Solar Power Project Plan

The document outlines a project plan with various tasks and their durations, including site survey, system design, procurement, construction, electrical work, final inspection, and documentation. Each main task is broken down into sub-tasks with specific durations, totaling 20 days for the entire project. The plan emphasizes key activities such as site inspection, supplier selection, and client training.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

Solar Power Project Plan

The document outlines a project plan with various tasks and their durations, including site survey, system design, procurement, construction, electrical work, final inspection, and documentation. Each main task is broken down into sub-tasks with specific durations, totaling 20 days for the entire project. The plan emphasizes key activities such as site inspection, supplier selection, and client training.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Task ID Task Name

Duration (Days)
1 Site Survey 2
1.1 Pre-Site Ev 1
1.1.1 Collect Sit 0.5
1.1.2 Define Sys 0.5
1.2 Site Inspe 1
1.2.1 Physical Si 0.5
1.2.2 Structural 0.5
2 System Des 2
2.1 Electrical 1
2.1.1 Solar Panel 0.5
2.1.2 Inverter & 0.5
2.2 Compliance 1
2.2.1 Standard C 0.5
2.2.2 Utility App 0.5
3 Procuremen 5
3.1 Supplier S 3
3.1.1 Vendor Eva 1.5
3.1.2 Purchase O 1.5
3.2 Logistics & 2
3.2.1 Shipping & 1
3.2.2 Incoming M 1
4 Constructio 6
4.1 Site Prepar 2
4.1.1 Safety & Se 1
4.1.2 Structural 1
4.2 Mounting St 2
4.2.1 Ground or 1
4.2.2 Secure Fou 1
4.3 Solar Panel 2
4.3.1 Panel Lifti 1
4.3.2 Mounting & 1
4.4 Inverter & 2
4.4.1 Inverter P 1
4.4.2 Battery Sto 1
5 Electrical 2
5.1 DC & AC Wir 1
5.1.1 Stringing S 0.5
5.1.2 Inverter to 0.5
5.2 Safety & P 1
5.2.1 Insulation 0.5
5.2.2 Voltage & 0.5
6 Final Inspe 1
6.1 Internal S 0.5
6.1.1 Load Testin 0.25
6.1.2 Documentat 0.25
6.2 Third-Party 0.5
6.2.1 Local Utili 0.25
6.2.2 Regulatory 0.25
7 Final Docu 2
7.1 Client Tra 1
7.1.1 User Train 0.5
7.1.2 Provide Ma 0.5
7.2 Project Cl 1
7.2.1 System Acti 0.5
7.2.2 Final Perf 0.5