Valiant Weekly Report No.13
Valiant Weekly Report No.13
PROJECT UPDATE
ACCOMPLISHMENT WEIGHTED (%)
%
CONTRACT REL. WT.
PART DESCRIPTION This SCHEDULED
AMOUNT (Pesos) (%) PREVIOUS THIS PERIOD TO DATE Previous To date TO DATE
Period
A. CIVIL WORKS
800.0 Clearing and Grubbing 285,951.93 0.32% 0.19 - 0.19 0.318% 0.000% 0.318%
200.0 Aggregate SubBase course 58,178.03 0.06% - - - 0.000% 0.000% 0.000%
704.0 Masonry 1,315,806.86 1.46% 432.45 61.12 493.57 1.068% 0.151% 1.219%
803.0 Excavation 48,668.64 0.05% 87.69 - 87.69 0.054% 0.000% 0.054%
804.0 Embankment from Borrow 977,851.81 1.09% 1,233.31 - 1,233.31 0.762% 0.000% 0.762%
900.0 Reinforced Concrete 5,115,471.82 5.69% 90.68 12.80 103.48 0.932% 0.132% 1.063%
1002.0 Plumbing Fixtures 99,900.85 0.11% - - - 0.000% 0.000% 0.000%
1602-4A PVC Pipes 52,499.80 0.06% - - - 0.000% 0.000% 0.000%
1602-4B PVC Pipes 120,999.55 0.13% - - - 0.000% 0.000% 0.000%
1013.2.3 Fabricated Metal Roofing Accessories 243,477.18 0.27% - 115.16 115.16 0.000% 0.190% 0.190%
1006.0 Steel Doors and Frames 25,192.72 0.03% - - - 0.000% 0.000% 0.000%
1014.0 Pre-painted Metal Sheets 675,196.78 0.75% 503.87 - 503.87 0.526% 0.000% 0.526%
1027.0 Cement Plaster Finish 271,884.36 0.30% - - - 0.000% 0.000% 0.000%
1018.0 Tile Works 112,549.41 0.13% - - - 0.000% 0.000% 0.000%
1032a Masonry Painting 989,577.84 1.10% - - - 0.000% 0.000% 0.000%
A1.1 Facilities for the Engineer/ Field Office 134,949.17 0.15% 3.38 0.31 3.68 0.051% 0.005% 0.055%
B.7 Construction Safety & Health 135,959.23 0.15% 3.38 0.31 3.68 0.051% 0.005% 0.056%
SPL 1 Project Signboards 9,670.94 0.01% 0.33 0.03 0.36 0.004% 0.000% 0.004%
SPL 2 Mobilization and Demobilization 543,897.31 0.61% 0.50 - 0.50 0.303% 0.000% 0.303%
B. MECHANICAL/ELECTRICAL WORKS - - -
1200.B Valves & Controls 5,049,529.32 5.62% - - - 0.000% 0.000% 0.000%
403.0 Metal Structure 7,651,358.27 8.51% 28,272.65 4,327.25 32,599.90 2.979% 0.456% 3.435%
SPL 3 Insulated Sandwich Panel 22,370,632.64 24.89% 991.66 - 991.66 8.711% 0.000% 8.711%
SPL 4 Pressure Vessel-Pump Separator 684,984.80 0.76% - - - 0.000% 0.000% 0.000%
SPL 5 Pressure Vessel-Receiver 642,136.05 0.71% - - - 0.000% 0.000% 0.000%
SPL 6 Site Materials-Cooling Coils 1,924,905.70 2.14% - - - 0.000% 0.000% 0.000%
SPL 7 Support Materials-Cooling Coils 1,713,951.99 1.91% - - - 0.000% 0.000% 0.000%
SPL 8 Insulated Sandwich Panel Supports 1,763,602.26 1.96% - - - 0.000% 0.000% 0.000%
SPL 9 Ammonia Pipes and Fittings 4,078,238.21 4.54% - - - 0.000% 0.000% 0.000%
SPL 10 P.U. Insulation & Cladding Materials 2,483,466.71 2.76% - - - 0.000% 0.000% 0.000%
SPL 11 Floor Insulation Materials 4,006,931.59 4.46% - - - 0.000% 0.000% 0.000%
SPL 12 Weathercoat for Flooring 1,031,284.54 1.15% - - - 0.000% 0.000% 0.000%
SPL 13 Pipes & Air Cooler Support Materials 302,004.42 0.34% - - - 0.000% 0.000% 0.000%
SPL 14 Temperature Monitoring Unit 219,354.50 0.24% - - - 0.000% 0.000% 0.000%
SPL 15 Blowers 1,621,734.02 1.80% - - - 0.000% 0.000% 0.000%
SPL 16 Refrigeration Equipment Electrical Works 1,974,182.74 2.20% - - - 0.000% 0.000% 0.000%
SPL 17 Staff/Manager/Engineering/E quipment/Genset Room Electrical
1,867,263.14
Works 2.08% - - - 0.000% 0.000% 0.000%
SPL 18 Transformer & Accessories 869,108.11 0.97% - - - 0.000% 0.000% 0.000%
1200.A.1 Compressor 1 8,343,983.26 9.28% - - - 0.000% 0.000% 0.000%
SPL 19 Ammonia Pump 1,156,511.03 1.29% - - - 0.000% 0.000% 0.000%
1200.A.3 Evaporative Condenser 3,169,884.78 3.53% - - - 0.000% 0.000% 0.000%
1200.A.4 Ammonia Unit Cooler 417,384.96 0.46% - - - 0.000% 0.000% 0.000%
SPL 20 Initial Ammonia Charge 1,109,145.85 1.23% - - - 0.000% 0.000% 0.000%
SPL 21 Initial Oil Charge 556,513.28 0.62% - - - 0.000% 0.000% 0.000%
SPL 22 Generator Set 1,996,039.34 2.22% 0.70 - 0.70 1.555% 0.000% 1.555%
SPL 23 Primary Line Distribution System 1,659,721.09 1.85% - - - 0.000% 0.000% 0.000%
TOTAL CONTRACT AMOUNT 89,881,536.83
100.00% - - 17.313% 0.938% 18.250% 18.09%
NOTE: Indicates notes which are necessary to supply information of the above figures. SLIPPAGE, +/- 0.156%
PROGRESS PHOTOS
Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"
Captions:
Prepared by
Signature
Name ENGR. IVAN NOEL LANDINGIN
Title Contractor's Engineer
Date