Building With Earth Design and Technology of A Sustainable Architecture
Building With Earth Design and Technology of A Sustainable Architecture
@arclib
@arclib
@arclib
@arclib
Gernot Minke
BUILDING
WITH EARTH
Design and Technology of
a Sustainable Architecture
Birkhäuser
Basel
@arclib
@arclib
Table of contents
Preface 7 6 Working with earth blocks 60
History 60
1 Introduction 9 Production of earth blocks 61
History 9 Material composition 64
Earth as a building material: the essentials 11 Laying earth blocks 64
Improving indoor climate 13 Surface treatment 65
Prejudices against earth as a building material 16 Fixing fasteners to walls 65
Lightweight earth blocks 65
2 The properties of earth as a building material 17 Special acoustic green bricks and adobes 66
Composition 17
Tests used to analyse the composition of loam 19 7 Large blocks and panels 67
Effects of water 22 Large blocks 67
Effects of vapour 26 Earth-filled wall panels 67
Influence of heat 29 Clay panels 69
Strength 30 Heating panels 71
pH-value 32 Floor slabs 71
Radioactivity 33 Floor tiles 72
Shelter against high-frequency electromagnetic Extruded loam slabs 72
radiation 33
8 Direct forming with wet loam 73
3 Preparing of loam 34 Traditional wet loam techniques 73
Soaking, crushing and mixing 34 The “Dünne loam loaf” technique 75
Sieving 36 The stranglehm technique 75
Mechanical slurrying 36
Water curing 36 9 Wet loam infill in skeleton structures 80
Thinning 36 Thrown loam 80
Sprayed loam 80
4 Improving the characteristics of loam by special Rolls and bottles of straw loam 81
treatment or additives 37 Lightweight loam infill 81
Reduction of shrinkage cracks 37 Infill with stranglehm and earth-filled hoses 82
Stabilisation against water erosion 38 Sprayed loam in steel-reinforced walls and ceilings 82
Enhancement of binding force 40
Increasing compressive strength 40 10 Tamped, poured or pumped lightweight loam 85
Strength against abrasion 45 Formwork 85
Increasing thermal insulation 45 Tamped lightweight straw loam walls 85
Lightweight loams 46 Tamped lightweight wood loam walls 87
Tamped, poured or pumped lightweight mineral loam
5 Rammed earthworks 50 walls 87
Formwork 51 Pumped lightweight mineral loam floors 88
Tools 52 Loam-filled hollow blocks 88
Method of construction 53 Loam-filled hoses 90
Shaping of openings 53
Wall construction techniques 54 11 Loam plasters 92
Rammed earth domes 59 Preparation of substrate 92
Drying 59 Composition of loam plaster 92
Labour input 59 Guidelines for plastering earth walls 94
Thermal insulation 59 Sprayed lightweight plaster 94
Surface treatment 59 Lightweight mineral loam plaster 95
@arclib
@arclib
Thrown plaster 95 Built examples
Plastered straw bale houses 95
Wet formed plaster 97 Residences
Protection of corners 97 Vineyard residence, Mornington Peninsula, Victoria,
Stabilised loam plasters 97 Australia 148
Characteristics of different loam plasters 97 Residence cum office, Kassel, Germany 150
Residence, Helensville, New Zealand 152
12 Weather resistance, coatings and coverings 100 Residence, Palo Alto, California, USA 154
Consolidating the surface 100 Weekend house, Ajijic, Mexico 156
Paints 100 Desert Outpost residence, Paradise Valley, Arizona, USA 158
Making surfaces water-repellent 103 Artist’s residence, Boulder, Colorado, USA 160
Lime plasters 104 Casa Martha, La Misión, Baja California, Mexico 162
Shingles, planks and other covers 105 Condominiums Los Maitenes, Peñalolén, Santiago de Chile,
Structural methods 105 Chile 164
Residence at Valle Tucán, Emboscada, Paraguay 168
13 Repair of loam structures 106 Barrel-vaulted residential buildings at Valle Tucán,
Occurrence of damage 106 Emboscada, Paraguay 170
Repair of cracks and joints with loam fillers 106
Repair of cracks and joints with other fillers 107 Cultural, educational and sacred buildings
Repairing larger damaged areas 107 National Environment Centre at Thurgoona Campus, Albury,
Retrofitting thermal insulation with lightweight loam 107 New South Wales, Australia 174
School, Rudrapur, Bangladesh 176
14 Customised design solutions 109 Chapel of Reconciliation, Berlin, Germany 178
Joints 109 WISE Centre for Alternative Technology, Machynleth,
Special wall constructions 111 Wales, UK 180
Intermediate floors 113 Primary school, Tanouan Ibi, Mali 182
Rammed earth floorings 113 Cemetery, Bushey, Hertfordshire, UK 186
Inclined roofs filled with lightweight loam 115 The Village Nursery, Bellingdon, Buckinghamshire, UK 190
Earth-covered roofs 115 Centre for People with Disabilities and Dipdii Textiles Studio,
Earth block vaults and domes 117 Rudrapur, Bangladesh 194
Earthen storage wall in winter gardens 129 Adobe Dome Music Space, Aiguá, Uruguay 198
Loam in bathrooms 129 Burkina Institute of Technology, Koudougou,
Built-in furniture and sanitary objects from loam 131 Burkina Faso 202
Passive solar wall heating system 132 Maison pour tous, Four, Isère, France 206
Bibliography 234
About the author 237
Illustration credits 237
Subject index 238
@arclib
@arclib
@arclib
@arclib
Preface
This handbook was written in response to bor für Experimentelles Bauen (Building Re-
an increasing worldwide interest in building search Institute – BRI) at the University of
with earth. While in Europe and North Amer- Kassel in Germany from 1978 to 2011. More-
ica earthen architecture may never play the over, the specialised techniques that the au-
dominant role as in warmer regions, we nev- thor developed and the practical experience
ertheless find an increasing tendency to build he gathered in the course of designing earth
with loam also in cooler climate zones. One buildings in a number of countries have also
reason for this is the growing environmental found their way into this book.
awareness as well as the desire to live in a
balanced and healthy indoor environment. This volume is loosely based on the German
Thus this fifth edition is timely and should publication Handbuch Lehmbau (Publisher:
encourage architects to explore the potential Ökobuch Verlag, Staufen), first published in
of this sustainable building material further. 1994 and now in its tenth edition (2022).
The publication provides a survey of all ap- Besides this English edition, the publication
plications and construction techniques of was translated into numerous languages
earth as a building material, including the such as Spanish, Russian, Japanese, Czech,
relevant physical data, while explaining its Farsi, Arabic and Rumanian.
specific qualities and the possibilities of op-
timising them. On many accounts, earth can While this is first and foremost a technical
offer an interesting alternative to industrial- book, the introductory chapter also provides
ised building materials. The data and expert the reader with a short survey on the histo-
knowledge contained in this volume may be ry of earth architecture. In this fifth English
used as guidelines for a variety of construc- edition, the relatively recent technology of
tion processes and possible applications by prefabricated rammed earth elements is in-
engineers, architects, builders and clients troduced and the growing segment of clay
who seek to use humanity’s oldest building panels is documented. The book’s final chap-
material for their purposes. ter depicts a number of attractive earth build-
ings from various regions of the world. These
Earth as a building material comes in many dif- constructions demonstrate the impressive
ferent compositions and can be variously pro- versatility of earth architecture and the many
cessed. Loam, or clayey soil, as it is referred to different uses of the building material earth.
scientifically, has different names when used Within this chapter, several older built exam-
in various applications, for instance rammed ples were replaced by seven new projects.
Left page:
earth, soil blocks, mud bricks or adobe. This
Minaret of the Al-Mihdar Mosque in Tarim, Yemen; it book documents the results of experiments Kassel, March 2025
is 38 m high and built of handmade adobes. and research conducted at the Forschungsla- Gernot Minke
7 Preface
@arclib
@arclib
1.1
1.2
8 Introduction
@arclib
@arclib
1 Introduction
9 Introduction
@arclib
@arclib
1.4 1.5
discovered in Assyria. Earth was used as the ple live in underground houses or caves that 15th to the 19th centuries. Near the city of
building material in all ancient cultures, not were dug in the silty soil. Lyon, there are several buildings that are
only for homes, but for religious buildings Bronze Age discoveries have established more than 300 years old and are still inhab-
as well. Illustrations 1.1 and 1.5 show the that in Germany earth was used as an ited. In 1790 and 1791, François Cointeraux
citadel of Bam in Iran, parts of which are infill in timber-framed houses or to seal published four booklets on this technique
ca. 2500 years old; 1.3 shows a fortified walls made of tree trunks. Wattle and that were translated into German 2 years
city in the Draa valley in Morocco, which is daub was also used. The oldest exam- later (Cointeraux, 1793). The technique
around 250 years old. The 4000-year-old ple of mud brick walls in northern Europe, came to be known all over Germany and in
Great Wall of China was originally built sole- found in the Heuneburg Fort near Lake neighbouring countries through Cointeraux
ly of rammed earth; only a later covering of Constance, Germany (1.11) dates back to and through David Gilly who described the
stones and bricks gave it the appearance the 6th century BC. We know from the an- rammed earth technique as the most advan-
of a stone wall. China has a long tradition cient texts of Pliny that there were rammed tageous earth construction method.
of building with earth; well-known are for earth forts in Spain by the end of the year In Germany, the oldest inhabited house
instance the Tulou ("house of earth") build- 100 BC. In Mexico, Central America and with rammed earth walls dates from 1795
ings (1.2; 15.1) in Fujian, Nanjing (Schittich, South America, adobe buildings are known (1.13). Its owner, the director of the fire de-
2019). Illustration 1.4 shows vaults in the in nearly all pre-Columbian cultures. The partment, claimed that fire-resistant houses
Temple of Ramses II at Gourna, Egypt, built rammed earth technique was also known in could be built more economically using this
from mud bricks 3200 years ago. The core many areas, while the Spanish conquerors technique, as opposed to the usual timber
of the Sun Pyramid in Teotihuacan, Mexico, brought it to others. Illustration 1.10 shows frame houses with earth infill.
built between the 300 and 900 AD, con- a rammed earth finca in the state of São The tallest house with solid earth walls in Eu-
sists of approximately 2 million tonnes of Paulo, Brazil, which is 250 years old. In Af- rope is at Weilburg, Germany. The so-called
rammed earth. rica, nearly all early mosques are built from Pisé House (referring to French piser or to
Many centuries ago, in dry climatic zones earth. Illustration 1.12 shows one from the stamp) by architect Wilhelm Jacob Wimpf
where wood is scarce, construction tech- 12th century, 1.6, 1.7 and 1.8 show later ex- was completed in 1828, has six storeys and
niques were developed in which buildings amples in Mali and Iran. is still in use today (1.14). All ceilings and
were covered with mud brick vaults or In the Medieval period (13th to 17th centu- the entire roof structure rest on the solid
domes without formwork or support dur- ries), earth was used throughout Central Eu- rammed earth walls that are 75 cm thick at
ing construction. While the splendid Shah rope as infill in timber-framed buildings, as the bottom and 40 cm thick at the top floor
Mosque was built from earth bricks (1.8), well as to cover straw roofs to make them (the compressive force at the bottom of the
illustration 1.9 shows the bazaar quarter of fire-resistant. walls reaches 7.5 kg/cm2). Illustration 1.15
Sirdjan in Persia, which is covered by such In France, the rammed earth technique, shows the facades of other rammed earth
domes and vaults. In China, 20 million peo- called terre pisé, was widespread from the houses at Weilburg, built around 1830.
10 Introduction
@arclib
@arclib
1.6
1.7
Earth as a building material: the pare the mixture (moisture is required to acti-
essentials vate its binding strength and to achieve work-
1.8 ability), shrinkage cracks will occur. The linear
Earth, when used as a building material, is shrinkage ratio is usually between 3% and
often given different names. Referred to in 12% with wet mixtures (such as those used for
scientific terms as loam, it is a mixture of clay, mortar and mud bricks), and between 0.4%
silt (very fine sand), sand and occasionally and 2% with drier mixtures (used for rammed
larger aggregates such as gravel or stones. earth, compressed soil blocks). Shrinkage can
When speaking of handmade unbaked be minimised by reducing the clay and the wa-
bricks, the terms “mud bricks” or “adobes” ter content, by optimising the grain size distri-
are usually employed; when speaking of bution, and by using additives (see p. 37).
compressed unbaked bricks, the term “soil
blocks” is used. When compacted within a 3 Loam is not water-resistant
1.9 formwork, it is called “rammed earth”. Loam Loam must be sheltered against rain and
has three disadvantages when compared to frost, especially in its wet state. Earth walls
common industrialised building materials: can be protected by roof overhangs, damp-
proof courses, appropriate surface coatings
1 Loam is not a standardised building etc. (see p. 38).
material
Depending on the site where the loam is dug On the other hand, loam has many advan-
out, it will be composed of differing amounts tages in comparison to common industrial
and types of clay, silt, sand and aggregates. building materials:
Its characteristics, therefore, may differ from
site to site, and the preparation of the cor- 1 Loam balances air humidity
rect mix for a specific application may also Loam is able to absorb and desorb humid-
1.4 Storage rooms, temple of Ramses II, Gourna,
differ. In order to judge its characteristics ity faster and to a greater extent than any
Egypt
and alter these, when necessary, by apply- other building material, enabling it to bal-
1.5 Citadel of Bam, Kerman, Iran, detail ing additives, one needs to know the specific ance indoor climate. Experiments at the
1.6 Large Mosque, Djenne, Mali, built 1935 composition of the loam involved. Forschungslabor für Experimentelles Bau-
1.7 Mosque, Kashan, Iran en (Building Research Institute – BRI) at
1.8 Shah Mosque, Isfahan, Iran, 17th century 2 Loam mixtures shrink when drying the University of Kassel, Germany, demon-
1.9 Bazaar, Sirdjan, Iran Due to evaporation of the water used to pre- strated that when the relative humidity in
1.12
a room was raised suddenly from 50% to that the relative humidity in this house was
80%, unbaked bricks were able, in a two-day a nearly constant 50% throughout the year.
period to absorb 30 times more humidity It fluctuated by only 5% to 10%, thereby pro-
1.10 Rammed earth finca, São Paulo, Brazil
than baked bricks. Even when standing in ducing healthy living condition with reduced
1.11 Reconstruction of mud-brick wall, Heuneburg,
Germany, 6th century BC
a climatic chamber at 95% humidity for 6 humidity in summer and elevated humidity in
months, adobes do not become wet or lose winter. (For more details, see p. 13).
1.12 Mosque at Nando, Mali, 12th century
their stability; nor do they exceed their equi-
1.13 Rammed earth house, Meldorf, Germany, 1795
librium moisture content, which is about 5% 2 Loam stores heat
1.14 Rammed earth house (Pisé house), Weilburg,
Germany, 1828
to 7% by weight. (The maximum humidity a Like all heavy materials, loam stores heat.
dry material can absorb is called its “equi- As a result, in climatic zones with high di-
1.15 Around 1830, a number of rammed earth
houses were built in Weilburg, Germany. librium moisture content”). Measurements urnal temperature differences, or where it
1.16 Section through trachea with sane mucous
taken in a newly built house in Germany, becomes necessary to store solar heat gain
membrane (left) and dried out one (right) (Beckert, all of whose interior and exterior walls are by passive means, loam can balance indoor
1986) from earth, over a period of 8 years, showed climate.
12 Introduction
@arclib
@arclib
3 Loam saves energy and reduces 60). Similarly, loam can preserve small quan-
environmental pollution tities of straw that are mixed into it. Howev-
The preparation, transport and handling er, if lightweight straw loam with a density of
of loam on site requires only ca. 1% of the less than 500 to 600 kg/m3 is used, then the
energy needed for the production, transport loam may lose its preservative capacity due
and handling of baked bricks or reinforced to the high capillarity of the straw when used
concrete. Loam, then, produces virtually no in such high proportions. In such cases, the
environmental pollution. straw may rot when remaining wet over long
1.13 periods (see 10.3, p. 86).
4 Loam is always reusable
Unbaked loam can be recycled an indefinite 8 Loam absorbs pollutants
number of times over an extremely long pe- It is often maintained that earth walls help
riod. Old dry loam can be reused after soak- to clean polluted indoor air, but this has yet
ing in water, so loam never becomes a waste to be proven scientifically. It is a fact that
material that harms the environment. earth walls can absorb pollutants dissolved
in water. For instance, a demonstration plant
5 Loam saves material and transportation exists in Ruhleben, Berlin, which uses clay-
costs ey soil to remove phosphates from 600 m3
Clayey soil is often found on site, so that the of sewage daily. The phosphates are bound
soil excavated for foundations can then be by the clay minerals and extracted from the
used for earth construction. If the soil con- sewage. The advantage of this procedure is
tains too little clay, then clayey soil must be that since no foreign substances remain in
added, whereas if too much clay is present, the water, the phosphates are converted into
sand is added. The use of excavated soil calcium phosphate for reuse as a fertiliser.
means greatly reduced costs in comparison
1.14 with other building materials. Even if this soil Improving indoor climate
is transported from other construction sites,
it is usually much cheaper than industrial In moderate to cold climates, people usually
building materials. spend about 90% of their time in enclosed
spaces, so indoor climate is a crucial factor
6 Loam is ideal for do-it-yourself in well-being. Comfort depends upon the tem-
construction perature, movement, humidity, radiation to
Provided the building process is supervised and from surrounding objects, and pollution
by an experienced individual, earth construc- content of the air contained in a given room.
tion techniques can usually be executed by Although occupants immediately become
non-professionals. Since the processes in- aware when room temperatures are too high
volved are labour-intensive and require only or too low, the negative impacts of excessively
1.15 inexpensive tools and machines, they are elevated or reduced humidity levels are not
ideal for do-it-yourself building. common knowledge. Air humidity in contained
spaces has a significant impact on the health
7 Loam preserves timber and other of inhabitants, and earth has the ability to
organic materials balance indoor humidity like no other building
Owing to its low equilibrium moisture content material. This fact, only recently investigated,
of 0.4% to 6% by weight and its high capillar- is described in detail later in this section.
ity, loam conserves the timber elements that
remain in contact with it by keeping them Air humidity and health
dry. Normally, fungi or insects will not dam- Research performed by Grandjean (1973)
age such wood, since insects need a mini- and Beckert (1986) has shown that a relative
mum of 14% to 18% humidity to maintain humidity of less than 40% over a long period
1.16 life, and fungi more than 20% (Volz, 2004, p. may dry out the mucous membrane, which
48 hours 48 hours
1 Lime-sand brick 4 Solid brick 1 Clayey loam 4 Lime-cement plaster
2 Porous concrete 5 Porous hollow brick 2 Clayey loam plaster 5 Gypsum plaster
Temperature in °C 3 Cement concrete M 25 6 Clinker brick 3 Spruce, planed
1.17 1.18
can decrease resistance to colds and relat- The impact of air exchange on air humidity
ed diseases. This is so because normally the In moderate and cold climates, when the
mucous membrane of the epithelial tissue outside temperatures are much lower than
within the trachea absorbs dust, bacteria, vi- inside temperatures, the greater degree of
ruses etc. and returns them to the mouth by fresh air exchange may make indoor air so
the wavelike movement of the epithelial hair. dry that negative health effects can result.
If this absorption and transportation system For example, if outside air with a tempera-
is disturbed by drying, then foreign bodies ture of 0°C and 60% relative humidity enters
can reach the lungs and may cause health a room and is heated to 20°C, its relative
problems (1.16). A high relative humidity of humidity decreases to less than 20%. Even
up to 70% has many positive consequenc- if the outside air (temperature 0°C) had
es: it reduces the fine dust content of the 100% humidity level and was warmed up to
air, activates the protection mechanisms of 20°C, its relative humidity would still drop
the skin against microbes, reduces the life to less than 30%. In both cases, it becomes
of many bacteria and viruses, and reduces necessary to raise the humidity as soon as
odour and static charge on the surfaces of possible in order to attain healthy and com-
objects in the room. fortable conditions. This can be done by reg-
A relative humidity of more than 70% is nor- ulating the humidity that is released by walls,
mally experienced as unpleasant, probably ceilings, floors and furniture (1.17).
because of the reduction of oxygen intake by
the blood in warm-humid conditions. Increas- The balancing effect of loam on humidity
ing rheumatic pains are observed in cold Porous materials have the capacity to absorb
humid air. Fungus formation increases sig- humidity from the ambient air and to deso-
nificantly in closed rooms when the humid- rb humidity into the air, thereby achieving
ity rises above 70% or 80%. Fungus spores humidity balance in indoor climates. The
in large quantities can lead to various kinds equilibrium moisture content depends on
of pain and allergies. From these considera- the temperature and humidity of the ambi-
tions, it follows that the humidity content in a ent air (see 2.29, p. 28). The effectiveness
room should be a minimum of 40%, but not of this balancing process also depends upon
more than 70%. the speed of the absorption or desorption.
14 Introduction
@arclib
@arclib
48 hours 16 days
1.20 1.21
16 days Experiments conducted at the BRI show, for 3 × 4 m, a height of 3 m, and a wall area of
1 Silty loam 7 Lime-sand-brick
2 Clayey loam 8 Porous concrete
instance, that the first 1.5-cm-thick layer of a 30 m2 (after subtracting doors and windows),
(1900 kg/m³) 9 Loam with expanded mud brick wall is able to absorb about 300 g if indoor air humidity were raised from 50%
3 Straw loam clay
(1400 kg/m³) 10 Hollow brick
of water per m2 of wall surface in 48 hours if to 80%, unplastered mud brick walls would
4 Straw loam
(700 kg/m³)
11 Cement concrete the humidity of the ambient air is suddenly absorb about 9 litres of water in 48 hours. (If
M 15
5 Straw loam 12 Porous hollow brick
raised from 50% to 80%. However, limesand- the humidity were lowered from 80% to 50%,
(550 kg/m³)
6 Pine
13 Solid brick stone and pinewood of the same thickness the same amount would be released). The
absorb only about 100 g/m2, plaster 26 to same walls, if built from solid baked bricks,
1.19 76 g/m2, and baked brick only 6 to 30 g/ would absorb only about 0.9 litres of water
m2 in the same period (1.18). The absorp- in the same period, which means they are
tion curves from both sides of 11.5-cm-thick inappropriate for balancing the humidity of
unplastered walls of different materials over rooms.
16 days are shown in 1.19. The results show Measurements taken over a period of 5 years
that mud bricks absorb 50 times as much in various rooms of a house built in Germa-
moisture as solid bricks baked at high tem- ny in 1985, all of whose exterior and interior
peratures. The absorption rates of 1.5-cm- walls were built of earth, showed that the
1.17 Water vapour content of the air in relation to thick samples, when humidity was raised relative humidity remained nearly constant
temperature from 30% to 70%, are shown in 1.20. over the years, varying from 45% to 55%.
1.18 Absorption of samples, 15 mm thick, at a The influence of the thickness of a clayey soil The owner wanted higher humidity levels of
temperature of 21°C and a sudden increase of on absorption rates is shown in 1.21. Here 50% to 60% only in the bedroom. It was pos-
humidity from 50% to 80% we see that when humidity is raised sudden- sible to maintain this higher level (which is
1.19 Absorption curves of 11.5-cm-thick interior ly from 50% to 80%, only the upper 2 cm ab- healthier for people who tend to get colds or
walls with two sides exposed at a temperature of sorbs humidity within the first 24 hours, and flues) by utilising the higher humidity of the
21°C after a sudden rise in humidity from 50% to
that only the upper layer 4 cm in thickness adjacent bathroom. If bedroom humidity de-
80%
is active within the first 4 days. Lime, casein creased too much, the door to the bathroom
1.20 Absorption curves of 15-mm-thick samples,
and cellulose glue paints reduce this absorp- was opened after showering, recharging the
one side exposed, at a temperature of 21°C after
a sudden rise in humidity from 30% to 70% tion only slightly, whereas coatings of double bedroom walls with humidity.
1.21 Effect of the thickness of loam layers at a
latex and single linseed oil can reduce ab-
temperature of 21°C on their rate of absorption after sorption rates to 38% and 50% respectively,
a sudden rise in humidity from 50% to 80% as seen in 1.22. In a room with a floor area of
Prejudices against earth as a to handle as there are no sharp corners.” and bathrooms) can be dealt with by painting
building material The anxiety that mice or insects might live them with casein, lime-casein, linseed oil or
in earth walls is unfounded when these are other coatings, which makes them nonabra-
Owing to ignorance, prejudices against loam solid. Insects can survive only provided there sive. As explained on p. 129, bathrooms with
are still widespread. Many people have diffi- are gaps, as in “wattle-and-daub” walls. In earth walls are more hygienic than those
culty conceiving that a natural building mate- South America, the Chagas disease, which with glazed tiles, since earth absorbs high
rial such as earth need not be processed and leads to blindness, comes from insects that humidity quickly, thereby inhibiting fungus
that, in many cases, the excavation for foun- live in wattle-and-daub walls. Gaps can be growth.
dations provides a material that can be used avoided by constructing walls of rammed
directly in building. The following reaction by earth or mud bricks with totally filled mud
a mason who had to build an adobe wall is mortar joints. Moreover, if the earth con-
characteristic: “This is like medieval times; tains too many organic additives, as in the
now we have to dirty our hands with all this case of lightweight straw clay, with a density
mud.” The same mason, happily showing his of less than 600 kg/m3, small insects such
hands after working with adobes for a week, as wood lice can live in the straw and attack
said, “Have you ever seen such smooth ma- it. Common perceptions that loam surfaces
son’s hands? The adobes are a lot of fun are difficult to clean (especially in kitchens
16 Introduction
@arclib
@arclib
a_3_korr_an_bp_part_1 24.10.12 15:45 Seite 17
2
The properties of earth
as material
2 The properties of earth as a building a building material
on- 80
General ey soil. If it is more than 30% by weight, it is
Loam is a product of erosion from rock in
Percentage passing
high 70
General termed a rich clayey soil. Components that
w) 60 the earth’s crust. This erosion occurs mainly
50 Loam is a product of erosion from
through the mechanical grinding of rock via
rock in form less than 5% of the total by weight are
40 the earth’s crust.
the movement This
of glaciers, watererosion
and wind, occurs mainly not mentioned when naming the soils. Thus,
30
or through the
through thermal expansion andgrinding
mechanical contrac- of rock via for instance, a rich silty, sandy, lean clayey
20
tion of rock, or through the expansion of
10 the movement of glaciers, water and wind, or soil contains more than 30% silt, 15% to 30%
0 freezing water in the crevices of the rock.
