Assignment 2 P6 (1)
Assignment 2 P6 (1)
Create a project to construct the road. The project has two major work packages, such as
bridge construction and subway & utility culvert. The details on WBS, tasks, predecessors are
provided below in Table 1.
Save the project as Road Project
Create a project calendar with following working details
Working days: Monday to Friday
Working times: 8 am to 5 pm. provide a lunch break between 1 pm to 2 pm.
Project start date: 10th February, 2025
1. Create project and save with name as Road Project, Create calendar and assign to project:
2. Create WBS and activities
3. Link the tasks and create schedule, Find project duration, project finish date and total cost of
project.
4. Create resource sheet as provided in Table 2:
5. Load resource as provided in Table 3, level resources if required, find duration, finish date
of the project after levelling the resources.
15 excavation
19 concreting of 16 days 11
foundation
20 concreting of sub 12 days 19,12
structure
21 concreting of super 20 days 20,13
structure
22 finishing work
25 survey work
36 laying of 20 days 33
reinforcement
37 concreting of wall 2 days 36,34
38 concreting of road 2 days 37FF+1
day
making of reinforcement
cages
for foundation reinforcement 25 dia[110 kg],skilled labour[4],unskilled
labour[8]
for sub structure reinforcement 20 dia[105 kg],skilled labour[5],unskilled
labour[10]
for super structure reinforcement 12 dia[110 kg],reinforcement 8 dia[105
kg],skilled labour[6],unskilled labour[12],equipment
handler
construction work
excavation
for foundation equipment handler[2],helper[3]
for sub structure supervisor[2],skilled labour[10],unskilled labour[15]
concreting
construction work
laying of reinforcement reinforcement 20 dia[20 kg],reinforcement 25 dia[30
kg],bar bender[2],skilled labour[10],unskilled
labour[20]
concreting of wall aggregate[1 brass],aggregate 40mm[50 brass],aggregate
60mm[60 brass],bar bender[2],cement[100
bag],helper[5],sand[80 brass],skilled
labour[10],supervisor[2],unskilled labour[15]
concreting of road aggregate[1 brass],aggregate 40mm[50 brass],aggregate
60mm[60 brass],bar bender[2],cement[100
bag],helper[5],sand[80 brass],skilled
labour[10],supervisor[2],unskilled labour[15]