The document outlines the Job Hazard Analysis (JHA) for blinding and de-blinding activities at HPCL Visakh Refinery. It identifies various hazards associated with specific tasks and provides control measures to mitigate risks, such as using safety gloves and non-sparking tools. The document also specifies the type of work permit required for each activity, which is categorized as 'Cold'.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
34 views1 page
Blinding and de blinding
The document outlines the Job Hazard Analysis (JHA) for blinding and de-blinding activities at HPCL Visakh Refinery. It identifies various hazards associated with specific tasks and provides control measures to mitigate risks, such as using safety gloves and non-sparking tools. The document also specifies the type of work permit required for each activity, which is categorized as 'Cold'.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1
HPCL - VISAKH REFINERY
PROCESS SAFETY MANAGEMENT SYSTEM Doc No: PSM/FR/9.9B
Ref Doc : PSM/PR/9 WORK PERMIT SYSTEM Rev. : 1 FORMATS Date of this Rev : January, 2013 Page 1 of 1 JOB HAZARD ANALYSIS
DIVISION/ DEPT NAME Onsite / Maintenance
PROJECT/ WORK REQUISITION TITLE Base JHA for blinding & De blinding PROJECT/ REQUISITION NO JOB DESCRIPTION Blinding & de blinding ACTIVIT ACTIVITY IDENTIFIED HAZARDS CONTROL/ MITIGATION MEASURES TYPE OF PERMIT Y NO. DESCRIPTION REQUIRED J1-A1 Opening of bolts Oil Spillage, burns due to hot Lower most bolt to be opened for slacking of flange for draining any Cold & Spade insertion liquid/Steam. line content. Suitable Hand gloves to be used as per the service requirement. Safety goggle’s to be used for eye protection Bolt tightening Slipping of spanner, injury to hand Finger saver to be used. Safety Gloves to be used. Cold J1-A2 while tightening. J2-A1 Bolt Opening & Slipping of spanner, injury to hand Finger saver to be used. Safety Gloves to be used. Cold Spade removal while hammering for bolt removal. J2-A2 Flange make up & Usage of Underrating gasket. Gasket installation procedure to be followed and gasket to verified by Cold Bolt tightening Slipping of spanner, injury to hand inspection and countersigned operations after installation in the while hammering for bolt tightening. presence of Operations. Finger saver to be used. Safety Gloves to be used. J3-A1 Valve passing and Inhaling of HC/H2S Use non sparking tools and use Online respirator/BA set in case of Cold presence of H2S leak & presence of HC. Lighter HC Clear area if H2s LEAK IS MORE & inform Operation J3-A2 Working at Fall of objects/people from height SWP 06 Double harness safety belt to be used & material to be height properly fastened. Sign Prepared By Designation Executing Supervisor Sign Approved By Designation Executing Manager