02 - Pembaikan Cerun SK Puchong - Bbs Eng SDN BHD (Rev 1)

The document outlines the project for slope repair and related works at Sekolah Kebangsaan Pusat Bandar Puchong (2) in Selangor, Malaysia, detailing the project schedule, contractor information, and various construction methods. It includes specific procedures for site preparation, soil nailing, fencing, and safety management, along with required materials and equipment. The project is set to commence on February 21, 2025, and is expected to be completed by February 19, 2026.

Uploaded by

sharifah atiqah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views54 pages

02 - Pembaikan Cerun SK Puchong - Bbs Eng SDN BHD (Rev 1)

The document outlines the project for slope repair and related works at Sekolah Kebangsaan Pusat Bandar Puchong (2) in Selangor, Malaysia, detailing the project schedule, contractor information, and various construction methods. It includes specific procedures for site preparation, soil nailing, fencing, and safety management, along with required materials and equipment. The project is set to commence on February 21, 2025, and is expected to be completed by February 19, 2026.

Uploaded by

sharifah atiqah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 54

JABATAN KERJA RAYA MALAYSIA

PROJEK PEMBAIKAN CERUN DAN KERJA-KERJA BERKAITAN DI SEKOLAH


KEBANGSAAN PUSAT BANDAR PUCHONG (2), DAERAH PETALING, SELANGOR

Tarikh: 05 Mac 2025 (Rabu)


Masa: 10.30 AM
Tempat: Bilik Mesyuarat Utama Tingkat 3, JKR Daerah Petaling Kompleks Pejabat Kerajaan
Daerah Petaling Persiaran Atmosfera, Seksyen U5, Shah Alam

Kontraktor Reka dan Bina:


BBS Engineering Sdn Bhd
No. 35-1, Jalan Damai Raya 1, Alam Damai
Cheras, 56000 Wilayah Persekutuan Kuala
Lumpur
TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


TEMPORARY ACCESS SCHEDULE
Access Point A1
Site Location Existing Visibility Front

Existing Visibility Back


Preliminary Site Setup and Access Plan
Temporary Access Road
Materials Required:
• Crusher run
• Steel plate (soft soil)

Crusher run 75/100mm thk

Crusher run

Steel plate Existing ground


WORK PROGRAMME (CPM)
METHOD STATEMENT FOR
TEMPORARY ACCESS
ERECTION OF SITE HOARDING

Materials Required:
• Hoarding panel: Corrugated galvanized iron (CGI) sheets
• Supporting structure: Timber posts
• Concrete footing
• Fasteners and fixings
• Safety signage
ERECTION OF SITE HOARDING

01 02 03

Survey the site perimeter Foundation preparation


Hoarding panel
(For post-mounted hoarding)
installation
• Excavation
• Post installation
• Concrete Pouring
04

Gates access
Temporary Site Hoarding Layout
PROJEK:

PEMBAIKAN CERUN DAN KERJA-KERJA BERKAITAN DI


SEKOLAH KEBANGSAAN PUSAT BANDAR PUCHONG (2)
DAERAH PETALING, SELANGOR

PEGAWAI PENGUASA: JURUTERA DAERAH JKR PETALING

INSTALLATION OF PROJECT WAKIL PEGAWAI PENGUASA: JURUTERA JALAN JKR PETALING

SIGNBOARD (BASED ON JKR PELANGGAN: KEMENTERIAN PENDIDIKAN MALAYSIA

STANDARD DRAWING) KONTRAKTOR REKA & BINA: BBS ENGINEERING SDN BHD

ALAMAT KONTRAKTOR: NO. 35-1, JALAN DAMAI RAYA 1,


ALAM DAMAI CHERAS, 56000 WILAYAH PERSEKUTUAN
KUALA LUMPUR

TARIKH MULA: 21/02/2025

TARIKH SIAP: 19/02/2026


INSTALLATION OF PROJECT SIGNBOARD

01 02 03

Site selection and Foundation preparation Mounting and assembly


preparation (For post-mounted signboard) the signboard
• Excavation • Frame installation
• Post installation • Panel attachment
• Concrete Pouring • Stability check
METHOD STATEMENT
SITE CLEARING
METHOD STATEMENT OF SITE CLEARING

Clearing & Grubbing Section Division Manual Site Clearing


01 02 03

Remove trees, bushes, vegetation, Divide the failed slope into Work will be done manually
rubbish, and obstructions. sections for easier to ensure precision.
construction.

