The document outlines the Bill of Quantities (BOQ) for civil work related to a kitchen and bathroom, detailing various construction items, their quantities, rates, and total costs. The subtotal for the work amounts to ₹789,486.01, with an additional GST of 18% bringing the gross total to ₹931,593.49. It also notes that the rates for the water tank and urinal pot, as well as sanitary fittings, will be charged extra based on actual costs.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
182 views2 pages
Kitchen & Bathroom Estimate
The document outlines the Bill of Quantities (BOQ) for civil work related to a kitchen and bathroom, detailing various construction items, their quantities, rates, and total costs. The subtotal for the work amounts to ₹789,486.01, with an additional GST of 18% bringing the gross total to ₹931,593.49. It also notes that the rates for the water tank and urinal pot, as well as sanitary fittings, will be charged extra based on actual costs.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2
Estimate No:-
Name of the work:- CIVIL Work of Kitchen & Bathroom
BOQ ITEMS AMOUNT Item No Description of items UNIT QUANTITY RATE Ref No (Without GST) Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including 1 getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil cum 20.61 129.95 ₹ 2,678.27 1 Filling available excavated earth (excluding rock) in trenches, plinth. sides of foundations etc. in layers not exceeding 20cm 2 in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and for all lift cum 10.59 150.2 ₹ 1,590.62 3 Supplying and filling in plinth with sand under floors, including 3 watering, ramming, consolidating and dressing complete. cum 6.31 1098.15 ₹ 6,929.33 5 Reinforced cement concrete work in beams, suspended foors, roofs having slope up to 15* landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to foor five level, excluding 4 the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources). cum 1.77 9272 ₹ 16,411.44 11 Centering and shuttering including strutting, propping etc. and 5 removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers sqm 19.32 573.25 ₹ 11,075.91 14 Brick work with common burnt clay F.P.S. (non modular) bricks 6 of class designation 7.5 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) cum 16.03 6130.95 ₹ 98,279.13 18 Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength 7 in super structure above plinth level up to floor V level in : Cement mortar 1:6 (1 cement : 6 Coarse sand) cum 31.57 7039.85 ₹ 222,248.06 20 Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure 8 above plinth and upto floor V level. Cement mortar 1 : 4 (1 cement : 4 coarse sand) sqm 5.53 892.1 ₹ 4,933.31 19 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete 9 above plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. kg 285 98.9 ₹ 28,186.50 16 12 mm cement plaster of mix : 1:6 (1 cement: 6 fine sand) 10 sqm 219.11 265.15 ₹ 58,097.59 43 12 mm cement plaster of mix : 1:4 (1 cement: 4 fine sand) 11 sqm 140.19 277.95 ₹ 38,964.68 42 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat 12 cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. 40 mm thick with 20 mm nominal size stone aggregate sqm 65.07 491.6 ₹ 31,988.41 33 P/L damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural 13 sources : 4 graded stone aggregate 12.5mm nominal size derived from natural sources) sqm 50.90 331 ₹ 16,847.90 7 Construction of septic tank for 20 users with 1st class brick work in cement mortar (1:6) including two 560 mm dia. RCC manhole cover(heavy type)of approved make supplied, fitted and fixed in the 100mm thick RCC (1:2:4) top slab with necessary fittings, 20mm thick cement plaster with neat cement finish to the internal surfaces and 12 mm thick cement plaster to outside wall & 100 mm thick RCC(1:1.5:3) bottom 14 slab including supplying, fitting and fixing all necessry specials, fittings, tees, foot rest etc. & including constructing attached inspection pit and connecting all necessary pipes, joints etc. Finished level of Septic Tank should be 400 mm. from GL, Ventilation pipe & Mosquito proof mesh, should be follwed as per IS:2470 Part-I. each 2.00 56761.58 ₹ 113,523.16 83 Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer- in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid 15 scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer- in- charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. sqm 80.26 575.2 ₹ 46,165.84 84 17 Providing and fixing PVC Door each 6.00 2000 ₹ 12,000.00 18 Providing and fixing Flash Door. each 2.00 3700 ₹ 7,400.00 19 Providing and fixing Aluminium Window each 5.00 3200 ₹ 16,000.00 Providing and fixing white vitreous china water closet squatting 20 pan (Indian type) : Orissa pattern W.C. pan of size 580x440 mm each 1.00 2326.6 ₹ 2,326.60 21 Providing and fixing white Ceramic urinal pot each 5.00 ₹ - 22 Providing and fixing Water Tank (1000lt.) each 1.00 ₹ - Applying priming coat : With ready mixed pink or Grey primer 23 of approved brand and manufacture on wood work (hard and soft wood) 219.11 48.35 ₹ 10,594.07 Painting with synthetic enamel paint of approved brand and 24 manufacture to give an even shade : Two or more coats on new work 219.11 103.6 ₹ 22,700.02 Finishing walls with Acrylic Smooth exterior paint of required shade : New work (Two or more coat applied @ 1.67 ltr/10 25 sqm over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm) 138.91 147.9 ₹ 20,545.17 SUB-TOTAL AS PER BOQ ₹ 789,486.01 TOTAL ₹ 789,486.01 Add GST @18% ₹ 142,107.48 Gross total Including GST ₹ 931,593.49
* Rates of Water Tank and Urinal pot will be extra as per actual * Rates of Sanitary fitings will be extra as per actual