Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant (250226)

The document outlines the master schedule for the Tanjung Sauh 2x150MW Smart Energy Power Plant, detailing various activities, milestones, and their respective timelines from 2025 to 2027. Key milestones include contract signing, completion of soil tests, and various construction phases for both units of the power plant. The schedule also includes engineering, design, and procurement activities necessary for the project's completion.

Uploaded by

sukiharsono988
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views11 pages

Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant (250226)

The document outlines the master schedule for the Tanjung Sauh 2x150MW Smart Energy Power Plant, detailing various activities, milestones, and their respective timelines from 2025 to 2027. Key milestones include contract signing, completion of soil tests, and various construction phases for both units of the power plant. The schedule also includes engineering, design, and procurement activities necessary for the project's completion.

Uploaded by

sukiharsono988
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant

Activity ID Activity Name Original Start Finish 2025 2026 2027


Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Master Schedule of Tanjung Sauh 2x150MW Smart Energy911Power
24-10-01
Plant27-03-30 Master Sche

Milestone 896 24-10-01 27-03-15 Milestone

Unit 1 & BOP 806 24-10-01 26-12-15 Unit 1 & BOP


MS1005 Contract Sign 0 24-10-01 Contract Sign
MS1020 NTP 0 25-01-26 NTP
MS1010 Soil Test Completed (Owner's Scope) 0 25-02-14 Soil Test Completed (Owner's Scope)
MS1015 Basic design completed 0 25-02-28 Basic design completed
MS1006 Land filling/leveling Started (Owner's Scope) 0 25-02-28 Land filling/leveling Started (Owner's Scope)
MS1025 Temp Jetty Construction Completed (Owner's Scope) 0 25-03-15 Temp Jetty Construction Completed (Owner's Scope)
MS1035 Piling Works of Unit 1 Started 0 25-06-01 Piling Works of Unit 1 Started
MS1030 Excavation for Main Power Block area foundation Start 0 25-07-01 Excavation for Main Power Block area foundation Start
MS1040 Main Building Foundation Construction Started 0 25-09-01 Main Building Foundation Construction Started
MS1045 Boiler Steel Structure Erection Start 0 25-11-01 Boiler Steel Structure Erection Start
MS1050 Boiler Drum Lifting 0 26-01-18 Boiler Drum Lifting
MS1055 T/H Enclosed 0 26-03-17 T/H Enclosed
MS1065 Power back feeding 0 26-04-16 Power back feeding
MS1060 STG soleplate located 0 26-05-01 STG soleplate located
MS1070 Boiler Hydraulic Test 0 26-07-02 Boiler Hydraulic Test
MS1075 Turbine Casing-on 0 26-09-01 Turbine Casing-on
MS1080 Boiler Chemical Cleaning 0 26-09-26 Boiler Chemical Cleaning
MS1090 Steam Blow-out 0 26-10-31 Steam Blow-out
MS1085 Turbine oil flushing completed 0 26-10-31 Turbine oil flushing completed
MS1095 Initial Synchronization 0 26-11-20 Initial Synchronization
MS1100 COD 0 26-12-15 COD
Unit 2 577 25-08-16 27-03-15 Unit 2
MS1185 Piling Works of Unit 2 Started 0 25-08-16 Piling Works of Unit 2 Started
MS1175 Main Building Foundation Construction Started 0 25-11-16 Main Building Foundation Construction Started
MS1110 Boiler Steel Structure Erection Start 0 26-01-16 Boiler Steel Structure Erection Start
MS1115 Boiler Drum Lifting 0 26-04-03 Boiler Drum Lifting
MS1120 T/H Enclosed 0 26-06-17 T/H Enclosed
MS1125 STG soleplate located 0 26-07-17 STG soleplate located
MS1130 Boiler Hydraulic Test 0 26-09-15 Boiler Hydraulic Test
MS1135 Turbine Casing-on 0 26-11-17 Turbine Casing-on
MS1140 Boiler Chemical Cleaning 0 26-12-19 Boiler Chemical Cleaning
MS1180 Turbine oil flushing completed 0 27-01-16 Turbine oil flushing co
MS1145 Steam Blow-out 0 27-01-24 Steam Blow-out

Actual Critical Summary DEC & DR page 1 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
MS1150 Initial Synchronization 0 27-02-18 Initial Synchroniza
MS1155 COD 0 27-03-15 COD
Engineering & Design 485 24-10-01 26-01-28 Engineering & Design
E0000 Basic Design & Review 151 24-10-01 25-02-28 Basic Design & Review
E15 Piling Test Drawing 30 25-02-14 25-03-15 Piling Test Drawing
E0065 Jetty Detail Design (Owner's Scope) 61 25-03-01 25-04-30 Jetty Detail Design (Owner's Scope)
E25 Detail Piling Drawing 45 25-04-16 25-05-30 Detail Piling Drawing
E0005 Technical Specification 150 25-03-01 25-07-28 Technical Specification
E0080 Water Supply Detail Design 181 25-03-31 25-09-27 Water Supply Detail Design
E0070 Chemical Detail Design 213 25-03-31 25-10-29 Chemical Detail Design
E0040 Ash Handling System Detail Design 273 25-03-01 25-11-28 Ash Handling System Detail Design
E0030 Coal Handling System Detail Design 273 25-03-01 25-11-28 Coal Handling System Detail Design
E0010 Civil Detail Design 304 25-03-01 25-12-29 Civil Detail Design
E0020 Mechanical Detail Design 304 25-03-01 25-12-29 Mechanical Detail Design
E0050 Electrical Detail Design 334 25-03-01 26-01-28 Electrical Detail Design
E0060 I&C Detail Design 334 25-03-01 26-01-28 I&C Detail Design
Procurement (From PO to Site) 502 25-01-30 26-06-15 Procurement (From PO to Site)

