technical specificationns
technical specificationns
The proposed projects shall be commissioned as per the technical specifications given below. Any
shortcomings will lead to cancelation of CFA in full or part as decided by MPMKVVCL. Domestic
Modules are to be used failing which it will be assumed that system is not matching the requirement of
the scheme and bidder‘s PBG shall be forfeited. Competent Authority‘s decision will be final and
binding on the bidder.
DEFINITION
A Roof Top Solar (RTS) Photo Voltaic (PV) system shall consist of following equipment/components:
1. Solar Photo Voltaic (SPV) modules consisting of required number of CrystallinePV modules
2. Inverter/PCU
3. Module Mounting structures
4. Energy Meter
5. Array Junction Boxes
6. DC Distribution Box
7. AC Distribution Box
8. Protections – Earthing, Lightning, Surge
9. Cables
10. Drawing & Manuals
11. Miscellaneous
1. Solar PV modules
1.1. The PV modules and Solar Cell used should be made in India.
1.2. The PV modules used must qualify to the latest edition of IEC standards or equivalent BIS
standards, i.e., IEC 61215/IS14286, IEC 61853-Part I/IS 16170-Part I, IEC 61730 Part-1 & Part 2
and IEC 62804 (PID). For the PV modules to be used in a highly corrosive atmosphere throughout
their lifetime, they must qualify to IEC 61701/IS 61701.
1.3. The rated power of solar PV module shall have maximum tolerance up to +3%.
1.4. The peak-power point current of any supplied module string (series connected modules) shall not
vary by +1% from the respective arithmetic means for all modules and/or for all module strings
(connected to the same MPPT), as the case may be.
1.5. The peak-power point voltage of any supplied module string (series connected modules) shall not
vary by + 2% from the respective arithmetic means for all modules and/or for all module strings
(connected to the same MPPT), as the case may be.
1.6. The temperature co-efficient power of the PV module shall be equal to or better than -0.45%/°C.
1.7. Solar PV modules of minimum capacity 250 Wp to be used.
1.8. The PV Module efficiency should be minimum 16%.
1.9. Solar PV modules of minimum fill factor 75%, to be used.
1.10. All electrical parameters at STC shall have to be provided
1.11. The PV modules shall be equipped with IP 65 or better protection level junction box with required
numbers of bypass diodes of appropriate rating and appropriately sized output power cable of
symmetric length with MC4 or equivalent solar connectors. The IP level for protection may be
chosen based on following conditions:
Page 62 of 140
Sign & Round Seal of Bidder
i. An IP 65 rated enclosure is suitable for most outdoor enclosures that won‘t encounter extreme
weather such as flooding.
ii. An IP 67 rated enclosure is suitable at locations which may encounter temporary submersion at
depths of up to one meter.
iii. An IP 68 enclosure is recommended if there may exist situations of submergence for extended
periods of time and at substantial depths.
1.12. All PV modules should carry a performance warranty of >90% during the first 10 years, and
>80% during the next 15 years. Further, module shall have performance warranty of >97% during
the first year of installation—degradation of the module below 1 % per annum.
1.13. The manufacturer should warrant the Solar Module(s) to be free from the defects and/or failures
specified below for a period not less than five (05) years from the date of commissioning:
1.14. Defects and/or failures due to manufacturing.
1.15. Defects and/or failures due to quality of materials.
1.16. Nonconformity to specifications due to faulty manufacturing and/or inspection processes. If the
solar Module(s) fails to conform to this warranty, the manufacturer will repair or replace the solar
module(s), at the Owners sole option.
1.17. PV modules must be tested and approved by one of the NABL accredited and BIS approved test
centres.
1.18. Modules deployed must use a RF identification tag laminated inside the glass. The following
information must be mentioned in the RFID used on each module:
i. Name of the manufacturer of the PV module
ii. Name of the manufacturer of Solar Cells.
iii. Month & year of the manufacture (separate for solar cells and modules)
iv. Country of origin (separately for solar cells and module)
v. I-V curve for the module Wattage, Im, Vm and FF for the module
vi. Unique Serial No and Model No of the module
vii. Date and year of obtaining IEC PV module qualification certificate.
viii. Name of the test lab issuing IEC certificate.
ix. Other relevant information on traceability of solar cells and module as per ISO 9001 and ISO
14001.
x. Nominal wattage +3%.
xi. Brand Name, if applicable.
