Theses 2
Theses 2
PROJECT REPORT
On
Submitted to
CERTIFICATE
Date:
DECLARATION
PROJECTEES
Abdul Farman Sheikh
Vaibhav Rangari
Aniket Daule
Shital Paredi
ACKNOWLEDGEMENT
These words of thanks cannot express our feeling towards our parents
and guardians who understands innumerable hardships and troubles to
make us what we are. Last but not the least, we thankful toall the
teaching, non-teaching staff and friends who have directly or indirectly
help us in successful completion of our project work.
ABSTRACT
The road connecting Kalamna and Rajiv Gandhi Nagar is identified as the
busiest route in the city due to its pivotal role in linking two major hubs
Kalamna, renowned as one of Asia's largest wholesale and retail markets,
and Rajiv Gandhi Nagar, a bustling area of Nagpur. However, the presence
of three railway tracks intersecting the route poses a significant challenge,
leading to prolonged waiting times for vehicles due to frequent train
crossings. To address this issue and enhance transportation efficiency, the
Government of Maharashtra has proposed the construction of a railway over
bridge under the Central Road Funds initiative.
This report outlines the progress and details of the proposed project, which
aims to alleviate traffic congestion and reduce waiting times at the railway
crossing. The project is conducted on a percentage basis, with a vision to
foster the city's development and streamline traffic flow. The report includes
comprehensive information on the project's objectives,methodology, and
data collection techniques, which were carried out on- site. Despite ongoing
work and a targeted completion timeframe of two years, the report provides
insights into the progress made over the past six months. Additionally, it
acknowledges that certain data updates are pending from the designing
department of the Public Works Department (PWD) due to variations in
levels observed during construction.
1. INTRODUCTION 1
1.1 Introduction
1.1.1 General Arrangement Drawing of the Site
2. LITERATURE REVIEW 11
3. CONSTRUCTION OF BRIDGE 14
3.1 Piles
3.1.1 Excavation was done using Sr235 drill W-10
3.2 Pile Cap
4. REINFORCEMENT DETAILS OF 29
DIFFERENT PIERS OF OVER
BRIDGE
8. CONCLUSION 85
9. REFERENCE 87
CHAPTER – I
INTRODUCTION
Chapter 1. INTRODUCTION
1.1 Introduction
• Name of the Project : Construction of Railway Over Bridge From Kalamna
to Rajiv Gandhi Nagar (road) Nagpur , Maharashtra.
• Location : Kalamna old Kamptee Road To Rajiv Gandhi Nagar road.
(Note : The Project is divided in two sites.)
• Work site provided has railway over bridge section from kalamna old
kamptee road to kawarapeth cross over bridge.
• Map location of site.
1
• Period of Project : 24 months (2 years)
• Defect Liability Period of Project : 20 years
• Design Consultant M/s K.P. Techno Bhopal, Madhya Pradesh.
• Approved by Mr. Deole Executive Engineer , Public Work Department
Division Number 3 Nagpur Maharashtra.
• Under consultation of Public Work Department Division number 2 Nagpur
Maharashtra.
• Date of Commencement December 2021
• Percentage Based Contract
• Supervision and Observation of Activities performed during the period of
January to May 2022
• Laying of Piles – Excavation , reinforcement , concreting .
According to the traffic survey the road connecting Kalamna and Rajiv
Gandhi Nagar is the busiest route of the city. The road connects 2 hotspot of
the city whereas Kalamna is considered to be 2nd most biggest market of asia
for whole sale as well as retailers. The road which connects Kamptee kalamna
to Nagpur is Rajiv Gandhi Nagar Road which goes via Itwari station , Indora
and also few busiest place of Nagpur. Kalamna is also connected by railway
named Kalamna Station. As it is situated on the outskirt of the city, Kalamna
is well connected by highway as well railway. Though it is in outskirt local
vendors reach here for their supply. Kalamna looks after arrival of more then
60% produce from other states. It is used as transit centre as well as storage
silos for mainly all types of grains. The agriculture produce arriving here from
south states are transported further to north east states. Produce arriving from
all other states are packaged here
2
and sent to other states. It has turnover of more than Rs 2500 crores. It is
constructed on 145 acres and has daily arrival of 250 trucks plus 400 to 500
small vehicles. The major problem faced by the locals and the vendors
reaching Kalamna from city is the railway section. There are three railway
tracks connecting Kalamna station to Khaparkheda , Koradi and Chindwara
to Itwari. The railway portion is old rail road crossing with barricades. As
there are number of goods train and even passenger train crosses in a very
short intervals due to three railway tracks the waiting time for vehicles
approaching from Kalamna as well as Rajiv Gandhi Nagar is prolonged.