0.002 0.006 0.02 0.06 0.2 0.6 2 6 20 60 through
Due to organicthermal expansion
acids prevalent in plants,and contraction sand, and less than 15% clay with less than
Grain size (mm)
of rock, chemical
moreover, or through reactionsthedueexpansion
to water of freez- 5% gravel or rock. However, in earth con-
and oxygen also lead to rock erosion. The
100
Clay Silt Sand Gravel
ing water in the crevices of the rock. Due to struction engineering, this method of naming
composition and varying properties of loam
90
organic
depend onacids prevalent
local conditions. in plants,
Gravelly moun- moreover, soils is less accurate because, for example,
80
chemical
tainous loams, reactions
for instance,due to water
are more suit- and oxygen a loam with 14% clay which would be called
Percentage passing
70
able for rammed earth (provided they con-
60
also lead to rock erosion. The composition lean clayey in soil mechanics, would be con-
50 tain sufficient clay), while riverside loams are
40 and varying properties of loam depend on lo-
often siltier and are therefore less weather-
sidered a rich clayey soil from the point of
30 cal conditions.
resistant and weakerGravelly mountainous loams,
in compression. view of earth construction.
20
Loam is a mixture of clay,
for instance, are more suitable silt and sand, and for rammed
10
sometimes contains larger aggregates like
0
earth (provided they contain sufficient clay), Clay
0.002 0.006 0.02 0.06 0.2 0.6 2 6 20 60 gravel and stones. Engineering science
Grain size (mm) while
definesriverside
its particles loams
accordingare often siltier and are
to diameter: Clay is a product of the erosion of feldspar
Clay Silt Sand Gravel
therefore less weather-resistant and weaker
particles with diameters smaller than and other minerals. Feldspar contains alu-
100 0.002 mm are termed clay, those between
90
in compression. Loam is a mixture of clay, minium oxide, a second metal oxide and sili-
0.002 and 0.06 mm are called silt, and
80 silt
thoseand sand,0.06
between andandsometimes
2 mm are called contains larger con dioxide. One of the most common types
Percentage passing
70
60
aggregates
sand. Particles oflike gravel
larger diameter and arestones.
termed Engineer- of feldspar has the chemical formula Al2O3 ·
gravels and stones.
50 ing science defines its particles according to K2O · 6SiO2. If easily soluble potassium com-
40 Like cement in concrete, clay acts as a
diameter: particles with diameters smaller
binder for all larger particles in the loam. Silt,
pounds are dissolved during erosion, then
30
20 than
sand and0.002 mm constitute
aggregates are termed clay,
the fillers in those be- clay called Kaolinite is formed, which has the
10 the loam.0.002
Depending on which
0
tween and 0.06 ofmm the three
are called silt, formula Al2O3 · 2SiO2 · 2H2O. Another com-
components is dominant, we speak of a
0.002 0.006 0.02 0.06 0.2 0.6 2 6 20 60 and those between 0.06 and 2 mm are mon clay mineral is Montmorillonite, whose
Grain size (mm) clayey, silty or sandy loam. In traditional soil
2.1 called sand. Particles of larger diameter are formula is Al2O2 · 4SiO2. There also exists a
17 Properties of earth termed gravels and stones. variety of less common clay minerals such
Like cement in concrete, clay acts as a bind- as Illite. The structure of these minerals is
er for all larger particles in the loam. Silt, shown in 2.2.
sand and aggregates constitute the fillers in Clay minerals are also found mixed with oth-
the loam. Depending on which of the three er chemical compounds, particularly with hy-
2.1 Soil grain size distribution of loams with
components is dominant, we speak of a drated iron oxide (Fe2O3 · H2O) and other iron
high clay content (above), high silt content clayey, silty or sandy loam. In traditional soil compounds, giving the clay a characteristic
(middle), and high sand content (below) mechanics, if the clay content is less than yellow or red colour. Manganese compounds
2.2
impart a brown colour; lime and magnesi- a logarithmic scale. The curve is plotted cu-
um compounds give white, while organic mulatively, with each grain size including all
substances give a deep brown or black col- the fine components.
our. Clay minerals usually have a hexagonal The upper graph characterises a rich clayey
lamellar crystalline structure. These lamel- loam with 28% clay, 35% silt, 33% sand and
las consist of different layers that are usually 4% gravel. The middle graph shows rich silty
formed around silicon or aluminium cores. loam with 76% silt, and the bottom graph a
In the case of silicon, they are surrounded rich sandy loam containing 56% sand. An-
by oxygenations; in the case of aluminium, other method for graphically describing loam
by hydroxyl (ions) groups (-HO). The layers composed of particles no larger than 2 mm
of silicon oxide have the strongest negative is shown in 2.4. Here the percentage of clay,
charge, which endows them with a high inter- silt and sand can be plotted on the three
lamellary binding force (2.3). Because each axes of a triangle and read accordingly. For
layer of aluminium hydroxide is connected example, the loam indicated by an asterisk
to a layer of silicon oxide, the double-lay- in this graph is composed of 22% clay, 48%
ered Kaolinite has a low ion-binding capac- silt and 30% sand.
ity, whereas with the three-layered mineral
Montmorillonite, one aluminium hydroxide Organic constituents
layer is always sandwiched between two Soil dug from depths of less than 40 cm
layers of silicon oxide, thereby displaying a usually contains plant matter and humus
higher ion binding capacity. Most of the clay (the product of rotting plants), which con-
minerals have interchangeable cations. The sists mainly of colloidal particles and is acid-
binding force and compressive strength of ic (pH-value less than 6). Earth as building
loam is dependent on the type and quantity material should be free of humus and plant
of cations. matter. Under certain conditions, plant mat-
ter like straw can be added, provided it is dry
Silt, sand and gravel and there is no danger of later deterioration
The properties of silt, sand and gravel are (see 10.3, p. 86).
totally different from clay. They are simply
aggregates lacking binding forces, and are Water
formed either from eroding stones, in which Water activates the binding forces of loam.
case they have sharp corners, or by the Besides free water, there are three different
movement of water, in which case they are types of water in loam: water of crystallisa-
rounded. tion (structural water), absorbed water, and
water of capillarity (pore water). Water of
Grain size distribution crystallisation is chemically bound and is
2.2 Structure of the three most common clay miner-
als (Houben and Guillaud, 1984) Loam is characterised by its components: only distinguishable if the loam is heated to
2.3 Lamellar structure of clay minerals (Houben and
clay, silt, sand and gravel. The proportion of temperatures between 400°C and 900°C.
Guillaud, 1984) the components is commonly represented Absorbed water is electrically bound to
2.4 Soil grain size distribution depicted on a on a graph of the type shown in 2.1. Here, the clay minerals. Water of capillarity has
triangular grid (Voth, 1978) the vertical axis represents weight by per- entered the pores of the material by capil-
2.5 Soil grain size distribution of two loams tested centage of the total of each grain size, which lary action. Absorbed and capillary water
in the sedimentation test in turn is plotted on the horizontal axis using are released when the mixture is heated
to 105°C. If dry clay gets wet, it swells be- attain maximum compaction, the earth must
cause water creeps in between the lamel- have a specific water content, the so-called
lary structure, surrounding the lamellas with “optimum water content”, which allows parti-
a thin film of water. If this water evaporates, cles to be moved into a denser configuration
the interlamellary distance is reduced, and without too much friction. This is measured
the lamellas arrange themselves in a par- by the Proctor test (see p. 42).
allel pattern due to the forces of electrical
attraction. The clay thus acquires a “bind- Tests used to analyse the
ing force” (see p. 30), if in a plastic state, composition of loam
and compressive and tensile strength after
drying. To determine the suitability of a loam for a
specific application, it is necessary to know
2.4 Porosity its composition. The following section de-
The degree of porosity is defined by the to- scribes standardised laboratory tests and
Sample Content by vision Real
tal volume of pores within the loam. More simple field tests that are used to analyse
% (vol.) % (mass) % (mass)
important than the volume of the pores are loam composition.
K1 Clay 45 14 6
the dimensions of the pores. The larger the
Silt 18 26 38
porosity, the higher the vapour diffusion and Combined sieving and sedimentation
Sand 37 60 56
the higher the frost resistance. Specific sur- analysis
K2 Clay 36 17 2
face The specific surface of a soil is the sum The proportion of coarse aggregates (sand,
Silt 24 19 16
of all particle surfaces. Coarse sand has a gravel and stones) is relatively easy to distin-
Sand 40 64 82
specific surface of about 23 cm2/g, silt about guish by sieving. However, the proportion of
2.5 450 cm2/g and clay, from 10 m2/g (Kaolinite) fine aggregates can only be ascertained by
to 1000 m2/g (Montmorillonite). The larger sedimentation. This test is specified in detail
the specific surface of clay, the higher the in- in the German standard DIN 18123.
ternal cohesive forces which are relevant for
binding force as well as compressive Water content
and tensile strength. The amount of water in a loam mixture can
be easily determined by weighing the sample
Density and than heating it in an oven to 105°C. If
The density of soil is defined by the ratio of the weight stays constant, the mixture is dry,
dry mass to volume (including pores). Freshly and the difference of the two weights gives
dug soil has a density of 1000 to 1500 kg/m3. the weight of all water not chemically bound.
If this earth is compressed, as in rammed This water content is stated as a percentage
earthworks or in soil blocks, its density var- of the weight of the dry mixture.
ies from 1700 to 2200 kg/m3 (or more, if it
contains considerable amounts of gravel or Simple field tests
larger aggregates). The following tests are not very exact, but
they can be performed on site relatively
Compactability quickly, and are usually exact enough to esti-
Compactability is the ability of earth to be mate the composition of loam and ascertain
compacted by static pressure or dynamic if the mixture is acceptable for a specific ap-
compaction so that its volume is reduced. To plication.
100
Fine Medium Coarse Fine Medium Coarse Fine Medium Coarse only a few centimetres, the m
90 little clay. This test is inaccura
Percentage passing
80 BRI it was known to have m
70
of greater than 200% if the
60
50 well-kneaded and the thickn
40 of the ribbon varied.
30
For this reason, a new, more
20
10 was developed in which a 2
0 and 6-mm-high profile was
0.001 0.002 0.006 0.01 0.02 0.06 0.1 0.2 0.6 1 2 6 10 20 60
80
70
ribbon, when it breaks unde
60 weight, is measured by push
50 over a rounded edge with a
40
30
of 1 cm (2.11, right). For each
20 five samples were taken and
10 measured at the point of rup
0
0.001 0.002 0.006 0.01 0.02 0.06 0.1 0.2 0.6 1 2 6 10 20 60 The longest rupture lengths
2.8 Grain size (mm) have been plotted in 2.12, ag
21 Properties of earth
2.9 2.10
2.11
23 Effects of water
@arclib
@arclib
at portion
Water content W
0.35 dropped until the groove is closed over a mixture, then the water content can be calcu-
ht of the length of 10 mm. lated using the following formula:
ntent can 5. The numbers of strokes are counted and a
0.30 L
formula: sample of 5 cm3 is taken from the centre in W 0=
1-A
order to determine the water content. When
0.25 the groove closes at 25 strokes, the water where W0 is the calculated water content, L
content of the mixture is equal to the liquid the determined water content LL or PL, and
content, limit. A the weight of grains larger than 0.4 mm ex-
0.20
LL or PL, 15 20 25 30 35 40
pressed as a percentage of the dry weight of
r than Strokes It is very time-consuming to change the wa- the total mixture.
ge of the 2.16 2.16 ter content repeatedly until the groove closes
2.16 Deriving the liquid
at exactly 25 strokes. A special method de- Plasticity index
limit by the multi-point
method according scribed in the German standard DIN 18122 The difference between the liquid limit and
Type of loam LL [%] PL [%] PI = LL–PL
to the German standard allows the test to run with four different wa- the plastic limit is called the plasticity index
sandy
DIN 18122 10–23 5–23 <5
d limit and ter contents if the number of strokes is be- (PI). The table in 2.17 gives some typical val-
silty 15–35
2.17 Plasticity index of 10–25 5–15
city index loams (after Voth, 1978)
tween 15 and 40. Illustration 2.16 shows ues for LL, PL and PI.
clayey 28–150 20–50 15–95
typical val- 2.18 Test assembly to how the liquid limit is obtained using these
Bentonite 40of 8 32
obtain the w -values four tests. The four values are noted in a di- Consistency number
loam samples (Boemans,
2.17 agram whose horizontal co-ordinate shows The consistency number (C) can be calculat-
1990)
the stroke numbers in a logarithmic scale, ed for any existing water content (W) of the
be calculat- and the vertical co-ordinate shows the water plastic stage by using the following formula:
t (W) of the Type of loam LL [%] PL [%] PI = LL–PL content as a percentage. The liquid limit is
ng formula: obtained by drawing a line through the four C = LL – W = LL – W
sandy 10–23 5–23 <5 LL – PL PI
values and reading the interpolated value at
–W silty 15–35 10–25 5–15 the co-ordinate of 25 strokes. The consistency number is 0 at the liquid lim-
I it and 1 at the plastic limit.
clayey 28–150 20–50 15–95
he liquid Plastic limit
Bentonite 40 8 32 The plastic limit (PL) is the water content, ex- Standard stiffness
2.17 pressed as a percentage, at the boundary be- As the definition of the plastic limit in Atter-
tween plastic and semisolid states. It is deter- berg is not very exact, Niemeyer proposes
mit in Atter- mined by means of the following procedure: “standard stiffness” as a basis for the com-
proposes the same mixture that was be used to define parison of mixtures of equal consistency.
Acrylic glass plate
the com- the liquid limit is rolled by hand onto a wa- The method for obtaining this stiffness is de-
Polyurethene foam
sistency. ter-absorbent surface (cardboard, soft wood scribed on p. 23.
Filter paper
ffness is or similar material) into small threads of
Loam sample
3 mm diameter. Then the threads are mould- Slump
Glass-fibre reinforced polyester layer
ed into a ball and rolled again. This procedure The workability of mortar mixtures is defined
Water
is repeated until the threads begin to crumble by the slump. This can be specified by a
es is 2.18 at a diameter of 3 mm. Ca. 5 g are removed method described in the German standards
e specified from this mixture and immediately weighed, DIN 1060 (Part 3) or DIN 1048 (Part 1). Here,
rman then dried to obtain the water content. This the mortar is poured through a standard fun-
IN 1048 test is repeated three times. The average nel onto a plate that is lifted and dropped by
2.16 Deriving the liquid limit by the multi-point
d through method according to the German standard value of three samples that do not deviate a defined type and number of strokes. The
at is lifted DIN 18122 by more than 2% is identical with the plas- diameter of the cake thus formed is meas-
and number 2.17 Plasticity index of loams (Voth, 1978) tic limit. As the liquid and the plastic limits ured in centimetres and is called the slump.
Acrylic glass plate have been defined using a mixture contain-
ake thus 2.18 Test assembly to obtain the w -values of loam
samples (Boemans, 1990) Polyurethene foam ing only particles smaller than 0.4 mm, the Shrinkage limit
es and is Filter paper
2.19 Water absorption coefficient ‘w’ of loams in test results must be corrected if larger grains The shrinkage limit (SL) is defined as the
Loam sample
comparison with common building materials have been sieved out earlier. If that portion is boundary between the semi-solid and solid
Glass-fibre reinforced polyester layer
2.20 Water absorption curves of loams
Water
less than 25% of the dry weight of the entire states. It is the limit where shrinkage ceases
2.18
25 Effects of water
25 Properties of earth @arclib
@arclib
Water absorption w (kg/m2)
Filter paper
Silicone seal
Sealing
Time t (min)
2.21 2.22 2.23
the German standard DIN 18952 (Part 2), to the weather, the clayey soil showed a spe- content and increasing shrinkage of a sandy
as follows: a prismatic sample is immersed cial kind of scaling caused by frost. This was mud mortar dried in a closed room at a tem-
5 cm deep in water and the time it takes for due to thin hairline cracks that appeared perature of 20°C and with a relative humidity
the submerged part to disintegrate is meas- during drying, and through which rainwater of ambient air of 81% and 44% respective-
ured. According to this standard, samples that was absorbed by capillary action. When this ly is shown in 2.26. With 44% humidity, the
disintegrate in less than 45 minutes are un- water freezes, its volume increases, causing drying took about 14 days, while with 81%
suitable for earth construction. But this test is the upper layers to burst. In areas where humidity, about 30. Illustration 2.27 shows
unnecessary for earth construction practices, no hairline cracks were found, this effect the drying process of different loam samples
since earth components would never be per- did not occur. Furthermore, no rain erosion compared to other building materials. In this
manently immersed in water in any case. Sig- was observed in these areas. The sample on test, conducted at the BRI, brick-size samples
nificant instead is resistance to running water. the left does not show this type of erosion were immersed in 3 mm of water for 24 hours
after 3 years. Here we see that some loam and then kept in a room with a temperature
Resistance to running water is washed away by rain, so that the horizon- of 23°C and relative humidity of 50% in still
During construction, earth building elements tal shrinkage crack is partially filled by these air conditions. Interestingly, all loam samples
are often exposed to rain and sensitive to particles, but no frost erosion is observa- dried out after 20 to 30 days, whereas baked
erosion, especially if still wet. It is important, ble. This is because there were no hairline clay bricks, sand-lime bricks and concrete
hence, to determine their resistance to run- cracks, and because the loam contained had not dried out even after 100 days.
ning water. To compare the degrees of resist- pores large enough to allow the freezing wa-
ance of different loam mixtures, the BRI de- ter to expand. Effects of vapour
veloped a test apparatus capable of testing The test resulted in the following conclusions:
up to six samples simultaneously (2.24). In • sandy loam has little resistance against While loam in contact with water swells and
this apparatus, water jets with diameters of rain, but is frost-resistant when free of cracks; weakens, under the influence of vapour it
4 mm are sprayed onto the samples from a • loam with high clay content tends to devel- absorbs the humidity but remains solid and
45° angle and with a velocity of 3.24 m/sec, op hairline cracks, and is therefore suscepti- retains its rigidity without swelling. Loam,
simulating the worst driving rain conditions ble to frost. If there are no hairline cracks, it hence, can balance indoor air humidity, as
in Europe. is almost rain-resistant. described in detail on pp. 13–16.
The higher the porosity and the larger the
Rain and frost erosion pores, the higher loam’s resistance to frost. Vapour diffusion
Illustration 2.25 shows two samples: each is Therefore, extruded common clay bricks pro- In moderate and cold climates where indoor
shown prior to testing (left), and after 3 years duced in a factory are not frost-resistant and temperatures are often higher than outside
of weathering (right). The earth mixture of the should not be used on outer exterior walls in temperatures, there are vapour pressure dif-
sample on the right contained 40% clay; the climates with frost. By contrast, handmade ferences between interior and exterior, caus-
one on the left was mixed with sand, reduc- adobes made from sandy loam are usually ing vapour to move from inside to outside
ing the clay content to 16%. Both mixtures frost-resistant. through the walls. Vapour passes through
were tested with a mortar consistency in walls, and the resistance of the wall material
single layers 5 cm in thickness. After drying, Drying period against this action is defined by the “vapour
large shrinkage cracks appeared. The clayey The period during which wet loam reaches diffusion resistance coefficient”. It is impor-
mixture showed 11% shrinkage, the sandy its equilibrium moisture content is called tant to know the value of vapour resistance
mixture only 3%. After 3 years of exposure the “drying period.” The decreasing water when the temperature difference between
0 0.5 0.5
0.3 0.3
Water content (g/m3)
2.5
0.1 0.1
0.0 0.0
2.25 Loam samples before (left) and after (right) LoamLoam with expanded
with expanded glassglass
500500 kg/m
kg/m 3 3
1°C.
LoamLoam with expanded
glassglass
750750 kg/m 3
being exposed to weather for 3 years with expanded kg/m 3
In 2.31, the
Clayey
Clayey loamloam plaster
plaster
2.26 Linear shrinkage and drying period of lean loam
SiltySilty
loamloam plaster
plaster DIN 4108-4
mortar (clay 4%, silt 25%, sand 71%) with a slump of Cowdung-loam-lime-sand
Cowdung-loam-lime-sand plaster
plaster (12/4/3/20)
(12/4/3/20)
42 cm according to the German standard DIN 18555 High High hydraulic lime plaster
hydraulic lime plaster shown. 2 ar
LimeLime plaster
plaster
(Part 2) Lime-casein
Lime-casein plasterplaster (10/1)
(10/1) 3 and 4 of t
Lime-linseedoiloilplaster
Lime-linseed plaster(20
(20/1)
2.27 Drying period of loams and other building
(( )) Volumetric
Volumetric proportion
proportion
At the BRI, a
materials 2.28 2.28
a density of
2.28 The vapour diffusion coefficient μ of different
on the inside due to the vapour barrier. 0.20 W/mK,
loams and plasters according to the German stand-
ard DIN 52615, wet method In this case, the wall remains damp for a ed clay loam
longer period than it would without a gave a value
27 Effects of vapour
@arclib
@arclib vapour barrier.
Specific hea
Influence of heat The amount
specific
Water content W (%) Water content W (%)
1 Clayey loam 5 Loam brick 1 Straw loam 450 kg/m3 6 Loam with expanded
2 Silty loam 6 Kaolinite, pulverised 2 Straw loam 850 kg/m3 clay 700 kg/m3
3 Sandy loam 7 Bentonite, pulverised 3 Straw loam 1200 kg/m3 7 Expanded clay particles
inside and outside is so high that the indoor rium moisture content”, which depends on
air condenses after being cooled down in the the temperature and humidity of the ambi-
wall. ent air. The higher temperature and humidi-
The German standard DIN 52615 describes ty levels are, the more water is absorbed by
the precise test procedure used to deter- the material. If temperature and air humidity
mine these values. The product of m with are reduced, the material will desorb wa-
the thickness of the building element s gives ter. The absorption curves of different loam
the specific vapour diffusion resistance sd. mixtures are shown in 2.29. The values vary
Still air has an sd-value of 1. Illustration 2.28 from 0.4% for sandy loam at 20% air humid-
shows some of the μ-values determined ity to 6% for clayey loam under 97% air hu-
by the BRI for different kinds of loam. It is midity. It is interesting to note that rye straw
interesting to note that silty loam has an under 80% humidity displays an equilibrium
μ-value about 20% lower than that of clayey moisture content of 18%. In contrast, ex-
and sandy loams, and that lightweight loam panded clay, which is also used to achieve
with expanded clay weighing 750 kg/m3 has lightweight loam, reaches its equilibrium
a value 2.5 times higher than that of loam moisture content at only 0.3%. In 2.30, four
mixed with straw and having the same over- values of loam mixtures are shown in com-
all density. Chapter 12 (p. 100) describes parison to the values of other common build-
how painting reduces the permeation of va- ing materials.
2.29 Absorption curves of solid (left) and lightweight pour through walls. Here, one can see that the higher the clay
(right) loams content of loam, the greater its equilibrium
2.30 Equilibrium moisture content of different loams Equilibrium moisture content moisture content. Additionally, it should be
and other building materials Every porous material, even when dry, has mentioned that Bentonite, which contains
2.31 U-values of loam a characteristic humidity, called its “equilib- 70% Montmorillonite, has an equilibrium
Specific
weight
U-value (W/mK) (kg/m3)
1 Spruce, planed
2 Limba, planed
3 Earth block, clayey
Lightweight loam
4 Earth block, silty
5 Cement plaster
6 Lime-cement plaster
7 Lime-casein plaster
8 Silty loam plaster
9 Clayey loam plaster
10 Solid brick
11 Clinker brick
Solid loam
12 Porous brick
13 Lime-sand brick
14 Porous concrete
moisture content of 13% under 50% humidi- tion to the surface of the walls, where it can Influence of heat
ty, whereas the equilibrium moisture content evaporate. Therefore, materials like loam with
of Kaolinite under the same conditions is a high capillarity are advantageous. The common perception that earth is a very
only 0.7%. In order to reduce the danger of condensa- good material for thermal insulation is un-
The graph shows that silty earth blocks or tion in walls, vapour transmission resistance proven. A solid wall of rammed earth without
adobes (no. 4 on the graph) reach a mois- should be higher inside than outside. On straw or other light aggregates has nearly
ture content five times higher than a sandy the other hand, resistance to heat transfer the same insulating effect as a solid wall of
loam plaster (no. 9 on the graph) at a relative should be higher outside than inside. Though baked bricks. The volume of air entrained
humidity of 58%. the above principles normally suffice to in- in the pores of a material and its humidity
It should be noted that for the humidity bal- hibit the formation of condensation in walls, are relevant for the thermal insulation effect.
ancing effect of building materials, the speed it is also possible to create a vapour barrier The lighter the material, the higher its ther-
of absorption and desorption processes is on the inside by utilising paints or sheets. mal insulation, and the greater its humidity
more important than the equilibrium mois- It should be mentioned, however, that vapour level, the lower its insulating effect.
ture content, as explained on p. 12. barriers have two important disadvantages. The heat flowing through a building element
• Vapour barriers are never fully sealed in is defined by the overall heat transfer coeffi-
Condensation practice, especially at joints, as in walls with cient U.
In moderate and cold climatic zones, the water doors, windows and in ceilings. Harmful con-
vapour contained in indoor air diffuses through densation can occur in these joints. Thermal conductivity
the walls to the exterior. If the air is cooled down • With monolithic wall sections, water pen- The heat transfer of a material is charac-
in the walls and reaches its dew point, conden- etrates in the rainy season from the outside terised by its thermal conductivity k [W/
sation occurs. This dampness reduces thermal into the wall, and then cannot evaporate on mK]. This indicates the quantity of heat,
insulation capacity and may lead to fungus the inside due to the vapour barrier. In this measured in watts/m2, that penetrates a
growth. In such cases, it is important that this case, the wall remains damp for a longer pe- 1-m-thick wall at a temperature difference
humidity be transported quickly by capillary ac- riod than it would without a vapour barrier. of 1°C.
29 Influence of heat
@arclib
@arclib
In 2.31, the different k-values according to only temperature amplitude. In climates with
DIN 4108-4 (1998), indicated by a 1, are hot days and cold nights, where average tem-
shown. 2 are measurements of (Vanros, peratures lie within the comfort zone (usu-
1981), 3 and 4 of the BRI. ally 18° to 27°C), thermal capacity is very
Temperature °C
The comfort zone for Cairo The thermal capacity (heat storage capacity) times greater in the concrete house than in
S of a material is defined as the product of the earth house. In the concrete house, tem-
specific heat c and the density r: peratures at 4 pm were 5°C higher than out-
Outdoor air
side, whereas inside the earth house, they
temperature S = c · ρ[kJ/m3K] were 5°C lower than outside temperatures
at the same time (Fathy, 1986).
