The document outlines the assignment to create a project for constructing a road, including two major work packages: bridge construction and subway & utility culvert. It provides detailed instructions for creating a project schedule, resource sheets, and managing tasks with specific durations and dependencies. Additionally, it includes tables with activity details, resource information, and guidelines for generating reports related to the project management process using Primavera P6 software.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

Assignment 2 P6 (1)

The document outlines the assignment to create a project for constructing a road, including two major work packages: bridge construction and subway & utility culvert. It provides detailed instructions for creating a project schedule, resource sheets, and managing tasks with specific durations and dependencies. Additionally, it includes tables with activity details, resource information, and guidelines for generating reports related to the project management process using Primavera P6 software.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

MBA ACM 2024—2026

Primavera (P6) Project Assignment

ASSIGNMENT 2: ROAD PROJECT

Create a project to construct the road. The project has two major work packages, such as
bridge construction and subway & utility culvert. The details on WBS, tasks, predecessors are
provided below in Table 1.
Save the project as Road Project
Create a project calendar with following working details
Working days: Monday to Friday
Working times: 8 am to 5 pm. provide a lunch break between 1 pm to 2 pm.
Project start date: 10th February, 2025

1. Create project and save with name as Road Project, Create calendar and assign to project:
2. Create WBS and activities
3. Link the tasks and create schedule, Find project duration, project finish date and total cost of
project.
4. Create resource sheet as provided in Table 2:
5. Load resource as provided in Table 3, level resources if required, find duration, finish date
of the project after levelling the resources.

Table No:1 Activity Details

ACT. WBS Level1 WBS Level 2 ACTIVITY NAME ORIGINAL


ID DURATION
IN DAYS
1 bridge
construction
2 survey work
3 study of drawings 5 days
4 setting out bench 15 days 3SS
mark
5 level measurement 23 days 4
by leveling
instrument
6 line out 8 days 5SS+1 day
7 structural
work

8 cutting of 86 days 6FS+1 day


reinforcement
9 bending 13 days 8SS+1 day
10 making of
reinforcement
cages

11 for foundation 16 days 9


12 for sub structure 18 days 11
13 for super structure 19 days 12
14 construction
work

15 excavation

16 for foundation 20 days 11SS


17 for sub structure 20 days 16
18 concreting

19 concreting of 16 days 11
foundation
20 concreting of sub 12 days 19,12
structure
21 concreting of super 20 days 20,13
structure
22 finishing work

23 laying of final coat 20 days 21


24 subway &
utility culvert

25 survey work

26 setting out 5 days 4SS+3


benchmark days
27 level measurement 5 days 26
28 line out 2 days 27SS+1
day
29 excavation
work

30 for wall 6 days 28


31 for road 7 days 30SS+1
day
32 structural
work

33 for wall 3 days 28


34 for road 2 days 33SS
35 construction
work

36 laying of 20 days 33
reinforcement
37 concreting of wall 2 days 36,34
38 concreting of road 2 days 37FF+1
day

Table 2: Resources details

Resource Type Material Max. Std. Rate


Name Label Units
aggregate Material brass 5 Rs.3,600.00
60mm
aggregate Material brass 5 Rs.3,500.00
40mm
aggregate Material brass 5 Rs.3,300.00
cement Material bag 200 Rs.250.00
reinforcement Material kg 500 Rs42.00
25 dia
reinforcement Material kg 500 Rs.40.00
20 dia
reinforcement Material kg 500 Rs.39.00
12 dia
reinforcement Material kg 500 Rs.38.00
10 dia
reinforcement Material kg 500 Rs.40.00
8 dia
sand Material brass 6 Rs.3,500.00
project Work 2 Rs.45,000.00/mon
manager
assistant Work 4 Rs.25,000.00/mon
manager
site engineer Work 10 Rs.18,000.00/mon
supervisor Work 12 Rs.10,000.00/mon
skilled Work 75 Rs.750.00/day
labour
unskilled Work 150 Rs.500.00/day
labour
bar bender Work 10 Rs.540.00/day
equipment Work 4 Rs.500.00/day
handler
helper Work 8 Rs.430.00/day

