Concrete Society Stage 1-Session 2a
Concrete Society Stage 1-Session 2a
Stage 1
Session 2a
Dr Ian Heritage
Stage 1 – Concrete Practice
1.11.00 Proportioning, batching and mixing
Copyright
• Concrete Standards
– Old - BS 5328 – withdrawn Dec2003
– New - BS EN 206 and BS 8500
• BS 8500 in two parts
– Part 1 – Methods of specifying and guidance for the
specifier
– Part 2 – Specification for constituent materials and
concrete
Types of concrete
• Designated concretes
• Designed concretes
• Prescribed concretes
• Standardized Prescribed concretes
• Proprietary concretes
Types of concrete
• Designed
– C28/35, 325 min cc, 0.5 max w/c, CIIIA cement
• Designated
– GEN, RC, PAV, FND
• Standardised Prescribed
– ST
• Prescribed
– 300 cc + fibres
• Proprietary
– Self-compacting concrete
• Nominally Proportioned
– 1-2-3 by volume
Other Design Factors
• Cement type
• Cover to reinforcement
– Nominal cover = minimum cover + fixing tolerance
Current cement and combination types
Nominal cover =
minimum cover + tolerance to accommodate
fixing precision
• Aggregate – BS 12620
• Course
– Texture – bond with paste
– Size – cement content, pumping, shrink less
– Density – for lightweight or heavyweight concrete
• Fine
– Fine fines – cohesive mix, less bleed, less segregation
– Grading – should be well graded
– Colour – fine fraction influences weathered concrete
colour
Changes in Quantities of Constituents
• Cement
– Dry
• Aggregates
– No contamination
– No cross grading
– Freezing
• Admixtures
– Within manufacturers requirements
Material Storage – Readymix Plants
• CEMENT
– Stored in water-tight silos typically of 40 tonnes capacity. Plants
can hold on average between 100-160 tonnes of cement
• AGGREGATE
– Can be stored in overhead bins typically 50 tonnes capacity with
on average 4 bins (200 tonnes), most plants have ground bays for
storage of up to 500 tonnes
• ADMIXTURES
– Liquid type stored either in bunded tanks usually 2000 litres
capacity, drums of 205 litres, or smaller 25 litre containers. All
liquid admixtures should be protected from frost
• WATER
– Recycled or reclaimed water stored in tanks of up to 40000 litres
Stage 1– Concrete Practice
1.12.00 Transporting, handling and placing
Stage 1 Learning Objectives
• Segregation
• Loss in workability
• Stiffening
• Contamination
• Loss of fines
• Temperature
General Precautions
• If predicted
– Can retard first concrete
– Vibrate longer
– If hot, keep cool by shading or damping
– Smaller sections
• If unforeseen
– Create construction joint
1% air =
approx 5%
strength loss
Concrete Properties
For congested
rebar
Difficult access
for pokers
Vibrating Screed
Razorback
• Slabs up to 300mm
• Can be 30m wide
• Not often seen now
• Now flood pour and laser
screed
– Vibrates at depth
Counter Rotating Beam
• Bunyon tube
• Slab thickness
150mm?
• Surface finisher
only?
• Combine with
poker
Self-Compacting Concrete
•Curing is
absolutely
critical!
Curing
• Existing damage
– Deformed formwork
– Bent props
– Damaged pins
• Missing or incorrect elements
– Including early removal
• Ground support
– Soft or inadequate baseplates
– Nearby excavations
– Nearby plant vibration
Safety
• Regular inspections
– Before and
– During
• Appropriate person
– Signed off
Safety Checks
• Power floated
– After the surface has been levelled, the surface is
power-floated to smooth and close the previously
levelled concrete surface after it has stiffened
sufficiently - about three hours after laying
– Rotating circular disc attachment or large flat
individual blades
– Not highly polished and gives characteristic swirl marks
with a sandpaper/gritty texture to the surface
Unformed Finishes
• Power trowelled
– First power float
– Delay to allow excess surface moisture to evaporate,
the slab surface is further smoothed and made dense
with a power trowel
– Smooth, polished appearance
– Power trowel has tilted individual blades that are
smaller than the power float
– For extra hardness (industrial) use dry shake
Power Finishes
Trowelled
Floated
Dry Shake
Grinding
Grinding for
Terrazzo finish
Exposed Aggregate
• Factors affecting
– Formwork material (porosity)/pattern
– Release agent type/amount
– Striking time of formwork – later = darker
– Materials used in the concrete – cement type/fine
aggregate
– Placing of concrete – cold joints/sand runs etc
– Compaction of concrete - honeycombing
– Curing and protection – major influence
• Further finish procedures – acid wash etc
Appearance of Formed Finishes
• Inherent blemishes
– Blowholes
– Colour variation
• Avoidable blemishes
– Honeycombing
– Aggregate bridging
– Deflections etc etc
Viewing Distance