Unit 1 & BOP 502 25-01-30 26-06-15 Unit 1 & BOP


MECH 488 25-01-30 26-06-02 MECH
P1M1000 Embedded Itme & Bolt 212 25-01-30 25-08-29 Embedded Itme & Bolt
P1M1005 Boiler Steel Structure (First Batch) 241 25-02-01 25-09-30 Boiler Steel Structure (First Batch)
P1M1010 Boiler Air Pre-heater 272 25-02-01 25-10-30 Boiler Air Pre-heater
P1M1015 T/G House & C/B Steel Structure (First Batch) 200 25-04-30 25-11-16 T/G House & C/B Steel Structure (First Batch)
P1M1155 MP/LP Pipings, Valves, Fittings & Supports 180 25-06-01 25-11-28 MP/LP Pipings, Valves, Fittings & Supports
P1M1020 Boiler Drum 333 25-02-02 26-01-01 Boiler Drum
P1M1025 Boiler WW, Furnace, SH, RH & etc (First Batch) 334 25-02-01 26-01-01 Boiler WW, Furnace, SH, RH & etc (First Batch)
P1M1045 Desalination & DW Equipment 251 25-05-16 26-01-22 Desalination & DW Equipment
P1M1215 Condensate Pump 180 25-07-31 26-01-27 Condensate Pump
P1M1220 Vacuum pumps 180 25-07-31 26-01-27 Vacuum pumps
P1M1055 Boiler Fans 273 25-05-01 26-01-28 Boiler Fans
P1M1030 ESP (Support) 291 25-04-30 26-02-15 ESP (Support)
P1M1080 Turbine House Crane 239 25-07-06 26-03-03 Turbine House Crane
P1M1145 Turbine & Generator Deck-Plate 395 25-02-01 26-03-03 Turbine & Generator Deck-Plate
P1M1090 Condenser (shell, support, etc) 391 25-02-05 26-03-03 Condenser (shell, support, etc)
P1M1150 HP Pipings, Valves, Fittings & Supports 289 25-06-01 26-03-17 HP Pipings, Valves, Fittings & Supports
P1M1040 Boiler burners 409 25-02-03 26-03-19 Boiler burners
P1M1195 Generator Stator 423 25-02-02 26-03-31 Generator Stator

Actual Critical Summary DEC & DR page 2 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
P1M1225 Generator Rotor 423 25-02-02 26-03-31 Generator Rotor
P1M1160 CW Pump 287 25-07-02 26-04-15 CW Pump
P1M1035 Mill 350 25-05-01 26-04-16 Mill
P1M1180 Feed Water Pumps 287 25-07-03 26-04-16 Feed Water Pumps
P1M1085 Turbine Lubricating Oil System Euipment 436 25-02-04 26-04-16 Turbine Lubricating Oil System Euipment
P1M1120 EH Oil System Euipment 229 25-08-30 26-04-16 EH Oil System Euipment
P1M1205 HP/LP Heater 273 25-07-31 26-04-30 HP/LP Heater
P1M1075 Coal Feeder 304 25-07-01 26-05-01 Coal Feeder
P1M1190 Turbine 454 25-02-02 26-05-01 Turbine
P1M1200 Ash Handling & Bottom Ash Handling Equipments 258 25-08-31 26-05-16 Ash Handling & Bottom Ash Handling Equipments
P1M1210 Deaerator 260 25-08-30 26-05-17 Deaerator
P1M1230 Turbine Other Aux. Equipment 273 25-08-31 26-05-31 Turbine Other Aux. Equipment
P1M1115 Generator Sealing Oil System Euipment 487 25-01-30 26-06-01 Generator Sealing Oil System Euipment
P1M1125 Generator Stator Cooling Water Euipment 487 25-01-31 26-06-02 Generator Stator Cooling Water Euipment
ELEC 422 25-02-03 26-03-31 ELEC
P1M1065 DC & UPS System Equipment 183 25-07-01 25-12-31 DC & UPS System Equipment
P1M1105 Electrical Cable Tray 153 25-07-31 25-12-31 Electrical Cable Tray
P1M1070 150KV GIS 213 25-06-01 25-12-31 150KV GIS
P1M1235 Network & Switchyard Equipment 183 25-07-02 25-12-31 Network & Switchyard Equipment
P1M1165 Electrical Cable (First Batch) 168 25-07-31 26-01-15 Electrical Cable (First Batch)
P1M1100 LV Electrical Power Distribution Equipment 150 25-08-30 26-01-27 LV Electrical Power Distribution Equipment
P1M1060 Main & Unit Transformers 257 25-06-01 26-02-13 Main & Unit Transformers
P1M1095 HV Electrical Power Distribution Equipment 200 25-08-30 26-03-18 HV Electrical Power Distribution Equipment
P1M1050 BTG Area Electrical Equip ment 422 25-02-03 26-03-31 BTG Area Electrical Equip ment
P1M1185 Non-Segregated Busbar & IPB etc. 181 25-10-02 26-03-31 Non-Segregated Busbar & IPB etc.
I &C 319 25-07-31 26-06-15 I&C
P1M1110 I&C Cable Tray (Incl.Auxiliaries) 150 25-08-03 25-12-31 I&C Cable Tray (Incl.Auxiliaries)
P1M1130 I&C Pipings, Valves, Fittings & Supports 120 25-09-02 25-12-31 I&C Pipings, Valves, Fittings & Supports
P1M1175 I&C Cable(All Kind of Cable) 168 25-07-31 26-01-15 I&C Cable(All Kind of Cable)
P1M1135 I&C Panel/Desk (Incl. DCS,MCC) 196 25-10-02 26-04-16 I&C Panel/Desk (Incl. DCS,MCC)
P1M1170 PI/PS, TI/TS, Transmitter, etc 196 25-11-01 26-05-16 PI/PS, TI/TS, Transmitter, etc
P1M1140 I&C Actuator 196 25-12-01 26-06-15 I&C Actuator
Construction & Commissioning 911 24-10-01 27-03-30 Construction