Generally during working time of market the number of vehicles waiting at
the barricades of railway section is more than 30 to 40 CV in total every
time when the barricades are closed for trains to cross. This produces severe
traffic at the barricades junction and generally. To ease the transportation
between Kalamna and Rajiv Gandhi Nagar a railway over bridge is proposed
by the Government of Maharashtra under central road funds. The over bridge
not only eases the transportation between Kalamna and Rajiv Gandhi Nagar
but also cut-off the waiting time at railway road cross section.
Supervision of the work done on site is done by the sectional engineer sub
division no.2 Nagpur. The government releases fund on the percentageof
work done. All the work performed by contratctor is done under the
consultation of P.W.D. officials.
3
1.1.1. General Arrangement Drawing of the Site
• Each Pier is marked as P1 to P26 and Railway Section Pier as RP1 to RP5
• Green line denotes the carriageway joining the ring road crossing from
below the Over Bridge.
4
Fig 1.3 L-Section of Proposed Bridge
5
1 Length of the overall over bridge bridge is 1091m approx from pier 1 till
pier 26 as marked in fig
2 For the section approaching from kalamna Reinforced Earth wall is given
with rising gradient of 1:30 that is for 30m of lenght horizontally 1m height
is raised and the lenght of section is 267m approx.
3 After pier 1 the gradient is same as 1:30 and length between the piers are
marked on top in fig
4 Datum Reduced level is taken to be 250m.
5 The data in row shows the proposed Reduced Level in red marking then
the existing levels in the row below it for each points at a levelling staff
interval of 10m.
6 Below the existing levels chainage of the levelling points are given from
the mean point which has existing level of 295.404m. Mean distance in
chainage is taken as 10 m.
7 And the last row shows the parabolic crown type for ascending and
descending gradient where L shows the lenght of crown and R shows the
radius if crown in metres.
6
1.1.2. Interpretation of General Arrangement Drawing of
Railway Section
7
• Fig shows section of railway over bridge Railway Pier 1 to Railway Pier 5
where the width of pavement will be 20m in total and then diverged into 3
section from Pier 8 which is 2 carriageway of width 5.5m each joining the ring
road flyover. The other center section as you can see is crossing above the
flyover to Rajiv Gandhi Nagar.
• Length of the railway portion is to be for continuous 148m covering the 3
railway tracks below it.
• Section from where carriageway will be diverged and the raise in gradient also
the height of the over bridge for crossing the ring road flyover is marked as
height guage.
Fig 1.5 Elevation proposed ROB & approaches for traffic from Kalamna side to Rajiv Gandhi Flyover
8
• Carriageway piers are marked from divergence of over bridge as P8A.
• Elevation and descending gradient of carriageway joining the ring road
diverging from the railway section overbridge.
• It shows the chainage, existing levels and proposed road levels of bridge.
• Datum Road Level taken as 250m.
9
CHAPTER – II
Literature review
10
Chapter 2. Literature Review
1. Historical Development and Evolution of ROBs
• Early examples of ROBs and their significance.
• Evolution of design and construction techniques over time.
• Impact of technological advancements on ROB development.
2. Design and Structural Considerations
• Structural design principles for ROBs.
• Factors influencing the design of ROBs (e.g., railway standards,
traffic volume, environmental conditions).
• Case studies illustrating different design approaches and their
effectiveness.
3. Construction Techniques and Challenges
• Construction methods for ROBs (e.g., precast concrete, steel
trusses).
• Challenges encountered during ROB construction (e.g., site
constraints, foundation issues, utility relocation).
• Innovative solutions and best practices for overcoming
construction challenges.
4. Functionality and Operational Aspects
• Role of ROBs in facilitating efficient railway and road traffic
flow.
• Traffic management strategies implemented on ROBs (e.g.,
lane markings, signage, traffic signals).
