Assignment Area
Assignment Area
chainage 0 10 20 30 40 50 60 70 80 90
offset 2.41 3.61 6.08 9.14 9.20 7.16 5.08 3.82 2.56 0
Determine the area between the fence and the chain line by three method ?
52 Prof. Dr. / Mahmoud Mewafi, Assoc. Prof. / Fawzi Zarzoura, Dr. /Ahmed Awad
Engineering Surveying Part (1): Plane Surveying
Q3: using Simpson’s rule find the area of the following shape:
53 Prof. Dr. / Mahmoud Mewafi, Assoc. Prof. / Fawzi Zarzoura, Dr. /Ahmed Awad
Engineering Surveying Part (1): Plane Surveying
54 Prof. Dr. / Mahmoud Mewafi, Assoc. Prof. / Fawzi Zarzoura, Dr. /Ahmed Awad
Engineering Surveying Part (1): Plane Surveying
Q7: A tract of land has three straight boundaries AB , BC and CD . The fourth
boundary DA is irregular . The measured length are :
The offsets measured outside the boundary DA to the irregular boundary at a regular
interval of 30 m From D are :
55 Prof. Dr. / Mahmoud Mewafi, Assoc. Prof. / Fawzi Zarzoura, Dr. /Ahmed Awad