The Essentials of Project Management - (4 Managing Risk)
The Essentials of Project Management - (4 Managing Risk)
Everything we do, from getting out of bed in the morning to returning there at night,
carries risk. It is not surprising that projects, which metaphorically (and sometimes
literally) break new ground, attract many risks. Project risks can be predictable or
completely unforeseeable. They might be caused by the physical elements or they
could be political, economic, commercial, technical, or operational in origin. Freak
events have been known to disrupt projects, such as the unexpected discovery
of important archaeological remains or the decision by a few members of a rare
protected species to establish their family home on what should have been the site
of a new project.
Project risk management (and much of mainstream project management) is
concerned with attempting to identify all the foreseeable risks, assessing the chance
and severity of those risks, and then deciding what might be done to reduce their
possible impact on the project or avoid them altogether.
Risks can occur at any stage in a project. Some are associated with particular
tasks and others originate from outside the project and can manifest themselves
without warning. Generally speaking, a risk event that occurs late in a project can
be more costly in terms of time and money than a similar event nearer the start of
the project. That is because as time passes there will be a greater value of work in
progress and thus higher sunk costs at risk of loss or damage.
Some projects that are very small or which are similar to projects undertaken
by the contractor in the past might not need special attention to risk management
(other than obtaining some insurance cover). However, for any significant new
project a risk management strategy must be developed, first to identify as many
potential risks as possible and then to decide how to deal with them.
Copyright © 2014. Taylor & Francis Group. All rights reserved.
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
The Essentials of Project Management
money. With this vast breeding ground for possible risks it is apparent that the risk
manager’s first problem is to identify the risks that might affect the project.
Checklists (which should grow in size and value as companies gain more project
experience) are a good starting point for listing the foreseeable risks. Studying the
history of similar projects can also highlight possible problems and help the project
manager to learn from the mistakes, accidents and experiences of others.
A brainstorming meeting of key staff is a good method for identifying all the
possible risks (along with many of the improbable ones). Much depends on how
the brainstorming session is conducted. The meeting leader should encourage an
atmosphere of ‘anything goes’, so that participants feel free to propose even the
most bizarre risk possibilities without fear of ridicule. All suggestions, without
exception, should be recorded for subsequent appraisal and analysis.
Qualitative risk analysis involves considering each risk in a purely descriptive way.
We have to imagine various characteristics of the risk and the physical effect that it
could have on the project.
Fault-tree analysis and Ishikawa fishbone diagrams (not described here) are
methods used by reliability and safety engineers to consider and analyse the
effects of faults in design and construction, but they can be adapted easily for
project management.
A common project management method, which also has its roots in reliability
engineering, is failure, mode and effect analysis (FMEA). Failure mode and effect
Copyright © 2014. Taylor & Francis Group. All rights reserved.
analysis starts by considering possible risk events (failure modes) and then proceeds
to predict their possible effects. Figure 4.1 shows part of a simple FMEA chart. This
illustration contains only three items, but there might be hundreds in a large
project. This is a qualitative process because there is no attempt to give each risk a
priority ranking number or to quantify the damage if the risk should occur.
44
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
Managing Risk
Recommended
Item Failure mode Cause of failure Effect action
1 Project Engine refuses Poor Project manager Improve vehicle
manager’s to start maintenance marooned at maintenance
car remote site with procedures.
no other means Consider replacing
of transport the car.
2 Main building Building Errors in floor Personal injuries Triple check key
collapses during loading Project delays structural
installation of calculations Loss of calculations
heavy reputation
machinery
Quantitative risk analysis goes at least one stage further than qualitative analysis by
attempting to quantify the outcome of a risk event or to attach a numerical score
(rank) to the risk according to its perceived priority for arranging preventive or
mitigating action.
Although all quantitative methods produce ‘actual’ numbers they can give a
false sense of precision. The results are based on only on estimates and human
judgement. Those judgements might be fundamentally flawed, mistaken or simply
too difficult for any person to make with any degree of certainty.
