Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Master Schedule of Tanjung Sauh 2x150MW Smart Energy911Power
24-10-01
Plant27-03-30 Master Sche
Milestone 896 24-10-01 27-03-15 Milestone
Unit 1 & BOP 806 24-10-01 26-12-15 Unit 1 & BOP
MS1005 Contract Sign 0 24-10-01 Contract Sign
MS1020 NTP 0 25-01-26 NTP
MS1010 Soil Test Completed (Owner's Scope) 0 25-02-14 Soil Test Completed (Owner's Scope)
MS1015 Basic design completed 0 25-02-28 Basic design completed
MS1006 Land filling/leveling Started (Owner's Scope) 0 25-02-28 Land filling/leveling Started (Owner's Scope)
MS1025 Temp Jetty Construction Completed (Owner's Scope) 0 25-03-15 Temp Jetty Construction Completed (Owner's Scope)
MS1035 Piling Works of Unit 1 Started 0 25-06-01 Piling Works of Unit 1 Started
MS1030 Excavation for Main Power Block area foundation Start 0 25-07-01 Excavation for Main Power Block area foundation Start
MS1040 Main Building Foundation Construction Started 0 25-09-01 Main Building Foundation Construction Started
MS1045 Boiler Steel Structure Erection Start 0 25-11-01 Boiler Steel Structure Erection Start
MS1050 Boiler Drum Lifting 0 26-01-18 Boiler Drum Lifting
MS1055 T/H Enclosed 0 26-03-17 T/H Enclosed
MS1065 Power back feeding 0 26-04-16 Power back feeding
MS1060 STG soleplate located 0 26-05-01 STG soleplate located
MS1070 Boiler Hydraulic Test 0 26-07-02 Boiler Hydraulic Test
MS1075 Turbine Casing-on 0 26-09-01 Turbine Casing-on
MS1080 Boiler Chemical Cleaning 0 26-09-26 Boiler Chemical Cleaning
MS1090 Steam Blow-out 0 26-10-31 Steam Blow-out
MS1085 Turbine oil flushing completed 0 26-10-31 Turbine oil flushing completed
MS1095 Initial Synchronization 0 26-11-20 Initial Synchronization
MS1100 COD 0 26-12-15 COD
Unit 2 577 25-08-16 27-03-15 Unit 2
MS1185 Piling Works of Unit 2 Started 0 25-08-16 Piling Works of Unit 2 Started
MS1175 Main Building Foundation Construction Started 0 25-11-16 Main Building Foundation Construction Started
MS1110 Boiler Steel Structure Erection Start 0 26-01-16 Boiler Steel Structure Erection Start
MS1115 Boiler Drum Lifting 0 26-04-03 Boiler Drum Lifting
MS1120 T/H Enclosed 0 26-06-17 T/H Enclosed
MS1125 STG soleplate located 0 26-07-17 STG soleplate located
MS1130 Boiler Hydraulic Test 0 26-09-15 Boiler Hydraulic Test
MS1135 Turbine Casing-on 0 26-11-17 Turbine Casing-on
MS1140 Boiler Chemical Cleaning 0 26-12-19 Boiler Chemical Cleaning
MS1180 Turbine oil flushing completed 0 27-01-16 Turbine oil flushing co
MS1145 Steam Blow-out 0 27-01-24 Steam Blow-out
Actual Critical Summary DEC & DR page 1 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
MS1150 Initial Synchronization 0 27-02-18 Initial Synchroniza
MS1155 COD 0 27-03-15 COD
Engineering & Design 485 24-10-01 26-01-28 Engineering & Design
E0000 Basic Design & Review 151 24-10-01 25-02-28 Basic Design & Review
E15 Piling Test Drawing 30 25-02-14 25-03-15 Piling Test Drawing
E0065 Jetty Detail Design (Owner's Scope) 61 25-03-01 25-04-30 Jetty Detail Design (Owner's Scope)
E25 Detail Piling Drawing 45 25-04-16 25-05-30 Detail Piling Drawing
E0005 Technical Specification 150 25-03-01 25-07-28 Technical Specification
E0080 Water Supply Detail Design 181 25-03-31 25-09-27 Water Supply Detail Design
E0070 Chemical Detail Design 213 25-03-31 25-10-29 Chemical Detail Design
E0040 Ash Handling System Detail Design 273 25-03-01 25-11-28 Ash Handling System Detail Design
E0030 Coal Handling System Detail Design 273 25-03-01 25-11-28 Coal Handling System Detail Design
E0010 Civil Detail Design 304 25-03-01 25-12-29 Civil Detail Design
E0020 Mechanical Detail Design 304 25-03-01 25-12-29 Mechanical Detail Design
E0050 Electrical Detail Design 334 25-03-01 26-01-28 Electrical Detail Design
E0060 I&C Detail Design 334 25-03-01 26-01-28 I&C Detail Design
Procurement (From PO to Site) 502 25-01-30 26-06-15 Procurement (From PO to Site)
Unit 1 & BOP 502 25-01-30 26-06-15 Unit 1 & BOP
MECH 488 25-01-30 26-06-02 MECH
P1M1000 Embedded Itme & Bolt 212 25-01-30 25-08-29 Embedded Itme & Bolt
P1M1005 Boiler Steel Structure (First Batch) 241 25-02-01 25-09-30 Boiler Steel Structure (First Batch)
