B SCOPE OF WORK
*Pilling works at all zones *Positioning
of pile rig.
*Mobilisation of piles at site.
*Pitching of pile from position.
*Driving in pile to satisfied depth by stages – 15. Pile will be driven
to max of 32m.
*Welding works
*joining of Reinforcement
* Illumination
C ORGANISATION OF WORK CREW (Manager, Supervisors, Operatives, etc.)
Project Manager
Site Safety Officer
Project Engineer
Piling riggers (2)
Crane operator (2)
Welders
E JOB SAFETY ANALYSIS
Section 1: Risk Matrix
1 - Catastrophic: 2 - Critical: 3 - Marginal: 4 - Negligible:
Severity
Fatality or fatalities, Serious injury with Temporary disability, First-aid treatment injury,
(Consequence)
serious injury with permanent disability, lost time injury, minor cuts or bruises,
permanent disability, illhealth leading to outpatient treatment, irritation, ill-health with
life-threatening permanent disability, illhealth leading to temporary discomfort,
Likelihood major disruption and
occupational disease, temporary disability, clean-up effort for
major structural or damage to equipment minor or short-term environmental impact.
equipment damage, or structure, significant environmental impact.
detrimental environmental impact.
environmental impact.
1 - Frequent: likely to happen repeatedly. A A A B
5 - Improbable: very unlikely to happen; may assume exposure will not happen. C C D D
Piling Rig NA
Welding set
MSDS available:
Yes No
Applicable Relevant EH&S Legislation Approved Codes of Practice (COP) Applicable to the Works
Briefed and
agreement
established by all
of the area for
unloading.
3. Storage area identified Misscommunication Work carried out All have been 4 4 D Site
Piles will be stored at at the location of briefed of the engineer
all zones where piling storage area; Site
works will start. storage by other other trade are supervisor
trade. made know of the
location.
4. Transporter will be Loaded trailer Sunk into ground Ground condition 4 3 C Compactor is 4 4 D Site
guided into the site is inspected and used to compact Supervisor
checked to ground.
Traffic controller
will guide the
transporter to the
designated area.
5. All piles will be placed Misscommunic Work carried out Exclusion zone will 4 5 D Lay out of work 4 5 D Contractor
at the area designated. ation at the location of be will be displayed supervisor
established at the
storage by other designated area on notice board. Site safety
Location of Zones trade. with signage. personal
attach. Warning signage
will be placed.
Netting barricade
will be installed at
area.
6. Mobile crane Legal requirement Illegal crane PMA to be 4 5 D All documents to 4 5 D Site
used obtained kept as be obtain before Supervisor
crane is mobilised
record at site and at site. Sub-
placed on the contractor
crane where it supervisor
.
can be seen Site safety
visually. personal
To ensure no
hydraulic leaks or
black oil leakage
is spilled on to
ground.
A spill tray to be
stationed in the
event a leak is
observed
7. Mobile crane Condition Overload devise To ensure the 2 3 B Testing of load 4 4 D Crane
Mechanical / Load arrest overload alarm is must be done operator
in working
malfunction condition. during first Safety
causing loads to inspection of the supervisor
fall. crane.
8. Crane operator & Competency/ legal Non competent Induction to be 4 4 D Documents and 4 5 D Site
riggers requirement operator given before experience data Engineer
operating crane
operator starts must be collected Site
working at site. before Supervisor
mobilisation of
crew.
Riggers to be
trained and
competent/
experienced.
9. Lifting appliances/ Lifting Damage lifting All lifting 2 3 C SWL shall be 4 5 D Site
equipment equipment not equipment used equipment such more than 2.5 ton Supervisor
as slings are per sling.
maintained Site safety
inspected and in
Sling snapped good working personal
Hooks shall be
condition no closed hook.
damage or tears
to equipment.
Crane hook fitted
with safety latch
Certificate of
fitness to be
obtained and
records must be
kept at site.
All hydraulic
cables are
secured and tied
placed well along
the leader.
No leak
observes.
Rig moved to
pegged position
where the piles
are laid.
No workers to be
near the pile
rig while its
moving to
position.
Exclusion zone
to be placed with
proper signage.
To ensure no
hydraulic leaks or
black oil leakage
is spilled on to
ground.
A spill tray to be
stationed in the
Rig operator to
be trained and
18. Piling rig is in position and Communication Positioning of Site supervisor to 4 3 C Pre Planning of 4 5 D Site
ready to start piling rig is not brief the operators Task Supervisor
hoisting the pile toward and workers of
proper. the work method. Site safety
rhymer
personal
Rigger use
proper rigging
gloves – leather
gloves.
19. Lifting of Reinforcement Falling of load Injury/ accident to To ensure that 2 3 B No workers are to 4 4 D Contractor
by piling rig workers due to all lifting be in the lifting supervisor
reinforcement slip appliances are in radius of the pile.
out of sling. Site safety
good working
condition. personal
Exclusion zone to
Damage to pile be placed.
due to slip out Only riggers are Exclusion zone to
from hammer allowed to be in be placed with
cap. the area. proper signage.
20. Sling the wire rope to Slippage Reinforcement Riggers to ensure 2 3 B Only competent 4 4 D
the reinforcement damage due to that the sling is workers to carry out
slip from wire secured before work.
rope. signalling operator Lead man to
to carry out lifting ensure that the
works. slings are well
Injury to workers
secured.
from hot by pile
Workers to stay
away from the SUPERVISOR
swing radius at all TO
time.
MONITOR
WORKS CLOSELY
AT
ALL TIME.
Any abnormalities
must be reported
and works to be
stopped
immediately.
22. Reinforcement position Position of Pile fall off from Operator to push 2 3 B Site supervisor to 4 4 D Site
parallel to leader reinforcement not the grip damaging pile toward ground ensure that Supervisor
correct. and operator
Lead man to
inspect level.
Rigger to check
inspect that the
pile is upright and
correct angel.
Spill tray to be
stationed placed
during any works
with leak of
hydraulics or
black oils.
All waste to be
collected and
stored and
secured in
containers to be
collected by
waste collectors
to be disposed off
from site.
27. Personnel protection Injury First aid injury PPE – Safety 4 4 D Additional PPE Site
. accruing due to helmet, such as face Supervisor
Reflective Vest, shield, welding
handling of Sub-
Safety Boots, gloves and fire
materials retardant clothing contractor
Gloves and safety
to be used while supervisor
Goggles to be carrying out Site safety
used at all time welding works.
personal
while working or
accessing in
I have provided, to the best of my knowledge, as such accurate and sufficient information and instructions pertaining to this Job Safety Analysis / Risk Assessment - the hazards associated with each
work process / activity and type of potential incident or accident, the risk controls / reasonably practicable measures to be taken in the course of work and during an emergency - to ensure its / their
safe undertaking.
Instructed by (print name): .................................................................. Signed: .............................................................. Date: ….../…..../…... Time: .............. am / pm
PIC (print name): .......................................................... Signed: .............................................................. Date: ......./…..../….... Time: .............. am / pm
The works associated with this SWMS has been completed and the work area made safe and fit for subsequent use.
Subcontractor (print name): ................................................................. Signed: ...................................................................... Date: ......./…..../….... Time: .............. am / pm
PIC (print name): ........................................................... Signed: ...................................................................... Date: ......./…..../….... Time: .............. am / pm