Prepration Work 516 24-10-01 26-02-28 Prepration Work


C1T0010 Received Down Payment 117 24-10-01 25-01-26 Received Down Payment
C1T0005 Soil Test (Owner's Scope) 137 24-10-01 25-02-14 Soil Test (Owner's Scope)
C1T0002 Land filling/leveling (Owner's Scope) 151 24-10-01 25-02-28 Land filling/leveling (Owner's Scope)

Actual Critical Summary DEC & DR page 3 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1T1085 Temporary Jetty & Road Construction (Owner's Scope) 166 24-10-01 25-03-15 Temporary Jetty & Road Construction (Owner's Scope)
C1T0015 Mobilization 166 24-10-01 25-03-15 Mobilization
C1T0025 Concrete Supply (Batching plan or other ) 31 25-02-13 25-03-15 Concrete Supply (Batching plan or other )
C1T1010 Piling Test 61 25-03-16 25-05-15 Piling Test
C1T0020 Temp Camp & Office Construction 107 25-03-16 25-06-30 Temp Camp & Office Construction
C1T1091 Coal Unload Jetty Construction 304 25-05-01 26-02-28 Coal Unload Jetty Construction
Unit 1 & BOP 670 25-03-01 26-12-30 Unit 1 & BOP
Civil Works 630 25-03-01 26-11-20 Civil Works
Main Power Block 470 25-06-01 26-09-13 Main Power Block
Boiler Area 380 25-06-01 26-06-15 Boiler Area
Boiler 137 25-06-01 25-10-15 Boiler
C1T1015 Boiler Area Piling Work 30 25-06-01 25-06-30 Boiler Area Piling Work
C1T1020 Boiler Area Excavation 46 25-07-01 25-08-15 Boiler Area Excavation
C1T1030 Boiler Foundation Delivery for Install. 0 25-10-15 Boiler Foundation Delivery for Install.
C1T1025 Boiler Fundation Construction 87 25-07-21 25-10-15 Boiler Fundation Construction
Boiler Axuliary 350 25-07-01 26-06-15 Boiler Axuliary
C1T1074 Chimney Piling work 15 25-07-01 25-07-15 Chimney Piling work
C1T1058 ESP Piling work 16 25-07-16 25-07-31 ESP Piling work
C1T1062 IDF Piling work 10 25-08-01 25-08-10 IDF Piling work
C1T1079 Air Compressor House Piling work 21 25-08-11 25-08-31 Air Compressor House Piling work
C1T1185 Flue Gas Duct Supports Piling work 30 25-09-01 25-09-30 Flue Gas Duct Supports Piling work
C1T1060 ESP Foundation Construction 61 25-10-16 25-12-15 ESP Foundation Construction
C1T1070 PAF & FDF & IDF Foundation 61 25-12-16 26-02-14 PAF & FDF & IDF Foundation
C1T1180 Start-up Boiler House 90 25-12-16 26-03-15 Start-up Boiler House
C1T1265 Flue Gas Duct Supports Construction 90 25-12-16 26-03-15 Flue Gas Duct Supports Construction
C1T1080 Air Compressor House Construction 121 25-12-16 26-04-15 Air Compressor House Construction
C1T1075 Chimney Construction 243 25-10-16 26-06-15 Chimney Construction
T/H Area 440 25-07-01 26-09-13 T/H Area
MB 440 25-07-01 26-09-13 MB
C1T1031 MB Piling Work 46 25-07-01 25-08-15 MB Piling Work
C1T1032 MB Area Excavation 46 25-08-01 25-09-15 MB Area Excavation
C1T1035 MB Foundation Construction 91 25-09-01 25-11-30 MB Foundation Construction
C1T1040 Main Building Foundation up to 0m 0 25-11-30 Main Building Foundation up to 0m
C1T1045 MB Steel Structure Erection 77 25-12-01 26-02-15 MB Steel Structure Erection
C1T1050 MB Enclosing (TG house) 30 26-02-16 26-03-17 MB Enclosing (TG house)
C1T1195 HV &LV distribution room decoration 31 26-02-16 26-03-18 HV &LV distribution room decoration
C1T1205 bunker bay Floor Construction 90 26-02-16 26-05-16 bunker bay Floor Construction

