WEEK_5_EXPERIMENT
WEEK_5_EXPERIMENT
1. Organic
2. Semidetached
3. Embedded
Software project a b c
Organic 2.4 1.05 0.38
Semi-detached 3.0 1.12 0.35
Embedded 3.6 1.20 0.32
The Institute has a IT management team of its own. This team has been given
the task to execute the Library Information System project. The team consists of
a few experts from industry, and a batch of highly qualified engineers
experienced with design and implementation of information systems. It is
planned that the current project will be undertaken by a small team consisting of
one expert and few engineers. Actual team composition would be determined in
a later stage.
Using COCOMO and based on the team size (small) and experience (high), the
concerned project could be categorized as "organic". The experts, based on their
prior experience, suggested that the project size could roughly be around 10
KLOC. This would serve as the basis for estimation of different project
parameters using basic COCOMO, as shown below:
Effort = a * (KLOC)b PM
Tdev = 2.5 * (Effort)c Months
For organic category of project the values of a, b, c are 2.4, 1.05, 0.38
respectively. So, the projected effort required for this project becomes
Effort = 2.4 * (10)1.05 PM
= 27 PM (approx)
So, around 27 person-months are required to complete this project. With this
calculated value for effort we can also approximate the development time
required:
Tdev = 2.5 * (27)0.38 Months
= 8.7 Months (approx)
So, the project is supposed to be complete by nine months.