structure?
a) Internal order
b) WBS element
c) Claim
d) Network activity.
2) What PPIDS master data is necessary for using PP/DS? Note: There are
2 correct answers to this question
a) Location
b) Material
c) Production version
d) Resource
3) How can you grant individual authorization for WBS elements and
networks?
a) Define a user status to lock the business transaction Update Project.
b) Activate access control lists (ACL) for the project profile and the
network profile.
c) Set the system status to “Lock Master Data”.
d) Activate access control lists (ACL) for the user master record.
4) You use networks and internal activities in your project. You have
activated capacity requirements and notice that one work center is
overloaded. You have no authorization to change the work center. How
can you reduce the overload of the work center? There are 2 correct
answers to this question.
a) Increase the capacities of the work center in the project planning
board.
b) Shift activities backward or forward on the time axis where more
capacities are available.
c) Maintain subordinate internal activity elements assigned to other
work centers.
d) Trigger automatic capacity leveling inside the project planning
board.
5) You have a project with a network, material and milestones. You want
to plan an activity to start two days after its predecessor. There are 2
correct answers to this question.
a) Use an offset of two days for the relationship of both activities
b) Use an offset of two days for milestone date
c) Use an offset of two days for the requirement date of the material
component
d) Calculate the start date of the activity and set the constraint “must
start on” accordingly.