1.19. Other details as per IS/IEC 61730-1 clause 11 should be provided at appropriate place. In addition
to the above, the following information should also be provided:
i. The actual Power Output Pmax shall be mentioned on the label pasted on the back side of PV
Module.
ii. The Maximum system voltage for which the module is suitable to be provided on the back sheet
of the module.
iii. Polarity of terminals or leads (colour coding is permissible) on junction Box housing near cable
entry or cable and connector.
1.20. Unique Serial No, Model No, Name of Manufacturer, Manufacturing year, make in India logo and
module wattage details should be displayed inside the laminated glass.
Page 63 of 140
Sign & Round Seal of Bidder
2. Inverter/PCU
2.1. Inverters/PCU should comply with applicable IEC/equivalent BIS standard for efficiency
measurements and environmental tests as per standard codes IEC 61683/IS 61683, IS 16221 (Part
2), IS 16169 and IEC 60068-2(1,2,14,30) /Equivalent BIS Std.
2.2. Maximum Power Point Tracker (MPPT) shall be integrated in the inverter/PCU to maximize
energy drawn from the array. Charge controller (if any) / MPPT units environmental testing
should qualify IEC 60068-2(1, 2, 14, 30)/Equivalent BIS standard. The junction boxes/enclosures
should be IP 65 or better (for outdoor)/ IP 54or better (indoor) and as per IEC 529 Specifications.
2.3. All inverters/PCUs shall be IEC 61000 compliant for electromagnetic compatibility, harmonics,
Surge, etc.
2.4. The PCU/ inverter shall have overloading capacity of minimum 10%.
2.5. Typical technical features of the inverter shall be as follows-
i. Switching devices: IGBT/MOSFET
ii. Control: Microprocessor/DSP
iii. Nominal AC output voltage and frequency: as per CEA/MPERC regulations
iv. Output frequency: 50 Hz
v. Grid Frequency Synchronization range: as per CEA/MPERC Regulations
vi. Ambient temperature considered: -20°C to 60°C
vii. Humidity: 95 % Non-condensing
viii. Protection of Enclosure: IP-54 (Minimum) for indoor and IP-65(Minimum) for outdoor.
ix. Grid Frequency Tolerance range: as per CEA/MPERC regulations
x. Grid Voltage tolerance: as per CEA/MPERC Regulations
xi. No-load losses: Less than 1% of rated power
xii. Inverter efficiency (Min.): >93% (In case of 10 kW or above with in-built galvanic isolation)
>97% (In case of 10 kW or above without inbuilt galvanic isolation)
xiii. Inverter efficiency (minimum): > 90% (In case of less than 10 kW)
xiv. THD: < 3%
xv. PF: > 0.9 (lag or lead)
xvi. Should not inject DC power more than 0.5% of full rated output at the interconnection point and
comply to IEEE 519.
2.6. The output power factor of inverter should be suitable for all voltage ranges or sink of reactive
power, inverter should have internal protection arrangement against any sustain fault in feeder line
and against the lightning on feeder.
2.7. All the Inverters should contain the following clear and indelible Marking Label & Warning Label
as per IS16221 Part II, clause 5. The equipment shall, as a minimum, be permanently marked
with:
i. The name or trademark of the manufacturer or supplier.
ii. A model number, name, or other means to identify the equipment,
iii. A serial number, code or other marking allowing identification of manufacturing location and
the manufacturing batch or date within a twelve-month time period.
iv. Input voltage, type of voltage (a.c. or d.c.), frequency, and maximum continuous current for
each input.
v. Output voltage, type of voltage (a.c. or d.c.), frequency, maximum continuous current, and for
a.c. outputs, either the power or power factor for each output.
Page 64 of 140
Sign & Round Seal of Bidder
vi. The Ingress Protection (IP) rating
2.8. Marking shall be located adjacent to each fuse or fuse holder, or on the fuse holder, or in another
location provided that it is obvious to which fuse the marking applies, giving the fuse current
rating and voltage rating for fuses that may be changed at the installed site.
