Lecture_3_Economic dispatch solution including generator limits
Lecture_3_Economic dispatch solution including generator limits
EXAMPLE 6.19
Economic dispatch solution including generator limits Rework Example
6.18 if the units are subject to the following inequality constraints:
100 ≤P1 ≤600 MW
400 ≤P2 ≤1000 MW
Solution
At light loads, unit 2 operates at its lower limit of 400 MW, where its
incremental operating cost is dC2/dP2 = 15.2 $/MWh. Additional load
comes from unit 1 until dC1/dP1 = 15.2 $/MWh, or
For PT less than 725 MW, where P1 is less than 325 MW, the incremental
operating cost of the area is determined by unit 1 alone. At heavy loads,
unit 1 operates at its upper limit of 600 MW, where its incremental
operating cost is dC1/dP1 = 19.60 $/MWh. Additional load comes from unit
2 for all values of dC2/d P2 greater than 19.60 $/MWh. At dC2/dP2 = 19.60
$/MWh,
For PT greater than 1244 MW, where P2 is greater than 644 MW, the
incremental operating cost of the area is determined by unit 2 alone. For
725, PT, 1244 MW, neither unit has reached a limit value, and the
economic dispatch solution is the same as that given in Table 6.9. The
solution to this example is summarized in Table 6.10 for values of PT from
500 to 1500 MW.
TABLE 6.10 Economic dispatch solution for Example 6.19
Homework