Quantity Surveying Notes. Estimation
Quantity Surveying Notes. Estimation
Definition
Estimating is the process of producing an approximate calculation or judgment of the size, value, cost, duration
of a project, e.t.c.
Estimation is also the prediction of what the key cost of material, land and plant, labour for constructing a facility
will be and a person who carries out estimation is called an Estimator/ Building Economist/ Quantity surveyor.
Importance of estimating
One of the keys to commercial success is the estimator’s ability to estimate to estimate the cost of construction
work and to construct that work to the estimated cost.
In competitive tendering, the tender is based on the estimated cost which represent as much as 90% of the tender.
The other allowances added to are overheads and profits which are smaller to make a contractor win a tender.
The work connected with the construction of a new structure or with alterations and additions to an existing
structure is invariably (always) the subject of a contract agreement. The essence of such a contract is that a
builder promises to erect a structure as shown on the drawing and in accordance with the specification in return
to a specific amount of money called contract sum.
A prospective owner cannot give instructions to a contractor to erect a proposed project and accompany it with
an empty cheque to be filled later.
If these practices were to be adopted, the result would be a cost plus account with greater advantage to a
contractor and a great loss to the client.
Virtually, all contracts are obtained by competition between contractors and the subject of builders estimating
consists of the process involved in arriving at the contract sum.
Functions of an Estimator
The primary function of an estimator in construction work is to properly price the unit rates in a BoQ, calculate
the estimated cost of preliminary items applicable to the contract being priced and to prepare the estimate for
submission to managers for adjudication into a tender.
Estimating Process
1. Acquisition of documents (plans, specification, BoQs, Form of agreement, Conditions of contract) upon
acquiring information from client through newspaper, internet, friends.
2. Decision to tender considering resources, manpower, profitability, location.
3. Programming the estimate.
4. (a) Collection and calculation of cost information through site visits (labour, water, raw materials, power).
Note:
The process of preparing a tender document follows the estimating process but after production of the estimator’s
report, the following two steps are done:-
1. Presentation of the estimator’s report to directors to convert it to a tender.
2. Submission of tender.
c) Control estimate
For monitoring the project during construction, a control estimate is derived from available information to
establish;
• Budget estimate for financing
• Budgeting cost after contracting but prior to construction
• Estimated cost of completion during the progress of construction
Both the owner and the contractor must adopt some baseline for cost control during the construction.
For the owner, the budget estimate must be adopted early enough for planning along with financing the facility.
The detailed estimate is often used as a budget estimate as it reflects the project scope. The budget cost must
always be revised periodically as is necessary either because of change orders initiated by owner or unexpected
cost overrun.
For the contractor, the bid estimate is used as a budget estimate which will be used for control purposes as well
as for planning construction financing. Revise the budgeted cost periodically to reflect the estimate cost to
completion as well as to ensure adequate cash flow.
Importance of each of the above estimates to different parties in any construction project
To Owner
Design/Pre-tender Cost estimate Bid/ Tender Estimate Control estimate
Assessing best alternative Choosing best bidder Come up with control budget
To Contractor
Design/Pre-tender Cost estimate Bid/ Tender Estimate Control estimate
Understand scope of work Estimating tool Come up with control budget
Determine resource demand Come up with best bid Carryout cost analysis
Execute work as per schedule
To Consultant
Design/Pre-tender Cost estimate Bid/ Tender Estimate Control estimate
Choosing appropriate technology To select best bidder Valuing work done according
Design different facility components according to quotations to to specifications.
Allocating prices as drawn requirements of facility
Solution
Purchasing ………………………………………………. 1,923,077 per ton
Wastage of 5% of purchase……………………………… 96,154/
Add 2% of purchase for spacers and binding wires……… 38,462/
Total ……………. 2,057,693/ per ton
Labour (15+20) x 3000………….. 105,000/ per ton
Two
Compute the cost of dredging per CM if a total of 3,000,000CM of material is to be dredged from a harbour
basin and deposited off on land. From the programmed of work, dredging, reclamation and slope protection
extends over a duration of 6months.
Data
Hire rate for dredger $100,000 per month
Hire rate bulldozer $75,000 per month
Fuel cost estimated at 5% of the equipment cost (the fire rate)
Machine operator is paid $6.5 per hour for an average of 70hrs per week.
Bankman is paid $5.5 per hour for an average of 70hrs per week.