2.9. In case the consumer is having a 3-ϕ connection, 1-ϕ/3-ϕ inverter shall be provided by the vendor
as per the consumer‘s requirement and regulations of the MPERC.
i. Ballast structure
a. The mounting structure must be Non-invasive ballast type and any sort of penetration of roof to be
avoided.
b. The minimum clearance of the structure from the roof level should be in between 70-150 mm to
allow ventilation for cooling, also ease of cleaning and maintenance of panels as well as
cleaning of terrace.
c. The structures should be suitably loaded with reinforced concrete blocks of appropriate weight
made from M25 concrete mixture.
iii. RCC Elevated structure: It can be divided into further three categories:
Page 66 of 140
Sign & Round Seal of Bidder
A. Minimum Ground clearance (300MM – 1000 MM)(Which is covered in bidding price)
a. The structure shall be designed to allow easy replacement of any module and shall be in line
with site requirement. The gap between module should be minimum 30MM.
b. Base Plate – Base plate thickness of the Structure should be 5MM for this segment.
c. Column – Structure Column should be minimum 2MM in Lip section / 3MM in C-Channel
section. The minimum section should be 70MM in Web side and 40MM in flange side in Lip
section.
d. Rafter - Structure rafter should be minimum 2MM in Lip section / 3MM in C-Channel section.
The minimum section should be 70MM in Web side (y-axis) and 40MM in flange side (x-axis).
e. Purlin - Structure purlin should be minimum 2MM in Lip section. The minimum section should
be 60MM in Web side and 40MM in flange side in Lip section.
f. Front/back bracing – The section for bracing part should be minimum 2MM thickness.
g. Connection – The structure connection should be bolted completely. Leg to rafter should be
connected with minimum 12 diameter bolt. Rafter and purlin should be connected with
minimum 10 diameter bolt. Module mounting fasteners should be SS-304 only and remaining
fasteners either SS-304 or HDG 8.8 Grade.
h. For single portrait structure the minimum ground clearance should be 500MM.
Page 67 of 140
Sign & Round Seal of Bidder
f. Connection – The structure connection should be bolted completely. Leg to rafter should be
connected with minimum 12 diameter bolt. Rafter and purlin should be connected with
minimum 10 diameter bolt. Module mounting fasteners should be SS-304 only and remaining
fasteners either SS-304 or HDG 8.8 Grade.
D. Super elevated structure (More than 3000 MM) (for reference only)
D.1. Base structure
a. Base Plate – Base plate thickness of the Structure should be 10MM for this segment.
b. Column – Structure Column minimum thickness should be minimum 2.9MM in square hollow
section (minimum 60x60) or rectangular hollow section (minimum 80x40).
c. Rafter - Structure Rafter minimum thickness should be minimum 2.9MM in square hollow
section (minimum 60x60) or rectangular hollow section (minimum 80x40).
d. Cross bracing – Bracing for the connection of rafter and column should be of minimum
thickness of 4mm L-angle with the help of minimum bolt diameter of 10mm.
Page 68 of 140
Sign & Round Seal of Bidder
3.13. Material standards:
i. Design of foundation for mounting the structure should be as per defined standards which
clearly states the Load Bearing Capacity & other relevant parameters for foundation design (As
per IS 6403 / 456 / 4091 / 875).
ii. Grade of raw material to be used for mounting the structures so that it complies the defined
wind loading conditions (As per IS 875 - III) should be referred as follows (IS 2062 – for angles
and channels, IS 1079 – for sheet, IS 1161 & 1239 for round pipes, IS 4923 for rectangular and
square hollow section)
iii. Test reports for the raw material should be as per IS 1852 / 808 / 2062 / 1079 / 811.
iv. In process inspection report as per approved drawing & tolerance should be as per IS 7215.
v. For ascertaining proper welding of structure part following should be referred:
a. D.P. Test (Pin Hole / Crack) (IS 822)
b. Weld wire grade should be of grade (ER 70 S - 6)
vi. For ascertaining hot dip galvanizing of fabricated structure following should be referred: -
a. Min coating required should be as per IS 4759 & EN 1461.
b. Testing of galvanized material
Pierce Test (IS 2633)
Mass of Zinc (IS 6745)
Adhesion Test (IS 2629)
CuSO4 Test (IS 2633)
Superior High-Grade Zinc Ingot should be of 99.999% purity (IS 209) (Preferably Hindustan
Zinc Limited or Equivalent).
vii. Foundation Hardware – If using foundation bolt in foundation then it should be as per IS 5624.
4. Metering
4.1. A Roof Top Solar (RTS) Photo Voltaic (PV) system shall consist of following energy meters:
i. Net meter: To record import and export units
ii. Generation meter: To keep record for total generation of the plant.
