00 no 42,400.00
14assy 15,000.00
1.00 assy 27,000.00
1.00 assy 27,000.00
1.00 no 2,500.00
700.00 m -
650.00 m 47.25
45.00 no 472.50
45.00 m 202.50
26.00 set 3,375.00
40.00 no 1,350.00
6.00 no 3,375.00
1.00 no 27,000.00
HABILITATION CENTER FOR YOUTH
Total Unit
Labor Unit
Material
- 75,000.00
120,000.00
220,000.00
100,000.00
120,000.00
- 125,000.00
- 100,000.00
- 275,000.00
55,000.00 35,000.00
- 70,000.00
900,000.00 315,000.00
- 122,000.00
- 70,000.00
68,040.00 243.00
10,200.00 5,000.00
128,979.00 229.50
30,000.00 15,000.00
101,952.00 108.00
25,000.00 10,000.00
16,611.75 81.00
5,500.00 3,500.00
29,362.50 54.00
7,000.00 4,000.00
11,812.50 33.75
6,000.00 3,800.00
20,736.00 24.30
40,500.00 24.30
216,405.00 28.35
57,661.20 47.25
99,381.60 62.10
105,737.40 81.00
489,369.60 87.75
243,432.00 222.75
194,400.00 236.25
108,000.00 337.50
362,880.00 459.00
27,000.00 33,750.00
- 20,250.00
-
303,750.00 8,100.00
29,700.00 3,375.00
64,800.00 4,050.00
101,250.00 4,725.00
22,950.00 4,050.00
64,800.00 4,050.00
81,000.00 4,725.00
22,950.00 4,050.00
64,800.00 4,050.00
101,250.00 4,725.00
425,250.00 4,050.00
28,350.00 4,050.00
28,350.00 4,050.00
64,800.00 4,050.00
42,400.00 4,050.00
42,400.00 4,050.00
210,000.00 500.00
27,000.00 12,880.00
27,000.00 12,880.00
2,500.00 750.00
3,100,000.00 150,000.00
115,000.00 20,520.00
115,000.00 20,520.00
4,700,000.00 150,000.00
148,500.00 33,750.00
- 67.50
30,712.50 27.00
21,262.50 162.00
9,112.50 135.00
87,750.00 1,012.50
54,000.00 270.00
20,250.00 1,620.00
27,000.00 3,375.00
-
UTH
Total Labor
Total
Unit
75,000.00 75,000.00
- 120,000.00
- 220,000.00
- 100,000.00
- 120,000.00
125,000.00 125,000.00
100,000.00 100,000.00
860,000.00
275,000.00 275,000.00
35,000.00 90,000.00
- -
315,000.00 1,215,000.00
122,000.00 122,000.00
70,000.00 70,000.00
1,772,000.00
29,160.00 97,200.00
5,000.00 15,200.00
64,489.50 193,468.50
15,000.00 45,000.00
50,976.00 152,928.00
10,000.00 35,000.00
8,667.00 25,278.75
3,500.00 9,000.00
15,660.00 45,022.50
4,000.00 11,000.00
5,906.25 17,718.75
3,800.00 9,800.00
6,220.80 26,956.80
12,150.00 52,650.00
45,445.05 261,850.05
13,277.25 70,938.45
26,578.80 125,960.40
34,668.00 140,405.40
165,672.00 655,041.60
143,451.00 386,883.00
113,400.00 307,800.00
54,000.00 162,000.00
220,320.00 583,200.00
33,750.00 60,750.00
20,250.00 20,250.00
8,100.00 311,850.00
3,375.00 33,075.00
4,050.00 68,850.00
4,725.00 105,975.00
4,050.00 27,000.00
4,050.00 68,850.00
4,725.00 85,725.00
4,050.00 27,000.00
4,050.00 68,850.00
4,725.00 105,975.00
20,250.00 445,500.00
4,050.00 32,400.00
4,050.00 32,400.00
4,050.00 68,850.00
4,050.00 46,450.00
4,050.00 46,450.00
7,000.00 217,000.00
12,880.00 39,880.00
12,880.00 39,880.00
750.00 3,250.00
150,000.00 3,250,000.00
20,520.00 135,520.00
20,520.00 135,520.00
150,000.00 4,850,000.00
33,750.00 182,250.00
47,250.00 47,250.00
17,550.00 48,262.50
7,290.00 28,552.50
6,075.00 15,187.50
26,325.00 114,075.00
10,800.00 64,800.00
9,720.00 29,970.00
3,375.00 30,375.00
14,318,274.70
860,000.00
1,772,000.00
14,318,274.70
16,950,274.70
2,034,032.96
1,356,021.98
1,017,016.48
21,357,346.12
-
PROJECT
LOCATION
OWNER
SUBJECT
DATE
No.