Solution
Dredging
Cost of dredger hiring for 6months……………..$100,000x6……… $600,000
Fuel cost………………………………0.05x$600,000…………….. $30,000
Cost of disposal
Cost of bulldozer hire ……………………….$75,000x6………….. $450,000
Fuel cost…………………………………….0.05$450,000……….. $22500
Analysis of Rates
This is the process of determining the rate of an item or work/ supply of the materials. A reasonable profit,
usually 10%-20% for the contractor should be included in the analysis of rates.
LABOUR
Labour refers to workers who provide physical effort for the execution of particular works/ physical efforts
provided by work force.
Labour output is the most uncertain part of a unit rate. It can vary considerably depending upon the skill and
output of the operatives, the site organization, weather conditions and other factors outside the control of the
contractor.
An estimator should calculate the hourly cost to the builder of the skilled and unskilled labour which will be
employed on the contract if the tender is successful, and this is classified as the build-up of labour rate.
Calculations
Unskilled
Basic pay………………………………………………………8000/8 =1000*40 = 40000/=
Third party……………………………………………………..0.025*40000 = 1000/=
Guaranteed time………………………………………………. 0.02*40000 = 800/=
Graduated pension…………………………………………….. 0.02*40000 = 800/=
Sickness benefit………………………………………………..0.005*40000 = 200/=
Holiday with pay contribution…………………………………200,000/50 = 4000/=
National insurance & redundancy…………………………….. 128,000/50 = 2560/=
Public holiday…………………………………………………..120,000/50 =2400/=
Training Levy…………………………………………………………………………… =5000/=
Total per week =56760/=
Unskilled rate per hour 56760/40 =1419/=
Skilled
Basic pay…………………………………………………………15000/8 =1875*40 = 75000/=
Third party ………………………………………………………..0.025*75000 = 1875/=
Guaranteed time…………………………………………………..0.02*7500 = 1500/=
Graduated pension ……………………………………………......0.02*4000 = 1500/=
Sickness benefit………………………………………………….. 0.005*7500 = 375/=
Holiday with pay contribution…………………………………….350,000/50 = 7000/=
National insurance & redundancy…………………………………128,000/50 = 2560/=
Public holiday………………………………………………………120,000/50 =2400/=
Training Levy ………………………………………………………………………........=10000/=
Total per week = 102,210/=
Skilled rate per hour 102,210/40 =2555.256/=
For excavation in other materials than medium or heavy soils, adjust the above labour constants as follows:
Loose sand …………………………………………………………………………………...x0.7
Stiff clay or gravel ………………………………………………………………………….x1.50
Soft rock …………………………………………………………………………………….x3.00
Hard rock ……………………………………………………………………………………x8.00
Below are the increases in bulk of various types of soils after excavation
Gravel ……………………………………………..% increase ………………………………..10
Sand ……………………………………………………………………………………………12.5
Ordinary earth……………………………………………………………………………………25
Clay…………………………………………………………………………………………….33.3
Chalk …………………………………………………………………………………………..33.3
Rock …………………………………………………………………………………………….50
Example 1
Lifting and stacking turf (SM)
0.30 unskilled hours @500/……………………………………………………………………150/
Cost per SM……………………………………………………………………………………150/
Example 2
Surface excavation av.150mm deep to reduce level (SM)
0.45 unskilled hours @ 500……………………………………………………………………225/
Cost per SM of surface excavation…………………………………………………………….225/
Example 3
Excavate trench to receive fdn exc. 3m, n.e 4.5m deep (CM)
8.1256 unskilled labour hour @500………………………………………………………4062.5/
Cost per CM…………………….………………………………………………………..4062.5/
The labour constant above has been based on the following:
Two labourers excavating and taking 1.625 gang hours per CM to excavate and stage 1.5m
Summary
Excavate and stage 4.5 to 3.0 =2*1.625…………………………………………………….3.250
Stage 3 to 1.5m………………………………………………………………………………1.625
Stage 1.5 to ground level……………………………………………………………………..1.625
Clearing back at top………………………………………………………………………......1.625
Total …………………………………………………………………………………………8.125
8.125 hour per CM = 8.125 @ 500…………………………………………………………4062.5/
Example 4
Calculate the unit rate of excavation of over site 150mm and deposit at a distance 100m from the excavation.
A SM of surface excavation takes unskilled labour 0.45 hours
Say an hour labour rate is 500/=
Cost of excavation for 0.45 @ 500 …………………………………………………………225/=
Deposit 100m away by barrow takes 1 hour @ 500*0.15……………………………………75/=
300/=
The cost of excavating surface to average depth of 150mm and depositing 100m is 300/=.