Vegetation Removal Approval Slope Trimming


Disposal of Unfit
04 05 06
Material
• Minimizing the felling of trees and • Trim the slope to the required
Dispose of unsuitable
loss of top soil. gradient as per drawings.
earth at an approved
• Avoid unnecessary damage to the • Smooth and even out eroded
dumping site.
trees, crops trunks and canopy by surfaces for compacted
machines or by others. material placement in between
void and soil.
METHOD STATEMENT OF SITE CLEARING

Hazardous Material Removal Safety Precautions Site Maintenance


07 08 09

Safely remove unusable and Remove loose materials Keep the surface clean, stable,
hazardous materials. outside the work zone that and well-drained to prevent
pose a danger. water pooling.
METHOD STATEMENT
FOR SOIL NAILING
TOOLS & EQUIPMENT
✓ Drilling Equipment:
• Rotary air-flushed and water flushed.
• Down-the-hole hammer
• Tri-cone Bit
• It is important to procure drilling equipment with sufficient power and rigid drill rods.
TOOLS & EQUIPMENT
✓ Grout Mixing Equipment:
• In order to produce uniform grout mix, high speed shear colloidal mixer still to be
consider.
• Powerful grout pump is essential for uninterrupted delivery of grout mix.
• If fine aggregates is used as filter for economy, special grout pump shall be used
TOOLS & EQUIPMENT
✓ Compressor Equipment:
• The compressor shall minimum capacity to delivered air or shotcrete at the minimum rate
9m3/min.
• Sometime the noise of compressor can be an issue if the work is at close proximity to
residential area, hospital and school.
MATERIAL USED FOR SOIL NAILING
• Steel Reinforcement
• Grout Mix
• Shotcrete / Gunite
INSTALLATION SOIL NAILING

1. Staging or Platform Preparation


• At slope indicate in the drawing or confirm by engineer where soil nail is required.
• Staging shall be prepared where staging is required.
• Temporary or permanent berm drains shall be excavated to prevent slope surface
erosion.
• Staging shall be constructed using standard steel tubular scaffold tubes and to be
secured with standard fixed or swivel clamps.
• The staging shall be erected to the height where drilling for soil nail is required.
INSTALLATION SOIL NAILING

2. Setting out of soil nail positions


• Prior setting out position of Soil
Nail, a proposed numbering
system and positions shall be
submitted to the engineer.
• Upon confirmation, the soil nail
shall be marked on slope surface
with spray paint in accordance
with the engineer’s confirmation.
• All soil nail shall be numbered
for record purposes.
INSTALLATION SOIL NAILING

3. Drilling
• The drill shall be assembled and secured on the prepared staging. Appropriate bit
and hammer shall be fitted and short test run shall be conducted to ensure that the
equipment had been assembled correctly, properly secured and the necessary of
the hydraulic and pneumatic power is available.
• Drilling shall commence using suitable drilling bit to 125mm dia. at inclined position
20° as specified by engineer as shown in the drawing.
• As drilling progresses, the drilled hole shall be flushed periodically and extension
rods shall be added to achieve 6m depth or as specified by engineer as shown in
the drawing.
• On completion of drilling and removal of drilled hole shall be plugged to prevent
entry of foreign materials.
• The drilled hole must not be left behind, no more than 24 hours after being drilled.
INSTALLATION SOIL NAILING

4. Installation
• The T25 with galvanized steel bar of required length, threaded at the exposed end
for a sufficient length to facilitate fixing of nuts and washer, fitted with UPVC
centralizers at 2.0m c/c.
• Before lowering of the steel bar and grouting, the hole shall be flushed clean by
means of compressed air to remove any standing water.
INSTALLATION SOIL NAILING
5. Grouting
Grouting operation shall be in accordance with Section 10.4 BS 8081 (1989). The
proportions of the grout and minimum strength of work cubes shall comply with the
following requirements: -
• Range of water/cement ratio shall be 0.45.
• The quantities of cement in the mix shall be measured by weight in an approve
weight batching or as per bag.
• Site trial mixes shall be carrying out to verify the mix design for each concrete
grade. Non-shrink grout additives “Intra-plast-Z” or equivalent will be added
to cement grout to prevent grout shrinkage and improve workability.
• Six (6) numbers of test cubes (size 100mm x 100mm x 100mm) shall be taken
per one grouting operation for testing purpose. Three (3) test cubes shall be
tested at 7 days and the remaining cubes at 28 days after casting. The
characteristic strength of the grout shall be 21 N/mm² and 30 N/mm² at 7
days and 28 days
GROUT MIX DESIGN CALCULATION
SOIL NAILING PHOTOS
METHOD STATEMENT
FOR FENCING
MATERIAL USED FOR FENCING