Time of day
The thermal heat capacity defines the
2.32 amount of heat needed to warm 1 m3 of ma- Thermal expansion
terial by 1°C. The heat storage capacity Qs The expansion of a material caused by rais-
for a unit area of wall is S multiplied by the ing its temperature is relevant for mud plas-
Measurements in mm
thickness s of the element: ters on stone, cement or brick walls, and for
lime or other plasters on earth walls. The
Qs = c · ρ · c [kJ/m2K] coefficients of linear expansion measured by
the BRI for heavy loam range from 0.0043
Heat intake and release to 0.0052 mm/m·K; for mud brick masonry
The speed at which a material absorbs or up to 0.0062 mm/m·K; and for sandy mud
releases heat is defined by the thermal dif- mortar up to 0.007 mm/m·K. Soft lime mor-
2.33 fusivity b which is dependent on the specific tar has a value of 0.005 mm/m·K, and strong
heat c, density r and the conductivity k: cement mortar 0.010 mm/m·K, the same as
2.32 Comparison of indoor and outdoor air tempera- concrete (Knöfel, 1979 and Künzel, 1990).
ture of a building with adobe vaults (above) with one b = √c · ρ · k [kJ/Km2h0.5 ]
using prefabricated concrete slabs (below) (Fathy, Fire resistance
1986) The larger the b-value, the quicker the pene- In the German standard DIN 4102 (Part 1,
2.33 Mould for preparing test samples for the bind- tration of heat. 1977) loam, even with some straw content,
ing strength test according to the German standard
is “not combustible” if the density is not less
DIN 18952
Decrement factor and time lag than 1700 kg/m3.
2.34 Test apparatus to measure the binding force,
“Decrement factor” and “time lag” refer to
developed at the BRI
the way the exterior wall of a building reacts Strength
2.35 Relation of the binding force to the permissible
to damp and to the period of delay before out-
compressive stress in loam elements, according to
Niemeyer side temperatures reach the interior. A wall Binding force
2.36 Relation of binding force to compressive
with a high thermal storage capacity creates The tensile resistance of loam in a plastic
strength of various test loams according to Gotthardt, a large time lag and heat decrement, while state is termed its “binding force”. The bind-
1949, and tests of the BRI a wall with high thermal insulation reduces ing force of loam depends not only on clay
Cushioning effect in dB /
2.41 Amount of abrasion 99.99%
of different earth plasters
body as they are absorbed by the skin, but
2.42 Apparatus to mea- can be inhaled by breathing and, therefore,
30
sure the strength of 99.9%
may cause lung cancer. The following table
corners against dynamic
Specific weight Compressive showscompressive
Allowable the exhalation
forcerate of radon
[kg/cm 2
] given
impacts 20 strength
2.43 Shelter effect of dif- 99% by the OECD (1979) for Germany, measured
[kg/m3] [kg/cm2] wall column height/thickness
ferent building materials
11
in m12becquerel/kg
13
h. 14 15
against high-frequency 10
90% 1600 20 3 3 2 1
electromagnetic radiation
1900 30 4 4 3 Natural
2 gypsum1 25.2
0 2200 40 5 5 4 Cement
3 2 57.6 1
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0
Sand 54.0
2.37 Frequency in GHz
Baked clay bricks 5.0
1 Vegetation roof with 16 cm of substrate, 20 cm Lime-sand bricks 13.3
it has athermal
certain significance
insulation, when
24 cm green bricks judging
(earth blocks) the loaded by a weight of about 5 kg, and move
2 Vegetation
Porous concrete 18.0
quality of mudroof as in 1, without
mortar and thegreenedge
bricks rigidity of it over the loam sample from side to side.
mud3bricks.
24 cm green bricks (1600 kg/m , 15 cm loam plaster) 3
The material that comes off after a certain
Strength [N/mm2] 4 2 cm tensile
lime plaster, 25 cm lightweight loam (800 kg/m ), 3 This shows that a clay brick from a clayey
Bending strength depends main- number of cycles is weighed and compared
Compression Bending Tension 1.5 cm loam plaster soil discharges very little radon.
tension ly on5 the10 cmclay content
lightweight and
loam block (1400the
kg/mtype) of the 3
with that of other samples. A plate covered
3
6 17.5 cm porous concrete (500 kg/m )
Green Brick A 3.5 1.1 0.4 clay minerals involved. Montmorillonite clay 3
with sand paper can also be used in place of
7 24 cm hollow bricks (1200 kg/m )
Green Brick B 4.4 1.3 0.5 has 8 a much higher bending (1800 kg/mtensile strength 3 a metal brush. At the BRI, a special test for
24 cm lime-sand-stone )
Shelter against high-frequency elec-
Green Brick C 6.1 1.6 0.6 than9 Kaolinite.
1.3 cm tile The lowest value investigat- loam surfaces was developed: a strong plas-
10 aluminium sunshade element tromagnetic radiation
Mortar D 2.02 0.69 0.21 ed 11 by metal
Hofmann, Schembra et. al. (1967)
insect grid (1x1 mm mash)
tic brush of 7 cm diameter is rotated on the
Mortar E 2.63 0.85 0.35 with12Kaolinite
double glazing,reached 1.7 kg/cm2, the high-
gold film covered surface under a pressure of 2 kg. After 20
2.43 Illustration 2.43 shows the differing degrees
2.38 est with Montmorillonite clay 223 kg/cm2. cycles, the amount of abrasion is weighed.
of effectiveness of solid building materials in
2.41
Clays without Montmorillonite tested by Illustration 2.41 shows the apparatus and
screening (reducing) high-frequency electro-
Hofmann, Schembra et. al. (1967) showed 2.39 the results with different earth plasters
Samples Abrasion in g pH-value magnetic radiation, as measured at the Uni-
0.5 1.0 1.5 2.0 2.5 3.0 3.5
tensile bending strengths between 17 and available on the German market.
versity of the Federal Armed Forces at
918 N/cm2.
0.7 Clayey soil is usually basic, with pH-values Munich.
Loam mortars
bricks.
tion, On caused
probably the contrary, some
by additives like flybricks tested screening (reducing) high-frequency electro-
60
99.9999% ash or blast furnace slag.
by this author exhibited muchMuch more impor-
more radia- magnetic radiation, as measured at the Uni-
tant than the beta and gamma rays are the
50
tion, probably caused by additives like fly versity of the Federal Armed Forces at Mu-
99.999% alpha rays emitted by the radioactive gas
ash and
radon or blast furnace
its short-lived slag.
decay Much more im-
products. nich. In the area of 2 gigahertz frequencies
portant
The than
“soft” rays the penetrate
cannot beta and thegamma
human rays are at which most cellular (mobile) phones are
Cushioning effect in dB / %
40
99.99%
the asalpha
body rays
they are emitted
absorbed by thebyskin,
thebutradioactive working, a 24-cm-thick mud brick wall cre-
can be inhaled by breathing and, therefore,
gas radon and its short-lived decay products. ates a reduction of 24 dB (decibels), where-
30
99.9%
may cause lung cancer. The following table
The “soft” rays cannot penetrate the human as an equal tick wall of a lime-sand stone
shows the exhalation rate of radon given
20 body as they are absorbed by the skin, but
by the OECD (1979) for Germany, measured
only absorbs 7 dB.
99%
It is not always easy to produce building ma- The easiest way to prepare the right loam
terial out of a clayey soil, and experience is mixture is by mixing the wet loam with a hoe
required. The right preparation depends on or moulding it with the feet. Animal power
the type of earth, its consistency and its ex- can also be used. Straw, chaff, coarse sand
pected application. and other additives can be mixed during the
Moist crumbled earth with less clay and more same operation.
sand content can be used immediately to At the Building Research Institute – BRI at the
build a rammed earth wall even as it is dug University of Kassel in Germany, an effective
out. Clods of earth with high clay content can- mud wheel was built (3.1) in which two pairs
3.1 not be used as a building material; they must of old truck tyres were filled with concrete
either be crushed or dissolved in water and and used to prepare the mixture. The tyres
thinned with sand. This chapter describes were mounted on a horizontal beam fixed to
the different possibilities of preparing earth a vertical central post and powered by a trac-
for specific applications. tor or by animal or manual power. With an
adequate addition of water, 1 m3 of usable
Soaking, crushing and mixing loam could be produced in about 15 minutes
(with the help of two or three people, mainly
There are several methods available for to scoop the overflowing mud back into the
making workable building material out of track). If a tractor is available, it is easy and
clods of earth. One of the easiest methods more effective to simply spread earth on a
for reducing the size of clods and making field and drive back and forth over it.
their consistency workable without mechan- For small quantities, a small garden cultiva-
ical labour is to place the earth clods in wa- tor is very useful (3.2). In modern earth con-
ter so that they can become plastic on their struction technology, forced mixers are used.
own. The loam-clods are placed in large flat Here, the mixing is done with the help of re-
containers in a layer 15 to 25 cm high and volving arms that are fixed either to a vertical
then covered with water. After 2 to 4 days, (3.3) or horizontal axis (3.6). It is convenient
a soft mass is obtained which can be easi- to have a mechanical device for filling this
ly moulded and mixed by hand, feet or ma- mixer, as seen in 3.5.
chines, together with aggregates such as Old mortar mixing machines can also be
sand and gravel. used, like ones that have rotating rollers
In cold climates where there is sufficient frost, (3.4). The machine in 3.6 was specially devel-
a traditional method is to stack the moistened oped for preparing loam from any kind of soil
earth 20 to 40 cm high and allow it to freeze (by the German firm Heuser). A quicker meth-
over winter so that disintegration occurs due od of preparing a loam from dry clods of clay-
to the expansion of freezing water. ey soil is to crush them in a machine (3.8).
34 Preparing of loam
@arclib
@arclib
3.3
3.6
3.7 3.8
36 Preparing of loam
@arclib
@arclib
As a rule, it is only necessary to modify the
hence the shrinkage ratio. The results of this
characteristics of loam for special applica-
method are shown in 4.2 and 4.3. In 4.2, a
tions. As we can see in 4.1, additives that
loam with 50% clay and 50% silt content
improve certain properties might worsen
was mixed with increasing amounts of sand
others. For instance, compressive and bend-
until the shrinkage ratio approached zero.
44 Improving
Improving
4 Improving the earth’s characteristics by special thecharacteristics
characteristics
treatment
the earth’s
of loam
by special treatment
ing strength can be raised by adding starch
To insure comparability, all samples tested
and cellulose, but these additives also
were of standard stiffness (see chapter 2,
Without
Linseed oil 3%
or additives
ISOFLOC 2%
Shrinkage
byorspecial
additives treatment or additives
Cellulose 0.5 %
Cellulose 0.75 %
Binding force
shrinkage ratio, which is disadvantageous.
0.1% is reached at a content of about 90%
Whey 2 %
Whey 4 %
e clayey loam cellulose, but these additives also reduce 2 mm diameter with 90% to 95% pure Kao-
Linseed oil 3%
ISOFLOC 2%
Shrinkage
e strength reduce the binding force4.3 andReduction
increase the strength p. 22). Interestingly, a shrinkage ratio of
Cellulose 0.5 %
g strength Compressive
of shrink- reduce the binding force and increase the p. 22). Interestingly, a shrinkage ratio of
Gelatine 0.5 %
Gelatine/Alum 0.5 %
by adding sand
force to a Thinning Bentonite, consisting of 71% Montmoril-
Binding
shrinkage ratio, which is disadvantageous. 0.1% is reached at a content of about 90%
Whey 2 %
Whey 4 %
4.14 4.15
The compressive and binding strengths of application of floor wax increase abrasion
Kaolinite can be significantly increased by resistance considerably.
adding urea and ammonium acetate (Weiss, A traditional German recipe that produces a
1963). Weiss also suggests that the high hard-wearing, strong surface is a coating of
bres always increase compressive strength as straw, reeds, seaweed, cork and other
is false. When fine fibres or hair are added in light plant matter. Naturally or artificially
small amounts, tensile strength – and there- foamed mineral particles like pumice, lava,
fore compressive strength – is increased expanded clay, foamed glass, expanded per-
Silty loam : Sand = 6 : 4
slightly. The addition of cut straw, however, lite and foamed plant matter like expanded
has the opposite effect, as shown by inves- cork can also be added. Waste products like
tigations carried out at the BRI (see table sawdust, wood shavings, husk of grains can
Bentonite :
Kaolinite :
Sand 0- 4
Sand =
1:9
1:9
47 Lightweight loams
@arclib
@arclib
Na2O (5% to 10%). Expanded lava is similar ods of preparing and handling this mixture
to expanded perlite of volcanic origin, except are explained in greater detail in chapter 10.
that its bulk density is higher.
Pumice is a naturally porous stone that has Thermal insulation
already been “expanded” during its forma- The thermal insulation properties of light-
tion in a volcano. Its bulk density usually var- weight mineral loam depend mainly on its
ies from 500 to 750 kg/m3. density and are equal to that of lightweight
straw loam if the density is higher than
Mixing 600 kg/m3. For mixtures below 600 kg/m3,
While forced mixers are usually required to the thermal insulation properties of light-
produce loam mixtures (see chapter 3, p. weight mineral loams are somewhat better
35), lightweight mineral loam can be pro- than those of lightweight straw loams, since
duced in an ordinary concrete mixer. There, straw has a higher equilibrium moisture con-
aggregates can be placed in advance and tent, and therefore more moisture, which
the loam slurry poured over it. The mix is reduces insulation. The equilibrium moisture
ready in 3 to 5 minutes. The slurry needs to content of rye straw at a relative humidity
have a rich clay content and binding force. of 50% and a temperature of 21°C, for in-
The production of loam slurry is described in stance, is 13%, whereas under the same
chapter 3, p. 36. conditions, it is only 0.1% in the case of ex-
panded clay.
Grain size distribution
The grain size distribution of mineral aggre- Embodied energy
gates affects the properties of lightweight It is often argued that artificially foamed
mineral loam. For example, a density as mineral aggregates like expanded clay re-
low as 500 kg/m3 can be reached with quire considerable energy for production. In
expanded clay fractions of 8 to 16 mm di- this context, one should be aware that the
ameter. The quantity of loam slurry has to embodied energy of timber or bricks used in
be designed so that the volumes between construction is much higher. The embodied
aggregate particles are not completely energy of timber is computed to be 6 times
filled, that is, the aggregates are only glued as high as that of mineral wool, and twice as
together at points of contact. This density high as expanded clay for the same volume
of 500 kg/m3 can be reached if 2.5 parts (Turowski, 1977; Weller and Rehberg, 1979;
of loam are added to 12 parts of expanded Elias, 1980; Marmé and Seeberger, 1982).
clay (8 to 16 mm). However, blocks of this In making an overall assessment of the con-
mixture have a low edge and surface rigid- struction energy entailed by a given project,
ity. A stronger mixture is obtained with 24 then, we must remember that while it may
parts expanded clay (8 to 16 mm), 5 parts be technically true that loams with artifi-
expanded clay (1 to 2 mm), and 5 to 7 parts cially expanded minerals use more energy
loam. The density reached by this mixture than those containing other aggregates, this
will be 640 to 700 kg/m3. To achieve higher difference is negligible when compared, for
density, expanded clay fractions 4 to 8 mm instance, to the total energy input involved
can be chosen, adding enough loam to fill in the processing, production and transpor-
all spaces between the aggregates. In this tation of timber.
case, it is advantageous to thin the loam
with coarse sand. Lightweight cork loam
Expanded cork can be used to form light-
Handling weight loam in place of porous mineral ag-
Lightweight mineral loam, unlike lightweight gregates. The advantage of expanded cork
straw loam, can be poured or even pumped is its low density. The disadvantage is that
if the mix is chosen accordingly. The meth- this material is relatively expensive and has
49 Lightweight loams
@arclib
@arclib
5 Rammed earthworks
On all five continents, rammed earth has de terre or terre pisé in French; the Spanish
been well-known for centuries as a traditional names are barro apisonado or tapial; and the
wall construction technique. In fact, rammed German word is Stampflehmbau.
earth foundations found in Assyria date back Traditional rammed earth techniques are still
as far as 5000 BC. used in many developing countries. Refined
With rammed earth techniques, moist earth formwork systems and electrical or pneumat-
is poured into a formwork in layers of up to ic ramming reduces labour input significantly
15 cm thick, and then compacted by ram- and makes rammed earth techniques rele-
ming. The formwork usually consists of two vant in some industrialised countries as well.
parallel walls separated and interconnected For ecological, and sometimes for economic
by spacers (5. 1). This technique is called pisé reasons as well, mechanised rammed earth
50 Rammed earthworks
@arclib
@arclib
5.2
5.3
51 Formwork
@arclib
@arclib
5.6 5.7
the form should not be wrenched off, but in- flat bases (5.8). If conical or wedge-shaped
stead slipped off the rammed earth smooth- rams are used, the different layers are bet-
ly along the surface, thus preventing it from ter mixed and, provided there is sufficient
being spoiled by clayey particles sticking to moisture, a better bond is obtained. Howev-
the form. Furthermore, it is neither desirable er, this takes more time than ramming with
to have a surface that is too rough (such as flat-based rams. Walls rammed with flat-
saw-cut timber), nor one that is too smooth based rams show less lateral shear resist-
(such as varnished and planed timber). ance and therefore should only be loaded
If the formwork is not optimised for this tech- vertically. The base of the ram should not be
5.8 nique, then up to 30% of total labour input too sharp, so that the formwork, if made of
could be invested simply in erecting, adjust- timber, is not damaged. The base should be
ing, and dismantling the formwork. Therefore, no smaller than 60 cm2, and no larger than
the following points should be borne in mind: 200 cm2. The weight of the ram should be
• Boards must be stiff so that they do not between 5 and 9 kg. It is preferable to use
bend outwards while ramming is underway. a two-headed ram with a round head on one
• All parts must be light enough to be carried side and a square one on the other. This al-
by two workers. lows the ram to be used with the round side
• The formwork should be easy to adjust in for general work, and with the square edge
both vertical and horizontal directions. to compact corners effectively. Such a ram
• Variations in the thickness of the wall must can be found even today when labour costs
be controllable within a specified tolerance. are low (5.7).
• It is preferable that the edges require no Electric and pneumatic rams were used as
special formwork. Therefore, the formwork early as the second quarter of the 20th cen-
should allow varying lengths of wall to be tury in Germany, France and Australia. In
cast. Australia in the 1950s, a pneumatic ram was
used (5.9). It acted like a jackhammer, had
Tools a frequency of 160 strokes per minute, and
weighed 11 kg. A petrol hammer, as manufac-
In former times, earth was rammed manual- tured for instance by Wacker Neuson, can be
ly, using rams with conical, wedge-shaped or used together with a ramming shoe (5.10 and
52 Rammed earthworks
@arclib
@arclib
5.9
5.12 5.13
5.11). The ram is very effective; its only disad- fore, there is a higher shrinkage in the upper
vantage might be difficulty in handling, since course than in the lower, leading to horizon-
it weighs 24 kg. Normally, soil compaction tal shrinkage cracks at the joint (5.14). This
tools of the type used in road construction are can be dangerous, since capillary water can
unsuitable for rammed earthwork, because enter this joint and remain, causing swelling
their frequency is too high and their lift too and disintegration. As can be seen in the
low. Tools which only vibrate might be suitable same figure, vertical cracks can also occur
5.10 5.11 for sandy soils, but not for clayey ones. in such walls.
All the rams illustrated require a pressure of With the French pisé technique, this problem
6 bar and an air flow rate of 0.4 to 0.9 m3/ was solved by using a layer of lime mortar
min. Due to their high costs and the infra- above each course before laying a new one.
structure and energy required to run them, A lime mortar cures over several weeks and
these rams are used only for larger building remains plastic until the loam has stopped
projects. An electrical vibration ram was de- shrinking; sometimes even the side joint be-
veloped at the BRI and manufactured for a tween sections of the course is made with
while by the German firm Heuser (5.12). Its mortar at an incline (5.15).
engine had a frequency of 1000 to 1200 cy- Another method to avoiding horizontal
5.14 cles per minute. The most important part of shrinkage cracks is to ram in a way that the
this vibrating ram was its specially shaped wall is produced vertically. This is described
base, which allowed the apparatus to move in greater detail below.
within the formwork by itself while compact-
ing the earth. It could compact loose soil in Shaping of openings
layers 7 cm thick.
5.6 The circular barn, Bollbrügge, Germany (1831) The formwork can be dismantled immediate-
5.7 Two-head ram used at low-cost housing project Method of construction ly after ramming is completed. At the same
in Ecuador time, this rammed earth can be shaped
5.8 Rams used for manual compacting In nearly all traditional rammed earth easily by scraping, cutting, scooping or
5.9 Pneumatic ram, Australia techniques, the formwork is removed and scratching. Normally, inserts are left in the
5.10 Petrol hammer BH 65 (by Wacker Neuson) re-erected horizontally step by step. This formwork to create openings. However, with
5.11 Ramming shoe for petrol hammer (by Wacker means that earth is rammed in layers from rammed earth, the opening can be cut with
Neuson) 50 to 80 cm high, forming courses of that much less effort with a knife or a barbed
5.12 Vibrating ram (by Heuser) height before the formwork is moved. When wire used as a saw. This technique also al-
5.13 Slicing rammed earth directly after the form- one course is complete, the next course that lows shaping of jambs and sills, as shown
work is dismantled is rammed is moister than the one already in 5.13. It should be mentioned that at this
5.14 Shrinkage cracks in a rammed earth wall in place, which is partially dried out. There- stage rammed earth has already achieved
53 Method of construction
@arclib
@arclib
5.15
5.16
sufficient strength to grip nails (they can be The formwork is spaced at the bottom with Earth was filled into the forms by a dumper
driven into the wall without making a guiding only a steel bar, which leaves a very small and compacted by a pneumatic ram. By this
hole with a drill). hole after dismantling. The top space is po- means, the labour input could be as low as
sitioned above the top level of the wall and 2 h/m3. In Australia, several firms are also
Wall construction techniques does not interfere with the process. As the using this type of highly mechanised con-
figures show, it is possible to use either a sim- struction process (5.23 and 5.24). Illustra-
Rammed earth panels pler solution with a timber spacer on top fixed tion 5.25 shows a church in Margaret River
In order to prevent horizontal shrinkage to the vertical members, thus forming a yoke, designed by Hodge and Wilson and built by
cracks at the vertical joints in traditional or a more sophisticated version made from the firm Ramtec. As seen in 5.26, even the
rammed earth construction, a new tech- steel, which also allows fine adjustments of columns supporting the roof structure are
nique was developed at the BRI for produc- distance at the top. The first building using made from rammed earth.
ing one-storey-height panels, with widths of this technique was built at the University of In 1992, the Kooralbyn Valley Hotel was
up to 2.4 m, in a continuous ramming pro- Kassel in 1982 (5.22). The soil contained built in Australia by Ramtec (Greenway Archi-
cess. This technique avoids horizontal joints, about 10% clay and about 50% sand. The tects: I. Hannaford, F. Raadschelders and D.
and the vertical joints that occur are closed earth was compacted by a vibrating ram Oliver), where all walls were made of unplas-
only after the shrinkage is complete. For (5.12). The linear shrinkage of these ele- tered rammed earth (5.27).
lateral stability, the vertical joints are made ments was only 0.4%. After drying, the joints
in a tongue-in-groove pattern. No shrinkage were filled with a loam stabilised with 8% Pre-cast rammed earth panels
cracks occur within the panels for these siz- double-boiled linseed oil. A roof overhang of An innovative development, also by Rammed
es. The reduction of length due to shrinkage 60 cm and a plinth of 50 cm were sufficient Earth Works in Redding, California, for non-
is only visible at the joint. (The joint acts like to ensure that the wall did not erode and that load-bearing applications are thin pre-cast
a pre-designed contraction joint). In order to it required no surface treatment. panels, only 76 mm thick (5.19). The recep-
avoid a formwork that would have to be an tion area of Stadium Tech Center office build-
entire storey in height, a slip form was devel- Mechanised rammed earth construction ing in Santa Clara (5.20) consists of four
oped at the BRI. Illustration 5.18 shows the The firm Rammed Earth Works from Red- panels stacked on top of each other, each
design in steel, while 5.16 and 5.17 show a ding, California, has built several rammed 5 m high and 6.7 m long. These panels are
later design in wood (which proved easier to earth houses utilising a special formwork cast in the factory and allow for relatively fast
work with). made of thick plywood, as shown in 5.21. production. They are also an option when the
54 Rammed earthworks
@arclib
@arclib
5.17 5.19 5.20
5.18
5.22
5.21
5.26
56 Rammed earthworks
@arclib
@arclib
Plaster Plaster Plaster
Plaster
5.28
Plaster Bricks
Soil blocks
5.29
footprint is too small to accommodate an on- is directly plastered. In this case the form- tria, the USA and Germany, for instance, built
site rammed earth wall with a depth of 46 work is only required for the outer face. In the walls with prefabricated elements. They were
to 60 cm. second case, a somewhat better stiffness of produced in a factory or in a locally built-up
the inner adobe or soil block leaf is attained sheltered production line. The advantages
Wall construction with lost formwork due to the bonding pattern in the compo- of this technique is a reduced erection time,
As with rammed earth techniques, the cost nents. In the section shown on the right, the so that normally no special weather shelter
of the formwork is quite high. In some cas- lost formwork is on the outside and is made is needed. The disadvantage are the higher
es, it is preferable to use a thin masonry wall from stabilised lightweight soil blocks. Illus- costs. A recent example built in Germany by
or stiff thermal insulation elements made of tration 5.29 shows vertical sections of ex- the Austria-based company Lehm Ton Erde
wooden materials as lost formwork, so that ternal walls that have lost formwork on both Baukunst was the Alnatura office building in
either no formwork or only one-sided form- sides. The inner leaf can be made from ado- Darmstadt (pp. 224–227) where a tempo-
work is required. It is also advantageous if bes or soil blocks, larger prefabricated loam rary field factory was established (5.30). The
this formwork can contribute to a substantial elements, or stiff plywood boards, fibre-rein- company started to experiment with prefab-
increase in thermal insulation. The stiffness forced gypsum boards, or Magnesite or ce- ricated parts in 1997 and by 2015 already
of this lost formwork has to be sufficient to ment-bonded wood particleboard. Protection one third of its work relied on prefabrication.
take care of the lateral impacts created by of the wall surface against the elements can Instead of gradually ramming the material
ramming. Illustration 5.28 shows horizontal be achieved by plaster, masonry or timber into the formwork at the building site, wall
sections through an external wall. The first panelling with air cavity. segments are prefabricated and then as-
two cases show an inner leaf built of adobes sembled on site (Rauch, 2020). To reduce
or soil blocks and an outer rammed earth lay- Prefabricated rammed earth elements the amount of formwork required, a so-called
er made with lightweight mineral loam which In recent years, companies in France, Aus- endless wall (5.31 and 5.32) is produced in
5.32
5.34
5.33
58 Rammed earthworks
@arclib
@arclib
the workshop. After removing the formwork, ration, transportation and construction, is
the endless wall is cut into smaller wall ele- from 20 to 30 h/m3. By refining the formwork
ments (5.33). These are lifted up and then system and using an electrical vibrator, la-
re-installed on the construction site (5.34). bour input is reduced to 10 h/m3. With the
mechanised techniques explained before
Rammed earth domes (see p. 54), in which transportation and fill-
ing is done by a dumper and compacted by
5.35 Probably the first rammed earth dome was heavy pneumatic rams, labour input can be
built by the BRI in Kassel, Germany, in 1983 reduced to as little as 2 h/m3, which is only
using a special technique developed by that 10% of the labour used with traditional tech-
laboratory. This consists of a rotating slip niques, and significantly less than that need-
form in which the earth is rammed (5.35 to ed for masonry work.