This excludes the contractor’s profits and overheads.
Example 5
Calculate the unit rate of excavation of over site 250mm and deposit at a distance 200m from the excavation.
Since the depth and haulage distance has changed, we can use proportion.
Cost of excavation 250mm is 0.25/0.15*225….……………………………………………..375/=
Deposit 200m away by barrow takes 2 hour @ 500*0.25……………………………………250/=
625/=
The cost of excavating surface to average depth of 250mm and depositing 200m is 625/=.
This excludes the contractor’s profits and overheads.
Extra payments
Extra payments for discomfort or risk, continuous extra skill or responsibility, intermittent responsibility, and
similar items should be added to the built up hourly rate, in accordance with the working rule agreement.
Overtime
The estimator must decide the amount of overtime which is to be included in the labour rate for the contract
being tendered for.
Fluctuation
When the fluctuation clause is included in the conditions of contract, it is necessary for the estimator to ascertain
whether his built up rates are to be on current rates of wages if known increases are to be included. If known
increases have to be included, they are dealt with in a similar manner to the section ‘firm price tender’
Firm price tender
When the project tendered for has had the fluctuation clause deleted from the conditions of the contract, it’s
necessary for the estimator to add or omit all known increases or decreases in labour after the date of tender and
during the estimated contract period. The estimator also needs to make allowance for further anticipated
variations in labour cost over the period.
computations
Total working hrs a week with overtime = 40 + (5*1.5) + (6*1.5) ……………..56.5hour a week
Actual working hours a week = 40+5+6…………………………………………51hrs a week
Total amount per week = 1875*56.5…………………………………………105937.5/= a week
Cost of productive hrs (labour rate) = 105937.5/51…………………………..2078/= per hour
Effect of over time =2078 – 1875……………………………………………..203/=
Note:
Where labour rates cannot be built up due to inadequate time, labour rates can be got from;
MECHANICAL PLANT
The estimator must decide on the type of machines to be used and their respective sizes before pricing any of
the items involved.
The type of machine will depend largely on; amount of work, nature of work or material to be excavated, weather
conditions, time frame.
Excavation plants, concrete mixers, rollers or even transport vehicles are usually charged on site at an hourly
hire rate based on a normal working week.
Any time worked over the number of hours on hire agreement is charged extra also travelling time expenses to
and from the site.
Methods of acquiring a plant
By purchasing
By hiring
By leasing
Depreciation of machines
Plants suffer wear, tear, and physical deterioration in constant use. Invested capital must be recorded to remain
in business.
Causes of depreciation
o Age
o Introduction of newer most efficient plant
o Lack of maintenance o Nature of work o Wear and tear
Example
Consider purchase of a tipper lorry at £16,000. The ripper lorry has a life of 4years and salvage value of £4,000.
Solution
The depreciation cost =£(16,000 – 4000)/4 =£3000.
Year Amount to recover (£) Net book value (£)
0 0 16,000
1 3000 13,000
2 3000 10,000
3 3000 7,000
4 3000 4,000
Example
Consider purchase of a dump truck at £16,660 with useful life of 4years. Use the method of declining to compute
the yearly amounts to recover if the fixed percentage to recover is 30 and the salvage value is £4,000.
Year Beginning of year (£) End of year (£) Yearly amount to be recovered (£)
0.7P 0.3P
1 16,660 11662 4998
2 11662 8163.4 3498.6
3 8163.4 5714.4 2449
4 5714.4 4000 1714.4
Salvage, S = P(1-r)n
Where n = no of years (period)
r = fixed depreciation rate
P = initial cost.
Example
Consider purchasing an excavator at UGX 300m with a life of 3years and a resale value of UGX100m. Interest
on capital is 20%, running cost is 10%. Profits and overheads are 20%. Calculate the cost per hour of the
equipment assuming 8hours a day, 5 days a week and 50 weeks a year.
Solution
Example
If a truck is purchased at 30m shillings and the resale value is 10m at the end of the 5th year, the digits are 1,2,3,4
and 5. Determine the depreciation charge.