4.2. The installation of meters including CTs & PTs, wherever applicable, shall be carried out by
MPMKVVCL as per the terms, conditions and procedures laid down by the concerned MPERC/
MPMKVVCL.
5.1 The junction boxes are to be provided in the PV array for termination of connecting cables. The
Junction Boxes (JBs) shall be made of GRP/FRP/Powder Coated aluminium /cast aluminium
alloy with full dust, water & vermin proof arrangement. All wires/cables must be terminated
through cable lugs. The JBs shall be such that input & output termination can be made through
suitable cable glands. Suitable markings shall be provided on the busbars for easy identification
and cable ferrules will be fitted at the cable termination points for identification.
5.2 Copper bus bars/terminal blocks housed in the junction box with suitable termination threads
Conforming to IP 65 or better standard and IEC 62208 Hinged door with EPDM rubber gasket to
prevent water entry, Single /double compression cable glands should be provided.
Page 69 of 140
Sign & Round Seal of Bidder
5.3 Polyamide glands and MC4 Connectors may also be provided. The rating of the junction box shall
be suitable with adequate safety factor to interconnect the Solar PV array.
5.4 Suitable markings shall be provided on the bus bar for easy identification and the cable ferrules
must be fitted at the cable termination points for identification.
5.5 Junction boxes shall be mounted on the MMS such that they are easily accessible and are
protected from direct sunlight and harsh weather.
6.1 May not be required for small plants, if suitable arrangement is available in the inverter.
6.2 DC Distribution Box are to be provided to receive the DC output from the PV array field.
6.3 DCDBs shall be dust & vermin proof conform having IP 65 or better protection, as per site
conditions.
6.4 The bus bars are made of EC grade copper of required size. Suitable capacity MCBs/MCCB shall
be provided for controlling the DC power output to the inverter along with necessary surge
arrestors. MCB shall be used for currents up to 63 Amperes, and MCCB shall be used for currents
greater than 63 Amperes.
7.1 AC Distribution Panel Board (DPB) shall control the AC power from inverter, and should have
necessary surge arrestors, if required. There is interconnection from ACDB to mains at LT Bus
bar while in grid tied mode.
7.2 All switches and the circuit breakers, connectors should conform to IEC 60947:2019, part I, II and
III/ IS 60947 part I, II and III.
7.3 The isolators, cabling work should be undertaken as part of the project.
7.4 All the Panel‘s shall be metal clad, totally enclosed, rigid, floor mounted, air -insulated, cubical
type suitable for operation on 1-ϕ/3-ϕ, 415 or 230 volts, 50 Hz (or voltage levels as per
CEA/MPERC regulations).
7.5 The panels shall be designed for minimum expected ambient temperature of 45 degree Celsius, 80
percent humidity and dusty weather.
7.6 All indoor panels will have protection of IP 54 or better, as per site conditions. All outdoor panels
will have protection of IP 65 or better, as per site conditions.
7.7 Should conform to Indian Electricity Act and CEA safety regulations (till last amendment).
7.8 All the 415 or 230 volts (or voltage levels as per CEA/MPERC regulations) AC devices /
equipment like bus support insulators, circuit breakers, SPDs, Voltage Transformers (VTs) etc.,
mounted inside the switchgear shall be suitable for continuous operation and satisfactory
performance under the following supply conditions.
i. Variation in supply voltage: as per CEA/MPERC regulations
ii. Variation in supply frequency: as per CEA/MPERC regulations
7.9 The inverter output shall have the necessary rated AC surge arrestors, if required and MCB/
MCCB. RCCB shall be used for successful operation of the PV system, if inverter does not have
required earth fault/residual current protection.
Page 70 of 140
Sign & Round Seal of Bidder
8 Protections
The system should be provided with all necessary protections like earthing, Lightning, and Surge
Protection, as described below:
i. The SPV power plants shall be provided with lightning & over voltage protection, if required. The
main aim in this protection shall be to reduce the overvoltage to a tolerable value before it reaches
the PV or other sub system components. The source of over voltage can be lightning, atmosphere
disturbances etc. Lightning arrestor shall not be installed on the mounting structure.
ii. The entire space occupying the SPV array shall be suitably protected against Lightning by
deploying required number of Lightning Arrestors (LAs). Lightning protection should be provided
as per NFC17-102:2011/IEC 62305 standard.
iii. The protection against induced high voltages shall be provided using Metal Oxide Varistors
(MOVs)/Franklin Rod type LA/Early streamer type LA.
iv. The current carrying cable from lightning arrestor to the earth pit should have sufficient current
carrying capacity according to IEC 62305. According to standard, the minimum requirement for a
lightning protection system designed for class of LPS III is a 6 mm2 copper/ 16 mm2 aluminum or
GI strip bearing size 25*3 mm thick). Separate pipe for running earth wires of Lightning Arrestor
shall be used.