5.37).
The thickness of the dome was 18 cm Thermal insulation
at the bottom and 12 cm at the top. The
walls, which form a hexagon on the inside, The thermal insulation capacities of solid
were also made of rammed earth. In order rammed earth walls using normal soil is not
to transfer the thrust from the dome to the sufficient to provide the levels of thermal in-
foundation, buttresses were integrated with sulation required in cold climates. The U-val-
the walls. The shaping of the top of the but- ue of a 30-cm-thick rammed earth wall is
tresses as well as the windows was done as much as 1.9 to 2.0 W/m2K. To achieve a
5.36 with a kitchen knife soon after the formwork U-value of 0.5 W/m2K, necessary in many Eu-
was dismantled. The formwork of the wall ropean countries, a thickness of 1.6 to 1.8 m
was custom-designed according to the plan would be required. In cold climates, there-
of the dome, as seen in 5.35. The earth was fore, either a thick wall of lightweight loam
rammed into the formwork using a vibrator, or additional conventional thermal insulation
described on p. 53 in this chapter (5.12), should be used. Some potential methods
and by hand. for making loam walls with improved ther-
The dome formwork itself was so designed mal insulations are described in chapter 14,
that it could be lifted not just at the centre, p. 111.
course after course; it also had a guide that
automatically adjusted the radius and incli- Surface treatment
nation of the formwork (5.37).
A rammed earth wall requires less labour
Drying and material inputs for surface treatment
compared to walls made using other earth
It is seldom possible to say when a loam construction techniques. As a rule, it is nei-
5.37 wall is dry, but the drying process is in any ther necessary nor advisable to plaster a
case faster than those of masonry or con- rammed earth wall. If the surface is sponged
crete walls (see chapter 2, p. 26). Given dry with a moist felt trowel immediately after
5.30 Field factory for the production of prefabricated
rammed earth elements
warm weather and sufficient air movement, dismantling the formwork, then a smooth
shrinkage stops after just a few days. After surface is easily produced, one that may be
5.31 and 5.32 Compaction of the earth mixture in
the formwork 3 weeks, the wall feels completely dry, al- painted or wallpapered (in cases involving
5.33 Cutting the prefabricated rammed earth wall though water content is still slightly higher interior wall surfaces). If exterior surfaces
into sections than the equilibrium moisture content. thus treated are sheltered from rain by roof
5.34 Lifting the cut elements into place overhangs and against splashing by a plinth,
5.35 Rammed earth test structure, University of Labour input a coating of paint is sufficient to protect them
Kassel, plan and section against the elements. Care should be taken
5.36 and 5.37 Constructing the rammed earth dome The labour input in traditional rammed earth that coatings neither peel nor crack.
with a rotating formwork walls constructed manually, including prepa-
6.1
6.3 6.2
permits simultaneous production of three Fully automatic presses are only economical
blocks. Manually operated presses of this if they have long lives, are utilised extensively
type produce pressures up to 5 to 25 kg/ on a daily basis, and if raw material of even
cm2, and require three to five persons for consistency is available locally and in suffi-
optimum operation. Despite mechanised cient quantities. Otherwise, capital, mainte-
production of soil blocks using presses, nance and repair costs quickly diminish any
the output per person per day is only 150 potential economic advantages. In low-wage
to 200 blocks, considerably less than that countries, manual adobe production is usu-
of the primitive method involving throwing ally more economical, as is the production of
loam into moulds. The manual block press green bricks in brick plants in industrialised
shown in 6.13 can yield up to 800 blocks countries. In industrialised countries, brick
daily. The advantage of these mechanised production using such machines would be
presses, however, is that loams with lower economical only if transportation costs were
water contents can be used. This makes it high.
possible to stack blocks immediately after The production method developed in the
6.9 production. The disadvantage is that the USA by Hans Sumpf and patented in 1946,
blocks are usually stabilised with a 4% to and consisting of a block making apparatus,
8% cement content in order to endow them seems comparatively more efficient (6.14
with sufficient strength. This is necessary and 6.15). With this method, loam is pre-
because of the absence of either sufficient pared to a pasty consistency in a forced mix-
water or adequate dynamic impact capable er and then poured into a large funnel that
of significantly activating the binding forc- moves over a grid of moulds. The moulds are
es of the clay minerals. Without cement, filled, and the top and the blocks are then
pressed blocks usually have dry a compres- smoothed mechanically. A lever lifts this
sive strength lower than that of handmade grid, leaving the separated blocks to dry on
adobes (see p. 42). the ground. After a preliminary drying period,
Another disadvantage of such presses is the blocks can be turned on their edges for
that the soil mix must be kept at a constant even drying.
6.10 level of moisture and composition. If compo- In mechanised brick plants, crushed soil
sitions vary, then both the volume of the ma- is mixed and pushed by rollers into an ex-
terial to be filled and the pressure changes. truder, where it is again mixed and pressed
This leads to variations in the heights and through a vacuum-operated mouthpiece into
strengths of the blocks. long profiles, which are then sliced by a wire.
Fully automatic block-making presses such Drying is accomplished in ovens using com-
as the one shown in 6.12 can produce 1300 mercial energy. Since this entire process is
blocks in 8 hours. However, they require large computerised in industrialised brick plants,
investments and may be difficult to maintain, it may be difficult to order green bricks, and
especially in developing countries. To assure the prices quoted are sometimes more than
even loam consistencies, such machines of- those for ordinary fired bricks.
ten require separate crushers and mixers.
Percentage passing
70
60
50
40
30
20
10
0
0.001 0.002 0.06 0.01 0.02 0.06 0.1 0.2 0.6 1 2 6 10 20 60 100
Grain size (mm)
6.20
6.22
Clay Silt Sand Gravel 6.21 Grain si
Fine Medium Coarse Fine Medium Coarse Fine Medium Coarse
100 tion curve of
90 in a brick plan
6.22 Optimis
80
size distributi
Percentage passing
70
for adobes
60 6.23 Expose
50 block wall fin
40 with a loam-l
30 Bendigo, Aus
20 6.24 Booksh
to an earth b
10
6.25 Industri
0 produced unb
0.001 0.002 0.06 0.01 0.02 0.06 0.1 0.2 0.6 1 2 6 10 20 60 100
lightweight b
Grain size (mm)
6.19 6.21
If the blockscomposition
Material are dipped in water for a short Surface
minimumtreatment
shrinkage. But at the same time,
timeloam
The to make used theinsurface
common softbrick
and pliable,
plants itre- there must be enough clay to create sufficient
becomes possible to build
quires high clay content in order to achievewalls from earth Ifbinding
sufficiently
forcemoistened
for the block withto a tool like a
be handled.
blocks without
sufficient strengthusingafter mortar.firing.
TheseIllustration
soaked felt trowel, exposed earth block masonry
blocks can be simply stacked
6.20 shows a typical soil grain size distribu- , as with any with uneven
Laying surfaces
earth blocksor joints can be easily
dry of
tion masonry
this type work,
of loam,and they will bind.
containing 24%Suchclay, smoothened. Plastering is not advisable,
50% silt, 23% sand and 3% gravel. and
work, however , requires a very fine eye When since
It is itimportant
interferes towith the capacity
shelter of loamfrom
earth blocks
skilledofworkmanship,
loam this composition for it isisdifficult
used for to con-
earth walls to balance internal air humidity
rain on site. In industrialised countries, (see as
trol the horizontal joints and
block work, it creates swelling and shrinking the pattern, chapter
a rule, 1,green
p. 14).bricks
However , exposed
ordered fromearth
factories,
6.22
since no tolerance
problems upon wetting of mortarandthickness is
drying respec- block masonry can , if not aesthetically
are palletised and covered entirely in plastic.
available.
tively. Illustration 6.19 shows cracks occur- acceptable,
Earth blocks be are
given
laida with
washeither
of loam
loam slurry
mortar,
Earthwhen
ring blocksthese can be green cut much
bricksmore wereeasily
used in stabilised
hydraulicwith , for
lime example,
mortar lime, lime-
or high-hydraulic lime
than baked bricks , using
a project where a wall was drenched ordinary sawsby, for
sud- casein
mortar. etc.While
(6.23). small
This wash also impacts
quantities of cement
example, as seen
den rain during construction. in 6.20. If parts of blocks the
may wall’s
be surface
added stability
to these (formortars,
more details
pure ce-
are required
The soil grain , theysize candistribution
either be sawed right
of a leaner about
ment mortar is not advisable, as it is12,
surface treatment , see chapter too rigid
through , or else cut to depths
sandy loam appropriate for earth blocks is of about p.and
100).
brittle. To avoid shrinkage cracks inside
2 cm, after
shown in 6.21.which It sections
shows 14% can be clay,broken
22% silt, the mortar during drying, the mortar should
off with the tap of
62% sand and 2% gravel, and showsa hammer. In place of a no contain sufficient quantities of coarse sand.
saw, a groove can also be
shrinkage cracks after drying. Generally, scored with a it The clay content may vary from 4% to 10%.
trowel
can be or a knife
stated that before
earthusing
blocks theshould
hammer. have The formation of shrinkage cracks can also
enough coarse sand to allow them to achieve be avoided when the mortar layer is thinner
high porosity (and therefore high frost resist- than usual. It is a pleasure to work with loam
ance), and high compressive strength with mortar, since it is not abrasive to the skin.
64 Working with earth blocks
64 Working with earth blocks
@arclib
@arclib
6.23 6.24
Lime mortar, however, attacks the skin and p. 14). However, exposed earth block mason-
may also cause allergies. ry can, if not aesthetically acceptable, be giv-
If the blocks are dipped in water for a short en a wash of loam slurry stabilised with, for
time to make the surface soft and pliable, it example, lime, limecasein etc. (6.22). This
becomes possible to build walls from earth wash also impacts the wall’s surface stability
blocks without using mortar. These soaked (for more details about surface treatment,
blocks can be simply stacked, as with any dry see chapter 12, p. 100).
masonry work, and they will bind. Such work,
however, requires a very fine eye and skilled Fixing fasteners to walls
workmanship, for it is difficult to control the
horizontal joints and the pattern, since no Nails can be driven into an earth block walls
tolerance of mortar thickness is available. more easily than into those constructed
Earth blocks can be cut much more easily of baked bricks. The more porous and hu-
than baked bricks, using ordinary saws, for mid the material, the easier one can drive
example, as seen in 6.17. If parts of blocks a nail through it. Green bricks tend to split
are required, they can either be sawed right more easily than soil blocks and adobes. If
through, or else cut to depths of about 2 cm, very thick nails are used, it is advisable to
after which sections can be broken off with drill a hole into the block. Heavy shelves or
the tap of a hammer. In place of a saw, a wallhung cabinets can be fixed to the wall
6.19 Shrinkage cracks that occurred after rain-
groove can also be scored with a trowel or a easily using screws and dowels. Dowel holes,
drenched green bricks dried out
knife before using the hammer. however, should be drilled large enough to
6.20 Grain size distribution curve of loam used in a
prevent blocks from cracking. In 6.23, heavy
brick plant
6.21 Optimised grain size distribution curve for
Surface treatment bookshelves are fixed to a green brick wall
adobes using dowels and screws.
6.22 Exposed earth block wall finished with a loam-
If sufficiently moistened with a tool like a felt
lime slurry, Bendigo, Australia trowel, exposed earth block masonry with un- Lightweight earth blocks
6.23 Bookshelves fixed to an earth block wall even surfaces or joints can be easily smooth-
6.24 Industrially produced unburned lightweight
ened. Plastering is not advisable, since it So-called lightweight loam blocks have a
bricks with aggregates such as straw, saw dust or interferes with the capacity of loam walls to specific weight of less than 1200 kg/m3 and
cellulose fibres. balance internal air humidity (see chapter 1, consist of clayey soil with light aggregates
65 Surface treatment
@arclib
@arclib
6.25
6.26
6.27 6.28
such as straw, saw dust, cellulose fibres, absorption is produced by the cut-off joints
cork, perlite, pumice or expanded clay. Due and the holes in the brick. For domes con-
to their good thermal insulation effects, they sisting of adobes the author optimised the
are used for exterior walls in cool or cold cli- shape further by making the adobes slight-
mates. Illustration 6.24 shows some of these ly conical, i.e. the end of the brick is wider
unburned bricks that are produced industri- than the front in order to save mortar and to
ally in Germany. increase the stability of the dome. The end
is given an inclination to achieve a smooth-
Special acoustic green bricks and er outside surface of the dome (6.26). Illus-
adobes tration 6.27 shows the interior texture of a
dome with acoustic adobes. Additional ex-
6.25 Special loam brick to improve acoustic In order to optimise the acoustic behaviour amples of the use of acoustic adobes are the
behaviour of domed rooms, a special extruded loam Residence in Emboscada (pp. 168–169), the
6.26 Optimised adobe shape for domes (acoustic brick with rounded corners was developed Village Nursery in Bellingdon (pp. 190–193)
adobe) by the author (6.25). The rounded corners and the Adobe Dome Music Space in Aiguá
6.27 Interior view of a dome with acoustic adobes and the corbelling effect of the bricks (6.28) (pp. 198–201).
6.28 Detail of loam brick dome yield good sound distribution, while sound
With monolithic rammed earth walls, or even ferent sections for larger wall panels made
with small-sized brick masonry, manpower is of lightweight mineral loam, and developed
high and drying time can delay construction by the author of this book, are shown in 7.5.
work due to the inherent water. Therefore, These can be used either in internal walls,
several ideas involving larger prefabricated or to increase the thermal insulation of exte-
elements have been developed. rior walls from the outside. Cavities reduce
weight and increase thermal insulation,
Large blocks while simultaneously providing grip holds
for easy handling. Illustration 7.6 shows sim-
7.1 Provided they are light enough to be carried ilar elements that can be used for making
in one hand, or at most in both, larger blocks vaults.
can be laid faster. Lightweight aggregates A recent product are the thermal insulation
and cavities can be used to reduce weight. boards made of expanded glass and loam
For easy handling, grip holds should be incor- by Lehmwerk Kleinfahner in Germany. They
porated in block shapes. have a gross density of only 500 kg/m³.
Lightweight straw blocks, 50 × 60 × 30 cm, They are 5.5 cm or 9.5 cm thick and meas-
used in several projects by the German ar- ure 24.5 × 61 cm (7.9). The firm also pro-
chitect Sylvester Dufter, are more efficient vides smaller lightweight earth blocks with
for making walls. Though each block weighs the same density, measuring 24 × 17.5 ×
26 kg, they are produced under cover and 11.5 cm (7.10).
close to the wall, and can then be almost
flipped over into their final positions (7.1 and Earth-filled wall panels
7.2). Using such blocks, a 50-cm-thick wall
gives a U-value of 0.3 W/m2K. Dufter guid- Illustration 7.7 shows a wall built with “Kar-
ed several do-it-yourself projects using these phosit” elements, which were produced from
blocks. In one case, the owner-builder family clay powder and straw cuttings, and had a
7.2 produced 1500 blocks in 5 weeks, sufficient density of 850 kg/m3. They measured 62.5
for their entire house. × 25 × 10 cm. Until a number of years ago,
Lightweight mineral loam blocks measur- the German firm HDB Weissinger produced
ing 15 × 15 × 30 cm, which are made of 1-m-wide and up to 3-m-high timberframe
loam and expanded clay (7.4), have been wall elements filled with lightweight loam
produced in Hungary utilising egg layers (of (7.8). Several houses were built with these
the type used in making concrete blocks). wall elements.
7.1 Making lightweight straw loam blocks Such blocks were used to provide addition-
7.2 Exterior wall made of large blocks of lightweight al external thermal insulation to a rammed
straw loam earth wall house in Tata, Hungary (7.3). Dif-
7.5 7.6
7.7 7.8
69 Clay panels
@arclib
@arclib
7.14 7.15
7.16 7.17
7.18 7.19
7.20 7.21
7.22
71 Heating panels
@arclib
@arclib
7.23 7.24
7.25 7.26
thor of this book developed load-bearing infill hardness. Tests at the Building Research In-
elements with cement-stabilised lightweight stitute – BRI showed that a high degree of
loam. Illustration 7.25 shows such an ele- surface hardness could be obtained by add-
ment along with its mould. Illustration 7.24 ing 6% double-boiled linseed oil in conjunc-
depicts various designs for load-bearing floor tion with compacting the surface and using
panels. floor wax as a polish. Methods of increasing
surface hardness are described in chapter
Floor tiles 14, pp. 113–114.
8.1
8.2
Unlike other building materials, wet loam has shrinkage was not taken into account. The
the capacity to be formed into any shape. It following sections explain how pre-designed
therefore presents a creative challenge to shrinkage cracks of smaller dimensions, or
designers and builders. The manual shaping the use of curved elements can help to re-
of walls from lumps of wet loam or thick loam duce or even avoid such cracks. The theory
paste is widespread in Africa and Asia, and involving reducing shrinkage by modifying
is also known in Europe and America. Since loam composition is explained in chapter 4,
no tools are required to work with earth, it is p. 37.
the simplest and most primitive technique.
The prepared mixture is used directly (with- Traditional wet loam techniques
out intermediate products being formed or
intermediate processes). Its disadvantage is While in the case of earth block work, dry
that even lean loam of only 10% to 15% clay elements are built up with mortar joints, no
shows linear shrinkage of 3% to 6% when mortar is used with wet loam work. Plastic
drying. The higher the clay content and the loam is bound simply by ramming, beating,
more water employed, the greater the shrink- pressing or throwing.
age. Thick loam paste with high clay content In southern India, a very simple wet loam
may even have a linear shrinkage ratio of technique is still in use today: using a hoe,
8.1 Forming a bench from wet loam above 10%. Illustrations 8.1 and 8.2 show a earth is mixed with water to a pasty consist-
8.2 Shrinkage cracks in the same bench after drying bench formed with wet loam elements where ency, carried to the site in metal containers
8.4 8.5
balanced on the worker’s head, and poured A technique of building using loam clods
on the wall being built. It is then spread by called “cob” was widespread in southwest
hand in layers from 2 to 4 cm thick. As the England beginning in the 15th century, and
paste dries fairly quickly in the sun, the wall was used at least until the 19th century,
can be built continuously, layer by layer. especially in Devon. In 1843, Hill described
In northeast Ghana, another technique is this technique as follows: a man stands with
used. Here, balls of wet earth are formed and a three-pronged pitchfork on the plinth of the
then used to construct circular walls simply wall, while a second man forms clods as large
by stacking and pressing (8.3 and 8.4). Af- as two fists. The second man then throws the
ter the wall dries, the surface is plastered on clods to the first one, who catches them on
8.6 both sides and then smoothed and polished his pitchfork and, walking backwards, throws
using flat stones in a rotary rubbing move- them onto the wall. Where necessary, he also
ment. Illustration 8.5 shows a compound compacts the wall with his feet. In this way,
built using a similar primitive technique. layers 50 to 60 cm in height are built up. To
In northwest Ghana, 40-cm-thick walls have give an even finish, the surface is sliced. Wall
been constructed with wet loam clods using thicknesses are generally 45 to 60 cm (Mc-
another traditional technique. Here, they are Cann, 1983; Streiff et al., 2020). Illustration
built up in layers so that each successive 8.12 shows a house, one still inhabited, at
layer slightly overlaps the previous one (8.6). Cockington (Devon, England) that was built
8.3 and 8.4 Making walls using balls of wet earth,
The rooms of these houses are more or less using this technique in 1410.
northeast Ghana (Schreckenbach and Abankwa,
1983)
rectangular, and have rounded corners (8.8). A similar technique called Wellerbau, has
In north Yemen, multi-storeyed houses have been known in German since medieval times,
8.5 Nankansi courtyard house, north Ghana
been built using a wet loam technique called and was especially widespread in Thuring-
8.6 Traditional wet loam construction, northwest
Ghana (Schreckenbach and Abankwah, 1983) zabur (8.7, 8.9 and 8.10). Here, clods of ia and Saxony. Here, the straw loam is not
8.7 Multi-storeyed houses made using the zabur
straw loam are shaped by hand and thrown formed into clods as in the cob technique,
technique, Yemen with strong impact to build the wall in such nor compacted by throwing as with the za-
8.8 Typical Lobi dwelling, northwest Ghana, plan and a way that they are compacted and adhere bur technique, but is directly stacked with a
section (Schreckenbach and Abankwa, 1983) to the base, forming a homogenous mass. pitchfork and then compacted using feet or
8.9 and 8.10 Construction of a loam wall, using the The surface is often beaten and compacted rams (8.11). The wall is built up in layers of
zabur technique by hammering with a kind of wooden trowel. 80 to 90 cm. After a short drying period, the
8.8
8.20 8.21
8.23 8.24
thus formed is divided into 3 parts with ver- exterior walls. The space between the two
tical timber elements 4 × 4 cm in section at extruded loam walls can be filled with light-
0.7 m/centres. They act as tongues fitting weight bulk material such as cork particles,
into the loam elements to provide lateral sta- expanded clay, pumice etc., to increase ther-
bility. In order to ensure separation of these mal insulation. Structural elements can also
elements during the drying process a cut is be positioned in this space. If the other walls
made with a trowel, so that the joints act as illustrated need to be provided with thermal
pre-designed contraction joints. Upon drying, insulation, a common solution is given in
this gap widens due to shrinkage, and can be 8.31, the U-value of the illustrated wall being
favourably filled when dry with a mixture of 0.295 W/m2K.
lime, gypsum, sand and loam. It is very easy Illustrations 8.25, 8.27 and 8.28 show work
to smooth the surface of these elements with done on a residential house in Germany,
a moist sponge (8.22), though to get a richly with smaller extruded loam profiles obtained
textured and a regular effect (as seen in the from a brick manufacturing plant. Due to the
8.25 photographs), more shaping by hand may be production process, this loam had to have
done before sponging. Illustration 8.24 and higher clay content, causing a large number
8.25 show finished walls. Walls composed of shrinkage problems; repairing the cracks
of these elements can be shaped easily in that occurred turned out to be very time-con-
a wet state; a finished example is shown in suming.
8.23, where material has been added to the
wall, as well as sculpted out of it.
Wall types
Due to shrinkage of 3% to 5%, long ele-
ments are not recommended. Illustration
8.26 shows several possibilities for internal
and external walls using shorter elements.
Solution C in this figure is only intended for
8.27 8.28
Plastic loam has been used for thousands ping a 10 cm diameter ball from a height of
of years to fill gaps in log houses where the 1 m onto a hard surface. If the diameter of
logs are laid horizontally, as well as in pali- the flattened disc thus formed measures 13
sades (where the tree trunks are positioned to 14 cm, the consistency is just right.
vertically). In traditional European Fachwerk Illustrations 9.2 and 9.5 show a variation of
(timber-framed) houses, as well as in Amer- the wattle-and-daub technique in which the
ican, African and Asian wattle-and-daub size of the mesh is larger (up to 20 cm apart),
9.1 structures, wet loam (usually containing cut and there is an exterior and an interior net-
straw) is thrown on an interwoven mesh of work. The spaces in the grid thus formed are
twigs, branches, bamboo sticks and the like filled in with clods of loam. Coarse gravel or
(9.1). As shown in this chapter, there exist even stones are sometimes also used as in-
many variations of this technique. Modern fill. The type of wall shown in 9.5 is construct-
techniques of infill that use mechanical de- ed of prefabricated components, and was
vices to reduce labour input are described in used in several low-cost housing projects in
this chapter. Bahia, Brazil.
Thrown loam techniques have been used in Since wattle-and-daub techniques are very
all tropical, sub-tropical and moderate cli- labour-intensive, various attempts have been
mates of the world, and are probably older made to use spraying machines to apply mix-
than rammed earth and earth block practices. tures. The main problem with all of these
These wattle-and-daub techniques are called techniques has been the common occur-
bahareque, bajareque, bareque or quincha in rence of shrinkage cracks.
Spanish and lehmbewurf in German. The German architect Hans-Bernd Kraus
Such structures consist of vertical and hori- developed a technique in which a thin loam
zontal members that form a network. Euro- mixture is sprayed simultaneously together
pean systems usually employ vertical timber with dry sawdust (from a separate nozzle).
members interwoven with twigs (9.4). Loam, Both sprays intermix before hitting the wall.
usually mixed with cut straw, and sometimes Layers 4 to 6 cm thick are sprayed on wood-
9.2 with fibres, is thrown or pressed onto this net- wool slabs used as a lost formwork. The
work so that it covers at least 2 cm of all the wood-wool slabs also provide considerable
members. If this cover is not thick enough thermal insulation (9.6). Another sprayable
and cracks are not wellrepaired, walls quick- lightweight loam used for enhancing the
ly deteriorate (9.3). The consistency of the thermal insulation of walls is described in
mortar being used is easily checked by drop- chapter 11, p. 94.
9.4
Rolls and bottles of straw loam tles”. Here, secondary vertical members are
fixed 15 to 20 cm apart within the frame. The
In Germany and France, openings in the “bottles” are made by taking 1.5-litre mass-
frameworks of traditional timber-framed es of the mixture and dropping them onto
houses are sometimes filled in with ele- the centre of a cross made of two bundles of
ments formed by rolling straw loam around a straw. The ends of the bundles are then lifted
wooden batten, as seen in 9.7 and 9.8. This up around the loam, which formed into bot-
9.5 is less labour-intensive then the wattleand- tle-like shapes and covered with loam. The
daub technique, and has the added advan- bottle is then held horizontally, and the neck
tage that hardly any shrinkage cracks occur. wound around the vertical member, while
Two main systems are used: either a loam the bottom is pressed against the neck of
dipped straw rope is wound helically around the previous bottle.
a batten, or a straw mat pasted with loam
is rolled onto a batten. The labour inputs of Lightweight loam infill
these techniques is still higher than those
using “loam strand” techniques (see chapter Since they fail to provide sufficient thermal in-
8). A variation of the rolling technique was sulation, the traditional techniques described
successfully tested at the Building Research in earlier sections cannot be used in modern
9.6 Institute – BRI. It used a loam mortar with a construction in cold climates. To provide ther-
high coarse sand content, which was pasted mal insulation, the frames can be filled with
onto a metal or plastic wire mesh (common- lightweight loam mixtures (or the exterior
9.1 Traditional pit house of the Pueblo Indians, 3rd ly used for reinforcing mortars). The loam covered with layers of commonly used ther-
century AD, (Bardou and Arzoumanian, 1978) was pasted onto the mesh in a thickness of mal insulation materials). This technique has
9.2 Variations of wattle-and-daub technique 2 cm, and both were rolled around a bam- the advantage of less labour input and no
(Vorhauer, 1979) boo stick to form infill elements (9.9 to 9.11). shrinkage whatsoever. Systems with greater
9.3 Traditional wattleand- daub building, Venezuela Surprisingly, shrinkage cracks nevertheless thermal insulating effects are shown in chap-
9.4 Traditional wattleand- daub technique, Germany occurred with this technique. ter 14, p. 111. The lightweight additives are
9.5 Prefabricated wattle-and-daub system, Brazil Illustration 9.12 depicts the traditional Ger- described in chapter 4, pp. 46–49.