Solution
Total digits = 1+2+3+4+5 = 15
Depreciable sum = 30 – 10 = 20m
Depreciation in the 1st year = (5/15)*20 = 6.7m
Book value at the beginning of 2nd year = 30 -6.7 = 23.3m
Depreciation in the 2nd year = (4/15)*20 = 5.3m
Book value at the beginning of 3rd year = 30 -5.3 = 24.7m
Depreciation in the 3rd year = (3/15)*20 = 4m
Book value at the beginning of 4th year = 30 -4 = 26m
Depreciation in the 4th year = (2/15)*20 = 2.7m
Book value at the beginning of 5th year = 30 -2.7 = 27.3m
Depreciation in the 5th year = (1/15)*20 = 1.3m
MATERIALS
The cost of materials varies considerably depending upon the firm which supplies and the purchaser.
Factors determining cost of material (unit rate of materials)
Quantity to be purchased
Inflation
Annual turnover of the supplier
Law of demand and supply
Speed with which the purchaser settles the account
Wastages to be encountered e.g cutting waste, application waste, stock pile waste, residue waste, transit waste
and theft & vandalism.
Sources of information for the prices of resources
Press on radios, TVs by technical teams.
Site visits
Manufacturers
15 | P a g e Quantity surveying notes ©Musiimenta Milly Asiimwe
Institutions set up as the source of cost information centers e.g UBOS.
From sister companies and dealers
From sub contractors and suppliers Contacting local people
Examples of earthworks
Site stripping
Clearing and grabbing
Cut & fill site balancing
Rough and fine grading
Earth moving and stock pilings
Earth compaction
Field survey and layout
Building temporary roads
Soil stabilization
Park development
Site rehabilitation
Top soil placement
There are two methods of excavation that is the manual and mechanical method.
Solution
Total cost is 24000+1200 = 25200/=
Therefore, cost per cubic metre = 25200/9 = 2800/=
Solution
a) Output of excavator
Where; Q = Capacity
CE = Bucket fill factor
T = Time period for which production is done.
F = Soil factor
E = Job efficiency
Cm = Cycle time
Three
Estimate the cost per CM of a 7m wide road sub-base supposed to be filled to a 600mm thickness in layers of
150mm and compacted using a 10 tonnes roller costing 800,000 per day of 8 working hours. A grader hired at
600,000 per day is to be used for spreading the marrum; the marrum shall be excavated using a 2.5m3 excavator
and it’s assumed to have just the original moisture content for maximum compaction and will be loaded directly
into lorries of 15m3 capacity for disposal at the site 3km away. Travel speed for the lorry is 40km/hr loaded and
55km/hr empty.
The excavator is able to excavate and load in 2 minutes per every bucket. The maneuvering time at both ends is
2minutes, waiting time is 1minute and tipping time is 2minutes. Bulking factor is 25%.
The excavator and lorry were purchased at 400m UGX and 120m UGX respectively and have useful lives of 10
years.
The cost of capital is 15% and as a prospecting contractor, the other figures for maintenance, insurance, taxes,
profits and overheads are to be assumed. Use the method of depreciation of your choice to determine the total
cost of the sub-base per a km.
Add one supervisor for both skilled and for unskilled and 2 watch men, 2 flag men plus one standby for skilled
and unskilled.
Total skilled = 1+3+1+1+1 = 7
Total Unskilled = 1+3+1+1+1+2+2 = 11
Assume 3000 for supervisor 2000 for skilled and 1500 for unskilled per hour
Total = (3000 + 2000x7 + 1500x11) x8 = 268,000/ per day
Equipment
Excavator
Initial capital 400m
Interest on capital = 15%
Assume all other rates (profit, overheads, running) = 20%
Using sinking fund method
Lorry
Initial capital 120m
Interest on capital = 15%
Assume all other rates (profit, overheads, running) = 20%
Using sinking fund method
Grader
Hire rate per day 600,000x1.2 = 720,000/= per day
Roller
Hire rate per day 800,000x1.2 = 960,000/= per day
Total cost is 268,000 +382,354 + 344,304 + 720,000 + 960,000 = 2,674,658/= per day
Cost per CM = 2,674,658/510 = 5,244/= per CM
Cost per km = 5,244x6000 =31,464,000/= per km.
CONCRETE WORKS
Factors that affect the cost of concrete
There are three main initial factors to be considered in the costs of concrete:
• Method of mixing
• Materials being used, their specifications and grade of concrete
• Site transportation, placing and compaction
For mortar
The voids in mortar take up 25%
(V +∂v )0.75 = V
V +∂v =1.333V
∂v = 0.333V
Question One
Concrete of mix grade 20 (1:2:4).
Calculate using volume batching, the unit rate of concrete and prepare the materials delivery list given the
following information considering a slab of 7m by 15m of 150mm thick:
Item Description Skilled Un skilled Labour Rate (Ush)
1 Concrete 03 6 2500, 1000 respectively
Concrete mixer takes 1hour to mix 2m3 of concrete @ 6250 per hour.