• Integration of ROBs with surrounding transportation
infrastructure.
5. Safety and Risk Management
• Safety considerations in ROB design and operation.
• Measures to mitigate risks of accidents and collisions.
• Analysis of historical incidents and lessons learned for
improving safety.
6. Environmental Impact and Sustainability
• Environmental effects of ROBs (e.g., habitat fragmentation,
noise pollution, air quality).
• Sustainable design principles and practices for minimizing
environmental impact.
• Case studies highlighting successful implementation of
environmentally friendly ROB projects.
11
7. Economic Analysis and Cost-Benefit Assessment
• Cost factors associated with ROB construction and
maintenance.
• Economic benefits of ROBs in terms of reduced travel time,
congestion, and accident costs.
• Cost-benefit analysis methodologies used to evaluate ROB
projects.
8. Social and Community Considerations
• Social impacts of ROBs on local communities (e.g.,
accessibility, land use).
• Stakeholder engagement processes in ROB planning and
decision-making.
• Strategies for addressing community concerns and maximizing
benefits.
9. Technological Innovations and Future Trends
• Emerging technologies in ROB design, construction, and
operation (e.g., BIM, IoT, automation).
• Potential future developments and their implications for ROB
infrastructure.
• Challenges and opportunities in adopting new technologies for
ROBs.
10. Case Studies and Comparative Analysis
• In-depth analysis of select ROB projects from different
geographical regions.
• Comparative assessment of ROB designs, construction
techniques, and outcomes.
• Lessons learned and recommendations derived from case
studies.
12
CHAPTER – III
Construction of Bridge
13
Chapter 3. Construction of Bridge
3.1. Piles
3.1.1. Excavation was done using Sr235 drill W-10
• Length of the pile is 16m.
• Excavation done is 12.56 cubic metre for 1 pile.
• Concreting is done with a funnel which settles the concrete properly at
the bottom.
• Grade of concrete for pile is M40 i.e. 1:1:2 (Cement:Sand:Aggregate)
14
Fig : 3.3 Steel Casing for Pile
15
Fig:3.5 Schedule of bar
2. 10mm bar of Helicals outside of 175mm spacing from center to center of.
16
4. After Piling and construction of pile caps reinforcement of pier is being
coincided before the conreting of pile cap is done.
3.2.1. Removal of concrete from bars for 1.4m below the ground
17
• Fig shows reinforcement of pier bars coincided into pile cap before
concreting
• Fig shows lintern bars between the top and bottom mesh frame of pile
cap.
Fig: 3.9 Reinforcement of Cappier in pile cap Fig:3.10. Link bars in pile
18
3.2.3. Reinforcment detail of Pile Cap (P1 to P5)
• Reinforcement Detail differ for different piles cap for differet piers , the
following details are for Pile cap of Pier 1 to 5.
• Top Mesh bars are of 20mm with centre to centre distance of 125mm.
• Bottom mesh bar are of 20mm with centre to centre distance of 125mm.
• Side Facing bars are of 10mm with spacing of 200mm between them.
• Also the link bars between top mesh and bottom mesh has 10mm link
bars and distance between them 250mm for both the ways.
19
Fig:3.13 Section of reinforcement Fig: 3.14 Section A-A in pile cap
detail in pile cap reinforcement
20
Fig:3.17 Section of reinforcement Fig: 3.18 Section A-A in pile cap
detail in pile cap reinforcement
21
Fig:3.20 Concreting of Pile Cap through mixer truck brought form mixer plant
3.3. Pier
22
Fig:3.21 Reinforcement of Fig:3.22 Pier Stirrups of square and
pier rectangular Inside pier
23
3.3.2. Reinforcement of Pier is layed according to reinforcement plan
and schedule of each Pier
• A part of pier is raised above ground level to support shuttering properly and
for ease of concreting of whole.(Fig)
24
• Rest of the reinforcement is tied till its desirable height and variable of
reinforcement is left to coincide properly with peir cap reinforcement.
25
Fig: 3.28 Steal Shuttering Fig:3.29 Steel shuttering
26
Fig:3.31 Pouring of concrete Fig:3.32 Concreting of pier through crane
inside pier through crane
• Stripping of Framework of the Pier after 7 days for curing using ruck sacks.