Actual Critical Summary DEC & DR page 4 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1T1255 Coal Bunkers 120 26-05-17 26-09-13 Coal Bunkers
Turbine Auxiliary 212 25-10-02 26-05-01 Turbine Auxiliary
C1T1055 TG Pedestal Construction 92 25-10-02 26-01-01 TG Pedestal Construction
C1T1240 Lubricating Oil foundation 15 26-02-16 26-03-02 Lubricating Oil foundation
C1T1260 Emergency Oil Pit 75 26-02-14 26-04-29 Emergency Oil Pit
C1T1245 MB 0m equipment foundation Construction 45 26-03-18 26-05-01 MB 0m equipment foundation Construction
Coal Handling & Fuel Oil Supply System 407 25-08-16 26-09-26 Coal Handling & Fuel Oil Supply Syste
C1T1086 Bucket wheel Stacker reclamer Foundation 120 25-08-16 25-12-13 Bucket wheel Stacker reclamer Foundation
C1T1250 Fuel Oil Tank Foundation 40 26-01-20 26-02-28 Fuel Oil Tank Foundation
C1T1105 Fuel Oil Pump House Construction 90 25-12-31 26-03-30 Fuel Oil Pump House Construction
C1T1088 Emergency Reclaim Hopper 90 26-01-03 26-04-02 Emergency Reclaim Hopper
C1T1096 Coal Control building 150 25-12-01 26-04-29 Coal Control building
C1T1097 Available Bottom Coal for Coal Yard 30 26-03-31 26-04-29 Available Bottom Coal for Coal Yard
C1T1095 Coal Transfer Tower Construction 119 26-01-15 26-05-13 Coal Transfer Tower Construction
C1T1090 Coal Crusher House Construction 150 25-12-31 26-05-29 Coal Crusher House Construction
C1T1089 Underground coal transportation corridor 150 26-01-03 26-06-01 Underground coal transportation corridor
C1T1100 Coal Conveyor Trestle Construction 121 26-02-13 26-06-13 Coal Conveyor Trestle Construction
C1T1087 Coal yard (Piling work of Dry coal shed) 210 25-12-14 26-07-11 Coal yard (Piling work of Dry coal shed)
C1T1252 Bulldozer house 120 26-05-30 26-09-26 Bulldozer house
Ash Handling System 268 26-01-19 26-10-13 Ash Handling System
H1010 Bottom Ash Silo Foundation 45 26-01-19 26-03-04 Bottom Ash Silo Foundation
H1005 Fly Ash Silo foundation 45 26-04-16 26-05-30 Fly Ash Silo foundation
H1015 CEMS room 60 26-06-16 26-08-14 CEMS room
H1000 Ash Yard 120 26-06-16 26-10-13 Ash Yard
Water Supply & Treatment System 344 25-10-01 26-09-09 Water Supply & Treatment System
Water Supply System 256 25-10-16 26-06-28 Water Supply System
C1T1109 Flocculating sedimentation pond 30 25-12-01 25-12-30 Flocculating sedimentation pond
C1T1111 Sea water Pond 30 25-12-31 26-01-29 Sea water Pond
C1T1106 CWP House lower structure (Piling work) 90 25-12-01 26-02-28 CWP House lower structure (Piling work)
C1T1115 Comprehensive water pump house (Piling work) 105 25-12-01 26-03-15 Comprehensive water pump house (Piling work)
C1T1275 Siphon Well 45 26-01-30 26-03-15 Siphon Well
C1T1108 CW Pipeline Excavation & Backfill 196 25-10-16 26-04-29 CW Pipeline Excavation & Backfill
C1T1107 CWP House Civil Structure & Enclosure 60 26-03-01 26-04-29 CWP House Civil Structure & Enclosure
C1T1112 Fresh Water Reservoir 90 26-01-30 26-04-29 Fresh Water Reservoir
C1T1113 Domestic water pond 30 26-04-30 26-05-29 Domestic water pond
C1T1285 CW Outfall (Piling work) 90 26-03-16 26-06-13 CW Outfall (Piling work)
C1T1114 Reusing water pond 30 26-05-30 26-06-28 Reusing water pond