9.6 Spraying lightweight loam man technique of building with “loam bot-
9.10 9.11
Infill with stranglehm and earth- ment (up to 30% of the cement content) the
filled hoses percentage of this mixture increases to 12%.
The earth should be free from organic mate-
Modern solutions of filling the openings in rial and have a relatively uniform mixture of
timber skeleton structures or timber-framed aggregates, ranging from gravel of no more
houses with stranglehm or earth-filled hoses than 12 mm diameter.
are described in chapter 8, p. 75 and chap- Soil and cement are well mixed and then con-
ter 10, p. 90. veyed via high-pressure air. Water is added to
A very recent development in the application the dry mix at the nozzle of the spraying gun.
of loam infill involves the spraying of loam by For a 38 mm hose, for instance, the compres-
means of a spray gun system. sor must produce 21 m3 of air per minute.
9.8 As a rule of thumb the operating pressure,
Sprayed loam in steel-reinforced which is the pressure at the material outlet or
walls and ceilings air inlet on the gun, should not be less than
275 kPa when the hose is 30 m or shorter.
David Easton, founder of Rammed Earth The wall formwork should be in place a mini-
Works in Napa, California, uses a system mum of 12 hours prior to stripping.
of constructing earthquake-resistant earth The architect Marcelo Cortés from Chile has
walls by spraying a mixture of earth, cement developed a technique involving spraying
and water over a steel reinforcement struc- of loam for the construction of earthquake-
ture against a formwork, as shown in the resistant structures, which he calls “Quincha
residence for himself and Cynthia Wright metálica” – quincha being a traditional con-
in Napa Valley, California, in 1995 (9.13 to struction system that uses wood and cane
9.18). The cement content is normally 10%. to forme a framework that is covered in mud
If fly ash or slag is added in order to save ce- and plaster. The structural system is a steel
9.20
9.21
skeleton, which is covered on both sides by this technique. The lime content, which nor-
steel reinforcement mats (9.20). He then mally is 10% of the mix, has two effects: it
sprays a mixture of clayey soil, wheat straw, improves the stability of the infill after curing
sand, lime and water against a formwork that and its high pH-value prevents corrosion of
is fixed onto the back of the steel structure, the steel structure. In climates of high hu-
so that all the space between the mats is midity the steel structure can be covered by
9.19 Machine for mixing and pumping filled (9.21). Even ceilings can be made by a bituminous emulsion or by epoxy resin.
9.20 Spraying process
9.21 Filled-in wall before plastering (Residence in
Santiago, Chile, architect Marcelo Cortéz)
This chapter introduces several techniques This could be done with a board on the out-
that use lightweight loam by tamping, pour- side, in which case the mixture can be thrown
ing or pumping for floor, wall or roof systems. onto it from the inside by hand or with a trowel.
The different types of lightweight loams are
examined in chapter 4, while chapter 9 dis- Tamped lightweight straw loam
cusses how lightweight loam can be used as walls
infill for timber-framed and skeleton struc-
tures. Sprayed plasterwork is described in The preparation of the mix is described in
chapter 11. Special designs for walls which chapter 4, p. 44. The mixture is thrown into
provide high insulation are discussed in the formwork in layers 10 to 20 cm in height
chapter 14, and additional thermal insula- either by hand or (more usually) with a pitch-
tion measures using lightweight loam are fork, and compacted with lightweight hand
addressed in chapter 13. tampers.
It should be mentioned that lightweight loam
Formwork mixtures tend to settle, so that the gaps that
10.1 form must be inspected and later refilled.
Lightweight loam walls can be constructed The 1-m-high test element shown in 4.21,
using any type of formwork, but since less p. 49, displayed settling of 9%. It should also be
impact is involved than with rammed earth- mentioned that when working with very light
work, the shuttering boards can be thin- mixtures (with densities below 600 kg/m3)
ner. Five different possibilities are shown and with walls more than 25 cm in thickness,
in horizontal section in 10.1. The fastening the straw might rot in the interior of the wall. Il-
of the formwork panels or formwork boards lustration 10.3 shows an example of a 30-cm-
depends on whether the load-bearing tim- thick wall built of lightweight straw loam with
ber supports consist of a rectangular (A) or a density of 350 kg/m3. After some months,
round post (B), plank supports (C) or dou- when the outside appeared to be complete-
ble-T supports (D). For thinner walls and ly dry, the core was chased for an electrical
thicker walls with a high proportion of straw, installation, and was found to be rotting.
horizontal profiles should be clamped or Even the structural timber member had been
nailed between the vertical elements every attacked by micro-organisms to depths of
40 to 80 cm to stiffen the wall (D, E). 2 cm (Schmitt, 1993). With lightweight walls,
10.2 In order to reduce the number of boards, wood lice may also appear and eat the straw.
climbing formwork is often used. Four types of Therefore, it is always advisable that the
10.1 Horizontal sections with different inbuilt timber this system are illustrated in 10.2. When work- stacks of straw are totally sealed by the loam,
elements ing with lightweight mineral loam, it is even which means that the mixture should have a
10.2 Systems of climbing formworks possible to use only a one-sided formwork. density of more than 600 kg/m3.
10.6
10.5 10.7
10.8 10.10
Tamped lightweight wood loam straw loam and wood loam. Various miner-
walls al lightweight aggregates are described in
chapter 4, p. 47.
Wood chips and sawdust are often used
as lightweight aggregates instead of straw. Tamped walls
These are easier to mix with the loam, but Illustration 10.4 shows the construction of a
10.3 Cut-out from lightweight straw loam wall with
have a lesser degree of thermal insulation low-cost housing prototype in Pujili, Ecuador,
rotted interior effect, and drying takes a very long time. using pumice as lightweight aggregate mixed
10.4 Ramming an earth wall of loam and pumice, in the loam and lightly tamped into a form-
low-cost housing project, Pujili, Ecuador Tamped, poured or pumped light- work. The formwork was immediately dis-
10.5 Shaping a window sill using a machete weight mineral loam walls mantled after the wall was finished. The wall
10.6 Mixing lightweight mineral loam showed a high degree of strength, although it
10.7 Pouring lightweight mineral loam Lightweight mineral loam can be tamped was still possible to cut out window openings
10.8 Preparing a loam slurry using an electric hand
into formwork like straw loam. But it can also and to form sills with a machete, as shown
mixer be poured or pumped if the consistency is in 10.5.
10.9 Mixing of lightweight mineral loam using an correct. It also absorbs less water (therefore
ordinary concrete mixer drying faster), exhibits less fungus growth, Poured walls
10.10 Transporting and pouring lightweight mineral greater dry strength, higher vapour diffusion The easiest way to make a wall of lightweight
loam resistance and higher surface hardness than mineral loam is to simply pour it into a form-
work (10.7). In this case, the mix was pre- 300-year-old half-timbered house restored in
pared in a force mixer, shown in 10.6. With Germany, where the mix was prepared by a
this technique, it is even possible to use an regular mobile concrete mixer, funnelled into
ordinary cement concrete mixer in which a pump, and then piped to the formwork.
the loam slurry is poured over the aggre-
gate while it is being turned (10.9). Here, Surface treatment
the slurry was prepared with an electrically After removing the formwork, the surface of
driven hand mixer, shown in 10.8. The form- tamped, poured or pumped mineral loam
work was simply left open on one side for the walls with densities of 600 to 900 kg/m3
upper portion of the wall, and the mix was can be seen to be fairly hard, albeit rough
thrown into it and tamped with a flat piece (10.14). This surface need only be plastered
of timber. In a two-storey house at Tata, with a single thin layer (unlike equivalent
Hungary, a load-bearing wall of 50 cm thick- straw loam walls which require at least two
ness was made with a mixture of loam and layers). In 10.15, we see a lightweight min-
expanded clay. The mixture was poured into eral loam wall with a density of 1000 kg/m3
the formwork through a funnel carried by a being scraped by a rake directly after deshut-
crane, a method commonly used in concrete tering. This forms a nice, roughly textured
10.11 Pouring mineral loam in lost formwork construction (10.10). A simple method of re- surface that need only be whitewashed later,
10.12 Study model for interior walls using lightweight ducing expenditures is to use a lost formwork thus saving plaster.
mineral loam and lost formwork of textile stressed made of reed on one or two sides of the wall
by cables (10.11). Illustration 10.12 shows how a lost Pumped lightweight mineral loam
10.13 Vertical section and horizontal section show- textile formwork, designed by the author, may floors
ing the ceiling pattern for a bathroom with a central be used. A piece of fabric maintains its shape
skylight
and is stressed by cables fixed to the timber Lightweight mineral loam pumped in pipes
10.14 Surface of a light loam wall made of clayey frame. This gives an idea of the unlimited va- is especially suitable for ground floors and
loam and expanded clay (8 to 16 mm) after the
riety of creative surface textures. intermediate floor slabs. Illustration 10.16
formwork was removed
shows a vertical section of a ground floor
10.15 Scraping lightweight mineral loam wall in order
Pumped walls with high thermal insulation, which in cold
to get a textured surface (without using plaster)
For larger projects, especially if there are climates offers a warm, comfortable feeling
10.16 Vertical section through floor with lightweight
mineral loam firms to make the lightweight mineral loam, upon entering. Illustration 10.17 illustrates
10.17 Lightweight mineral loam used as infill in
it is advisable to pump the mix into the form- the possibility of using lightweight miner-
timber flooring work with the use of mortar or concrete al loam as a cast in situ infill between floor
10.18 Transporting and pumping lightweight mineral pumps. The consistency must be a little bit joists. If this mineral loam has a density high-
loam thinner than for pouring. It can be pumped er than 1000 kg/m3, it serves as a good bar-
10.19 Loam-filled hollow blocks forming a corner with up to heights of two storeys using hoses. rier for airborne noise and gives good ther-
different positions of structural post Illustration 10.17 shows the example of a mal storage.
Carpet
Lightweight loam
Thermal insulation
Damp-proof barrier
Coarse gravel
10.16
10.17
10.13
10.18
10.19
Loam-filled hollow blocks weight mineral loam mixture. The hose can
be filled either using a pump (10.20), or by
In industrialised countries, there are many hand through a funnel (10.21). When the
different types of hollow blocks available, required length is reached, the hose is cut
which are usually filled with concrete. They and the end is stretched and knotted. Owing
are made of materials such as pumice to the reinforcement provided by the fabric,
bound in cement mortar, expanded clay, these loam-filled hoses can then be easily
cement-bound woodwool, lime-bound sand, handled. Before being laid onto a wall, they
baked clay or foamed polystyrene. If the wall are smoothed with the hands so that some
is not load-bearing, loam can also be used loam oozes and forms a thin loam cover on
instead of concrete infill loam. Load-bear- the fabric. When stacked, these loam cover-
ing members can be integrated with these ings stick together (10.22 and 10.23). Since
walls or placed inside the walls, as shown in these hoses can be shaped easily without
10.19. If high airborne noise insulation and breaking, attractive sculptural patterns can
thermal capacity is required, a high propor- be created (10.24 and 10.26).
tion of gravel should be mixed into the loam. After laying and some drying, the surface can
If high thermal insulation is required, light- be easily smoothed with a wet brush. In the
weight aggregates should be added. wall shown in 10.27, hoses 70 cm in length
are laid between vertical posts of 4 × 4 cm
turned at 45°, or triangular elements fixed to
Loam-filled hoses the main posts of the end of the wall, shown
in section in 10.25. As a rule, three to five
A new technique, developed by the author layers can be stacked per day, but in order to
of this book, was used in 1992 for three increase this number some cement can be
residences in Kassel, Germany. Though the added to speed up the drying process. Chap-
outward appearance of walls made by this ter 13, p. 108 explains how these hoses can
technique is similar to those made with the be used in order to increase the thermal in-
technique for making stranglehm described sulation of walls.
in chapter 8, the production, handling and
laying is quite different. With this technique,
an elastic cotton hose is filled with a light-
10.22
10.25 10.26
91 Loam-filled hoses
@arclib
@arclib
11 Loam plasters
Loam plasters, in some countries also called small rake or a nail-trowel (11.2 and 11.3).
clay plasters, earth or mud plasters, consist In order to ensure that the plaster adheres
mainly of sand and silt with only as much well, plaster supports can be applied in the
clay as is necessary (usually between 5% form of galvanised wire mesh, plastic mesh,
and 12%) for developing their adhesive and reed mats etc.
binding forces. It is difficult to determine
the proportions of an ideal loam plaster, be- Composition of loam plaster
cause not only the proportions of clay, silk
and sand influence a mixture’s properties. In order to keep loam plaster free of shrink-
Other factors affecting the composition are age cracks, the following points must be kept
the grain size distribution of the sand frac- in mind:
11.1 tion itself, the water content, the type of • The loam should contain enough coarse
clay, the method of preparation and the ad- sand.
ditives. In order to test the appropriateness • Animal or human hair, coconut or sisal fi-
of loam plasters, samples with varied com- bres, cut straw or hay should be added (how-
positions should be tested. If the surface is ever, too much of these additives reduce the
rough enough, then loam plasters stick well ability of the plaster to adhere to the ground).
not only to loam surfaces, but also to those • For interior plastering, sawdust, cellulose
made of brick, concrete and stone. For the fibres, chaff of cereal or similar particles can
ability of loam plasters to balance indoor air also be used as additives.
humidity see chapter 14. • In order to develop enough binding force,
the adhesive forces of the clay minerals
Preparation of substrate should be sufficiently activated by an ade-
11.2 quate amount of water and by movement.
As loam plaster does not react with the sub- • When the plaster sticks to a sliding met-
strate chemically, the substrate surface has al trowel held vertically, yet is easily flicked
to be sufficiently rough in order to develop a away, the correct consistency has been
good physical bond. If masonry is to be plas- achieved.
tered, especially when using larger and very
smooth bricks, it is recommended that a 45° In order to test the characteristics of a loam
groove be cut with a trowel into the joints, as plaster, a simple adhesion test can be car-
shown in 11.1. Another method of obtaining ried out. The plaster to be tested is applied
a good bond when rammed loam walls are 2 cm thick to the flat surface of an upright
to be plastered is to wet them sufficiently baked brick. The plaster should stick to the
until surfaces are soft, and to then scratch brick until it is totally dry, which might take
11.3 diagonal patterned grooves into them with a 2 to 4 days.
92 Loam plasters
@arclib
@arclib
If the plaster falls off in one piece by itself, as Interior loam plasters
seen in the left sample in 11.4, then it is too Interior plasters are less problematic. As a
clayey, and should be thinned with coarse rule, fine shrinkage cracks cause no prob-
sand. If it falls off in portions after the sam- lems because they can be covered with
ple is hammered on the floor, like the second coats of paint. Dry loam plaster surfaces can
sample in 11.4, then it possesses insuffi- be easily smoothed by wetting and worked
cient binding force, and should be enriched with a brush or felt trowel.
with clay. If the plaster sticks to the brick If the surface of the walls demands a plaster
but displays shrinkage cracks like the third thicker than 15 mm, this should be applied
11.4 sample in 11.4, it is too clayey and should be in two layers, with the ground layer contain-
slightly thinned with coarse sand. However, it ing more clay and coarse aggregates than
can be used without thinning as the first lay- the second one. If the ground layer acquires
er of a two-layer plaster. If the surface shows shrinkage cracks, this is not problematic,
no cracks and the plaster does not come off and it might even be beneficial by providing
when hammered, as in the fourth sample a better bond to the final layer of plaster.
seen in 11.4 (right), then the sample might Adding rye flour improves the workability of
be adequate. In this case, it is advisable to the plaster and enhances the resistance of
make a larger test, about 1 m wide and 2 m the surface against dry and moist abrasion.
high, on the actual wall. If shrinkage cracks Through testing, the author of this book has
now occur, then the mixture needs to be ei- proven that such resistance can also be built
ther thinned with coarse sand or mixed with up by adding casein glue made of 1 part hy-
fibres. draulic lime and 4 to 6 parts fatfree white
cheese, borax, urea, sodium gluconate and
Exposed exterior earth renders shredded newspaper (which provides cel-
Exposed exterior renders must either be sea- lulose fibre and glue). The following mixes
sonably weather-resistant, or else must be worked well:
given perfect weatherproof coating. In cold Lime reacts with the casein within the fatfree
climates, it is important that the renders, cheese to form a chemical waterproofing
11.5 together with their coatings, have a low va- agent. A similar reaction is obtained with
pour diffusion resistance, so that water con- lime and borax (which is contained in shred-
densed in the wall can be easily transported ded newspaper). Sodium gluconate acts as
to the exterior. In order to meet thermic and a plasticiser, so that less water needs to
hygric influences without cracking, the ex- be mixed for preparation (thereby reducing
terior plastering must be more elastic than shrinkage). Urea raises compressive and
its ground. For cold climates, in general, an tensile bending strength, especially with silty
external loam plaster is not recommended, soils (see chapter 4, p. 41).
unless sufficient roof overhang, plinth pro- Shredded wastepaper leads to better work-
tection and good surface coating can be as- ability and reduces shrinkage. The mixes B,
sured. C and E exhibited the best workability. When
11.6 Since plastered wall edges are very easily using mixes A and E, it is best to begin by mix-
damaged, they should either be rounded or ing the casein glue and the shredded news-
11.1 Cutting joints with the use of a trowel lipped with a rigid element. In extreme cli- paper together with the water and adding
11.2 Scratching a moistened loam surface with a mates, when the elasticity of large expanses loam and sand after an hour. With all mixes,
small rake of flat plaster is insufficient to cope with the it was found that when the final smoothing
11.3 Tools for scratching moistened loam surfaces effects of weather, vertical and horizontal was executed using a felt trowel, it was best
11.4 Loam mortar test grooves filled with elastic sealants are rec- to wait several hours or even a day.
11.5 Spraying lightweight loam plaster ommended. Chapter 4 discusses the over-
11.6 Lightweight loam plaster with expanded clay
all possibilities of reducing shrinkage and
particles (1 to 4 mm). The large aggregates create a enhancing weather resistance and surface
coarse surface. hardness.
Guidelines for plastering earth walls ties of coarse sand as well as fibres or hair.
8. To improve surface hardness, cow dung,
Since pure loam plaster does not react chem- lime, casein or other additives should be
ically with the ground, it might be necessary added to the top layer (see chapter 4, p. 38
to treat the ground so that sufficient curing and p. 45).
can occur. In doing so, the following guide- 9. In order to provide surface hardness and
lines should be kept in mind: resistance against wet abrasion, the surface
1. The earth surface to be plastered must should be finished with a coat of paint.
be dry enough so that additional shrinkage 10. When using plasters, changes in the
does not occur. physical properties of materials caused by
2. All loose material should be scraped off additives and coatings should be kept in
the surface. mind, especially with respect to vapour diffu-
3. The ground should be sufficiently rough sion resistance. Illustration 11.9 summaris-
and, if necessary, moistened and grooved es typical components for the various earth
or the mortar joint chamfered, as described plasters.
Mix(1)
above in this chapter.
Components
A B C D E 4. Before plastering, the ground should be Sprayed lightweight plaster
sufficiently moistened so that the surface
Loam slurry(2) 10 10 10 10 10
softens and swells and the plaster perme- In 1984, the author of this book successfully
Sand (0–2) 25 25 25 25 25
ates the soft layer. developed a sprayable lightweight loam plas-
5. The plaster should be thrown with strong ter with high thermal insulation, containing
Shredded newspaper(3) 5 5 5
impact (slapped on) so that it permeates the shredded newspaper. This plaster can be
Casein glue(4) 1 1
outer layers of the ground and achieves a applied even in a single layer up to 30 mm
Fat-free cheese 1
Urea 0.2
higher binding force due to the impact. thick using an ordinary mortar pump (11.5).
Sodium gluconate 0.2
6. If the plaster has to be more than 10 to In order to shorten the curing period, high-hy-
(1)
all proportions are stated in volumetric terms
15 mm thick, it should be applied in two or draulic lime and gypsum were added to the
(2)
made of 1 part clayey soil and 2 parts sand even three layers in order to avoid shrinkage mixture. Other lightweight sprayable plasters
(3)
treated with borax content
cracks. used to fill the frames of timber-framed hous-
(4)
made of 4 parts fat-free cheese and 1 part hydraulic
lime mixed intensively for 2 minutes 7. To reduce shrinkage cracks while drying, es and skeleton structures are described in
11.9 the mortar should contain sufficient quanti- chapter 9, p. 80.
94 Loam plasters
@arclib
@arclib
11.10
Illustration 11.6 shows the surface of an Straw bale houses, known since the end
8-mm-thick loam plaster with expanded of the 19th century when the first example
clay aggregates 1 to 4 mm in diameter. To was built in Nebraska, USA, found a renais-
reduce curing time and increase vapour dif- sance in the 1980s. Meanwhile, a lot of new
fusion resistance, the plaster was stabilised houses with straw bale walls were built in
with 5% high-hydraulic lime. It is not easy to Australia, France, Scandinavia and other Eu-
smooth the surface with a trowel, since the ropean countries. Most historic walls of this
aggregate tends to come out during the pro- kind were load-bearing. Nowadays mainly
cess. To avoid this, shredded paper, cellulose timber skeleton structures are used which
fibres or casein-glue can be added into the are filled or surrounded by straw bales. The
mix. simplest method for covering such walls is to
use loam plaster. To create a good bond and
Thrown plaster rigidity a chicken wire or plastic net has to be
fixed to the bales before plastering. This can
Illustrations 11.7 and 11.8 show how a tradi- be done manually or by spraying with guns.
tional African technique, consisting of throw- Illustration 11.11 shows the plastering of a
ing loam balls onto a wall, has been adapted. straw surface with a spraying gun, 11.12 the
Here, this technique is used on a wood-wool gathered texture and. For additional informa-
board for the wall of a winter garden, de- tion on such structures, see Minke and Krick
11.7 and 11.8 Thrown plaster in a winter garden scribed in chapter 14, p. 129. In order to in- (2020).
11.9 Components for various types of earth plaster crease adhesion, bamboo dowels were ham-
11.10 Sculptural earth wall mered halfway into the board.
11.14
11.15
96 Loam plasters
@arclib
@arclib
Wet formed plaster thinned by 2 parts of boiling water. Then this
mixture is cooked until its hue turns from
As loam plaster retains its plastic state for a white to a nearly colourless appearance.
long time and is not corrosive to the hands If using cowdung (plasters A, B, F) it is im-
like lime or cement plasters, it is an ideal portant to let the mix of 1 part of cowdung
material for moulding with the hands. Illus- with 1 part of loam, a relatively wet slurry,
tration 11.10 shows an example of an exteri- rest for several days to allow a fermentation
or loam wall stabilised by a limecasein finish. process. After this, the resistance against
abrasion and erosion will be 5% to 15% high-
Protection of corners er, as proven by tests made by the author at
the Building Research Institute (BRI), Kassel
As loam plaster is susceptible to mechan- University.
ical impact, corners should preferably be Table 11.15 shows results from erosion and
covered by wooden profiles, baked bricks or abrasion tests also conducted at the BRI.
similar lippings (11.13). The test procedures are described in chap-
ter 2 (“Resistance to running water”, p. 26,
Stabilised loam plasters “Resistance to abrasion”, p. 32). The results
show that the non-stabilised plaster (1) start-
Exterior loam plasters normally have to be ed to erode after 3 seconds, while several of
stabilised against erosion by wind and rain. the stabilised ones (2 to 23) did not display
An exception can be made only where the any signs of erosion, even after 6 days of
facade is sheltered by a large roof overhang constant spraying.
and when there is a plinth protecting against The same stabilised loam plasters showed a
splashing rain. very different behaviour under the abrasion
General possibilities to increase the resist- test as illustrated in the right part of the
ance of loam surfaces against abrasion and table.
erosion by additives are described in chapter
3 (pp. 38–41). Characteristics of different loam
Stabilised loam plasters are plasters to which plasters
other mineral, organic or synthetic binding
agents like lime, cement, gypsum, modified Besides the resistance against erosion by
starch, cellulose, cowdung, oils, bituminous running water and abrasion by scratching
emulsion, acrylic or silicone resin have been the surface, the quality of loam plasters de-
added. The mixture after curing is no longer pends on their linear shrinkage during the
water-soluble. It has to be taken into account drying process as shrinkage creates cracks.
that many of these additives increase the Therefore, the art of making perfect loam
vapour-barrier effect of the facade, which surfaces is to avoid cracks. The shrinkage
can pose a risk in climatic zones with high can be reduced by adding coarse particles
temperature differences in the course of the or fibres. But this has restrictions, because
year. the more particles of this kind are added the
Preferable mixtures that have been tested in more the abrasion increases. Another possi-
the moderate climate zones of Colombia are bility of reducing the appearance of cracks is
shown in table 11.14. Among these mixtures to apply the plaster in several thin layers and
11.11 Spraying of earth plaster to straw bale wall those with cement and lime and the one to treat the surface by pressure of a trowel.