27
CHAPTER – IV
Reinforcement
Detailes of Different
Piers of Over Bridge
28
Chapter 4.Reinforcement Details of Different Piers of Over
Bridge
Note :
• All dimensions are in mm.
• Reduced Level are in metres
• Grade of concrete of pier, pile cap and pile to be M40.
• TOR indicates fe500 TMT bars.
• Example-TOR 10 indicates 10mm diameter of TMT bars .
• Example-@ 150 c/c represents 150 mm of spacing between centre to centre
of reinforcement bars.
• Minimum clear concrete cover shall be
50mm for pier and pier cap
75mm for pile and pile cap
• Piles as per reinforcement plan are end bearing piles of maximum design
load to be 350tons.
e. Length of Pier above pile cap top level to Pier cap bottom level of P5
= 7.573m
29
Fig:4.1 Elevation Reinforcement detail of Pier
30
Fig: 4.2 Pedastal Reinforcement detail of pier
31
Fig: 4.4 Reinforcement detail inside pier
32
Fig:4.5 Plan at foundation level Pile Cap
33
Fig:4.6 Reinforcement Detail of Pile
34
Table 4.1 Schedule of Pier 1 to Pier 5
35
Table 4.2 Details of Reduced Levels of Piers
36
Fig:4.7 Elevation Reinforcement detail of Pier 22 to Pier 26
37
Fig4.8 Section Elevation reinforcement detail of Pier 22 to Pier 26.
38
Fig:4.9 Pedastal Reinforcement detail of Pier 22 to Pier 26.
Fig:4.10 Sectional elevation showing details of Pier cap 22 to Pier cap 26.
39
Fig:4.11 Reinforcement detail inside Pier 22 to Pier 26.
40
Fig: 4.13 Reinforcement Detail of Pile 22 to Pile 26
41
Table 4.3 Schedule of Pier 23 to Pier 26
42
Table 4.4 Details of Reduced Levels of Piers
43
CHAPTER – V
Analysis And Test
Result
44
Chapter 5. Analysis And Test Result
3 Degree of quality control Good 1.The same stipulations as per letter are considered for mix design
4 Degree of workability (slump) 50mm 2.Some of the stipulation are assumed with respect to normal
condition as the same were not informed
45
5.2. Properties of Ingredient
46
8 Soundness(m 4 40mm -
m)
47
5.3.1. METHODS
1. Weighing some representative oven dried obtained a representative oven- dried soil
sample
2. Using a mortar and pestle or a mechanical soil pulverizer,pulverize the soil sample as
finely as possible,
3. Obtain a soil sample of about 500 g and determine its mass W0 (g).
4. Stack the sieves so that those with larger openings (lower numbers) are placed above
those with smaller openings (higher numbers). Place a pan under the last sieve
(150micron) to collect the portion of soil passing through it. Make sure the sieves are
clean, If soil particles are stuck in the openings, use a brush to poke them out.
48
5.3.2. Sieve Analysis
Values
Table 5.3 Sieve Analysis Values
40mm 0%
20mm 60%
10mm
Proportion in 0 60 40 - -
%
80.00 - -- - 0.00 -
12.5 - - - - 100
600 micron - - - - 5
49
300micron - - - - 1
150 - - - - 0
60% 40%
50
5.5. Mixed Design Recommendation
Table 5.5 Mixed Design Recommendation
1 Mix Proportion (by weight ) 1 1.21 2.898.53
51
5.6.1. Procedure
• Step 1.A pit of depth 0.5 m is excavated and leveled smoothly as the load
applied on it should be distributed equally. A layer of sand is laid of maximum
of 1 inches .
52
• Step 3. A steel cribbing is placed on the disk to reach the desirable level of
height to place the hydraulic jack.
• Step 4. Dial support is placed on the Steel cribbing and adjusted correctly to
place hydraulic jack on top of it.
53
Fig: 5.6 Hydraulic Jack on top dial
• Step 6. Dial supports are placed from at least 4 ft from bearing plate with
dial micrometers attached around both left and right side of dial support.
54
• Step 7. A truck of sand weighing around 20 tons is kept above the jack to
support the load applied on ground vertically by the jack.