Actual Critical Summary DEC & DR page 5 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
WaterTreatment System 114 25-10-01 26-01-22 WaterTreatment System
C1T1126 Demineralized water storage tank Foundation 30 25-11-30 25-12-29 Demineralized water storage tank Foundation
C1T1120 Seawater desalination Plant Foundation 30 25-12-01 25-12-30 Seawater desalination Plant Foundation
C1T1121 Water Treatment Building Construction (Piling work) 114 25-10-01 26-01-22 Water Treatment Building Construction (Piling work)
Waste Water Treatment 234 26-01-19 26-09-09 Waste Water Treatment
C1T1127 Acid and Alkali Wastewater Pond 60 26-01-19 26-03-19 Acid and Alkali Wastewater Pond
C1T1128 Chlorine making house 107 26-03-01 26-06-15 Chlorine making house
C1T1130 Coal contained wastewater treatment plant 60 26-07-12 26-09-09 Coal contained wastewater treatment pl
C1T1290 Sanitary sewage treatment station 90 26-06-12 26-09-09 Sanitary sewage treatment station
C1T1132 Coal particle sedimentation pond 60 26-07-12 26-09-09 Coal particle sedimentation pond
Electrical System 396 25-03-01 26-03-31 Electrical System
C1T1155 150kV GIS Foundation & Building 122 25-09-01 25-12-31 150kV GIS Foundation & Building
C1T1150 Net Control building 122 25-09-01 25-12-31 Net Control building
C1T1157 Outside Truss 17 25-12-15 25-12-31 Outside Truss
C1T1135 Main TR Foundation (Piling work) 45 25-12-31 26-02-13 Main TR Foundation (Piling work)
C1T1145 Unit TR Foundation 45 25-12-31 26-02-13 Unit TR Foundation
C1T1160 Transmission Line construrction (Owner's Scope) 396 25-03-01* 26-03-31 Transmission Line construrction (Owner's Scope)
Axuiliary Plant 278 26-02-16 26-11-20 Axuiliary Plant
C1T1330 Foam fire extinguishing room 60 26-03-01 26-04-29 Foam fire extinguishing room
C1T1320 Storage Building 120 26-02-16 26-06-15 Storage Building
C1T1065 Administration Building Construction 151 26-02-16 26-07-16 Administration Building Construction
C1T1345 Plant Road 150 26-03-01 26-07-28 Plant Road
C1T1325 Guard House 60 26-06-16 26-08-14 Guard House
C1T1322 Fence Works & Gates 90 26-05-17 26-08-14 Fence Works & Gates
C1T1346 Parking Lot 30 26-07-29 26-08-27 Parking Lot
C1T1321 Workshop 120 26-06-16 26-10-13 Workshop
C1T1140 Operation & Maintenance House 166 26-05-17 26-10-29 Operation & Maintenance House
C1T1355 Landscaping 60 26-09-22 26-11-20 Landscaping
Installation Works 366 25-10-31 26-10-31 Installation Works
Main Power Block 365 25-11-01 26-10-31 Main Power Block
Boiler & Accessories 330 25-11-01 26-09-26 Boiler & Accessories
C1J1000 Boiler Steel Structure Install. Start 0 25-11-01 Boiler Steel Structure Install. Start
C1J1005 Boiler Steel Structure Install. 76 25-11-01 26-01-15 Boiler Steel Structure Install.
C1J1010 Boiler Drum Lifting & Postioned 3 26-01-16 26-01-18 Boiler Drum Lifting & Postioned
C1J1050 Induced Air Fan Install. 124 26-01-29 26-06-01 Induced Air Fan Install.
C1J1055 FD Fan Install. 124 26-02-15 26-06-18 FD Fan Install.
C1J1065 ESP Install. 196 25-12-16 26-06-29 ESP Install.

Actual Critical Summary DEC & DR page 6 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1J1015 Boiler Heating Surface Install. 163 26-01-19 26-06-30 Boiler Heating Surface Install.
C1J1045 Coal Feeder Install. 77 26-04-17 26-07-02 Coal Feeder Install.
C1J1020 Boiler Hydraulic Test 2 26-07-01 26-07-02 Boiler Hydraulic Test
C1J1140 Coal Mill Install. 135 26-03-18 26-07-31 Coal Mill Install.
C1J1060 Primary Air Fan Install. 94 26-05-03 26-08-04 Primary Air Fan Install.
C1J1025 Boiler Painting and Insulating 75 26-07-03 26-09-15 Boiler Painting and Insulating
C1J1035 Boiler Pneumatic Test 3 26-09-16 26-09-18 Boiler Pneumatic Test
C1J1040 Boiler Chemical Cleaning 5 26-09-22 26-09-26 Boiler Chemical Cleaning
Turbine & Accessories 259 26-02-15 26-10-31 Turbine & Accessories
C1J1125 Overhead Crane Install. 30 26-03-03 26-04-01 Overhead Crane Install.
C1J1070 Turbine Deck-Plate Install. 30 26-04-02 26-05-01 Turbine Deck-Plate Install.
C1J1090 Generator Deck-Plate Positioning 31 26-05-02 26-06-01 Generator Deck-Plate Positioning
C1J1095 Generator Stator Lifting & Positioning 3 26-06-02 26-06-04 Generator Stator Lifting & Positioning
C1J1150 lubricating Oil System install. 60 26-04-17 26-06-15 lubricating Oil System install.
C1J1100 Generator Rotor Penetrating 15 26-07-18 26-08-01 Generator Rotor Penetrating
C1J1120 FW Pump Install. 92 26-05-02 26-08-01 FW Pump Install.
C1J1110 HP Bypass System Install. 77 26-06-01 26-08-16 HP Bypass System Install.
C1J1115 LP Bypass System Install. 77 26-06-01 26-08-16 LP Bypass System Install.
C1J1105 Condensor Assembly & Install. 197 26-02-15 26-08-30 Condensor Assembly & Install.
C1J1075 Turbine Proper Install. 122 26-05-02 26-08-31 Turbine Proper Install.
C1J1080 Turbine Casing-on 0 26-09-01 Turbine Casing-on
C1J1135 Main Steam Pipe Install. 180 26-03-18 26-09-13 Main Steam Pipe Install.
C1J1130 Boiler FW Pipe Install. 180 26-03-18 26-09-13 Boiler FW Pipe Install.
C1J1085 Turbine Oil Flushing 90 26-08-03 26-10-31 Turbine Oil Flushing
Coal Handling & Fuel Oil Supply System 198 26-01-13 26-07-29 Coal Handling & Fuel Oil Supply System
C1M1020 Fuel Oil Pump House Equip. & Piping Install. 90 26-03-31 26-06-28 Fuel Oil Pump House Equip. & Piping Install.
C1M1025 Stack Reclaimer Install. 180 26-01-13 26-07-11 Stack Reclaimer Install.
C1M1005 Coal Transfer Tower Equipment Install. 92 26-04-12 26-07-12 Coal Transfer Tower Equipment Install.
C1M1010 Coal Cushing Equipment Install. 60 26-05-30 26-07-28 Coal Cushing Equipment Install.
C1M1000 Coal Conveyor Belt System Install. 61 26-05-30 26-07-29 Coal Conveyor Belt System Install.
Ash Handling System 136 26-06-05 26-10-18 Ash Handling System
C1H1000 Slag Crusher Install. 136 26-06-05 26-10-18 Slag Crusher Install.
C1H1005 Fly Ash Handling Equipment & Piping Install. 136 26-06-05 26-10-18 Fly Ash Handling Equipment & Pip
Water Supply & Treatment System 319 25-10-31 26-09-14 Water Supply & Treatment System
C1S1010 WTP Equipment Install. 77 26-01-23 26-04-09 WTP Equipment Install.
C1S1015 Service Water Pump House Equip. Install. 60 26-03-16 26-05-14 Service Water Pump House Equip. Install.
C1S1005 CW Pipe Install. 222 25-10-31 26-06-09 CW Pipe Install.