ENGINEERING DESIGN FOR THE ELECTRICAL POWE
BILL OF MATERIALS
November 12.2023
Item Description
GENERAL REQUIREMENTS
Mobilization
Bonds and Insurance
Permits for Upgrading
Temfacil
Water and Electricity Consumption
Admin/Management/Supervision Cost
As Built Plan
sub-total
CIVIL WORKS
Chipping of Existing Flooring
Excavation Works
Sand Bedding
Construction of Hand Hole
Construction of Power House with Genset Pad
Electrical Pole
Electrical Panel Board Enclosure
Back Filling
Restoration of Flooring
Restoration of Paintings of Existing Building
Clearing of Debris
Hauling and Pullout of Debris
sub-total
ELECTRICAL WORKS
Main Electrical System
Distribution Panel 02
MAIN: 450AT/500AF, 3P, 400/230V, 60Hz, 35 Ka, MCCB
BRANCHES:
1 - 250AT/250AF, 3P, 400/230V, MCCB
1 - 125AT/150AF, 3P, 230V, MCCB
4 - 70AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 3R, with neutral and ground busba
B06-PB (Infirmary)
MAIN: 125AT/150AF, 3P, 400/230V, 60Hz, 10 Ka, MCCB
BRANCHES:
13 - 30AT/100AF, 1P, 230V, MCCB
7 - 20AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 1, with neutral and ground busbar
B07-PB (Main)
MAIN: 250AT/250AF, 3P, 400/230V, 60Hz, 10 Ka, MCCB
BRANCHES:
3 - 125AT/150AF, 1P, 230V, MCCB
3 - 70AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 3R, with neutral and ground busba
B11-PB (Chapel)
MAIN: 70AT/100AF, 1P, 230V, 60Hz, 10 Ka, MCCB
BRANCHES:
11 - 20AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 1, with neutral and ground busbar
B16-PB (Quadrangle)
MAIN: 70AT/100AF, 1P, 230V, 60Hz, MCCB
BRANCHES:
11 - 20AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 1, with neutral and ground busbar
Transformer to ECB
3 sets of 4 - 200mm² XLPE + E
ECB to ATS
4 sets of 4 - 200mm² THWN and 1 - 30mm2 THWN grou
GENSET to ATS
4 sets of 4 - 200mm² THWN and 1 - 30mm2 THWN grou
B07-PB to B07-PB01
1 set of 2 - 38mm² THHN/THWN and 1 - 14mm2 THHN/T
grounding
B07-PB to B07-PB02
1 set of 2 - 38mm² THHN/THWN and 1 - 14mm2 THHN/T
grounding
B07-PB to B07-PB03
1 set of 2 - 38mm² THHN/THWN and 1 - 14mm2 THHN/T
grounding
ECB to ATS
150mm dia. IMC
Endbell
ATS to Genset
150mm dia. IMC
Locknut and Bushing
ATS to MDP
150mm dia. IMC
Locknut and Bushing
MDP to DP1
100mm dia. IMC
Locknut and Bushing
MDP to DP2
100mm dia. IMC
Locknut and Bushing
MDP to DP3
100mm dia. IMC
Locknut and Bushing
DP3 to B01-PB
20mm dia. IMC
Locknut and Bushing
DP3 to B02-PB
20mm dia. IMC
