IDAM Access - Manager - Upgrade - 04-OCT-2024

The document outlines a six-week plan for migrating the DC Access Manager to version 5.0.4, detailing tasks, durations, and ownership for each step. Key tasks include creating new VM servers, backing up configurations, and performing the migration process while ensuring rollback measures are in place. The plan involves multiple teams, including SIB Infra and IDAM, with several tasks currently marked as open for initiation.

Uploaded by

Raj Khanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views3 pages

IDAM Access - Manager - Upgrade - 04-OCT-2024

The document outlines a six-week plan for migrating the DC Access Manager to version 5.0.4, detailing tasks, durations, and ownership for each step. Key tasks include creating new VM servers, backing up configurations, and performing the migration process while ensuring rollback measures are in place. The plan involves multiple teams, including SIB Infra and IDAM, with several tasks currently marked as open for initiation.

Uploaded by

Raj Khanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Plan of Action for DC Access manage

Sr.No

8
9

2
6 Weeks Duration

Plan of Action for DC Access manager migration to 5.0.4


Tasks Duration
Perquisites
SIB to provide 3 new VM Server to be created with given
2 Day's
specification ( Spec same as in DR - 3 no's )
Backup of Access manager configuration and all configuration
1 Day
files

Take Backup of DC NAM Servers Snapshot 1 Day

Port openings as required ( Hostname should be changed,


2 Day's
details will be shared by Process IT)
NAM VERSION MIGRATION PLAN
Remove the OLD VM's from the cluster and remove from DNS 1 Day
Create New VM with the given ISO file ( Process IT to provide
1 Day
the ISO file )
Install Access Manager Appliance 5.0 Service Pack 4 as a
secondary appliance and point to the 4.5.3 primary appliance.
2 Day's
Performing basic configuration of the secondary access
manager such as hostfile,ntp etc.
Take a backup of the primary Administration Console which is
1 Day
on 4.5.3 by using the ambkup.sh script

Switch off the primary VM which is on 4.5.x. 1 Day

Log in as root at the secondary Access Manager Appliance


and run the migration script. Follow the steps in the upgrade 1 Day
document to complete the process
Login to primary access manager 5.0.1 administration console,
remove the old primary Access Manager Appliance and all
3 Day's
objects that reference the old primary Access Manager
Appliance as described in the document
Checking of applications access 3 Day's
Reintegration of SAML based applications with revised
7 Day's
Metadata
ROLLBACK PLAN
Take a VM backup of existing 4.5.x version before performing
upgrade.
In case of failure power off the new VM 5.0.1 and restore the
backup of 4.5.x to new VM.
r migration to 5.0.4
Ownership Status

SIB Infra team Process to start

SIB Infra team Process to start

SIB Backup team Process to start

SIB Process to start

IDAM /SIB VM team OPEN

SIB VM/SIB InfraTeam OPEN

IDAM Team OPEN

IDAM Team OPEN

IDAM Team OPEN

IDAM Team OPEN

IDAM Team OPEN

IDAM Team OPEN


IDAM Team OPEN

SIB/IDAM team OPEN