Cement…………………………………………..@ 36,000/ per 50kg bag
Transport for cement………………………………500/ per bag
Unloading cement………………………………….50/ per bag
Sand ……………………………………………….15,000/ per CM delivered
Aggregate………………………………………….40,000/ per ton delivered
Allow 5% westage on concrete
Allow 25% profits and overheads
Densities
Cement……………………………………………..1.3ton/CM to 1.4 (1300kg/m3 to 1400kg/m3)
Moist sand………………………………………….1.3
Dry sand…………………………………………….1.5
Aggregate …………………………………………..1.6
Solution
1400kg of cement are contained in 1CM
1kg…………………………….. …CM/1400…………………………………..(i)
50kg of cement are contained in 1bag
1kg…………………………………bag/50…………………………………….(ii)
From (ii)/(i)
1CM of cement contains 1400/50 = 28bags.
1CM of cement……………………………28bags @ 36,0000……………………1,008,000/
Transport for 28 bags @ 500……………………………………………………….14,000/
Unloading of 28 bags @ 50…………………………………………………………1,400/
Total 5,040,000
Question Two
A 150mm thick reinforced concrete slab is to be cast in-situ in concrete grade 30 (1:1.5:3).
a) Compute the unit rate for concrete ignoring the cost of reinforcement and formwork.
b) Produce a material delivery list if the slab required 100m3of concrete.
Data
OPC delivered and offloaded per bag of 50kg cost 29,000/
1 ton of lake sand delivered cost 15,000/
Solution
(a) Unit rate of concrete
Volume batching in the ratio 1:1.5:3
1CM of cement……………………………28bags @ 29,000………………………812,000/
1.5CM of sand each ton @ 15,000………...........1.5x1.3x15000 delivered................29250/
3CM of aggregates delivered …..3x1.6x40,000……………………………………...192,000/
Total 1………………………………..1,033,250/
Cost of 1CM of dry cement with ………(1,033,250 + 0.667x1,033.250)/5.5………..313,169/
Voids catered for
Allow 5% waste…………………………………………………………………………156581/
Concrete mixer (40000/8)x0.5hours…………………………………………………….2500/
Porker vibrator (24000/8)x0.5hours……………………………………………………..1500/
Unskilled labour 6 @ 625…………………………………………………………..........3750/
Skilled labour 0.3x1500/………………………………………………………………….450/
Total 2…………………………………………..337,027/
Add 20% profits and overheads……………………………………………………………67405/
Total 3…………………………………………..404,432/
Cost per CM of concrete of grade 30 is ……………….404432/
Cost per SM of floor slab is……0.15x404432…………60665/
Therefore the unit rate for the floor slab is 60665/ per square metre.
FORM WORK
Before pricing the unit rates for form work, the estimator will consider the following items:
• Whether metal or timber form work
• The design of the form work to be used
• The estimated number of times the form work can be used.
• The labour involved in making, fixing and stripping.
Timber form work
The following is a typical method of building up:
Cost of material in making, plus cost of labour in making, divide by the estimated number of uses.
Braces
Using a spacing of 500mm
L = 100+275+100 = 475mm = 0.475m
Volume = 0.475x0.05x0.05 = 1.1875x10-3CM
Cost of braces = 1.1875x10-3x500000x7x4 = 16625/=
Boards
3x0.025x0.275x500000x4 = 37500/=
Cost of eucalyptus poles = 4x2000 = 8000/
Question Two
What will be the cost of reinforced concrete column of 225x225x3 if it requires 16mm bars of 6No. per column
and 8mm stirrups at 200mm centres are to be used. Reinforcement costs 2,000,000/ per ton delivered to site. Use
example two on calculations for cost of concrete to get the cost per CM of plain concrete (404432/=)
Data
Wastage =5%
Tie wires and spacers =2%
Cutting and bending rate =15hrs/ton
Fixing rate = 20hrs/ton
Bar bending machinery = within on-site cost
Site transportation = with in on-site cost
Labour for steel fixer = 3000/hr
Solution
Compute the volume of the column = 0.225x0.225x3 = 0.1485CM
Using the unit cost of concrete (404432/), compute the cost of concrete required for the column as
0.1485x404432 = 60,058/=
Reinforcement
Purchasing 2,000,000/ per ton
Wastage of 5% of purchase 100,000/
Add 2% of purchase for spacers and binding wire 40,000/
Labour (15+20)x 3000105,000/ per ton
Total 2,245,000/per ton
BRICK/BLOCK WORK
Factors that affect the costs of brick/block work
Wall thickness
Workmanship or finishing expected
Height of workplace
Whether activity is continuous or intermittent
Specification of building unit
Skills of masons
Level of supervision and site organization
In order for the estimator to price the unit rate for brick or block, it is necessary for him to know the following:
• How to build up the price per cubic metre for the mortar to be used
• The number of bricks or block in a SM
• The percentage to be added for waste
• Amount f skilled and unskilled hours required for each unit operation
Materials required
Cement = 7.5x1.353………………10.1 bags. Say 11bags.