Failure mode effect and criticality analysis (FMECA) is a common method for
attempting to quantify and rank risks. The example in Figure 4.2 is based on the
FMEA illustrated in Figure 4.1 but now contains ranking assessments. The numbers
written against each risk in the columns headed ‘Chance’, ‘Severity’ and ‘Detection
difficulty’ are allocated on a scale of 1 to 5, where 5 is at the highest end of the
perceived impact scale. Multiplying these three numbers for each particular risk
Copyright © 2014. Taylor & Francis Group. All rights reserved.
gives that risk a ranking number. The higher this ranking number, the greater
must be the management attention given to prevent the risk from occurring or to
mitigate its effects should it happen.
Item 2 in Figure 4.2, for example, considers the possibility and potential
seriousness of a building collapse. This is for a building created as part of a project, and
the collapse in question might happen during the installation of heavy machinery
on an upper-level floor. If the floor has been incorrectly designed or constructed, it
might not be sufficiently strong to carry the weight of the machinery. The assessor
clearly thinks this is unlikely to happen because they have ranked chance at the
45
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
The Essentials of Project Management
Cause of Detection
Item Failure mode failure Effect Chance Severity difficulty Rank
bottom end of the 1–5 scale. There is no doubt, however, that if this event did occur
it would be extremely serious, so the severity has been marked as 5.
Detection difficulty means the difficulty of noticing the cause of a risk in time
to prevent the risk event. In this example of possible floor collapse, the risk assessor
thinks that although the chance of a design error is very low, the difficulty of
spotting a mistake if it did occur would be fairly high (3 on the scale of 1–5).
The product of these three parameters, 1 × 5 × 3 gives a total ranking number
of 15. Theoretically, when this exercise has been performed on every item in the
list, the list can be sorted in descending sequence of these ranking numbers, so that
risks with the highest priority for management attention come at the top of the list.
Some assessors use weighted parameters. For example, it might be considered
that the severity of the risk should play a higher part in deciding ranking priority,
so the severity column could be marked on a higher scale, say from 1–10. Item 2 in
Copyright © 2014. Taylor & Francis Group. All rights reserved.
Figure 4.2 might then be marked 9 on this extended scale, which would increase
the ranking factor for this item from 15 to 27.
Risk Register
When all the known risks have been listed, assessed and ranked it is time to consider
what might be done about them. That process requires that all potential risks be
listed in a risk register (or risk log). An example of a risk register page is shown
46
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
Managing Risk
The risk register should be reviewed and updated regularly throughout the life of
the project. It is advisable to use the computer to sort the risks according to their
ranking, with the highest-ranked risks placed at the top.
Risk Date Risk description and Probability Impact Detection Risk Recommended mitigating or Action by:
ID registered consequences (severity) difficulty ranking risk avoidance action
P = 1-3 S = 1- 3 D = 1-3 P x S x D
When all the known risks have been identified, assessed, ranked and registered it is
time to consider what might be done about them. The resulting decisions must be
entered in the two right-hand columns of the risk register.
The project manager usually has a range of options about how to deal with
each possible risk:
1. Avoid the risk – the only way to avoid a risk is to remove all the possible causes,
which could even mean deciding not to do the job at all.
47
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
The Essentials of Project Management
48
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
Managing Risk
Risk
?
The contractor or
Compulsory legal Contractual Management the customer
requirement requirement choice must accept the
risk
49
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.
The Essentials of Project Management
Obtaining Insurance
Insurance can be sought directly from an underwriter, or through a broker;
preferably one with a good reputation and experienced in the insured’s type of
project activity. The insurer will need to be supplied with sufficient information
for the risk to be adequately defined, and the contractor will be expected to inform
the insurer of any change of circumstances likely to affect the risks insured. The
insurer may wish to make investigations or even follow up the project work using
its own experts.
Professional advice from experienced insurers can often be of great benefit in
reducing risks, especially in the areas of health and safety and crime prevention.
The time to seek such advice is before work on the project starts.
Copyright © 2014. Taylor & Francis Group. All rights reserved.
50
Lock, D 2014, The Essentials of Project Management, Taylor & Francis Group, Farnham. Available from: ProQuest Ebook Central. [22 November 2023].
Created from UNICAF on 2023-11-22 16:16:55.