Conduits
Conduits
The document outlines conduit types, material specifications, support and fastener requirements, and applications as
per Aramco standards and the National Electrical Code (NEC). It also incorporates details regarding conduit sizes,
dimensions, naming conventions, and installation guidelines.
2. Conduit Hangers
• Determine the precise location of the stub-up based on the electrical system layout and equipment placement.
• Ensure proper alignment between the stub-up, horizontal conduit run, and electrical box or panel.
• Cut the conduit to the required length for the vertical run.
• Use a conduit bender to create a 90-degree bend at the base of the stub-up if needed.
• Ensure the bend radius complies with NEC Article 344 for Rigid Metal Conduit (RMC) or NEC Article 358 for
Electrical Metallic Tubing (EMT).
• Secure the stub-up with conduit straps or clamps to the structure (walls, floors, or slabs).
• When working with concrete slabs, use sleeves or embedment fittings to protect the conduit during the pouring
process.
• Use appropriate conduit fittings (e.g., couplings or connectors) to join the stub-up to the horizontal conduit run.
• Ensure the joints are tight and watertight if the installation is outdoors or in wet locations.
• Connect the stub-up to the electrical box or panel using a conduit connector.
6. Pulling Wires
• using tools such as fish tape or a pull string to guide the wires without damaging them.
1. Bending Radius:
▪ RMC/IMC: Minimum radius = 6 times the conduit diameter.
▪ EMT: Minimum radius = 5 times the conduit diameter.
▪ PVC: Minimum radius = 6 times the conduit diameter.
o Avoid sharp bends that could damage the conduit or the wires inside.
2. Support and Spacing:
▪ RMC/IMC: Maximum spacing of 10 feet for horizontal runs and 5 feet for vertical runs.
▪ EMT: Maximum spacing of 5 feet for horizontal runs and 3 feet for vertical runs.
3. Grounding:
o Metallic conduits must be properly grounded and bonded as required by NEC Article 250.
4. Sealing:
o Use sealing fittings or compound to prevent moisture ingress in outdoor, underground, or hazardous
locations.
5. Labeling:
o Label the stub-ups for easy identification during maintenance or future upgrades.
Applications of Stub-Ups
1. Slab-on-Grade Construction:
o Stub-ups provide vertical conduit connections from underground conduit systems to electrical boxes or
panels above the slab.
2. Wall-Mounted Equipment:
o Stub-ups allow for conduit transitions from horizontal runs to wall-mounted panels or devices.
3. Outdoor Installations:
o Stub-ups are used for outdoor lighting, equipment, and electrical devices.
4. Industrial Facilities:
o Commonly used in oil refineries, process plants, and other industrial settings for connecting electrical
equipment to the main conduit system.
Step Details
Planning Determine alignment with horizontal conduit run and location of equipment.
Cutting and Bending Cut conduit to the required length, bend as needed.
Securing Secure stub-up using straps or clamps.
Connecting Connect the stub-up to the horizontal run using appropriate fittings.
Installing Box/Panel Attach stub-up to the electrical box or panel.
Pulling Wires Pull wires or cables through the conduit system.
2. Bending Radius
• NEC:
o Minimum bending radius for conduits:
▪ RMC/IMC: 6 times the conduit diameter.
▪ EMT: 5 times the conduit diameter.
▪ PVC: 6 times the conduit diameter.
• NEC:
o Metallic conduits must be properly grounded and bonded to prevent electrical hazards.
o Complies with NEC Article 250 on grounding and bonding.
• NEC:
o Maximum support spacing:
▪ RMC/IMC: 3 meters (10 feet) for horizontal runs, 1.5 meters (5 feet) for vertical runs.
▪ EMT: 1.5 meters (5 feet) for horizontal runs, 1 meter (3 feet) for vertical runs.
Duct Bank:
A duct bank is a group of conduits used to protect and route electrical cables, communication lines, or utilities
underground or within concrete structures. Duct banks are used in industrial, commercial, and utility installations to
provide a safe and organized pathway for cables while safeguarding them from mechanical damage, moisture, and
environmental hazards.
1. Cable Protection: Protects cables from physical damage, moisture, and environmental threats.
2. Organization: Provides a systematic and organized pathway for multiple cables.
3. Future Expansion: Enables easy addition or replacement of cables over time.
4. Heat Dissipation: Assists in managing heat, especially in high-load applications.
1. Conduit Material
• Determined by:
o Number of cables.
o Cable diameter and fill capacity (per NEC Article 310).
o Future expansion needs.
• For metallic conduits, grounding and bonding must comply with NEC Article 250. Grounding rods and
connections are required .
• As per NEC 300.5(D), use warning tape (buried 12 inches above the duct bank) to indicate the presence of
buried electrical lines.
• Alternatively, in certain cases, red dye can be added to the concrete encasement for high-voltage duct banks as
an additional visual marker for underground cables (a common practice in Aramco installations).
Installation Process for Duct Banks
1. Trench Excavation
• Dig to the required trench depth, ensuring the bottom is smooth and level.
2. Conduit Placement
• Pour concrete around the conduits to form the duct bank. Ensure complete coverage and adequate strength for
mechanical protection.
Aramco adheres to SAES-P-114 (Electrical Conduits and Fittings) Key standards include:
Application Details
Industrial Facilities Protects power and control cables in plants and refineries.
Commercial Buildings Routes electrical and communication lines underground.
Utility Installations Provides pathways for power distribution and communication cables.
Oil and Gas Facilities Ensures safe and reliable cable routing in hazardous environments.
Data Centers Organizes and protects high-capacity power and data cables.
Aspect Details
Conduit Material PVC, HDPE, RMC, or IMC based on application.
Conduit Size and Number Determined by cable size, fill capacity, and future expansion.
Spacing and Arrangement Maintain proper spacing for heat dissipation and concrete encasement.
Depth and Trench Dimensions Follow NEC and local code requirements for burial depth.
Grounding and Bonding Ensure proper grounding for metallic conduits.
Marking and Identification Use warning tape or red dye, and label conduits for easy identification.