9 CABLES
9.1 All cables should conform to latest edition of IEC/equivalent BIS Standards along with IEC
60227/IS 694, IEC 60502/IS 1554 standards.
9.2 Cables should be flexible and should have good resistance to heat, cold, water, oil, abrasion etc.
9.3 Armoured cable should be used and overall PVC type ‗A‘ pressure extruded insulation or XLPE
insulation should be there for UV protection.
Page 71 of 140
Sign & Round Seal of Bidder
9.4 Cables should have Multi Strand, annealed high conductivity copper conductor on DC side and
copper/FRLS type Aluminium conductor on AC side. For DC cabling, multi-core cables shall not
be used.
9.5 Cables should have operating temperature range of -10°C to +80°C and voltage rating of
660/1000 V.
9.6 Sizes of cables between array interconnections, array to junction boxes, junction boxes to Inverter
etc. shall be so selected to keep the voltage drop less than 2% (DC Cable losses).
9.7 The size of each type of AC cable selected shall be based on minimum voltage drop. However,
the maximum drop shall be limited to 2%.
9.8 The electric cables for DC systems for rated voltage of 1500 V shall conform to BIS 17293:2020.
9.9 All cable/wires are to be routed in a RPVC pipe/ GI cable tray and suitably tagged and marked
with proper manner by good quality ferule or by other means so that the cable is easily identified.
9.10 All cable trays including covers to be provided.
9.11 Thermo-plastic clamps to be used to clamp the cables and conduits, at intervals not exceeding 50
cm.
9.12 Size of neutral wire shall be equal to the size of phase wires, in a three-phase system.
9.13 The Cable should be so selected that it should be compatible up to the life of the solar PV panels
i.e., 25 years.
10 DRAWINGS& MANUALS:
10.1 Operation & Maintenance manual/user manual, Engineering and Electrical Drawings shall be
supplied along with the power plant.
10.2 The manual shall include complete system details such as array lay out, schematic of the system,
inverter details, working principle etc.
10.3 The Manual should also include all the Dos & Don‘ts of Power Plant along with Graphical
Representation with indication of proper methodology for cleaning, Operation and Maintenance
etc.
10.4 Step by step maintenance and troubleshooting procedures shall also be given in the manuals.
10.5 Vendors should also educate the consumers during their AMC period.
11 Miscellaneous:
11.1 Connectivity: The maximum capacity for interconnection with the grid at a specific voltage
level shall be as specified in the MPERC regulation for Grid connectivity and norms of
MPMKVVCL and amended from time to time.
11.2 Safety measures: Electrical safety of the installation(s) including connectivity with the grid must
be considered and all the safety rules & regulations applicable as per Electricity Act, 2003 and
CEA Safety Regulation 2010 etc. must be followed.
11.3 Shadow analysis: The shadow analysis report with the instrument such as Solar Pathfinder or
professional shadow analysis software of each site should be provided, and the consumer should
be educated to install the system only in shadow free space. Lower performance of the system
due to shadow effect shall be liable for penalty for lower performance.
Page 72 of 140
Sign & Round Seal of Bidder
Quality Certification, Standards and Testing for Grid-Connected Rooftop Solar PV
Systems/Power Plants
Solar PV Modules/Panels
IEC61215 and DesignQualificationandTypeApprovalforCrystallineSiliconTerrestrial
IS14286 Photovoltaic(PV)Modules
IEC 61701:2011 Salt Mist Corrosion Testing of Photovoltaic(PV)Modules
IEC 61853-1:2011/ Photovoltaic(PV)moduleperformancetestingandenergyrating–
IS16170-1:2014 :Irradianceandtemperatureperformancemeasurements,andpower
Rating.
IEC 62716 Photovoltaic(PV)Modules–Ammonia(NH3)Corrosion Testing (as
per the site condition like dairies, toilets etc)
Page 74 of 140
Sign & Round Seal of Bidder