Actual Critical Summary DEC & DR page 7 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1S1020 Start-up Boiler Install. 107 26-03-16 26-06-30 Start-up Boiler Install.
C1S1000 CW Pump House Equipment Install. 91 26-04-30 26-07-29 CW Pump House Equipment Install.
C1S1030 Chlorine making system Install. 60 26-06-16 26-08-14 Chlorine making system Install.
C1S1025 Fire Fighting System Install. 121 26-05-17 26-09-14 Fire Fighting System Install.
Electrical System 200 26-01-01 26-07-19 Electrical System
C1D1015 DC System Install. & Battery Test 46 26-01-01 26-02-15 DC System Install. & Battery Test
C1D1025 UPS Install. & Adjustment 61 26-01-01 26-03-02 UPS Install. & Adjustment
C1D1040 150kV GIS Install. equipment and Cable Install. 76 26-01-01 26-03-17 150kV GIS Install. equipment and Cable Install.
C1D1045 Net Control equipment & Cable Install. 76 26-01-01 26-03-17 Net Control equipment & Cable Install.
C1D1030 Main TR Install. and Oil Polishing. 60 26-02-14 26-04-14 Main TR Install. and Oil Polishing.
C1D1035 Unit TR Install. and Oil Polishing. 60 26-02-14 26-04-14 Unit TR Install. and Oil Polishing.
C1D1055 Power back feeding 0 26-04-16 Power back feeding
C1D1050 Common Electrical system Comm. 30 26-03-18 26-04-16 Common Electrical system Comm.
C1D1000 No-Segregated Bustduct Install. 62 26-02-27 26-04-29 No-Segregated Bustduct Install.
C1D1020 Electrial Equipment & Cable Install. inside CCR & T/H 57 26-03-19 26-05-14 Electrial Equipment & Cable Install. inside CCR & T/H
C1T1165 Coal handling system electrical Instal. 60 26-04-30 26-06-28 Coal handling system electrical Instal.
C1D1005 IPBD Install. 30 26-06-05 26-07-04 IPBD Install.
C1D1010 IPBD Unit TR Branch Install. 15 26-07-05 26-07-19 IPBD Unit TR Branch Install.
Instrument & Control System 160 26-03-26 26-09-01 Instrument & Control System
C1K1020 DCS Equipment Install. 15 26-04-17 26-05-01 DCS Equipment Install.
C1K1015 WTP I&C Install. 60 26-03-26 26-05-24 WTP I&C Install.
C1K1025 Cabling & Wiring relevant to DCS Power-on 54 26-05-07 26-06-29 Cabling & Wiring relevant to DCS Power-on
C1K1000 Common Control System Install. in CCR 60 26-05-02 26-06-30 Common Control System Install. in CCR
C1K1030 DCS Power-on 2 26-07-01 26-07-02 DCS Power-on
C1K1005 Boiler Part I&C Install. 77 26-05-17 26-08-01 Boiler Part I&C Install.
C1K1035 Coal Handling System I&C Install. 62 26-06-13 26-08-13 Coal Handling System I&C Install.
C1K1010 Turbine Part I&C Install. 108 26-05-17 26-09-01 Turbine Part I&C Install.
Commissioning 220 26-05-25 26-12-30 Commissioning
System & Sub-System Commissioning 175 26-05-25 26-11-15 System & Sub-System Commi
C1C1005 WTP Commissioning 30 26-05-25 26-06-23 WTP Commissioning
C1C1014 Fuel Oil System Commissioning 15 26-07-29 26-08-12 Fuel Oil System Commissioning
C1C1015 Start-up Boiler Commissioning 15 26-08-13 26-08-27 Start-up Boiler Commissioning
C1C1010 CW System Commissioning & Flushing 20 26-08-15 26-09-03 CW System Commissioning & Flushing
C1C1030 Coal Handling System Comm. 61 26-07-30 26-09-28 Coal Handling System Comm.
C1C1020 Boiler & Auxiliary System Comm. 61 26-07-31 26-09-30 Boiler & Auxiliary System Comm.
C1C1035 Boiler Firing & Steam Blowing 15 26-10-17 26-10-31 Boiler Firing & Steam Blowing
C1C1025 Turbine & Auxiliary System Comm. 61 26-09-16 26-11-15 Turbine & Auxiliary System Com