11.12 Smoothened surface after spraying with linseed oil proved unfavourable both in The linear shrinkage of lime and cement
11.13 Protection of earth wall corners terms of mixing and application. Adding 6% plaster is less than 0.1% while loam plasters
11.14 Composition of stabilised loam plasters for of a bituminous emulsion paste provided can have values of more than 3%. Recom-
moderate climates best results. The wheat glue used in plaster mended are values below 2%. As part of a re-
11.15 Erosion and abrasion of stabilised loam C was prepared from 1 part of wheat flour search project at the BRI, 15 different loam
plasters stirred well into 1 part of cold water and then plasters available on the European market
98 Loam plasters 98
99 Loamplasters
Loam plasters
99 Loam plasters
@arclib
@arclib
were tested with respect to their main char- The capacity of clay to absorb humidity
acteristics: linear shrinkage, abrasion, re- from the ambient air if the relative humidity
sistance against compression and bending, is higher than 50% and to release this ab-
and absorption of humidity. The procedure of sorbed water when the relative humidity is
testing the linear shrinkage is described on less than 50% is one of its most interesting
p. 22 and 23, the method to test the abra- characteristics; it is described in detail on
sion on p. 32, the way to measure the com- p. 14 and 15. How this is influenced by ad-
pression and bending strength on p. 31 and ditives and paints is explained on p. 15. In
32 and the evaluation of the absorption on 11.19 the absorption and desorption curves
pp. 14–16. When comparing tables 11.16 of the mentioned 15 different loam plasters
and 11.17, we can see that plasters with are put in relation to the absorption curve
high shrinkage normally are subject to little of a loam brick. The unfired brick, due to
abrasion and plasters with low shrinkage its higher content of clay, has a higher ab-
show higher abrasion. sorption capacity. Plasters in general have a
In 11.18 the compressive strength and the lower absorption capacity due to their higher
tensile bending strength and in some cases content of silt and sand. But, as becomes
also the tensile strength of the tested plas- apparent in the table, the absorption rate of
ters are noted. The tensile bending strength these different products varies by more than
is of little importance when judging the qual- 100%. The reason is that some have thin
ity of a loam plaster, but in cases of deflec- organic fibres added which increase the ab-
tion of the wall elements by seismic forces sorption capacity; the amount and the type
or by vibrations caused by bypassing lorries of clay differ as well. Montmorillonite clay for
it may play a role. The bending strength of instance has a higher absorption rate than
the tested plasters is between 12% and 34% caolinite clay.
of the compressive strength and the tensile
strength is about 10% of the compressive
strength.
Loam surfaces need not always have addi- diffusion to the outside. Latex and dispersion
tives in to be made weather-resistant. It is of- paints, therefore, are not recommended.
ten sufficient to protect or harden them with For information supplementing that con-
plaster or paint. This chapter describes the tained in this chapter, see Wehlte (1985).
different ways loam surfaces can be made
more resistant to environmental forces, and Preparation of ground
the structural measures required to shelter If the ground is very silty and lime-based
them from these forces. paints are used, the surface should be
primed with thin lime-casein milk and then
Consolidating the surface rubbed. The primer can be made of 2 parts
of hydraulic lime, 1 part fat-free white cheese
The simplest method of hardening the sur- and 15 parts water.
face, especially against rain and wind ero-
sion, is to consolidate it. This can be done Recommended paint mixtures
by rubbing a metal trowel with high pressure
onto the surface when it is moist and slightly Pure lime wash
pliable. Traditional Indian and African meth- The lime wash mixture has to be very thin, al-
ods employ flat but light convex stones that lowing the paint to penetrate deeply enough
are rubbed in a circular motion across the into the ground so that flaking does not oc-
surface with great force. The treatment is ad- cur during drying. Therefore, three or even
equate if the surface appears shiny and no four thin coats are recommended, with the
pores or cracks are visible. While this leaves first coat being the thinnest. The mix can be
the composition of the material unaltered, it made from 50 kg hydraulic lime dissolved in
nonetheless creates a surprisingly high de- 60 litres of water. It is often preferable to add
gree of weather resistance. 1 to 2 kg of kitchen salt; being hygroscopic,
the salt allows the mixture to remain moist
Paints longer, thereby ensuring better curing of the
lime. Pure lime wash is perfectly white when
Paints on exposed loam surfaces have to be dry, but can be toned down by adding clay or
renewed periodically. The paint can be phys- loam powders or other lime-proof earthen pig-
ically eroded by wind, frost or rain, or chem- ments. Pure lime wash is not wipe-resistant.
ically eroded by ultraviolet radiation or acid
rain. External paints should be simultane- Lime-casein wash
ously water-repellent and, especially for cold Lime washes are much more wipe-resistant
climates, porous, i.e., should contain a co- and durable if whey, fat-free white cheese
herent net of micro-pores that allow vapour (quark) or casein powder is added. Quark is
non-treated
Stone proofer H, Wacker
Façade impregnation, Herbol, hydrophobic
Indula, HYDROPHOBIN
Wacker, BS 15
Metroark, SYLTRIT 1772
Baysilone impregnation, Bayer
Silty plaster (clay = 3%, silt = 18%, sand = 79%)
non-treated
Stone proofer H, Wacker
Façade impregnation, Herbol, hydrophobic
Indula, HYDROPHOBIN
Wacker, BS 15
Metroark, SYLTRIT 1772
Baysilone impregnation, Bayer
sd-value
Water repellents
Wacker, BS 15, 2 layers 0.00
Metroark, SYLTRIT, 2 layers 0.00
Baysilone impregnation, Bayer, 2 layers 0.02
Façade impregnation, Herbol, hydrophobic, 2 layers 0.02
Stone proofer H, Wacker, 2 layers 0.09
Indula, HYDROPHOBIN, 2 layers 0.10
( ) = Proportion by volume
12.1
obtained when rennet from young cows is time (sometimes every 5 minutes). An even
added to skimmed milk. This cheese contains stronger and more wipe-resistant paint is ob-
11% casein. Lime, together with casein, forms tained by mixing 1 part hydraulic lime with 5
a chemical waterproofing agent called lime parts fat-free cheese and 5 parts loam.
albuminate. Today, the use of cheese is the In bathrooms and kitchens, where greater
best solution for lime-casein washes. In tradi- dry and wet wipe resistance is required, the
tional lime-casein washes, whey or sometimes following procedure is recommended: 1 part
skimmed milk was used instead of cheese. hydraulic lime and 5 parts fat-free cheese
Mixtures containing 1 part fat-free cheese, are mixed without water for about 2 minutes
1 to 3 parts hydraulic lime and 1.5 to 2.5 using an electric mixer. This is allowed to
parts water proved effective. Small amounts stand for some time, and then 20 parts hy-
of double-boiled linseed oil (not more than draulic lime, 2% to 4% doubleboiled linseed
4% of the amount of cheese) increase wipe oil and water are added. Two coats of this
resistance but reduce the workability of wash give a dry and wet wiperesistant sur-
12.1 μ-values of water-repellent loam plasters and the wash. To get an even emulsion, it has face. Earthen pigments can be substituted
sd-values of coatings to be well-mixed and stirred from time to for some portion of the lime.
101 Paints
@arclib
@arclib
Paint g/m2 kg/m2h0.5
Without 0 9.5 Borax-casein wash Institute – BRI showed that it bonds well with
Linseed oil 400 0.0
Borax can be used instead of hydraulic lime. a rough, lean loam plaster. But with a rammed
Lime casein 1:1 420/350 0.6/1.5 0.6hr/6–24hrs
Lime casein 1:8 300/300 0.7 It reacts chemically with casein in a way sim- earth surface made of clayey loam, parts of
Silin-paint 700/250/310 0.3 ilar to lime. With high borax content, crystals the coating became detached over a period of
(van Baerle)
form, which can be seen in the wash. Unlike several months due to rain and frost, probably
Hydrophob 390/390 0.0
(Herbol) lime, borax does not give a white colour, and because the bond between the coating and
Baysoline LD 400/290 0.2
(Bayer) is therefore preferable if dark colours are the ground was insufficient.
Syltrit (Metroark) 350/320 0.0 desired. Chalk powder is added in order to
BS 15 (Wacker) 450/430 0.1
Stone proofer H 290/290 0.0
make the paint thicker and lighter in colour. Other stabilised lime washes
(Wacker) A small addition of clay powder increases its Several old text sources claim that in addi-
12.2 workability. tion to mixing hydraulic lime into whey, it can
If casein powder is being used instead of fat- also be mixed into urine. Weiss (1963) found
free cheese, it must be allowed to swell un- that using Kaolinite clay, strength could be
der water for 3 hours (320 g casein powder increased by adding urea and ammonium
in 1 litre of water). Afterwards, 65 g of borax acetate. This practice was also common in
dissolved in 1 litre hot water is mixed into the ancient China, where extremely thin porce-
12.3 casein slurry and the whole thinned with 12 lain was produced by adding putrefying urine
litres of water. to the mix.
According to Jain et al. (1978), the addition
Colourless casein coating of 70 g of animal glue dissolved in 0.5 litre of
In order to retain the natural colour of the boiling water and mixed with 1 kg of hydrau-
loam surface while improving its wipe resist- lic lime proved good.
ance, a coating of the following mix can be In Auroville, India, the following coating was
used: 1 part fat-free cheese with 1.8 to 2 used successfully for mud brick domes: the
parts water and 1/8 to 1/9 part of hydraulic whites of 60 eggs mixed with 2 litres of but-
lime powder. This coating will give a colour- termilk and 5 litres of palm liquor stirred
less to slightly milky surface, with a mild silky and mixed with 40 litres of shell lime and
sheen caused by its fine crystal structure. 4 litres of cement (Pingel, 1993). According
to various sources, the following plant matter
Lime-suet coating added to the lime also enhances wipe and
The following recipe from Nepal gives a thick, weather resistance:
pasty weatherproof exterior coating: 15 kg of • rye flour glue (15 litres of rye flour boiled in
powdered quick lime together with 6 kg of 220 litres of water with the addition of some
tallow (melted suet) is poured into 36 litres zinc sulphate),
of water. This mixture is stirred carefully (care • agave juice,
has to be taken because the lime reacts very • boiled banana leaf juice,
intensely with water and may splash and burn • juice of the cactus opuntia,
the skin). After adding 6 kg of kitchen salt and • juice of euphorbia lactea,
carefully stirring, this mix should be allowed to • kapok oil,
stand for 24 hours in a not-too-cold environ- • raw and double-boiled linseed oil.
ment. The water layer that forms on the top
of the mixture is decanted. The pasty mix that Cellulose glue paint
remains is then mixed with 3 kg of fine quartz Since it is very cheap, cellulose glue mixed
12.2 w-values of loam plasters with coatings
sand and applied with a brush in 3- to 5-mm- with chalk powder is often used for painting
12.3 Drop of water on a surface that has been treat-
ed with water repellent (right, angle larger than 90°)
thick layers to the wall (Manandhar, 1983). interiors. However, it offers little weather re-
and on an untreated surface (left, angle smaller than This coating requires several weeks to cure. In sistance. Its wipe resistance is also low.
90°) Nepal, it is said to last for 4 to 6 years. A sim-
12.4 Simple spraying test (BRI) ilar recipe was used successfully in Australia Bitumen coating
12.5 Church of San Francisco de Asis, Ranchos de (Department of Housing, 1981). Tests per- Bituminous emulsions offer good weather
Taos, USA formed with this mix at the Building Research protection for exterior walls. The following
Repair of damaged sections of loam, espe- can fall off. Therefore, it is important to pre-
cially cracks and larger joints, demands spe- treat the joint and use a mixture having as
cial measures differing from those used for little shrinkage as possible.
conventional masonry or lime plasters. This
chapter describes loam-specific repair prob- Mixtures
lems and retrofitted thermal insulation meth- While designing the composition of the loam
ods using lightweight loam. filler for cracks and joints, the following
should be considered:
Occurrence of damage • The filler must have sufficient binding force
to stick to the moistened surfaces of the
Damage in loam components can occur crack or joint.
due to shrinkage by thermal contraction • The mix should contain sufficient coarse
and expansion, through water impact or sand or other coarse particles so as to min-
by mechanical impact and abrasion. If a imise the shrinkage. Fibres or hair may also
plaster contracts when drying, or does not be added for the same reason.
bond sufficiently with the ground surface, • In order to decrease the curing time, gyp-
13.1 it may separate from it. Such weak areas sum, lime or cement can be added. As these
can be easily located by knocking the additives also make the mixture leaner, the
plaster with the knuckles. If large quantity shrinkage is reduced. The disadvantages
of water condenses in the wall and cannot while adding these substances might be
be removed quickly enough, the loam might that the binding force and the compressive
swell and cause the plaster to crumble strength are reduced. Joints and cracks in
and fall off. Such damage can also occur internal elements can be filled with a mixture
when water seeps through from the outside of 1 part loam, 0.5 to 1 part hydraulic lime
through cracks or holes. and 0.5 to 1 part gypsum.
If the joints are exposed to weather, gypsum
Frost can also cause a similar damage if the should not be used, but cement, highhydrau-
wall is moist and the freezing water expands. lic lime or a mixture of these totalling from 8%
to 20% can be used as an additive. Instead
Repair of cracks and joints with of these binders 4% to 7% double-boiled lin-
loam fillers seed oil can also be added. This filler stays
plastic for several weeks.
Joints and cracks in dry loam components
13.1 Pumping lightweight mineral loam cannot be repaired with plastic loam as this Application of filler
13.2 Additional interior thermal insulation layer of does not bond with the dry loam surface. In order to get a good bond between the old
lightweight mineral loam in a timber frame wall When drying, the filler will separate out and loam surface and the filler material, cracks
14.1 Possible joint designs of stranglehm respec- Lightweight loam Loam plaster Timber
Insulation (λ = 0.04)
Lime render
Cork (λ = 0.5)
14.3
but instead on timber wall plates or beams ty lightweight loam walls. In climates prone
as seen in 14.2 A. If the rafters rest on a tim- to driving rain, designs A to F are preferable
ber post-and-beam structure and the wall is because they have separated outer leaves,
not load-bearing, the shrinkage of the timber which act as protection from the weather.
structure has to be taken into account.
In 14.2 B, an elastic sealant has been intro- Earth-filled tyre walls
duced between the beam and wall in order A possible method of using hollow blocks
to provide sufficient tolerance for this shrink- filled with lightweight loam for walls has been
age; while in 14.2 C, the structural system described in chapter 10, p. 90. If the insu-
is separated from the wall, thereby allowing lation requirements are not very high, these
a greater vertical movement of the timber walls can be filled with plain clayey soil.
structure. Michael E. Reynolds built several residences
in New Mexico, USA, having walls made of
Special wall constructions discarded car tyres filled with soil dug out of
the foundation (14.4). Only the top tyre was
Loam walls with high thermal insulation filled with concrete to which a wooden ring
The U-value of a 30-cm-thick rammed earth anchor was fixed. The interior surface was
wall (without lightweight aggregates) is about covered with expanded metal mesh rein-
1.3 W/m2K. In order to achieve a U-value forcement and then plastered.
of 0.3 W/m2K with this wall, it would need
to be 1.65 m thick. This shows that in cold Earth-filled bags
climates where high thermal insulation is The Building Research Institute – BRI, Uni-
required, it is not possible to build only with versity of Kassel, Germany, tested several ap-
normal loam. The examples provided in 14.3 proaches to building walls of earth- or sand-
not only show sufficient thermal insulation filled bags or hoses. Illustration 15.47 shows
with a U-value of 0.3 W/m2K, but are also a dome built in 1977 of sand and earth-filled
designed to have sufficient thermal mass for hoses of polyester fabric; 14.5 shows the
balancing the indoor air temperature, suffi- wall of a low-cost housing prototype built in
cient loam for balancing the indoor air hu- Kassel in 1978. In the latter case, the hoses
midity and sufficient noise insulation as well. were made of jute fabric covered by several
Designs E and F are for load-bearing walls, layers of lime wash to prevent rotting.
while the others are not. The outer thermal The California architect Nader Khalili further
14.2 Vertical sections of roof structure and
insulation panels, shown in G and H, can be developed this idea utilising endless hoses,
load-bearing and non-load-bearing walls used as a lost formwork for pouring the light- usually used to make bags for sugar or flour.
14.3 Horizontal sections of various loam walls with weight loam, while also acting as a ground Illustrations 14.6 and 14.7 show the filling
U-values of 0.3 W/m2K for the external lime plaster. The simplest and the ramming process; 14.8 displays a
14.4 Wall of discarded car tyres filled with soil, USA and best performing solutions are J and K, built example in Brazil.
14.5 Prototype building, Kassel, Germany which are formed with monolithic low-densi-
14.8
14.9 14.10
Earth bricks
Shuttering boards
Wooden flooring
Wooden substructure
Felt strips
Earth bricks
Trickle protection
Shuttering boards
14.11 14.12
14.20 14.21
layer. This provides both sufficient thermal in- All three mixtures displayed very good sur-
sulation and the required structural strength. face hardness. The linseed oil mixture had
The lightweight loam was prepared in a nor- the disadvantage of its strong odour and a
14.19 mal concrete mixer and then poured from a long drying time, but showed the best sur-
wheelbarrow (14.21). face hardness.
Loam mortar
In order to reduce hardening time, 4% ce-
Mineral lightweight loam
ment was added to the mix. In order to Inclined roofs filled with
Thermal insulation
achieve adequate surface hardness, a 3-cm- lightweight loam
Damp-proof barrier thick loam mortar (containing sufficient
Coarse gravel coarse sand to minimise the occurrence of Commonly used tile-covered rafter roofs can
shrinkage cracks) was applied in two layers. be filled with lightweight loam in order to in-
For this mortar, 6% (by dry weight) of three crease their thermal and sound insulation.
different stabilising agents were successfully If the space created by a typical 16-cm-high
14.22 tested: the first, soda waterglass was added rafter is filled with lightweight loam with a
after being thinned 1:1 with water; the sec- density of 600 kg/m3 and the ceiling made
ond, double-boiled linseed oil; and the third, of timber boards, the roof achieves an U-val-
lime-casein glue (made from 1 part hydraulic ue of 0.8 W/m2K (14.23 A). Three solutions,
lime and 5 parts fat-free white cheese mixed B, C and D, show possibilities for attaining
vigorously without water for 2 minutes and higher levels of thermal insulation, as de-
then allowed to stand) with additional chalk manded in many northern countries.
at the rate of 10%.
The mixtures were applied like plasters Earth-covered roofs
with low moisture content and the surface
smoothed with a rotary motion of the trowel. In dry climate zones, flat roofs covered with
After fully drying, all of these surfaces were earth have been in use for centuries in tra-
waxed. ditional rural architecture. One of the great-
Cork Cork
14.23
14.24
14.30
14.29
14.31
14.32 14.33
ispherical dome rests on the lower part of a zontally, so that the masonry blocks create
truncated dome. The doubly curved triangu- overhangs within (14.33, bottom), then we
lar surfaces are called pendentives. Solution speak of a “false” vault or dome. In such
C shows a squinch dome whose lower circle cases, since each course is cantilevered
is inscribed on the square and the inter- over the one before, the blocks are subject-
connecting surfaces, called squinches, are ed to bending forces. One example of a false
composed of a series of arches of increasing dome is shown in the model illustrated in
radius. This solution can also be described 14.34 and 14.35.
as a truncated dome resting on the inscribed The main problem in constructing vaults is
diagonal square with the surfaces thus left how to transfer of the outward thrust force at
(triangular in plan) being the squinches. the bottom to the supports and foundations.
Solution D is a partial squinch dome whose Illustration 14.36 shows how the resultant
14.35 bottom circle is drawn around the largest forces at the support can be separated into
regular octagon that fits the square, form- vertical and horizontal components. The
ing truncated planes on four of the sides steeper the forces are conducted into the
and squinches on the other four. Solution E foundation, the smaller are the horizontal
shows a totally different way of solving this forces, and the easier the formation of foun-
problem and can be called a bell-shaped dation. A rule of thumb is that the forces re-
dome. Here, we have a continuously chang- sulting from vault thrust and wall loads must
ing double curvature beginning at the edges fall within the middle third of the pedestal
with an anticlastic (saddle-shaped) curva- and foundation bases. This means that ec-
ture (i.e., a curvature that is convex in one centricity should be no more than 1/6 of the
direction and concave in the perpendicular breadth (14.37).
direction) and continuing to the apex with a Since this consideration can mean a very
synclastic (dome-shaped) curvature (i.e., one large and, hence expensive foundation, it
that is similarly curved in both directions). may prove expedient to plan for additional
structural measures, such as those shown
Structural behaviour in 14.38. In solution A, for example, the in-
14.34 and 14.35 Model of a building with “false” Structurally speaking, vaults and domes clination of the resulting load is reduced by
vaults are curved surfaces that transfer almost means of superimposed loads. A second sim-
14.36 Separation of forces at the support exclusively compressive forces to their ple solution, shown in B, consists of buttress-
14.37 Deflection of the resultant shear force into the supports. They are usually constructed of es. In this case, to prevent excessive bending
foundation baked bricks or flat stones, with joints set stress, spacings between buttresses should
14.38 Possibilities of structural stabilisation perpendicular to the surface of the dome, not be too large. A structurally superior vari-
14.39 Horizontal forces so that the courses form a radial pattern ation is shown in C, with buttresses connect-
14.40 Reversed catenary as in 14.33, top. If the courses are set hori- ed by arches. Solution D shows the transfer
of the resultant horizontal thrust to tensile represents the ideal supporting line (line of
structural elements in the floor (reinforced thrust) for a vault in which only compressive
concrete plates, for example), which neu- forces occur under dead load (14.40). This
tralise the thrust so that only vertical forces line can be computed by the catenary formu-
are transferred to the foundation. Solution la y = a cosh (x/a), and can be defined by the
E shows single tensile ties which act in the position of the two points of support and the
same way. They are placed above the walls apex (14.41). In a semicircular vault, the line
supporting the vault. In this case, ring or pe- of support does not run in the centre of the
ripheral beams have to be provided, which wall thickness. It might even fall outside the
can take the bending forces that occur be- structure, as shown in 14.42 A. This causes
tween the tie ends. Solutions F and G show bending stresses and usually leads to failure.
two different ways of diverting the thrust of If the thickness of the vault is large enough
the central dome to low lateral vaults. to contain the line of thrust within its middle
If two identical barrels converge in one strip third (14.42 B), then this danger is avoided.
14.39 foundation, then the horizontal components The ideal cross-section of a dome under dead
of the resultant thrust are neutralised (14.39, load is that which only creates compressive
right). If, on the other hand, the barrels have forces going downwards (meridional). This
different shapes, then only a portion of this means a form that creates neither tensile nor
horizontal thrust will be neutralised (14.39, compressive ring forces. If the cross-section
left). has the shape of a catenary, then compres-
Since adobe vaults can endure only very sive ring forces will occur. This might be dis-
small tensile forces, it is important to design advantageous if openings have to be cut into
them so that, as nearly as possible, only com- the dome, or if it is a dome of large span.
pressive forces occur. With a barrel vault that To work out the ideal shape of a vault, a
bears only its own weight, this is the case slice as shown in 14.44, left, is taken out
if its cross-section is an inverted catenary and divided into segments of equal length.
curve, defined as the shape assumed by a This gives segments of identical area and,
freely hanging chain, which is subjected only therefore, can be substituted by single
14.40 to tractive force. When inverted, this curve loads of equal magnitude acting at the cen-
14.42
14.43
14.44
14.45 14.46
Optimised section
Semicircle
Catenary
14.47 14.48
14.49
tre of each segment. However, in the case The first assumption (that the dome is a
of a dome, if we take a slice, as shown in hemisphere) cannot be used if the height is
the figure on the right, and divide this into not equal to the half-span. In this case, one
segments of equal length, the widths and, should start from the shape of an ellipse
therefore, the areas are continuously de- whose axis is below the base of the dome.
creasing from the base to the apex. If these This stating assumption is already close to
segments are substituted by single loads, the ideal form, which can then be refined by
then their loads are also thereby propor- the model.
tionally decreased. If the ideal form is to be A more exact method to derive ideal curve
derived from a model, then, corresponding is by graphic methods used in statics engi-
loads can be added to a chain which then neering. At the BRI, these methods were
forms this ideal curve, as seen in 14.43. used to develop a computer programme.
Here, this ideal curve is shown in contrast Some results for eleven different dome pro-
14.41 Catenaries of same length
to a catenary. In 14.45, formulas are given portions from h = 1.5 r to h = 0.5 r (where h
14.42 Risk of deformation with barrel vaulting
for calculating areas of the segments of a is the height and r the half-span) are plotted
14.43 Experimental determination of the ideal
sphere. However, since the ideal form is not in 14.46. In each case, a skylight opening of
cross-sectional shape for a dome carrying only its
own load in a suspension test spherical, its segments have an area slightly 0.2 r was taken into account. Illustration
14.44 Decomposition of the dead weight into individ-
differing from the one that we started from. 14.47 shows the ideal curve in comparison
ual forces for vault and dome Therefore, this procedure has to be consid- with a parabola, catenary and semicircle.
14.45 Calculation of surface areas ered a first approximation, which is in prac- In the section of the dome is inside the
14.46 Optimised cross-sections with different h : r tice sufficiently accurate for smaller spans. ideal curve, as happens with the catenary,
ratios Greater accuracy can be achieved by suc- compressive ring forces are created. If it is
14.47 Comparison of semicircle, parabola, catenary cessive iterations, substituting the actual outside, tensile ring forces will occur, as with
and support line for a dome changing radii of curvature of the segments the lower part of a hemispherical dome. Ten-
14.48 Nubian vault measured from the model and adjusting the sile ring forces usually lead to failure. Com-
14.49 Nubian vaults with support walls and support loads according to the surface areas of the pressive ring forces usually do not create
arch (side elevations) segments thus calculated. problems, except when interrupted by large
h h
h h
h h
h
r r r r r r r
openings. Table 14.50 gives the coordinates ble to lean the arches against a central “sup-
of the ideal line of support for seven differ- porting arch”, which typically has the section
ent dome proportions, from h = 0.8 r to h = of the vault and has to be made with shutter-
1.4 r (where h is the height and r the half- ing (14.49 C and 14.51). The cross-section
span), without taking into account any open- of the Nubian vault, which is mainly loaded
ings at the apex. by its own weight, should have the form of
To take into account asymmetric loads which an inverted catenary, so that it contains only
might occur in practice due to wind, main- compressive stresses.
tenance etc., and to conservatively ensure At the BRI this traditional technique was re-
that no tensile ring forces occur, it is better fined in two ways: first, instead of using rec-
to keep the section inside the ideal curve, tangular formats, a square block measuring
especially in the upper part. 20 × 20 cm, 6 cm thick was used for the low-
er part of the vault, and tapered versions of
Nubian vaults these blocks were used in the upper part of
With the Nubian vault technique, used for the vault, with the lower part shortened by
centuries in Upper Egypt, vaults can be built 1.5 cm. This reduced labour input and the
without any formwork by using reclining arch- quantity of mortar required. It was found that
es made of adobe. Illustration 14.48 shows by using an optimum mortar composition with
such a vault, which is 3200 years old and high binding force, it is also possible to use
stands within the temple precincts of Ram- adobes with thicknesses of up to 10 cm. This
ses II near Luxor. Such vaults are commonly leads to further savings in mortar and time.
constructed of adobes measuring 15 cm in Second, the shape of the vault was con-
width, 25 cm in length and only 5 to 6 cm trolled during construction by stretching a
in thickness. This means that the weight of cord from one support wall to the next (or to
each brick per unit area of mortar joint is the corresponding scaffolding). It is essential
very low, which prevents adobes in inclined that this cord passes through an eyelet on
positions from sliding during construction. one end and is held taut by a weight. When
The degree of inclination of the arches is a deformed by lateral pressure, the cord will be
decisive factor in the construction process. immediately restored by the moving weight
This should be between 65° to 70° with the to the correct position. When building the re-
horizontal. As tests have shown, if the arches clining arches, it is advisable that the blocks
are built up at a lower angle, the lower part of forming the arch are held together by keeping
the vault might collapse during construction, them touching on the inner edge with hard-
while if the angle is larger, the adobes might ly any mortar in between, and wedging with
14.50 Coordinates of structurally optimised domes slide off the top. Nubian vaults need one or a stone chip on the outer edge if required,
14.51 and 14.52 Construction of a Nubian vault with two vertical walls onto which the inclined so as to display arch action even before the
support arch arches lean (14.49 A and B). It is also possi- mortar is dry (14.52).