55
5.6.2. Observation Table :
Partly saturated
reading
15 31 KN 0 0 0 0 0 0
(3100kgf)
56
9.00 7.24 7.89 7.80 7.80 7.68
25.00
(5200kgf)
57
30.00 9.85 8.86 10.00 9.99 9.67
5.6.4.Calculation :
Ku = Pressure applied / settlement on that area =0.07/7.56-7.45= 6.363636
MPa/cm
The pile was r. c. bored pile with diameter of 1000mm, details of which are
given below. The pile was tested using 4.9 tons hammer falling from a
height ranging from 0.5m to 2.6m.
58
5.7.1. TEST EQUIPMENT
a. A Pile Driving Analyzer and its associated pile top force and velocity
transducers were used to conduct the dynamic pile test.
b. Two strain transducers and two accelerometers were attached to the pile
head. They were mounted on opposite sides of the pile to cancel bending
effects during each strike of the hammer. The signals of strain and
acceleration were conditioned and processed by PDA.
d. The PDA onsite uses a program based on closed form Case-Goble solutions
to compute static pile capacity from the pile top force and velocity data. This
is subsequently checked with the computer program CAPWAP to confirm the
static pile capacity obtained on site.
59
5.7.2. PDA FIELD TESTING
a. Dynamic testing on the pile was conducted by striking the pile with the
hammer during the restriking process. During testing of the pile, complete
dynamic measurements were obtained for each hammer blow delivered to
the pile. The field results along with comments are summarized in Table The
PDA measures the total (static plus dynamic) resistance acting on the pile.
The portion of total resistance that is computed as static resistance by the
Analyzer is determined by the soil damping factor Jc set into the analyzer. A
more accurate independent measure of the applicable soil- damping factor was
determined using a CAPWAP analysis.
60
b. The values measured by the PDA on field are obtained assuming that the pile
is uniform throughout its length. Also, the soil parameters like quake and
damping should be assumed during the field test. Hence the CAPWAPis
mandatory for all bored piles to estimate realistic soil parameters as well as
pile profile. Typically one of the blows that is close to the test load is subjected
to CAPWAP analysis. In summary, PDA measures the field capacity while
CAPWAP refines the field results and hence field capacities measured using
PDA may not match with the CAPWAP analysis.
c. The BETA Value (Integrity Factor) indicates change in the pile impedance
and is derived from the CAPWAP analysis. The PDA is basically used to
compute capacity and the BETA factor. Particularly for bored piles BETA
may never be 100% due to inherent nature of installation. A BETA factor less
than 60% indicates a shaft with poor integrity. Such shaft may require
remedial action in the form of reduced loads, redesigning the cap or
installation of additional pile as recommended by the engineer to the project.
General guidelines for the assessment of pile integrity are presented in table
below.
d. The PDA field capacity is estimated by either RMX or RSU for an assumed
Jc value and on the assumption of uniform cross-section of the pile. RMX is
the maximum Case-Goble Resistance (Maximum Capacity) for the assume
Jc value (Case Damping) at the project site. The RMX capacity generally
holds good when the pile shows a reasonable movement under the load. The
RSU capacity is applicable when there is very high skin friction and in most
cases the pile movement is nominal. Hence a more realistic estimate of the
pile capacity is obtained from the CAPWAP analysis conducted on one typical
blow at the end of testing program.
61
5.7.3. DISCUSSION OF RESULTS
a. The CAPWAP analysis results for Pile No. TP2 showed that the pile had
achieved an activated capacity of 989.0 tons at the time of testing. This
resistance is more than the design/working load. The capacity is applicable
at the time of testing and further soil strength changes with time had to be
considered.
c. From CAPWAP analysis, the pile top load vs. settlement curve is obtained by
simulating static load test. The pile top settlement at 875 tons (equivalent test
load for static test) is estimated to be around 3.6mm. Please refer to static
analysis in Appendix A.
62
5.7.4. CONCLUSIONS
1. The CAPWAP analysis results for Pile No. TP2 showed that the pile had
achieved an activated capacity of 989.0 tons at the time of testing which is
more than required test load of 875 tons.
2. The pile integrity was observed to OK.
3. The stresses in the pile were within the acceptable limits during any stage of
testing.
4. This report has been prepared with generally accepted high strain dynamic
pile testing practices and as per ASTM D4945. No other warranty, expressed
or implied, is made. The findings provided in this report are based on the result
of the individual pile tested and information made available to us.