Locknut and Bushing
DP3 to B03-PB
20mm dia. IMC
Locknut and Bushing
MDP to B04-PB
20mm dia. IMC
Locknut and Bushing
DP1 to B05-PB
40mm dia. IMC
Square Box (Pull Box)
Locknut and Bushing
DP1 to B10-PB
32mm dia. IMC
Square Box (Pull Box)
Locknut and Bushing
DP1 to B11-PB
32mm dia. IMC
Locknut and Bushing
DP1 to B12-PB
32mm dia. IMC
Locknut and Bushing
DP1 to B13-PB
32mm dia. IMC
Locknut and Bushing
DP1 to B14-PB
32mm dia. IMC
Coupling
Locknut and Bushing
DP1 to B15-PB
32mm dia. IMC
Locknut and Bushing
DP1 to B16-PB
32mm dia. IMC
Locknut and Bushing
DP2 to B06-PB
40mm dia. IMC
Square Box (Pull Box)
Locknut and Bushing
DP2 to B07-PB
80mm dia. IMC
Locknut and Bushing
DP2 to B08-PB
32mm dia. IMC
Square Box (Pull Box)
Locknut and Bushing
DP2 to B09-PB
32mm dia. IMC
Locknut and Bushing
B04-PB to B04-LP
20mm dia. IMC
Locknut and Bushing
B07-PB to B07-PB01
32mm dia. IMC
Locknut and Bushing
B07-PB to B07-PB02
32mm dia. IMC
Locknut and Bushing
B07-PB to B07-PB03
32mm dia. IMC
Square Box (Pull Box)
Locknut and Bushing
Meter Center
Meter Center 1 - 8pcs of CL200
Meter Center 2 - 4pcs of CL200
Meter Center 3 - 4pcs of CL200
Exothermic Weld
Ground Test Pit
Lighting Event Counter
30-50mm sq. BCW
sub-total
SUBTOTAL FOR GENERAL REQUIREMENTS
SUBTOTAL FOR CIVIL WORKS
SUBTOTAL FOR ELECTRICAL WORKS
GRAND SUB TOTAL
OVERHEAD/CONSUMABLES/CONTINGENCIES - 12%
CONTRACTORS PROFIT - 8%
TAX - 5%
GRAND TOTAL
0.04999666
0.0668786
Prepared and Submitted by:
NAME
POSITION
AA MODERN BUILDERS CONSTRUCTION CORP.
STEM OF THE G.R.A.C.E.S
1.00 lot
1.00 lot 135,000.00
1.00 lot 450,000.00
1.00 lot 195,000.00
1.00 lot 75,000.00
1.00 lot
1.00 lot
1.00 lot
1.00 lot
1.00 lot 25,000.00
5.00 nos 55,000.00
1.00 lot 900,000.00
1.00 lot 1,100,000.00
2.00 sets 75,000.00
1.00 lot
1.00 lot 35,000.00
1.00 lot 75,000.00
1.00 lot
1.00 lot
120.00 lm 4,500.00
40.00 lm 3,950.00
40.00 lm 3,950.00
40.00 lm 3,950.00
220.00 lm 4,500.00
110.00 lm 3,900.00
10.00 lm 3,200.00
50.00 lm 335.00
15.00 lm 335.00
45.00 lm 1,423.50
40.00 lm 1,423.50
10.00 lm 425.00
75.00 lm 950.00
85.00 lm 750.00
70.00 lm 425.00
10.00 lm 750.00
10.00 lm 750.00
40.00 lm 425.00
52.00 lm 750.00
62.00 lm 425.00
45.00 lm 950.00
10.00 lm 1,260.00
35.00 lm 425.00
60.00 lm 425.00
18.00 lm 1,008.00
15.00 lm 867.00
33.00 lm 867.00
1,200.00 lm 450.00
140.00 no 1,000.00
5.00 no 7,500.00
1.00 no 20,000.00
2,150.00 lgth 450.00
Total Unit Total Labor
Labor Unit
Material Unit