Actual Critical Summary DEC & DR page 8 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Integral Start-up & Test Run 45 26-11-16 26-12-30 Integral Start-up & Test R
C1C1040 Steam Admission & Initia l Synchronization 5 26-11-16* 26-11-20 Steam Admission & Initia l Syn
C1C1045 Unit Test in Low Load 10 26-11-21 26-11-30 Unit Test in Low Load
C1C1060 COD of Unit 1 0 26-12-15* COD of Unit 1
C1C1050 Unit Restart & up to Full Load Comm 15 26-12-01 26-12-15 Unit Restart & up to Full Lo
C1C1070 SLO Preparation and Process of Certificate 10 26-12-06 26-12-15 SLO Preparation and Pro
C1C1065 Test After COD (such as RB, FCB, AGC, PT, etc) 15 26-12-16 26-12-30 Test After COD (such as
Unit 2 592 25-08-16 27-03-30 Unit 2
Civil Works 485 25-08-16 26-12-13 Civil Works
Main Power Block 485 25-08-16 26-12-13 Main Power Block
Boiler Area 273 25-08-16 26-05-15 Boiler Area
Boiler 138 25-08-16 25-12-31 Boiler
C2T1005 Boiler Area Piling Work 31 25-08-16 25-09-15 Boiler Area Piling Work
C2T1010 Boiler Area Excavation 46 25-09-16 25-10-31 Boiler Area Excavation
C2T1050 Boiler Foundation Delivery for Install. 0 25-12-31 Boiler Foundation Delivery for Install.
C2T1030 Boiler Fundation Construction 87 25-10-06 25-12-31 Boiler Fundation Construction
Boiler Axuliary 242 25-09-16 26-05-15 Boiler Axuliary
C2T1020 ESP Piling work 15 25-09-16 25-09-30 ESP Piling work
C2T1025 IDF Piling work 10 25-10-01 25-10-10 IDF Piling work
C2T1000 Flue Gas Duct Supports Piling work 30 25-10-11 25-11-09 Flue Gas Duct Supports Piling work
C2T1055 ESP Foundation Construction 45 26-01-01 26-02-14 ESP Foundation Construction
C2T1070 PAF & FDF & IDF Foundation 61 26-02-15 26-04-16 PAF & FDF & IDF Foundation
C2T1075 Flue Gas Duct Supports Construction 90 26-02-15 26-05-15 Flue Gas Duct Supports Construction
T/H Area 454 25-09-16 26-12-13 T/H Area
MB 454 25-09-16 26-12-13 MB
C2T1015 MB Piling Work 46 25-09-16 25-10-31 MB Piling Work
C2T1035 MB Area Excavation 46 25-11-01 25-12-16 MB Area Excavation
C2T1040 MB Foundation Construction 91 25-11-16 26-02-14 MB Foundation Construction
C2T1060 Main Building Foundation up to 0m 0 26-02-14 Main Building Foundation up to 0m
C2T1065 MB Steel Structure Erection 92 26-02-15 26-05-17 MB Steel Structure Erection
C2T1080 MB Enclosing (TG house) 31 26-05-18 26-06-17 MB Enclosing (TG house)
C2T1090 bunker bay Floor Construction 90 26-05-18 26-08-15 bunker bay Floor Construction
C2T1105 Coal Bunkers 120 26-08-16 26-12-13 Coal Bunkers
Turbine Auxiliary 198 25-12-17 26-07-02 Turbine Auxiliary
C2T1045 TG Pedestal Construction 92 25-12-17 26-03-18 TG Pedestal Construction
C2T1100 MB 0m equipment foundation Construction 45 26-05-18 26-07-01 MB 0m equipment foundation Construction
C2T1095 Lubricating Oil foundation 15 26-06-18 26-07-02 Lubricating Oil foundation