63
Table 5.9 Summary of CAPWAP analysis Result
Pile No. TP2 Permissible Limits
Pile capacity 989.0 tons 2.5 * Design Load
Skin friction 677.8 tons -
End bearing 311.2 tons -
Set per blow 2.0 mm 3.4mm
Total displacement 6.6 mm -
Compressive stress 25.6 mmsq 0.85t(st)
Pile integrity(below sensor OK 80%-99% classified as
level) minor defect
64
Fig: 5.11 Aggragte at the site of 20mm and 10mm
65
5.8.1. Procedure
The impact machine is rest on a horizontal flat surface like the level plate,
block, or floor without any packing. So, the application of a hammeris
straight and vertical.
The cup is fixed in a proper position on the base of the impact machine.
Transfer aggregate sample from cylindrical measure to cut fitted in an
impact test machine and apply 25 strokes of the rod to compact it.
Then the hammer is lifted 380mm and falls on the upper surface of
the aggregate which fills in the cup.
A total of 15 blows are applied to the cup each delivered at an interval of not
less than 1 second.
The crushed aggregates are removed from the cup and the crushed sample is
sieved from the 2.36mm IS sieve.
Weight the fraction of sample passing through 2.36mm IS sieve accuracy up
to 0.1 gm. (W1)
Weight the fraction of sample retains on the 2.36mm IS sieve. ( weight W2)
The total weight of the sample (W1 + W2) is less than the initial weight
(weight W) by more than one gram than the result discarded.
5.8.2. Calculation
The aggregate impact value is the ratio of the weight of the fraction passing
through 2.36 mm (weight W2) by the total weight of the sample (weight W1
+ W2).
Aggregate Impact Value = (W2/ (W1+W2)) * 100
Where,
W1= Weight of the fraction passing through a 2.36 mm IS sieve.
(220 gm)
W2= Weight of sample retained on 2.36 mm IS sieves. (80 gm)
66
5.8.3. Aggregate Impact Value Test
Observation
Table 5.10 Aggregate Impact Value Test Observation
Sr..No. Determination Trial 1 Trial 2 Trial 3 Average
2 Wt. Of Material 60 45 55
Retained on 2.36mm
after testing –
W2[gms]
67
5.9. Consistency of Cement
Vicat Test
68
Fig: 5.13 Vicat Mould Specimen
69
5. Place the cement paste-filled mold together with the non-porous resting
plate, under the consistency test plunger in the Vicat apparatus.
6. Now, Lower the plunger such that it touches the top surface of mould
filled with paste, and quickly release, allowing it to sink into the paste.
This process shall be done quickly after filling the mould.
7. Observe the penetration value on the Vicat apparatus scale. It shouldbe
around 33 to 35 mm from the mould filled with cement paste. It is not, then
increase the % of water and repeat the above steps.
8. Repeat the whole process with varying % of water to cement,until
penetration value comes to 33 mm to 35 mm from the top of mould toward
the bottom of the mould.
5.9.2. Observation
Cement Grade – J.K. Laxmi OPC-43
Temperature-30 Degree Celcius
70
Results
Standard Consistency of Cement: 33%
Initial Setting Time :102 Minutes
Final Setting Time : 328 Minutes
71
Fig:5.15 Soil Sample Collected From Site
72
5.10.2. Observations for Specific Gravity of Soil
5.10.3. Calculations
73
• Specific Gravity
G= A/(A-(C-B)
Trial 1
= 2.82gm/cubic cm
Trial 2
= 2.83gm/cubic cm
Trial 3
= 2.81gm/cubic cm
Average Specific Gravity
= 2.82gm/cubic cm
74
5.11.1. APPARTUS
5.11.2. PROCEDURE
Take sample of aggregates from the stockpile to be tested.
Let the total sample dry in the oven of a constant weight at a temperature of
105° C to 110°C and cool at room temperature.
Sieve the whole sample through the sieves mentioned in the columns (1) and
(2) of the Table: 5.13
75
5.11.3. FLAKINESS INDEX
Take minimum 200 pieces from each fraction and weigh (A).
Separate flaky material from each fraction by gauging through the standard
thickness gauge.