- 175,000.00 175,000.00
135,000.00 -
450,000.00 -
195,000.00 -
75,000.00 -
- 700,000.00 700,000.00
- 100,000.00 100,000.00
- 12,000.00 12,000.00
- 22,000.00 22,000.00
25,000.00 12,000.00 12,000.00
275,000.00 22,000.00 110,000.00
900,000.00 320,000.00 320,000.00
1,100,000.00 275,000.00 275,000.00
150,000.00 18,000.00 36,000.00
- 12,000.00 12,000.00
35,000.00 18,000.00 18,000.00
75,000.00 42,000.00 42,000.00
- 35,000.00 35,000.00
- 50,000.00 50,000.00
- - -
36,300.00 635.25 12,705.00
90.00 31.50 31.50
360.00 31.50 126.00
- - -
32,670.00 635.25 11,434.50
180.00 31.50 63.00
- - -
18,150.00 635.25 6,352.50
180.00 31.50 63.00
- - -
36,300.00 635.25 12,705.00
90.00 31.50 31.50
360.00 31.50 126.00
- - -
350,000.00 122,500.00 122,500.00
175,000.00
135,000.00
450,000.00
195,000.00
75,000.00
700,000.00
100,000.00
1,830,000.00
12,000.00
22,000.00
37,000.00
385,000.00
1,220,000.00
1,375,000.00
186,000.00
12,000.00
53,000.00
117,000.00
35,000.00
50,000.00
3,504,000.00
135,622.35
116,330.18
35,397.00
31,470.53
31,470.53
116,397.00
29,465.78
78,124.10
59,404.59
50,633.10
78,730.79
50,633.10
50,633.10
37,271.75
37,271.75
37,762.20
37,271.75
55,384.56
55,384.56
37,271.75
55,384.56
37,271.75
518,932.57
276,103.49
965,527.50
4,625,000.00
729,000.00
213,300.00
213,300.00
213,300.00
1,336,500.00
579,150.00
43,200.00
22,612.50
6,783.75
86,477.63
76,869.00
5,737.50
96,187.50
86,062.50
40,162.50
10,125.00
10,125.00
22,950.00
52,650.00
35,572.50
57,712.50
17,010.00
20,081.25
34,425.00
24,494.40
17,556.75
38,624.85
9,085.50
270.00
105,840.00
2,127.60
105,840.00
2,127.60
86,913.00
2,592.00
57,942.00
2,592.00
57,942.00
2,592.00
8,100.00
213.30
13,500.00
106.65
13,500.00
213.30
13,500.00
213.30
73,237.50
486.00
1,485.00
29,403.00
243.00
729.00
29,403.00
729.00
2,450.25
243.00
12,251.25
243.00
49,005.00
1,336.50
-
56,355.75
729.00
61,256.25
972.00
58,590.00
121.50
594.00
-
72,427.50
2,592.00
-
49,005.00
121.50
486.00
49,005.00
486.00
-
5,400.00
213.30
-
44,104.50
243.00
-
24,502.50
243.00
-
49,005.00
121.50
486.00
-
472,500.00
2,250,000.00
200,000.00
50,000.00
50,000.00
50,000.00
100,000.00
217,500.00
127,500.00
127,500.00
3,500,000.00
599,400.00
40,500.00
359,437.50
729,000.00
189,000.00
50,625.00
27,000.00
1,306,125.00
23,339,722.96
1,830,000.00
3,504,000.00
23,339,722.96
28,673,722.96
3,440,846.76
2,293,897.84
1,720,423.38
36,128,890.93
-
PROJECT
LOCATION
OWNER
SUBJECT
DATE
No.