Sand = 1.391x1.353……………..1.9 tons. Say 2 tons.
Item Description Unit Qty Rate Amount
Total 1,433,000
Waste
The cutting and waste factor on insitu carpentry and joinery can be generally at about 10% but for certain
members in some situations, it may be higher.
28 | P a g e Quantity surveying notes ©Musiimenta Milly Asiimwe
Factors that are considered in estimating for any carpentry and joinery work
The size of sections required
Labour involved
Type of item being made e.g roof trusses, door and windows
Purpose of structure
Battens
Consider spacing of 325mm
Number (length) of battens in a SM 1/0.325 ……………………………………………….3.08
If 150x50x4200 costs 24,000Ushs, then 38x50x3.08 costs 4,458/=
0.05 x 0.038 x 500,000 x 3.08…………………………………………………………….. 2926/
Allow 10% cutting waste …………………………………………………………………..293/
Total 2 3219/
Nails
Consider a spacing of 600mm
Number of nails 3.08/0.6 ……………………………………………………………………..5
5*30 …………………………………………………………………………………………150/
G32 iron sheet @ 6000 …………………………………………………………………….6000/
Unskilled labour 0.3 @ 1000 ………………………………………………………………..300/
Skilled labour 0.6 @ 2500 …………………………………………………………………1500/
Total 3 7950/
FINISHES
1. Plaster work and other floor, wall and ceiling finishes and beds
Lime plaster has backing and rendering of course stuff and a finishing or setting coat of fine stuff. Before the
price of lime plastering can be analyzed, the basic cost of course, stuff and fine stuff must be ascertained.
The labour in mixing plastering materials is covered by the time of the attendant labourers in the plastering gang,
as two labourers can supply 3 plasterers with all the materials they require and do all the mixing. Generally, the
mixing is carried out by mixing machines.
Example Two
Calculate the unit rate for plaster in cement-lime-sand mix of 1:2:9 to a thickness of 20mm. First coat be 12mm
thick, second coat be 6mm thick and finishing coat be 2mm (this is normally lime-cement mix).
Cement-lime-sand mix of 1:2:9 costs 227,375/
First cost 12mm…………0.012 x 227375…………………………………………………..2,729/
Compression of 50%................................................................................................................1,365/
Second coat 6mm……...0.06 x 227375……………………………………………………..1,364/
Compression of 20%................................................................................................................273/
5,371/
Finishing coat cement - lime (1:10) of 2mm
28 bags of cement ………………………………………………………………………784,000/
56 bags of lime (25kg/bag)……………10 x 2 x 28000…………………………………560,000/
1,344,000/
Allow for voids and waste of 10% 134,400/
1,478,400/
Cost per CM 1,478,400/11………………………………………………………………134,400/
Therefore cost of finishing coat 0.002 x 134,400…………………………………………….269/
Unskilled labour 0.75 x 2500 ………………………………………………………………..1875/
Skilled labour 1.5 @ 1000 …………………………………………………………………...1500/
3,375/
Total is 5731 + 269 + 3375 9,375/
Allow 20% profits and overheads 1,857
11,250/
The cost of plastering a SM of wall is 11,250/
2. Floor Screed
Specifications: 40mm thick mix of 1:4 cement – sand
0.04CM @ 300,000………………………………………………………………………12,000/
Waste of 10%.......................................................................................................................1,200/
Cement slurry of 0.5mm thick @ 784,000…………………………………………………392/
Skilled labour 1.5 @ 2500………………………………………………………………….3750/
Unskilled labour 1.5 @ 1000……………………………………………………………….1500/
18,842/
Add 20% profits and overheads …………………………………………………………...3768/
22,610/
The cost of screeding 40mm thick concrete in cement-sand mix of 1:4 is 22,610/