• Chain link mesh


• Fence posts
• Tension wire
• Steel ties
• Concrete ( for stump)
• Other accessories
PROCEDURE FOR FENCING

• Shovel ( hole digger)


• Measuring tape
• Levelling tools
• Wire cutters
• Pliers
• Concrete mixer ( for stump)
PROCEDURE FOR FENCING

Site preparation Post installation Installing chain link mesh


01 02 03

• Mark the layout • Dig post holes and insert • Attach the mesh to the terminal
• Verify the positions of the posts the posts • Use steel ties to secure the chain
link
• Pour concrete into the post
• Attach the mesh to the posts at
holes the specified intervals
Tensioning the Mesh Final Checks
04 05

• Install tension wire along the


bottom of the fence
• Use a tensioning device to tighten
the mesh,
• Secure the tension wire to the
posts using tie wire
METHOD STATEMENT
SURVEYING & GROUND
PREPARATION
SITE SURVEY & SETTING OUT PROCEDURE
• Site Survey & Control Point Establishment
• Setting Out Works

INSPECTION & TESTING PROCEDURE

• Survey & Setting Out Verification


• Concrete Testing (Cube test)
- Allowing slab support, nail grout application, and drainage.
• Reinforcement tensile test
• Pull out test
EQUIPMENT FOR PULL OUT TEST
• Load Plate – Size 450mm x 450mm x 25mm (min. thickness)
• Extension Apparatus – Steel angle adjuster (min. 20 mm thicknesses), Jam nut coupling,
extension cylinder, adjustable angle plate.
• Hydraulic Jack – Durajack, model DH-306 (capacity : 30 ton)
• Load Cell – Model ELC – 30S
• Dial Gauge – WIKA, accuracy (0.01mm)
PULL OUT TEST PROCEDURE
1. Selection of Test Point
a) The location of test point for the pull-out test shall be selected by the Engineer
before testing work starts.

2. Preparation
a) A large thick steel bearing plate with a center hole shall be used as a reaction plate
over the surface of the slope. The pull-out of the anchor shall be in exact parallel
direction of the bolt into the slope. This is achieved by the preparation of a
concrete pad and additional adjustment plate to achieve an exact perpendicular
surface to the bar for the bottom of the Hydraulic Hollow Jack to sit on.
b) Specification detail of the Jack must be provided showing the effective area of the
Hydraulic Cylinder Ram.
c) A Calibrated Load Cell with enough capacity must also be used as a Primary Load
Preference.
PULL OUT TEST PROCEDURE
2. Preparation
d) A Calibrated Pressure Gauge with enough capacity must also be used as a
Secondary Load preference.
e) At least 3 Calibrated Dial Gauges with 0.01 mm accuracy must be use over the
surface of the reference plate.
f) The overall setup of the equipment arrangement for the Pull-out Test is as shown in
the sketch below.
PULL OUT TEST PROCEDURE
3. The pullout test
a) A Connecting Coupler shall be used to extend the anchor to accommodate the
equipment installed.
b) The loading sequence of the Pullout Test shall be according to the one proposed
by the consultant.
c) The acceptance criteria of the Pullout Test and the termination of the test shall be
according to the BS 8081: 1989 or to be determined by the engineer at site.
d) The acceptance of rock bolt pullout test to follow BS 8081 Clause 11.4.11.
PULL OUT TEST PHOTOS
METHOD OF CALCULATIONS
The pressure value of a hydraulic jack at a specific load with a hydraulic jack ram area of 7.22 inches
square is calculated as below:
SAFETY MANAGEMENT
PERSONAL PROTECTIVE EQUIPMENT (PPE)

Head protection Signboard


(Helmet)

Foot protection AWAS caution


(Safety shoe) tape

Body protection
(Vest)
SAFETY SIGNBOARD