A.
B.
C.
D.
F.
G.
H.
I.
ENGINEERING DESIGN FOR THE ELECTRICAL POWE
BILL OF MATERIALS
November 12.2023
Item Description
GENERAL REQUIREMENTS
Mobilization
Bonds and Insurance
Permits for Upgrading
Temfacil
Water and Electricity Consumption
Admin/Management/Supervision Cost
As Built Plan
sub-total
CIVIL WORKS
Excavation Works
Sand Bedding
Construction of Hand Hole
Construction of Power House with Genset Pad
Back Filling
Hauling and Pullout of Debris
sub-total
ELECTRICAL WORKS
Mains and Submain distribution System
Miscellaneous(Mc Gill)
Pullboxes
Testing
Incandescent Bulb
LED 100w, 12000 lumen
Lighting Post
Wiring Devices
Supply and Installation of Wiring Devices and necessary
accessories as shown on drawings and as described on
specifications to make the system operational.
Switches(PANASONIC)
Outlets (PANASONIC)
Duplex Grounding Outlet 16A, 250V,
Wall mounted Simplex for Electric Range
Wall mounted Simplex for REF
Wall mounted Simplex for Washing Machine/GFCI
Blank plate, for Water Heater
Duplex Grounding Outlet 16A, 250V, for Hand Dryer
Special Purpose outlet for WAC 1.5Hp
Special Purpose outlet for WAC 2.5Hp
Substation Works
Supply of Labor for the installation of Substation Equipm
i.e. Distribution Transformers, MV Cables, complete with
testing and commissioning and necessary accessories a
shown on drawings and as described on specifications to
make the system operational.
Others:
Termnal lugs, accessories and consumables
Testing and Commissioning
ATS (SCHNEIDER)
1600A, 3-Pole, 400V in NEMA-3R Enclosure
Accessories (KUMWELL)
Ground Rod (Copper coated)
20mmФ x 3mm, Copper Accessories
sub-total
SUBTOTAL FOR GENERAL REQUIREMENTS
SUBTOTAL FOR CIVIL WORKS
SUBTOTAL FOR ELECTRICAL WORKS
GRAND SUB TOTAL
OVERHEAD/CONSUMABLES/CONTINGENCIES - 12%
CONTRACTORS PROFIT - 8%
TAX - 5%
GRAND TOTAL
0.04999666515
0.0668786559
Prepared and Submitted by:
NAME
POSITION
AA MODERN BUILDERS CONSTRUCTION CORP.
R SYSTEM OF THE REGIONAL REHABILITATION CENTER F
1.00 lot
1.00 lot 120,000.00
1.00 lot 220,000.00
1.00 lot 100,000.00
1.00 lot 120,000.00
1.00 lot
1.00 lot
1.00 lot
1.00 lot 55,000.00
nos 175,000.00
1.00 lot 900,000.00
1.00 lot
1.00 lot
120.00 m 567.00
1.00 lot 47,520.00
281.00 m 459.00
1.00 lot 121,500.00
472.00 m 216.00
1.00 lot 101,250.00
107.00 m 155.25
1.00 lot 16,875.00
290.00 m 101.25
1.00 lot 24,300.00
175.00 m 67.50
1.00 lot 12,150.00
256.00 m 81.00
500.00 m 81.00
1,603.00 m 135.00
281.00 m 205.20
428.00 m 232.20