Actual Critical Summary DEC & DR page 9 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Ash Handling System 90 26-04-04 26-07-02 Ash Handling System
C2T1130 Bottom Ash Silo Foundation 45 26-04-04 26-05-18 Bottom Ash Silo Foundation
C2T1110 Fly Ash Silo foundation 45 26-05-19 26-07-02 Fly Ash Silo foundation
Electrical System 122 26-02-15 26-06-16 Electrical System
C2T1120 Unit TR Foundation 61 26-02-15 26-04-16 Unit TR Foundation
C2T1125 Main TR Foundation (Piling work) 61 26-04-17 26-06-16 Main TR Foundation (Piling work)
Installation Works 366 26-01-16 27-01-16 Installation Works
Main Power Block 366 26-01-16 27-01-16 Main Power Block
Boiler & Accessories 338 26-01-16 26-12-19 Boiler & Accessories
C2J1000 Boiler Steel Structure Install. Start 0 26-01-16 Boiler Steel Structure Install. Start
C2J1005 Boiler Steel Structure Install. 75 26-01-16 26-03-31 Boiler Steel Structure Install.
C2J1010 Boiler Drum Lifting & Postioned 3 26-04-01 26-04-03 Boiler Drum Lifting & Postioned
C2J1030 Induced Air Fan Install. 137 26-04-01 26-08-15 Induced Air Fan Install.
C2J1035 FD Fan Install. 137 26-04-17 26-08-31 FD Fan Install.
C2J1015 Boiler Heating Surface Install. 163 26-04-04 26-09-13 Boiler Heating Surface Install.
C2J1020 Boiler Hydraulic Test 2 26-09-14 26-09-15 Boiler Hydraulic Test
C2J1025 ESP Install. 196 26-03-18 26-09-29 ESP Install.
C2J1045 Coal Feeder Install. 77 26-07-17 26-10-01 Coal Feeder Install.
C2J1050 Primary Air Fan Install. 94 26-07-17 26-10-18 Primary Air Fan Install.
C2J1040 Coal Mill Install. 135 26-06-18 26-10-31 Coal Mill Install.
C2J1055 Boiler Painting and Insulating 80 26-09-16 26-12-04 Boiler Painting and Insulatin
C2J1060 Boiler Pneumatic Test 3 26-12-05 26-12-07 Boiler Pneumatic Test
C2J1065 Boiler Chemical Cleaning 7 26-12-13 26-12-19 Boiler Chemical Cleaning
Turbine & Accessories 244 26-05-18 27-01-16 Turbine & Accessories
C2J1110 Turbine Deck-Plate Install. 30 26-06-18 26-07-17 Turbine Deck-Plate Install.
C2J1120 Generator Deck-Plate Positioning 31 26-07-18 26-08-17 Generator Deck-Plate Positioning
C2J1125 Generator Stator Lifting & Positioning 3 26-08-18 26-08-20 Generator Stator Lifting & Positioning
C2J1080 lubricating Oil System install. 60 26-07-03 26-08-31 lubricating Oil System install.
C2J1085 HP Bypass System Install. 77 26-06-18 26-09-02 HP Bypass System Install.
C2J1095 LP Bypass System Install. 77 26-06-18 26-09-02 LP Bypass System Install.
C2J1105 FW Pump Install. 92 26-07-02 26-10-01 FW Pump Install.
C2J1130 Generator Rotor Penetrating 15 26-10-03 26-10-17 Generator Rotor Penetrating
C2J1115 Turbine Proper Install. 122 26-07-18 26-11-16 Turbine Proper Install.
C2J1140 Turbine Casing-on 0 26-11-17 Turbine Casing-on
C2J1070 Condensor Assembly & Install. 197 26-05-18 26-11-30 Condensor Assembly & Insta
C2J1145 Turbine Auxiliary Pipe Instal. 167 26-06-18 26-12-01 Turbine Auxiliary Pipe Instal.
C2J1090 Main Steam Pipe Install. 180 26-06-18 26-12-14 Main Steam Pipe Install.

Actual Critical Summary DEC & DR page 10 of 11


Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C2J1100 Boiler FW Pipe Install. 180 26-06-18 26-12-14 Boiler FW Pipe Install.
C2J1135 Turbine Oil Flushing 90 26-10-19 27-01-16 Turbine Oil Flushing
Ash Handling System 136 26-08-19 27-01-01 Ash Handling System
C2H1010 Slag Crusher Install. 136 26-08-19 27-01-01 Slag Crusher Install.
C2H1015 Fly Ash Handling Equipment & Piping Install. 136 26-08-19 27-01-01 Fly Ash Handling Equipm
Electrical System 155 26-05-15 26-10-16 Electrical System
C2D1005 Electrial Equipment & Cable Install. inside CCR & T/H 61 26-05-15 26-07-14 Electrial Equipment & Cable Install. inside CCR
C2D1010 IPBD Install. 30 26-08-21 26-09-19 IPBD Install.
C2D1015 IPBD Unit TR Branch Install. 15 26-09-20 26-10-04 IPBD Unit TR Branch Install.
C2D1000 Main TR Install. and Oil Polishing. 122 26-06-17 26-10-16 Main TR Install. and Oil Polishing.
Instrument & Control System 108 26-07-31 26-11-15 Instrument & Control System
C2K1000 Boiler Part I&C Install. 77 26-07-31 26-10-15 Boiler Part I&C Install.
C2K1005 Turbine Part I&C Install. 108 26-07-31 26-11-15 Turbine Part I&C Install.
Commissioning 151 26-10-31 27-03-30 Commission
System & Sub-System Commissioning 93 26-10-31 27-01-31 System & Sub-Syste
C2C1000 Boiler & Auxiliary System Comm. 61 26-10-31 26-12-31 Boiler & Auxiliary System
C2C1010 Boiler Firing & Steam Blowing 15 27-01-10 27-01-24 Boiler Firing & Steam
C2C1005 Turbine & Auxiliary System Comm. 61 26-12-02 27-01-31 Turbine & Auxiliary S
Integral Start-up & Test Run 45 27-02-14 27-03-30 Integral Star
C2C1015 Steam Admission & Initia l Synchronization 5 27-02-14 27-02-18 Steam Admission
C2C1020 Unit Test in Low Load 10 27-02-19 27-02-28 Unit Test in Low
C2C1035 COD of Unit 2 0 27-03-15* COD of Unit 2
C2C1025 Unit Restart & up to Full Load Comm 15 27-03-01 27-03-15 Unit Restart &
C2C1030 SLO Preparation and Process of Certificate 10 27-03-06 27-03-15 SLO Preparat
C2C1040 Test After COD 15 27-03-16 27-03-30 Test After CO

Actual Critical Summary DEC & DR page 11 of 11