Table 3: Resources load


Task Name Resource Names
bridge construction
survey work
setting out bench mark skilled labour[2]
level measurement by skilled labour[2]
leveling instrument
line out skilled labour[2]
structural work
study of drawings
cutting of reinforcement reinforcement 25 dia[100 kg],supervisor, skilled
labour[5]
bending reinforcement 25 dia[100 kg],skilled labour[2],unskilled
labour[4],bar bender

making of reinforcement
cages
for foundation reinforcement 25 dia[110 kg],skilled labour[4],unskilled
labour[8]
for sub structure reinforcement 20 dia[105 kg],skilled labour[5],unskilled
labour[10]
for super structure reinforcement 12 dia[110 kg],reinforcement 8 dia[105
kg],skilled labour[6],unskilled labour[12],equipment
handler
construction work
excavation
for foundation equipment handler[2],helper[3]
for sub structure supervisor[2],skilled labour[10],unskilled labour[15]
concreting

concreting of skilled labour[15],unskilled labour[20],supervisor,


foundation cement[50 bag],aggregate 40mm[1 brass],reinforcement
10 dia[50 kg],aggregate[500 brass]
concreting of sub skilled labour[15],unskilled
structure labour[20],supervisor[2],cement[50 bag],aggregate
40mm[1 brass],reinforcement 10 dia[50
kg],aggregate[500 brass]
concreting of super skilled labour[15],unskilled
structure labour[20],supervisor[2],cement[50 bag],aggregate
40mm[1 brass],reinforcement 10 dia[50
kg],aggregate[500 brass]
finishing work

laying of final coat skilled labour[3],unskilled labour[6]


subway & utility culvert
survey work
setting out benchmark assistant manager, site engineer[2]
level measurement assistant manager, site engineer[2]
line out assistant manager, site engineer[2]
excavation work
for wall equipment handler[2],helper[3],site engineer[2]
for road equipment handler[2],helper[3],site engineer[2]
structural work

for wall reinforcement 25 dia[20 kg],reinforcement 10 dia[10


kg],reinforcement 8 dia[50 kg],reinforcement 20 dia[30
kg],bar bender[3],skilled
labour[5],supervisor[3],unskilled labour[12]
for road reinforcement 25 dia[20 kg],reinforcement 10 dia[10
kg],reinforcement 8 dia[50 kg],reinforcement 20 dia[30
kg],bar bender[3],skilled
labour[5],supervisor[3],unskilled labour[12]

construction work
laying of reinforcement reinforcement 20 dia[20 kg],reinforcement 25 dia[30
kg],bar bender[2],skilled labour[10],unskilled
labour[20]
concreting of wall aggregate[1 brass],aggregate 40mm[50 brass],aggregate
60mm[60 brass],bar bender[2],cement[100
bag],helper[5],sand[80 brass],skilled
labour[10],supervisor[2],unskilled labour[15]
concreting of road aggregate[1 brass],aggregate 40mm[50 brass],aggregate
60mm[60 brass],bar bender[2],cement[100
bag],helper[5],sand[80 brass],skilled
labour[10],supervisor[2],unskilled labour[15]

Level Resource: Tools Level Resource Level

View Resource Over allocation in Resource Graph: Project Activities. Click


on Resource Usage Profile on Tool Bar

View Resources Schedule: Project Activities. Click on Resource Usage


Spreadsheet on Tool Bar

View Activities work Schedule: Project Activities. Click on Activity


Usage Spreadsheet on Tool Bar

View Activities Work Schedule Graph: Project Activities. Click on


Activity Resource Usage Spreadsheet on Tool Bar

Create Report Group: Tools Reports Report Group Add

Create new summary report:


Tools Reports Reports. Select the Report Group. Click on Add (+)

Response to the report wizard as per requirement


Create new time distributed report: Tools Reports Reports. Select the
Report Group. Click on Add (+). Tick the Time Distributed Data check
box. Response to the report wizard as per requirement