428.00 m 247.05
1,888.00 m 259.20
644.00 m 378.00
480.00 m 405.00
160.00 m 675.00
480.00 m 756.00
1.00 lot -
-
1.00 assy 303,750.00
1.00 no 29,700.00
1.00 no 101,250.00
2.00 no 81,000.00
1.00 no 85,050.00
2.00 no 22,950.00
1.00 no 64,800.00
1.00 no 54,000.00
2.00 no 37,800.00
2.00 no 32,400.00
1.00 no 28,350.00
1.00 no 10,800.00
5,000.00 m 36.45
250.00 m 60.75
550.00 no 33.75
550.00 no 89.10
235.00 no 67.50
1,200.00 m 60.75
620.00 set -
621.00 set -
22.00 no 1,485.00
22.00 set -
300.00 set -
200.00 set -
3,000.00 m 36.45
100.00 m 43.20
500.00 no 89.10
300.00 no 67.50
4,500.00 m 41.85
150.00 m 81.00
30.00 m 101.25
125.00 set -
5.00 set -
10.00 set -
10.00 set -
5.00 set -
6.00 set -
20.00 set -
15.00 set -
1.00 unit -
1.00 unit -
1.00 unit -
45.00 no 472.50
45.00 m 202.50
40.00 no 1,350.00
6.00 no 3,375.00
1.00 no 27,000.00
HABILITATION CENTER FOR YOUTH
- 75,000.00 75,000.00
120,000.00 -
220,000.00 -
100,000.00 -
120,000.00 -
- 125,000.00 125,000.00
- 100,000.00 100,000.00
- 275,000.00 275,000.00
55,000.00 35,000.00 35,000.00
- 70,000.00 -
900,000.00 315,000.00 315,000.00
- 122,000.00 122,000.00
- 70,000.00 70,000.00
- 20,250.00 20,250.00
-
303,750.00 8,100.00 8,100.00
29,700.00 3,375.00 3,375.00
- 270.00 167,400.00
- 405.00 251,505.00
32,670.00 472.50 10,395.00
- 5,400.00 118,800.00
- 270.00 81,000.00
- 270.00 54,000.00
-
-
Total
75,000.00
120,000.00
220,000.00
100,000.00
120,000.00
125,000.00
100,000.00
860,000.00
275,000.00
90,000.00
-
1,215,000.00
122,000.00
70,000.00
1,772,000.00
97,200.00
67,095.00
193,468.50
182,250.00
152,928.00
141,750.00
25,278.75
25,650.00
45,022.50
37,125.00
17,718.75
24,975.00
26,956.80
52,650.00
261,850.05
70,938.45
125,960.40
140,405.40
655,041.60
386,883.00
307,800.00
162,000.00
583,200.00
60,750.00
20,250.00
311,850.00
33,075.00
105,975.00
171,450.00
89,100.00
54,000.00
68,850.00
58,050.00
83,700.00
72,900.00
32,400.00
14,850.00
310,500.00
23,625.00
25,987.50
89,842.50
34,897.50
94,770.00
167,400.00
251,505.00
43,065.00
118,800.00
81,000.00
54,000.00
186,300.00
6,885.00
81,675.00
44,550.00
244,822.50
15,795.00
3,948.75
33,750.00
1,350.00
2,700.00
2,700.00
1,350.00
1,620.00
5,400.00
4,050.00
20,520.00
20,520.00
20,520.00
182,250.00
47,250.00
48,262.50
28,552.50
15,187.50
114,075.00
64,800.00
29,970.00
30,375.00
7,515,918.45
860,000.00
1,772,000.00
7,515,918.45
10,147,918.45
1,217,750.21
811,833.48
608,875.11
12,786,377.25
-
PROJECT
LOCATION
OWNER
SUBJECT
DATE
No.