14.58
14.63
14.60
can be moved on a curved metal T-section called a “funicular shell” in India), which
bent to shape. This T-section is fixed to a ro- is essentially a bell-shaped dome that can
tating arm, which is in turn fixed to a verti- cover triangular, square, rectangular or
cal post. Illustrations 14.64 to 14.67 show other shaped bases. Timber boards, steel
the application of this technique to a dome sheets and glass-fibre reinforced polyester
with a 7 m free span and 6 m of clear height, elements have been used for the formwork.
which was built at the University of Kassel in It is, however, much easier to make a form-
Germany in 1992. The apex is covered with work with moist sand, as shown in 14.69.
14.66 a 16-sided pyramidal skylight. The thick- When constructing vaults, it is much easi-
ness of the dome wall is only 20 cm and the er to build a formwork, as these only have
cross-section was derived using a computer singly curved surfaces. Furthermore, only
program in order to get the optimum shape a short piece of formwork can be used and
with no ring forces, as described on p. 121 shifted as the vault construction proceeds.
of this chapter. In order to prevent the blocks This technique is normally used to construct
of the upper layers from sliding while under jack vaults (14.13). The jack vault shown
construction, the courses are not exactly per- in 14.68 was built on a sparse formwork,
pendicular to the surface of the dome, but erected on thin laths positioned underneath
are slightly less inclined so that the top layer the joints of the earth blocks. These blocks
has 20° less inclination and a partial corbel- were arranged without mortar. The joints
ling effect can be seen. This, furthermore, were later moistened, and then mortar was
has the advantage that no sound-focusing filled in from above.
effect occurs (14.67). The blocks used were
tapered and extruded through a special Firing of earthen domes
snout in a mechanical brick plant. The Persian architect Nader Khalili has con-
structed several earthen domes in Iran and
Domes and vaults on formwork in the USA, which he attempted to strengthen
It is very labour- and material-intensive subsequently by firing them from the inside.
to build formworks for domes, which is While the combination of the four elements
why nearly all historical dome construc- used to create these spaces, earth, water, air
tion techniques avoided it. An exception is and fire, may lend them a mystic touch, they
14.67 the shallow Catalonian dome (sometimes yet have several disadvantages regarding
14.69 14.71
climate and external environment. The burn- sorbtion. The wall surface above the glazed
ing of the logs, branches and twigs creates opening, 14.71, was covered with thrown
pollution and consumes large quantities of loam balls, as described in chapter 11, p. 95.
energy. Furthermore, the burning process
cannot be fully controlled and is hence not Loam in bathrooms
optimum. The uneven heating of the blocks
may produce cracks reducing structural sta- The assertion that a loam-finished bathroom
bility. Also, most of the pores in the blocks is more hygienic than a tiled bathroom as-
14.70 are closed by burning, drastically reducing tonishes many. Both experiences over sev-
their capacity to absorb and desorb humidity eral years with bathrooms having loam walls
(see chapter 1, p. 12). This, however, means and scientific investigations regarding the
failing to exploit the principal advantage of absorptive and desorptive behaviour of loam
loam as a building material. have, however, demonstrated this assertion.
Mirrors in a bathroom that is tiled up to the
Earthen storage wall in winter ceiling have been observed to fog up after a
gardens normal hot shower. With doors and windows
closed, the mirror remains fogged up to a pe-
In order to enhance the thermal storage and riod of 30 to 60 minutes after the shower. In
14.72 the humidity balancing effect of a winter gar- a bathroom with loam walls, by contrast, the
den with a floor area of 20 m2, forming part mirror clears under similar conditions in only
of a residence at Kassel, Germany, a storage 3 to 6 minutes. This is because loam walls
14.64 to 14.67 Prototype dome (BRI) wall made of wet plastic loam loaves was absorb humidity from the room when its rel-
14.68 Jack arch with minimised formwork built (14.71 and 14.72). ative humidity is higher than about 50%, and
14.69 Dome, utilising moist sand as formwork The loaves, measuring 20 × 14 cm, were release it later when the air humidity falls be-
14.70 Completed vault in a private residence in formed by hand and stacked without mortar low about 50% (see also chapter 1, p. 12).
Kassel, Germany or filled joints, thereby effectively doubling Since humidity in bathrooms with loam walls
14.71 Heat storage wall in a winter garden the surface of the loam that is active in ther- reduces quickly, fungus growth cannot occur,
14.72 Laying loaves of loam mal storage and humidity absorption and de- whereas in tiled bathrooms, the humidity re-
mains high over a longer period due to the The bedroom wall shown in 14.75 is both an
sealed surfaces, allowing fungus growth in external wall and a built-in closet. It is built
the joints of the tiles, especially joints grout- from stranglehm elements (see chapter 8,
ed with silicone material. While formaldehyde p. 78). The side partition walls of the ward-
in the joint mixture prevents this, it should be robe also buttress the exterior wall. The bam-
mentioned that this chemical is carcinogenic. boo rod, built in during construction, acts
Even the wall behind the shower can be of as a hanger rod, and also stiffens the side
loam, as long as the shower curtain wraps partition walls. On another external wall of
around to prevent it from getting splashed, this bedroom, shown in 8.23, p. 78, niches
see 14.77. Illustration 14.73 shows a “loam and ledges for storing personal effects were
wallpaper” over a bath tub. Old curtain fab- carved out of the stranglehm wall.
ric was dipped into clayey loam slurry and Shelves can be easily fixed between stran-
slapped onto the wall and sculpted with the glehm walls (see chapter 8, p. 78) or light-
fingers. This surface can easily be made wa- weight loam-filled hoses (see chapter 10,
ter-resistant by coating it with water repel- p. 90). Illustration 14.74 shows such shelves
lents, double-boiled linseed oil, waterglass and a mirror integrated into the wall. Illus-
or other paints and coatings. tration 14.77 shows a bathroom whose
central shower, adjacent planter and bath
Built-in furniture and sanitary tab are covered by loam-filled hoses. Even
objects from loam washbasins can be built from unbaked loam.
The example shown in 14.76 is made of a
As already indicated, the plasticity of loam al- special sandy loam with high binding force,
lows not only for the building of exterior walls, in which shrinkage cracks were totally avoid-
ceilings and floors but also of built-in furni- ed. To this mixture 6% double-boiled linseed
ture. For this, loam elements when still wet oil was added. After drying, the basin was
are particularly suitable as they can be given coated with a layer of linseed oil. The sink
a great variety of shapes; they also open up and washbasin shown in 14.74 and 14.76
new aesthetic possibilities. was used for 28 years without signs of de-
Weight
Aluminium 20/100 mm
Timber frame
14.78 14.80
15.1
Earth as a building material has lost its cred- houses with lightweight roofs and flexible
ibility chiefly because most modern houses wattle-and-daub walls – like the Guatemalan
with earth walls cannot withstand earth- house in 15.2 – can withstand earthquake
quakes, and because earth is viewed a build- shocks because of their ductility (flexibility).
ing material for the poor. In this context, it The quality of an earthquake-resistant struc-
is worth mentioning that a census conduct- ture can be expressed in the formula
ed by the Salvadoran government after the
earthquake of January 13, 2001 (measuring structural quality = resistance × ductility
7.6 on the Richter scale), states that adobes
houses were not worse affected than other This means that the lower the resistance of a
types of construction. On the other hand, given structure, the higher its flexibility must
many historical earth buildings have with- be, while the higher its flexibility, the lower
stood several strong earthquakes in recent the required resistance. It is not earth as a
centuries, for example the housing of the building material which is responsible for
Hakkas in China (15.1; 1.2) and many solid structural failures, but instead the structural
15.1 Toulou building of the Hakkas, China rammed earth fincas in Argentina. But also system of a given building and the layout of
its openings, as discussed in the following mass, and that deflection increases signifi-
sections. cantly with height. When designing two-sto-
Earthquakes are caused by the movements reyed buildings, therefore, it is advisable that
of tectonic plates or by volcanic activity. The the ground floor be built solid, while the up-
world’s most earthquake-prone regions are per floor is kept light, preferably with a flexi-
shown in 15.3. In Asia, earthquakes with in- ble framed structure. Heavy roofs with slabs,
tensities of 8 on the Richter scale have been slates and tiles should be avoided in princi-
recorded; in the Andes, ones measuring up ple. Walls usually fall outwards because they
to 8.7. Annually, nearly a hundred earth- lack a closed ring beam, sufficient bending
quakes are recorded with intensities above and shear strength, and because door and
6, and twenty with intensities above 7 on the window openings weaken the wall structure.
Richter scale. Several thousand people are Under seismic influences, forces are concen-
affected by earthquakes every year. trated into the corners of these openings,
15.4 Buildings are mainly struck by the horizontal creating cracks. In order to reduce the dan-
acceleration created by the movement of the ger of collapse, the following points should
earth. The vertical accelerations created by be kept in mind:
seismic activity are less then 50% of the hori- 1. Houses should not be located on inclined
zontal ones. sites (15.6).
Since loam buildings are rarely higher than 2. The building’s resonant frequency should
two storeys, this section mainly discuss- not match the frequency of the earth move-
es the earthquake resistance problems of ment during earthquakes. This means that
these kinds of buildings. heavy houses with solid construction should
In one- or two-storeyed buildings, the princi- not rest on hard rock bases, but instead on
pal danger during earthquakes is that walls sandy or silty soils. Light houses, however,
will fall out and roofs will come down. There- perform better on hard rock than on soft soil.
fore, one of the main structural tasks when 3. The different parts of a house should not
designing earthquake-resistant buildings is have foundations on different levels, nor
to insure that walls do not fall out. have differing heights. If they do, then they
should be structurally separated. Since sec-
Structural measures tions of different heights display differing
resonant frequencies, they should be al-
When designing for earthquake-prone zones, lowed to oscillate independently.
it should be considered that the seismic forc- 4. Plans should be as compact as possible,
15.5 es acting on a building are proportional to its and should be symmetrical. Circular plans
give better rigidity than rectangular ones domes should be sufficiently contained by
(15.4). ring beams, buttresses or ties.
5. Foundations have to act like stiff ring an- 15. Openings destabilise walls and should
chors, and should therefore be reinforced. be carefully proportioned (15.23). There
6. Foundations, walls and roofs should be are two basic approaches to designing for
well fixed to each other, the joints being able earthquake resistance. The first and most
to withstand the shear forces produced. commonly used method is to construct walls,
7. Walls must be stable against bending and roofs and their joints stiffly enough so that
shear forces. Masonry work must have fully they cannot break or be deformed under
15.7 filled joints and strong mortar. seismic loads. The second approach is to
8. Load-bearing masonry walls should endow the structure with sufficient ductility
have minimum thicknesses of 30 cm; their so that the kinetic energy of any seismic im-
heights should not exceed eight times their pact will be dissipated via deformation. This
thicknesses (15.5). is the more intelligent solution, especially as
9. Masonry walls should be stiffened with it entails fewer structural problems and ma-
piers at a minimum every 4 m (with minimum terials.
sections of 30 × 30 cm), or with posts that If, for example, a vertical wall with a framed
are structurally fixed in the foundation (i.e. structure stabilised by tensile diagonals
able to take movement) (15.7). is impacted horizontally from the right (as
10. Wall corners, joints between walls and shown in 15.9), there will be a concentration
across walls, as well as door openings have of stress on both ends of the tie leading from
to be stiffened by vertical posts of either lower left to upper right. Weakness, then, will
timber or reinforced concrete, which are occur first at these joints, possibly leading
structurally fixed in the foundation, or by but- to wall failure. An elastically framed struc-
tresses, so that horizontal forces do not open ture without diagonals, on the other hand –
these elements (15.8, 15.22). provided the corners are able to take some
15.2 Wattle-and-daub house after heavy earthquake, 11. Walls have to be finished on top by a ring moment and that no structural element is
Guatemala 1976 beam, which has to be adequately fixed to overloaded – usually allows deformation to
15.3 Earthquake-prone areas (Houben and Guillaud, the walls. occur without leading to wall collapse. In the
1984) 12. Extra lintels above doors and windows second case, obviously, the infill of the frame
15.4 Floor plans should be avoided, and should be formed by must also be somewhat flexible. Therefore,
15.5 Wall proportion ring beams (15.21). walls built with the wattle-and-daub tech-
15.6 Location of houses on a slope 13. Roofs should be as light as possible. nique in which a flexible network of horizon-
15.7 Adobe walls, stabilised by buttresses 14. The horizontal thrusts of vaults and tal and vertical components is plastered with
15.10
loam, for example, are less prone to damage large cracks after the second stroke (15.11).
than masonry walls. Illustration 15.1 shows After three strokes, one section of the wall
a house in Guatemala that was struck by a separated (15.12), and after four strokes the
heavy earthquake and was flexible enough house collapsed (15.13). The rammed earth
to withstand the stress. There are three dif- house with circular plan, however, displayed
15.8 ferent general principles for designing earth- initial cracks only after three strokes (15.14),
quake-resistant structures: and one small section of the wall separat-
1. Walls and roof are well interconnected and ed only after six strokes (15.15) (Yazdani,
rigid enough that no deformation occurs dur- 1985).
ing earthquakes. A simple solution for stabilising rammed
2. Walls are flexible (ductile) enough so that earth walls of lesser thicknesses is to use
the kinetic energy of the earthquake is ab- L, T, U, X, Y or Z shaped elements (15.17).
15.9 sorbed by deformation. In this case it is nec- Due to their angles, they have better stability
essary to install a ring beam strong enough against lateral forces. If a wall is 30 cm thick,
to take bending forces; the joints between the free ends of the elements should not be
wall and ring beam, and ring beam and roof longer than 3/4 and no shorter than 1/3 of
must be strong enough. their heights (15.19). This minimal length
3. The walls are designed as mentioned un- is necessary to transfer loads diagonally to
der 2, but the roof is fixed to columns that the plinth or foundation. If the free ends are
are separated from the wall, so that both longer than 3/4 of their heights, they should
structural systems can move independently, be stabilised by another angle. If the angle
since they have different frequencies during is well fixed on the bottom to the plinth and
an earthquake. on the top to a ring beam, it should be larger
Three research projects undertaken by the or higher. Nevertheless, height should not ex-
15.8 Stabilisation of walls
Building Research Laboratory, University ceed the width by eight times (15.6).
15.9 Destabilisation through horizontal impact of
a vertical wall with a framed structure stabilised by
of Kassel, Germany, analysing earthquake The forces perpendicular to the wall are
tensile diagonals damage to single-story rural houses in Gua- transferred into the angle parallel to the di-
15.10 Typical design mistakes which might lead to a temala, Argentina and Chile, concluded that rection of force. This means that it is trans-
collapse of the house the same errors in structural design consist- ferred, instead of creating a concentration of
15.11 to 15.15 Earthquake tests with models of ently led to collapse. The ten principal mis- stress at the inner corner of the angle. It is
square and circular shape (Minke, 2002) takes are listed in 15.10. advisable, therefore, to enlarge the section
15.16 Simple test to study the influence of wall At the BRI, a simple test was developed with- at this corner, as shown in 15.17 and 15.18.
shape on resistance to seismic shocks (BRI) in the context of a doctoral thesis to show
15.17 Elements with correct corner details the influence of wall shape on resistance to Openings for doors and windows
15.18 Corner solution seismic shocks. A weight of 40 kg at the end
15.19 Recommended proportions of a 5.5-m-long pendulum was allowed to fall Wall apertures will destabilise a wall sys-
15.20 Typical failures caused by seismic movements against a model (15.16). The rammed earth tem. During earthquakes, diagonal cracks
(Tolles et al., 2000) house with a square plan showed the first often occur, starting at the window edges
15.14 15.15
15.17 15.18
15.16 15.19
15.20
15.22
(15.20). In order to achieve a good bond, (CEMAT), both in Guatemala (15.25 to 15.29). then painted with a mixture made of one
lintels must penetrate at least 40 cm into In this project, 80-cm-wide and one-storey- bag of hydraulic lime, 2 kg common salt,
the wall (15.21). In this case, however, the high bamboo-reinforced rammed earth el- 1 kg alum, 1 kg clayey soil and about 40 li-
area above the lintel may be weak and may ements were constructed using a T-shaped tres of water.
come off during an earthquake, so the best metal formwork 80 cm wide, 40 cm high In 1998 the BRI developed another rein-
solution is to use the lintel as a ring beam on and 14 to 30 cm thick (15.28). The stability forced rammed earth wall system that was
which the roof structure rests. It is also rec- of the wall was provided by four builtin bam- utilised for a low-cost housing project built in
ommended that the section below the win- boo rods 2 to 3 cm thick and the T-shaped cooperation with the University of Santiago
dow be built as a light, flexible structure, for section of the wall element. These elements de Chile in Alhué, Chile, in 2001 (15.30 and
instance from wooden panels or wattle and were fixed at the bottom to a bamboo ring 15.31). Here too, the idea was to separate
daub. The following rules have to be taken anchor that was embedded in the stone ma- the roof from the wall system and to use
into account (15.23 and 15.24). sonry plinth, and attached at the top to a rec- U-shape and L-shape elements, which stabi-
a) The width of a window should not be more tangular bamboo ring anchor. lise themselves by their shape.
than 1.2 m and not more than 1/3 of the Due to the rib that was integrated into the wall To obtain additional stability, they were re-
length of the wall. element, this element has about four times inforced by vertical rods of coligüe (similar
b) The length of walls between openings stronger resistance against horizontal forces to bamboo), 3 to 5 cm in diameter. Wall el-
must be at least 1/3 of their height and not than a 14 cm wall alone would have had. ements were also always separated by light,
less than 1 m. After drying, a 2 cm vertical gap appears be- flexible elements, or by doors and windows.
c) Doors must open outwards. Opposite the tween these elements. This is then packed The lower parts of the windows and the parts
entrance door should be a large window or with loam. This joint acts as a pre-designed above the doors were not built with solid el-
another door, which acts emergency exit failure joint, allowing an independent move- ements, but of light timber. The gables were
(15.24). ment of each element during the earth- built in lightweight straw-loam stabilised by
quake. wooden elements, similar to the wattle-and-
Bamboo-reinforced rammed earth This means that these joints can open and daub system.
walls the whole structure can deform (dissipating
seismic kinetic energy) without the wall unit Steel-reinforced sprayed loam
A bamboo-reinforced panelled rammed breaking or falling. The posts on which the walls
earth wall technique was developed in 1978 roof rests are located 50 cm away from the
as part of a research project by the BRI, walls (15.27) on the inside, so that the roof Two techniques utilising sprayed loam for
and successfully implemented jointly with structure is independent of the wall system. earthquake-resistant structures that employ a
the Francisco Marroquín University (UFM) The rammed earth surface was not plas- steel reinforcement respectively a steel skele-
and the Centre for Appropriate Technology tered, but only smoothed by a trowel and ton are described in detail on pp. 82–84.
15.29 15.30
+ 225 cm
OSB, 9 mm thick
Lightweight loam
Pine, 50.8 mm (2") Post 102 × 127 mm
(4 × 5")
Ring beam, ø 127 mm (5")
Vertical reinforcement (coligüe), ø Wooden reinforcement,
76 mm (3") @ 60 cm 25 × 102 mm
(1 × 4")(4 × 5")
Rammed earth
Damp-proofing
Floor
Damp-proofing
+/- 0.0
Sand
Steel support,
Fine gravel 6 mm thick
Coarse gravel
Stone
Natural ground
Compacted earth
Reinforcement (coligüe)
Stones
Footing (poor concrete)
15.32
Steel-reinforced adobe wall system in height, built in La Paz, Bolivia, in 2000. inner third of the surface of the foundation.
The dome is stabilised by two reinforced con- This means that eccentricity should be less
The foundation Tierra Viva from Colombia crete ring beams, one at the bottom of the than 1/6. The foundation must have a re-
used adobes with two holes through which dome, another at the top of the foundation. inforced concrete or steel beam, which can
steel-reinforcement bars can be threaded In order to provide good sound distribution also withstand the additional horizontal forc-
and cement slurry poured, see p. 146. within the dome, the adobes were made by es created by an earthquake (15.38). Illus-
hand in a special mould with rounded edges. tration 15.37 shows a section of a building
Domes The acoustic behaviour of the dome was fur- which was built in an earthquake-prone area
ther refined by deepening the vertical joints in Bolivia. Its plinth has structurally danger-
In order to construct a structurally optimised in order to achieve some sound absorption ous proportions, as the resultant force from
dome without formwork, the BRI developed and by a slight cantilevering position, which the vault creates a bending moment in the
a rotational guide that is fixed to a vertical prevents the sound from being focused to- plinth and does not stay within the inner third
mast. An angle is fixed at the end of the ro- wards the centre of the dome. of the wall, as necessary. This structure will
tating arm, against which the mason lays the readily collapse when hit by an earthquake.
adobe or soil block, allowing block to be po- Vaults The cross-section of a vault is very important
sitioned with precision. Illustrations 15.33 to for stability. For vaults that carry only their
15.36 show the application of this construc- An important rule for the design of plinth and own dead loads, an inverted catenary is the
tion technique for an earthquake-resistant foundation is that the resulting force at the optimal section, as no bending moments
dome with an 8.8 m free span that is 5.5 m bottom of the vault must pass through the will occur within the vault. Pointed vaults, as
15.37 15.38
15.36
15.41 15.43
15.44 15.45
shown in 15.39, or “flat” vaults as shown in guarantee a certain degree of ductility, was tensile forces during an earthquake. Above
15.40, typical for Iranian architecture, col- realised in a test structure built in 2001 at the adobe vault, a membrane of PVC-coat-
lapse very easily when hit by seismic shocks, the University of Kassel, Germany (15.42 to ed polyester fabric was fixed and tightened
whereas the vault in 15.41 withstood the 15.45). It was built using special U-shaped to the plinth. This has two functions: first,
heavy earthquake in Bam, Iran, in December adobes that rest on an arch, itself built of it provides shelter against rain and wind;
2003. Only the front part fell off. (cf. Beygi three layers of split bamboo. The bamboo second, it pre-tensions the arch, thereby
and Khosravi, 2020, on reconstruction ef- sections were soaked in water for 3 days in increasing its stability against tremors dur-
forts). The best solution for the facades of order to render them flexible. Then they were ing earthquakes. Such tremors may deform
vaults is to build them to be light and flexible, bent over sticks, which were pushed into the vault to a certain extent, causing adobe
either of mats covered with earth plaster, or the ground along a catenary curve (15.43). joints to open, but the vault will not collapse,
of timber planks. To maintain the shape of the arch, the three since it is held up by the tensile pre-stressed
Illustration 15.38 shows a design by the au- bamboo sections were wrapped together membrane at the top and the compressive
thor for an earthquake-resistant low-cost with galvanised steel wire at 50 cm intervals. prestressed bamboo arch underneath. The
housing project in the region of Gujarat, India. The arch was vertically positioned and fixed stability of this structure, then, depends
In 2001, a proposal by the author for stabilis- to steel bars that stick out of the plinth. This mainly on its ductility. However, it must be
ing adobe vaults with bamboo arches, which connection must be capable of absorbing taken into account that if the pre-tension of
143 Vaults
@arclib
@arclib
15.46
the membrane is high, the optimal section Thin wooden posts are hammered into the
of the vault is more like an ellipse and not a ground, and the fabric fixed to these from the
reversed catenary. inside. The space between is filled with soil.
For earthquake regions in Argentina and The research also showed that wall elements
Iran, the author developed a similar preten- of this type without infill can be prefabricat-
sioned system for mud brick vaults. Illustra- ed to lengths of up to 10 m and then folded
tion 15.46 shows a design for an orphanage and rolled up into small bundles (15.48 and
building in Bam, Iran, where vaults are con- 15.49).
structed with thicknesses of 25 cm. They are The second system consists of hoses of jute
pre-tensioned by steel strips, which are tight- fabric filled with pumice or sandy soil (15.51).
ened to the reinforced concrete ring beam The fabric is covered with several layers of
at the bottom of the vault. Equal pre-tension lime paint (15.52) in order to prevent rotting
forces in all parts are ensured by using a cal- of the material and to stabilise the surface
ibrated torque wrench. The optimal section and make it waterproof.
of the vault is derived by a computer pro- As part of a cooperative research project of
gramme. This system was successfully test- the BRI with UFM and CEMAT from Guatema-
ed in full scale on the earthquake-simulation la in 1978, a 55 m2 low-cost prototype house
table of the Catholic University at Lima, Peru. was erected in Guatemala using earth-filled
The video of this test can be seen at hoses for the walls. This technique, devel-
www.gernotminke.de/Publikationen oped during experiments with the earth-filled
hose technique described earlier, and adapt-
Textile walls with loam infill ed to local conditions in Guatemala (15.53 to
15.55), shows very good earthquake resist-
A BRI research project begun in 1977 exam- ance due to its ductility.
ined various approaches to forming walls us- Here, the hoses, measuring 10 cm in diame-
ing textile components filled with clayey soil, ter, were made from cotton fabric, and were
pumice or sand. filled with volcanic soil containing mainly
Illustration 15.47 shows the dome structure pumice. They were dipped into lime milk (in
built in 1977, from earth-filled polyester hos- order to prevent rotting of the fabric), and
15.46 Design for an orphanage in Bam, Iran es. then stacked between twin vertical posts
15.47 Dome, Kassel, Germany, 1997 Two newly developed systems were tested erected at distances of 2.25 m.
15.48 and 15.49 Prefabricated wall elements in a prototypical low-cost house intended for Additional stability was provided by bam-
15.50 Prototype building, Kassel, Germany, 1978 earthquake-prone areas in developing coun- boo rods fixed vertically at a spacing of
15.51 and 15.52 Prototype building, Kassel, tries. The first, illustrated in 15.50, consisted 45 cm within each panel. After the walls were
Germany of walls formed by two layers of jute fabric. stacked, they were finished with two layers of
15.47 15.49
15.50
15.51 15.52
15.55
15.54
lime paint. The roof structure rests on inde- tar drops into those holes, which are to be
pendent posts located 50 cm away from the filled with steel and cement, a plastic tube is
walls on the inside. The material costs of this inserted (15.56). The vertical bars are con-
structure were only about one half the cost nected to the horizontal concrete beams. Ad-
of a comparable house made of cement con- ditional horizontal reinforcement is given by
crete blocks. Walls built of fabric hoses filled steel bars inserted in the mortar layers. The
with mineral lightweight loam are described columns are reinforced by vertical steel bars
in chapter 10, p. 90 and chapter 14, p. 131. threaded through the holes (15.58). The sys-
tem was used for the Casa Viva settlement
Steel-reinforced earth walls in Vigachí, Colombia, a pilot project for social
housing of the government of Antioquia. The
Another possibility of creating earthquaker- 104 houses were built for 650 people and
esistant masonry walls from compressed have either one or two storeys (15.60). For
earth blocks was developed by the Tierra the project 401,440 blocks were produced.