Weigh the flaky material passing though the specified gauge from each
fraction c1+c2+c3+c4+c5+ ..................... = C.
63 50 - -
50 40 - -
40 31.5 - -
31.5 25 - -
25 20 710 185 150
20 16 1512 145 132
16 12.5 1432 125 110
12.5 10 362 95 80
Total 4016 A= 550 F= 472
76
5.11.5. Calculations
Flakiness index, ( %) = (C/A ) X 100
Elongation Index, (%) = (E / F) x 100.
5.11.6. Result
Flakiness Index = Mass of sample passing through slot *100/total mass of
sample=13.70%
Elongation Index = Mass of sample retained on the gauge *100/Total mass
of sample=13.62%
77
CHAPTER – VI
Equipment Used at The
Site
78
Chapter 6. Equipments used at the site
79
6.1.2. Hydraulic Reinforcement Bar Cutting Machine
Steel bar cutting machine is used for rapidly cutting various gauge steel
wire. These cutting machines allows to slice steel wire, steel bar, brass wire,
aluminium wire, polycarbonate fibre, PVC pipe and various other wires into
very thin gauge sizes. Steel bars are extensively used in construction
nowadays to reinforce concrete. The strength and thickness of steel bars can
be easily attained by using these machines
80
6.1.3. Hydraulic Reinforcement Bar Bending Machine
Bar bender machine can bend steel round bar and steel rebar. The steelbending
equipment can bend bars within a certain range of diameters into different arcs
between 0°and 180°. Generally, bending metal bars into 90° and 135° are
more often to see.
81
CHAPTER – VII
Limitations
82
Chapter 7. Limitations
1. Permission for railway section is yet to be granted therefore the part from
railway pier 7 to pier 13 is on stay.
2. Due to heavy traffic mostly construction work like concreting is done at night
as the cranes and mixer blocks the road totally during concreting.
3. During the reinforcement of pile cap there were differences in distance in bars
from centre to centre as there was space left for person to sneak inside the pile
cap to tie link bars from top to bottom reinforcement of pile cap.
4. Since there are severed water pipes in ground it caused problem during
excavation of pile cap.
5. Pier 18 to pier 22 faced problems during excavation of pile cap as there is a
drainage channel passing nearby it . The soil shows more settlement as well
as drainage problem. As black soil is a clayey soil it shows more settlement
then usual soil.
6. Since the road is the busiest there are delay in work due to traffic jams. This
shows the future scope of the bridge. It will improve the connectivity and
reduce the traffic.
7. Dimension of road top level has changes so the General Arrangement
Drawing of pavement is yet to be updated.
8. Due to water supply lines going from few places excavation of piles from P13
for carriageway and P14 is on pause.
9. High Electricity Wires and poles are yet to be relocated at the site.
83
CHAPTER – VIII
Conclusion
84
Chapter 8. Conclusions
Overall the project has been a really knowledgeable experience. Most
importantly it shaped me and nurtured me with more curiosity towards my
field and I certainly feel choosing to be a civil engineer has been my best
choice of life.The field experience taught me more about difficulties faced
by engineers on site like withdrawing permissions from different departments
like irrigation and railway department. The theoretical and practical
knowledge has a vast difference.The main objective of supervision of work
was to observe the details of reinforcement and designing of the bridge. Due
to rush hours the working was mostly done at night and being available at
those hours has been a really tough job. The guidance provided by my
supervisor has been really helpful to analyse the vision of the project.I learnt
more about interpretation of Ground Arrangement Drawing, pilecaps and pile
reinforcement major details. Assisting for field tests like K- value and
PDA(CAPWAP Analysis) has been really a new experience as these tests can't
be performed in testing labs. Performing tests individually attesting lab on site
was a crucial part of the training. Due to my minor flaws Ifaced errors while
testing in labs individually but with proper guidance I gradually had more
accurate results. Infact the project is splendid work of designing and
construction. The equipments used at the site are highlyadvanced. The scope
of the project is real high for the development of the city. Working with highly
trained officials taught more about over coming responsibilities at the work
site.
85
CHAPTER – IX
References
86
Chapter 9. References
1. Engineering Design and Principles: Raj Purohit and Piyush Gupta. (2016).
"Structural Analysis and Design of Railway Over Bridges." International
Journal of Engineering Research & Technology.
88