ECB & MCB; 800AT, 3P, 400/230V, 60Hz
ENGINEERING DESIGN FOR THE ELECTRICAL POWE
SYSTEM OF THE BAHAY SILUNGAN
BILL OF MATERIALS
November 12.2023
Item Description
GENERAL REQUIREMENTS
Mobilization
Bonds and Insurance
Permits for Upgrading
Temfacil
Water and Electricity Consumption
Admin/Management/Supervision Cost
As Built Plan
sub-total
CIVIL WORKS
Chipping of Existing Flooring
Excavation Works
Sand Bedding
Construction of Hand Hole
Construction of Power House with Genset Pad
Back Filling
Restoration of Flooring
Restoration of Paintings of Existing Building
Clearing of Debris
Hauling and Pullout of Debris
sub-total
ELECTRICAL WORKS
Main Electrical System
MDP
MAIN: 800AT/800AF, 3P, 230V, 60Hz, 42 Ka, MCCB
BRANCHES:
2 - 350AT/400AF, 3P, 230V, MCCB
1 - 125AT/225AF, 3P, 230V, MCCB
1 - 50AT/100AF, 1P, 230V, MCCB
3 - 30AT/100AF, 1P, 230V, MCCB
2 - 60AT/100AF, 1P, 230V, MCCB
Flush-Mounted NEMA 1, with neutral and ground busb
250mm² THHN/THWN-2
200mm² THHN/THWN-2
150mm² THHN/THWN-2
60mm² THHN/THWN-2
38mm² THHN/THWN-2
30mm² THHN/THWN-2
22mm² THHN/THWN-2
14mm² THHN/THWN-2
8.0mm² THHN/THWN-2
5.5.0mm² THHN/THWN-2
Pull Box
0.04999666515
0.0668786559
Prepared and Submitted by:
NAME
POSITION
AA MODERN BUILDERS CONSTRUCTION CORP.
Quantity Unit Material Unit
1.00 lot
1.00 lot 85,000.00
1.00 lot 300,000.00
1.00 lot 100,000.00
1.00 lot 75,000.00
1.00 lot
1.00 lot
1.00 lot
1.00 lot
1.00 lot 25,000.00
7.00 nos 55,000.00
1.00 lot 700,000.00
1.00 lot
1.00 lot 75,000.00
1.00 lot 55,000.00
1.00 lot
1.00 lot
osure
203.50 lm 1,850.00
184.80 lm 1,600.00
1,199.00 lm 1,250.00
302.50 lm 500.00
357.50 lm 320.00
275.00 lm 240.00
126.50 lm 170.00
176.00 lm 120.00
27.50 lm 85.00
253.00 lm 75.00
2.00 ea 15,000.00
1.00 lot -
Total Unit Total Labor
Labor Unit
Material Unit
- 110,000.00 110,000.00
85,000.00 -
300,000.00 -
100,000.00 -
75,000.00 -
- 100,000.00 100,000.00
- 150,000.00 150,000.00
- 45,000.00 45,000.00
- 55,000.00 55,000.00
25,000.00 12,000.00 12,000.00
385,000.00 22,000.00 154,000.00
700,000.00 320,000.00 320,000.00
- 18,000.00 18,000.00
75,000.00 25,000.00 25,000.00
55,000.00 28,000.00 28,000.00
- 35,000.00 35,000.00
- 50,000.00 50,000.00
- 175,000.00 175,000.00
Total
110,000.00
85,000.00
300,000.00
100,000.00
75,000.00
100,000.00
150,000.00
920,000.00
45,000.00
55,000.00
37,000.00
539,000.00
1,020,000.00
18,000.00
100,000.00
83,000.00
35,000.00
50,000.00
1,982,000.00
29,173.50
10,125.00
10,125.00
12,892.50
10,192.50
26,522.10
133,925.40
55,620.00
40,095.00
30,105.00
28,933.20
35,100.00
82,350.00
236,250.00
248,400.00
299,700.00
3,105,000.00
1,620,000.00
508,241.25
399,168.00
2,023,312.50
204,187.50
154,440.00
89,100.00
29,031.75
28,512.00
3,155.63
25,616.25
189,000.00
170,400.00
8,838.40
4,471.40
10,788.60
3,640.00
4,163.00
40,500.00
23,625.00
28,350.00
28,350.00
60,750.00
64,125.00
47,250.00
6,750.00
27,000.00
222,750.00
175,000.00
10,595,025.48
920,000.00
1,982,000.00
10,595,025.48
13,497,025.48
1,619,643.06
1,079,762.04
809,821.53
17,006,252.10
-