Viva Foundation in Barichara, Colombia. The
blocks are made of local soil and stabilised
by 8% of cement. They were produced by
a manually operated press. They show two
holes, into which steel reinforcement bars
can be inserted and cement slurry can be
filled (15.57). In order to prevent that mor-
15.59
15.59
15.56 to 15.58 Reinforc-
15.59 ing steel rods are thread-
15.56 to 15.58 Reinforc- ed through the com-
ing steel rods are thread- pressed earth blocks and
ed through the com- additional horizontal
pressed earth blocks and reinforcement is added
additional horizontal 15.59 The social housing
reinforcement is added project under constructi-
15.59 The social housing on
project under constructi- 15.60 Casa Viva settle-
on ment in Vigachí, Colombia
15.60 Casa Viva settle-
ment in Vigachí, Colombia
15.60 15.60
Vineyard residence
Mornington Peninsula, Victoria,
Australia
NATURAL PLANTING
DECK
STONE TERRACE
at summer times.
LAWN
VEGETABLE GARDEN
MEADOW
0 0.5 1 2 5 10 m
0 0.5 1 2 5 10 m
West elevation
157 Residences
@arclib
@arclib
Desert Outpost residence
Paradise Valley, Arizona, USA
ing System (HERS) was performed, ranking 8 Floor joists 16 Column GLASS PANELS ALONG FRONT OF ROOMS
EXHAUST FAN
CONCRETE SLAB
FLOOR
CONCRETE SLAB
HALF WALL
CONCRETE SLAB
FLOOR W/1" INSULATED
FOAM
Peñalolén is a community in the eastern sec- were built with earth and straw, and the fine
tor of Santiago de Chile, towards the moun- stuccos were stabilised with earth and sand,
tains. The Los Maitenes Condominiums are thus avoiding the use of cementitious addi-
located on a 4000 m2 plot of land and con- tives. During the construction process of the
sist of eight houses of 140 m2 each. The pro- homes, dozens of free practical workshops
ject faced two major challenges: first, it oc- on quincha and planting plant species were
cupied a site where all the native vegetation held with children, students and teachers
had been cut down and where 7000 m³ of to educate them about the importance of
fill material had been dumped. Thus, the soil regenerative and sustainable construction.
had to be improved to allow for the return of All houses were given a green roof, which
vegetation. Second, each of the houses – on provides excellent thermal insulation both in
a hill with a steep slope – had to be provided summer and winter while creating attractive
with an access from the street. conditions for birds and pollinating insects.
To ensure a minimal carbon footprint, the Green spaces account for 80% of the pro-
quincha technique was used as construction ject’s surface area, providing a high quality
system. The name derives from the Que- of life for its inhabitants and enhancing bio-
chua language and refers to walls, or fences, diversity on the site.
made of three materials: bamboo (or cane), The entire complex treats wastewater
woven bark panels (for reinforcement) and through a treatment plant (wetland) located
earth or mud to cover the structure. Essen- in the common square, which is then used to
tially, quincha is a post-and-beam structure irrigate common areas as well as the green
with infill of earth and straw. Earth from the roofs and gardens of each house, reducing
excavations was used for the insulation and water consumption by 80%.
plastering of the units; the rocks for the walls Most of the rainwater is captured and the
and landscaping were also found on the site, rest can infiltrate into the ground through the
thus achieving a substantial reduction of water-permeable pavement. Inside, recycled
construction waste. parquet was used and wooden windows with
The construction system only includes ce- thermopane achieve a good thermal perfor-
ment in the foundations of the houses and in mance.
the retaining walls, all the rest of the houses
R
R
SC
W
14 x 0,19 = 2,70
R
13 2
12 3
11 4
10 5
R
6
7
W W
W
LV
SC
FR SC
2% 2%
R
S H AFT
1
14 x 0,19 = 2,70 2
13
12 3
11 4
10 5
R
6
7
8
9
R
LV
R
SC W
FR SC
SC W
WISE Centre for Alternative circular rammed earth wall with a thickness
of 50 cm, a height of 7 m and an outside
Architect: Pat Borer, David Lea, Penybont- the case of someone leaning against the
wall. Since the site itself is a slate quarry and
fawr, Powys, UK had no soil, the material (some 300 tonnes)
was sourced from a quarry some 70 km
Consultant: Rowland Keable, Rammed away that supplied an overburden of 'scalp-
ings' and sieved it to 6 mm. The earth had
Earth Consulting excellent properties and was dry enough.
Section B-B
60 years. 4
8
A linear arrangement
West of buildings was de- 5
East
graveside. 5. Sloping floor paved in earth brown encaustic tiles 11. Corten steel doors 4
8
a corner of the sloping site. Rammed earth, 2 Oak slats to walls and sloping ceiling 8 Rammed earth walls exposed internally 00 5m
5m
3 Glulam roof structure 9 400-mm-thick rammed earth wall
sourced from the site, defines the overall 4 Oak bench 10 Corten steel canopy
design and was chosen for its symbolic and 5 Sloping floor paved in earth brown encaustic 11 Corten steel doors
tiles
practical sensitivity to the Jewish faith, echo- KEY 6 Zinc standing seam roof
1. Larch glulam canopy 7. Blown glass pendant light
ing the traditional sentiment of the deceased 2. Oak slats to walls and sloping ceiling 8. Rammed earth walls exposed internally
3. Glulam roof structure 9. 400mm thick rammed earth wall
being laid to rest in plain wooden caskets, 4. Oak bench 10. Corten steel canopy
“returning to the earth”. 5. Sloping floor paved in earth brown encaustic tiles 11. Corten steel doors
6. Zinc standing seam roof
The rammed earth walls are left exposed
and create a calm, peaceful atmosphere. BUSH E Y CEM E T ERY PR AY ER HALL S
0 2 4 10 20 m
0 0.5 1 2.5 5m
0 10 20 40 m
Boemans, U.: Sanierung und Umnutzung einer DIN 18952 Blatt 2: Baulehm, Prüfung von Ellington, Karl Johan: Modern Pisé-build-
Fachwerkscheune,. University of Kassel, 1990. Baulehm, October 1956. ing, House-building with Compressed Or
Rammed Earth. 2022.
Boenkendorf, Ulf; Knöfel, D.: “Les mortiers DIN 18954 Vornorm: Ausführung von
d'enduit dans la construction en pan de Lehmbauten, Richtlinie, May 1956. Fathy, H.: Natural Energy and Vernacular
bois”, in: Proceedings of the International Architecture, Chicago and London, 1986.
Congress on the Conservation of Stone and DIN 18957 Lehmschindeldach, May 1956.
Other Materials, Unesco/Rilem, Paris, Gilly, David: Praktische Abhandlung aus
June 29–July 1, 1993. DIN 4102-3:1977-09. Brandverhalten von der Lehmbaukunst betreffend den Bau der
Baustoffen und Bauteilen; Brandwände sogenannten Lehm- oder Wellerwände,
Boltshauser, Roger; Veillon, Cyril; Maillard, und nichttragende Außenwände, Begriffe, wie man dieselben dauerhaft mit wenigen
Nadja (eds.): Pisé. Rammed Earth – Tradition Anforderungen und Prüfungen (Fire be- Kosten und einer wahren Holzersparung
and Potential, Zurich: Triest Verlag, 2019. haviour of building materials and building aufführen könne, Berlin, 1787.
components; fire walls and non-load-bearing
Bourgeois, J.-L.: “Traditional Adobe is Illegal external walls; Definitions, requirements and Gilly, David: Beschreibung einer vorteilhaften
in New Mexico”, in: Adobe Journal, no. 5, tests), Berlin: Beuth Verlag, 1977. Bauart mit getrockneten Lehmziegeln, Berlin,
1991, p. 47. 1790.
DIN 18127:2012-09. Baugrund, Untersu-
Copinger Hill, Rev.: “On the Construction of chung von Bodenproben – Proctorversuch Gilly, David: Handbuch der Land-Bau-Kunst,
Cottages”, in: Journal of the Royal Agricultural (Soil, investigation and testing – Proctor-test), vorzüglich in Rücksicht auf die Construction
Society, vol. 4, London, 1843, pp. 356–369. Berlin: Beuth Verlag, 2012. der Wohn- und Wirthschafts-Gebäude für an-
gehende Kameral-Baumeister u. Ökonomen,
Cointeraux, François: L‘école d'architecture DIN 18947:2018-12. Lehmputzmörtel – Braunschweig and Halle, 1797 and 1822.
rurale (1790). German translation: Schule Anforderungen, Prüfung und Kennzeichnung
der Landbaukunst, Hildburghausen, 1793. (Earth plasters – Requirements, test and Gotthard, H.: “Über physikalische Eigenschaf-
labelling), Berlin: Beuth Verlag, 2018. ten des Baustoffes Lehm”, in: Naturbauweis-
CRATerre: Construire en terre, Paris, 1979. en, no. 5, 1949.
234 Bibliography
@arclib
@arclib
Grandjean, Etienne: Wohnphysiologie. Guide, Gabriola Island, BC: New Society tional Symposium of Hassan Fathy for
Grundlagen gesunden Wohnens, Zurich: Publishing, 2019. Architecture for the Poor, April 20–22, 1993,
Verlag für Architektur, 1973. Cairo, 1993.
Künzel, H.: “Die hygrothermische
Güntzel, J. G.: Zur Geschichte des Lehmbaus Beanspruchung von Außenputzen”, in: Minke, Gernot: “Humidity Control/Balancing
in Deutschland, Dissertation, University of Bauphysik, no. 4, 1990, pp. 104–109. Humidity Fluctuations”, in: Bansal, Narenda
Kassel, Staufen, 1986. K.; Hauser, Gerd; Minke, Gernot: Passive
Lepic, Andres; Beygo, Ayça: Francis Kéré. Building Design. A Handbook of Natural
Heringer, Anna; Howe, Lindsay Blair; Rauch, Radically Simple, Fundación ICO/Arquitectu- Climatic Control, Amsterdam: Elsevier, 1994,
Martin: Upscaling Earth. Material, Process, ra Viva and Berlin: Hatje Cantz, 2016. pp. 180–188.
Catalyst, Zurich: gta Verlag, 2019.
Leszner, T.; Stein, J.: Lehm-Fachwerk. Alte Minke, Gernot; Mukerji, K.: Structurally
Hofmann, U.; Schembra, F. W. et al.: “Die Technik neu entdeckt, Cologne, 1999. Optimized Domes – A Manual of Design and
Trockenbiegefestigkeit von Kaolinen und Construction, Braunschweig, 1995.
Tonen”, in: Berichte der Deutschen keramis- Manandhar, R.: “Mud Brick Dome and Vault
chen Gesellschaft, vol. 44, no. 4, 1967, pp. Construction”, in: Proceedings of the First Minke, Gernot: Construction Manual for
131–140. International Earth Sheltered Buildings Earthquake-Resistant Houses Built of Earth,
Conference, August 1–6, 1983, Sydney, Eschborn: GTZ, 2002.
Houben, Hugo; Guillaud, Hubert: Earth 1983, pp. 371–375.
Construction Primer, Brussels, 1984. Minke, G.: “Shrinkage, Abrasion, Erosion of
Marmé, W.; Seeberger, J.: “Der Primärener- Clay Plasters”, in: Informes de la construc-
Ingles, O. G.; Metcalf, J. B.: Soil Stabilisation, gieinhalt von Baustoffen”, in: Bauphysik, ción, no. 523, pp. 153–158, CSIC, Madrid,
Sydney, 1972. no. 5, 1982, pp. 155–169 and no. 6, 2011.
pp. 208–214.
International Labour Office (ed.): Small-Scale Minke, Gernot; Krick, Benjamin: Straw Bale
Manufacture of Stabilised Soil Blocks, McCann, J.: Clay and Cob Buildings, Construction Manual, Basel, 2020.
Geneva, 1987. Aylesbury, UK, 1983.
Morton, T.: Earth Masonry, Watford, UK,
Jain, J. P.; Kulshrestha, R. P.; Singh, I.: A New McHenry, P. G.: Adobe and Rammed Earth 2008.
Technique of Making Thatch Fire Retardant, Buildings, New York, 1984.
Technical Note, Central Building Institute, Mukerji, K.: Soil Block Presses: Product
Roorkee, India, 1978. McHenry, P. G.: The Adobe Story: A Global Information, Eschborn: GTZ, 1988.
Treasure, Albuquerque, 2000.
Karsten, Rudolf: Bauchemie für Studium und NCR 5324 Norma colombiana para fabri-
Praxis, Heidelberg: C. F. Müller Verlag, 10th Middleton, C. F.: Build Your House of Earth, cación de bloques de tierra estabilizada,
edition, 1997. Victoria, Australia, 1979 (revised edition). Bogota, 2011.
Keable, Julian; Keable, Rowland: Rammed Miller, T.; Grigutsch, E.; Schulze, K. W.: Niemeyer, Richard: Der Lehmbau und seine
Earth Structures. A Code of Practice, Rugby, Lehmbaufibel, Weimar, 1947. praktische Anwendung, Hamburg, 1946.
UK: Practical Action Publishing, 2011.
Minke, Gernot: “Earthquake-Resistant Low- OECD, Nuclear Energy Agency: “Exposure
Keefe, L.: Earth Building: Methods and Cost Houses Utilising Indigenous Building to Radiation from Natural Radioactivity in
Materials, Repair and Conservation, London, Materials and Intermediate Technology”, in: Building Material”, in: Report, May 1979,
2005. Proceedings, International Symposium on Paris, 1979.
Earthquake Relief in Less Industrialized
Knöfel, Dietbert: Bautenschutz mineralischer Areas, March 28–30, 1984, Zurich, 1984. Oliver, M.; Mesbah, A.: “The Earth as a
Baustoffe, Wiesbaden and Berlin, 1979. Material”, in: Proceedings International
Minke, Gernot: “Design and Construction Symposium on Modern Earth Construction,
Krahn, Tim J.: Essential Rammed Earth of Energy and Cost Saving Vault and Dome Beijng, 1985.
Construction. The Complete Step-By-Step Structures”, in: Proceedings of the Interna-
235 Bibliography
@arclib
@arclib
Pingel, M. and P.: Bericht über den Anstrich Schroder, L.; Ogletree, V.: Adobe Homes for Volhard, Franz: Bauen mit Leichtlehm. Hand-
der Lehmkuppeln ihres Hauses in Auroville, all Climates, White River Junction, Vermont, buch für das Bauen mit Holz und Lehm, 9th
Indien, unpublished document, 1993. 2010. revised edition, Basel: Birkhäuser, 2021
Popposwamy, G.: Rural India. Village Houses Sibtain, S. N.: To Build a Village – Earth- Volz, Michael: “Protecting wood”, in: Herzog,
in Rammed Earth, Stuttgart, 1979. quake-resistant Rural Architecture, Thomas; Natterer, Julius; Schweitzer,
Parramatta, Australia 1982. Roland; Volz, Michael; Winter, Wolfgang:
Pumpelly, R. (ed.): Explorations in Turkestan, Timber Construction Manual, Basel:
Washington, 1908. Smith, R. G.; Webb, D. T. J.: Small Scale Birkhäuser and Munich: Edition DETAIL,
Manufacture of Stabilized Soil Bricks, 2004, pp. 60–63.
Rael, R.: Earth Architecture, New York, 2009. Technical Memorandum, no. 12, Inter-
national Labour Office, Geneva, 1987. Vorhauer, K.: Low Cost/Self Help Housing,
Rauch, Martin; Kapfinger, Otto: Rammed Gate Modul 6/6, Eschborn: GTZ, 1979.
Earth/Lehm und Architektur/Terra cruda, Streiff, François; Goodhew, Steve; Morton,
Basel: Birkhäuser, 2001. Tom; Boutouil, Mohamed; Le Guern, Malo; Voth, Berthold: Boden, Baugrund und
Touati, Karim; Rattier, Raphaël; Hudson, Baustoff. Bautechnische Eigenschaften und
Rauch, Martin: "Unstabilised rammed earth – Anthony; Gualous Louahlia, Hasna: “Cob- Kenngrößen, Wiesbaden: Bauverlag, 1978.
100% EARTH. Why is it so hard to trust in Bauge – A hybrid walling technique combin-
100%?", in: Proceedings of 8th Internation- ing mechanical and thermal performance”, Walker, Peter; Keable, Rowland; Martin, Joe;
al Conference on Building with Earth, 30 in: Proceedings of 8th International Confer- Maniatidis, Vasilios: Rammed Earth. Design
October–1 November 2020. https://www. ence on Building with Earth, 30 October–1 and Construction Guidelines (EP 62),
dachverband-lehm.de/lehm2020_online/ November 2020. https://www.dachver- Bracknell, UK: IHS BRE Press, 2005.
pdf/lehm2020_b_rauch_en.pdf, accessed band-lehm.de/lehm2020_online/pdf/
3 October 2021. lehm2020_b_streiff-goodhew-et-al_en.pdf, Wehlte, Kurt: Werkstoffe und Techniken der
accessed 19 July 2021. Malerei, Ravensburg: Maier, 5th edition,
Röhlen, Ulrich; Ziegert, Christof: Earth 1985.
Building Practise. Planning – Design – Stulz, R.; Mukerji, K.: Appropriate Building
Building, Berlin: Beuth Verlag, 2011. Materials, St. Gallen, Switzerland, 1988. Weismann, A.; Bryce, K.: Building with Cob.
Dartington, Totnes, Devon, UK, 2006.
Sauer, Marko; Kapfinger, Otto (eds.): Martin Tolles, E. L. et al.: Seismic Stabilisation of
Rauch. Refined Earth Construction & Design Historic Adobe Structures, Los Angeles: The Weiss, A.: “A Secret of Chinese Porcelain
with Rammed Earth, Munich: Edition Getty Conservation Institute, 2000. Manufacture”, in: Angewandte Chemie,
DETAIL, 2015. vol. 75, 1963, pp. 755–762.
Turowski, R.: Entlastung der Rohstoff- und
Schittich, Christian (ed.): Vernacular Primärenergiebilanz der Bundesrepublik Weller, K.; Rehberg, S.: Lösungsansätze
Architecture. Atlas for Living Throughout Deutschland durch Recycling von Hausmüll, für den energie- und rohstoffsparenden
the World, Basel: Birkhäuser, 2019, Berichte der Kernforschungsanlage Jülich, Wohnungsbau, DFG research project,
pp. 172–189. no. 1453, Jülich, 1977. Technical University of Berlin, 1979.
Schmitt, C.: Leichtlehmbau, BPS-I Report, United Nations Centre for Human Settle- Yazdani, H.: Erhöhung der Lebensdauer
University of Kassel, unpublished document, ments (ed.): Earth Construction Technology, von Lehmbauten in erdbebengefährdeten
1993. Nairobi, 1992. Gebieten Afghanistans, Dissertation, Kassel
University, 1985.
Schreckenbach, Hannah; Abankwa, Jackson Vanros, Guy: Studie van bouwfysische Ken-
G. K.: Construction Technology for a Tropical merken van Lemen Vakwerkwanden, thesis, Zawistowski, Keith; Zawistowski, Marie;
Developing Country, Eschborn: GTZ and Uni- Catholic University of Leuven, 1981. Joffroy, Thierry: “Evolving Vernacular: Re-
versity of Science and Technology, Kumasi, inventing Rammed Earth in the Context of
Ghana, 1983. Volhard, Franz: Light Earth Building. A Twenty-First Century Seismic Regulation”, in:
Handbook for Building with Wood and Earth, Technology Ι Architecture + Design – TAD,
Basel: Birkhäuser, 2016. vol. 4, 2, 2020.
236 Bibliography
@arclib
@arclib
About the author
In 1974, Gernot Minke founded the Research Laboratory for Experimental Building (FEB) at
the University of Kassel, devoted to the exploration of natural building materials. At this lab-
oratory, he directed more than 40 research and development projects in the field of building
with earth, building with straw, green roofs and low-cost housing. He taught at the University of
Kassel for more than 35 years and was the invited speaker at more than 60 international con-
ferences. Minke is also an independent architect and worldwide advisor for building ecology
as well as the author of numerous articles and several technical books, among them Building
with Bamboo (Third and revised edition 2023) and Straw Bale Construction Manual (2020).
Illustration credits Hörbst, Kurt: pp. 176–177; p. 194 top; p. centre; bottom left and right
195; p. 197 Naturbo: 7.18–7.20
Front cover: Iago Corazza Huber, Samuel: p. 179 top Norman, Ann: p. 210; p. 211 top
Back cover: Federico Cairoli; Gernot Minke; Hueber, Eduard – archphoto/design- North, Graeme: pp. 152–153
Eduard Hueber – archphoto/designbuild- build-LAB: p. 206; p. 207 top left, bottom Oliver, D.: 5.23; 5.24
LAB; Trevor Mein (from top to bottom) left and bottom right, 209 top Picador Pictures/Shutterstock: 1.5
Janisch, Jörg: p. 168 bottom; p. 169 bottom Rammed Earth Works: 5.19–5.21
right Reyna, Victoria: p. 200
Aureka Equipment Inc., Auroville, India: 6.13 Keable, Rowland: p. 203 middle row, right Reynolds, M.: 14.4
Baan, Iwan: pp. 156–157 Kéré Architecture: p. 202; pp. 204–205 Rodríguez, Oscar Hernández: pp. 162–163
Bilbao, Tatiana: p. 156 (model) Khan, Lewis/Waugh Thistleton: p. 186; Schijns, W.: 14.24
Blanco Barros, Pablo: pp. 164–167 p. 187 top; pp. 188–189 Schreckenbach and Abankwa: 8.8
Borer, Pat: p. 180 bottom right Kittelty, Trevor/Shutterstock: 1.6 Sharon Davis Design: p. 218
Breshna: 14.29 Klomfar, Bruno: p. 178; p. 179 bottom Soar, Tim: p. 180 top and bottom left; p. 181
Browell, Anthony: p. 174; p. 175 bottom left Lehm Ton Erde Baukunst GmbH/Emmanuel Stanwix, Will: p. 192 top left and right, p. 193
and right Dorsaz: 5.30–5.34 Stephenson, Jim/Waugh Thistleton: p. 187
Cerveny, Ludmilla/designbuildLAB: p. 209 Lehmwerk Kleinfahner: 7.9; 7.10 bottom
bottom Lespinasse, Lauriane/designbuild LAB: Tatay, Fernando/Shutterstock: 1.3
Cairoli, Federico: p. 220 top; p. 221, p. 223 p. 207 top right; p. 208 Tierra Viva: 15.56–15.60
Castaño, Diego: p. 198; p. 201 LEVS architecten: pp. 182–185 Timmerman, Bill: pp. 158–159
Castaño, Diego; Matias Villegas: p. 199 Lorenz-Ladener, C.: 6.5 Wacker Neuson: 5.10; 5.11
Clare, Lindsay: p. 175 top Lukas, G.: 8.9; 8.10 WASP: p. 229 centre, bottom
Claytec: 7.11–7.17 Mein, Trevor: pp. 148–149 Weller, K.: 6.14; 6.15
Corazza, Iago: p. 228, 229 top Mendez, Leonardo: p. 222 WEM: 7.21–7.22
Dorazillo, Marc/haascookemmrich STUDIO Michel, Thomas J.: 1.12 WikiCommons/Bernard Gagnon: 14.28
2050: p. 216 top Minke, Gernot: S. 6; 1.1; 1.4; 1.10; 1.11; WikiCommons/John Mackenzie Burke: 6.3
Dufter, Sylvester: 7.1, 7.2 1.13; 1.15; 1.16–1.23; 2.1–2.43; 3.1–3.12; WikiCommons/Maria Gropas: 6.2
Dwell Earth, New Hampshire, USA: 6.12 4.1–4.21; 5.1–5.9; 5.13–5.18; 5.22; 5.25; WikiCommons/Oliver Abels: 1.14
Felicella, Elizabeth: pp. 216–217; p. 219 5.26; 5.28; 5.29; 5.35–5.37; 6.1; 6.4; Wikimapia/Ebrahim Keikhosro Kiani: 1.8
Fletcher, Joe: pp. 154–155 6.6–6.10; 6.16–6.28; 7.3–7.8; 7.23–7.26; Wolf, S.: 5.27
Florio, James: pp. 160–161 8.1–8.7; 8.11–8.29; 9.1–9.12; 9.19–9.21; Wright, C.: 9.13–9.18
Gerster-Rapho: 1.9 10.1–10.27; 11.1–11.19; 12.1–12.8; Wrigley, Ben: pp. 212–213
Halbe, Roland/haascookemmrich STUDIO 13.1–13.4; 14.1–14.3; 14.5–14.23; Yazdani, S.: 1.7; 14.53; 14.54; 14.55
2050: p. 225; p. 226 bottom, p. 227 14.25–14.27; 14.30–14.52; 14.56–14.78; Zernike, Harry: pp. 214–215
Harris, Andy: p. 190 top; p. 192 centre, 15.1–15.58; pp. 150–151; p. 168 top; p. Zhou, Tina/Shutterstock: 1.2
bottom left and right 169 top row, middle row, bottom left
Herraiz, Jaime/Kéré Architecture: p. 203 Mori, Stefano: p. 196 All plans and drawings in the chapter “Built
Heuser: 5.12 Mushen, Allen: p. 203 middle row, left and examples” were provided by the architects.
This work is subject to copyright. All rights are reserved, whether the whole or part of the
material is concerned, specifically the rights of translation, reprinting, re-use of illustrations,
recitation, broadcasting, reproduction on microfilms or in other ways, and storage in data-
bases. For any kind of use, permission of the copyright owner must be obtained.
ISBN 978-3-0356-2766-4
e-ISBN (PDF) 978-3-0356-2768-8
(Fifth and revised edition)
987654321
www.birkhauser.com
@arclib
@arclib