P1M1010 Boiler Air Pre-heater 272 25-02-01 25-10-30 Boiler Air Pre-heater
P1M1015 T/G House & C/B Steel Structure (First Batch) 200 25-04-30 25-11-16 T/G House & C/B Steel Structure (First Batch)
P1M1155 MP/LP Pipings, Valves, Fittings & Supports 180 25-06-01 25-11-28 MP/LP Pipings, Valves, Fittings & Supports
P1M1020 Boiler Drum 333 25-02-02 26-01-01 Boiler Drum
P1M1025 Boiler WW, Furnace, SH, RH & etc (First Batch) 334 25-02-01 26-01-01 Boiler WW, Furnace, SH, RH & etc (First Batch)
P1M1045 Desalination & DW Equipment 251 25-05-16 26-01-22 Desalination & DW Equipment
P1M1215 Condensate Pump 180 25-07-31 26-01-27 Condensate Pump
P1M1220 Vacuum pumps 180 25-07-31 26-01-27 Vacuum pumps
P1M1055 Boiler Fans 273 25-05-01 26-01-28 Boiler Fans
P1M1030 ESP (Support) 291 25-04-30 26-02-15 ESP (Support)
P1M1080 Turbine House Crane 239 25-07-06 26-03-03 Turbine House Crane
P1M1145 Turbine & Generator Deck-Plate 395 25-02-01 26-03-03 Turbine & Generator Deck-Plate
P1M1090 Condenser (shell, support, etc) 391 25-02-05 26-03-03 Condenser (shell, support, etc)
P1M1150 HP Pipings, Valves, Fittings & Supports 289 25-06-01 26-03-17 HP Pipings, Valves, Fittings & Supports
P1M1040 Boiler burners 409 25-02-03 26-03-19 Boiler burners
P1M1195 Generator Stator 423 25-02-02 26-03-31 Generator Stator
Actual Critical Summary DEC & DR page 2 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
P1M1225 Generator Rotor 423 25-02-02 26-03-31 Generator Rotor
P1M1160 CW Pump 287 25-07-02 26-04-15 CW Pump
P1M1035 Mill 350 25-05-01 26-04-16 Mill
P1M1180 Feed Water Pumps 287 25-07-03 26-04-16 Feed Water Pumps
P1M1085 Turbine Lubricating Oil System Euipment 436 25-02-04 26-04-16 Turbine Lubricating Oil System Euipment
P1M1120 EH Oil System Euipment 229 25-08-30 26-04-16 EH Oil System Euipment
P1M1205 HP/LP Heater 273 25-07-31 26-04-30 HP/LP Heater
P1M1075 Coal Feeder 304 25-07-01 26-05-01 Coal Feeder
P1M1190 Turbine 454 25-02-02 26-05-01 Turbine
P1M1200 Ash Handling & Bottom Ash Handling Equipments 258 25-08-31 26-05-16 Ash Handling & Bottom Ash Handling Equipments
P1M1210 Deaerator 260 25-08-30 26-05-17 Deaerator
P1M1230 Turbine Other Aux. Equipment 273 25-08-31 26-05-31 Turbine Other Aux. Equipment
P1M1115 Generator Sealing Oil System Euipment 487 25-01-30 26-06-01 Generator Sealing Oil System Euipment
P1M1125 Generator Stator Cooling Water Euipment 487 25-01-31 26-06-02 Generator Stator Cooling Water Euipment
ELEC 422 25-02-03 26-03-31 ELEC
P1M1065 DC & UPS System Equipment 183 25-07-01 25-12-31 DC & UPS System Equipment
P1M1105 Electrical Cable Tray 153 25-07-31 25-12-31 Electrical Cable Tray
P1M1070 150KV GIS 213 25-06-01 25-12-31 150KV GIS
P1M1235 Network & Switchyard Equipment 183 25-07-02 25-12-31 Network & Switchyard Equipment
P1M1165 Electrical Cable (First Batch) 168 25-07-31 26-01-15 Electrical Cable (First Batch)
P1M1100 LV Electrical Power Distribution Equipment 150 25-08-30 26-01-27 LV Electrical Power Distribution Equipment
P1M1060 Main & Unit Transformers 257 25-06-01 26-02-13 Main & Unit Transformers
P1M1095 HV Electrical Power Distribution Equipment 200 25-08-30 26-03-18 HV Electrical Power Distribution Equipment
P1M1050 BTG Area Electrical Equip ment 422 25-02-03 26-03-31 BTG Area Electrical Equip ment
P1M1185 Non-Segregated Busbar & IPB etc. 181 25-10-02 26-03-31 Non-Segregated Busbar & IPB etc.
I &C 319 25-07-31 26-06-15 I&C
P1M1110 I&C Cable Tray (Incl.Auxiliaries) 150 25-08-03 25-12-31 I&C Cable Tray (Incl.Auxiliaries)
P1M1130 I&C Pipings, Valves, Fittings & Supports 120 25-09-02 25-12-31 I&C Pipings, Valves, Fittings & Supports
P1M1175 I&C Cable(All Kind of Cable) 168 25-07-31 26-01-15 I&C Cable(All Kind of Cable)
P1M1135 I&C Panel/Desk (Incl. DCS,MCC) 196 25-10-02 26-04-16 I&C Panel/Desk (Incl. DCS,MCC)
P1M1170 PI/PS, TI/TS, Transmitter, etc 196 25-11-01 26-05-16 PI/PS, TI/TS, Transmitter, etc
P1M1140 I&C Actuator 196 25-12-01 26-06-15 I&C Actuator
Construction & Commissioning 911 24-10-01 27-03-30 Construction
Prepration Work 516 24-10-01 26-02-28 Prepration Work
C1T0010 Received Down Payment 117 24-10-01 25-01-26 Received Down Payment
C1T0005 Soil Test (Owner's Scope) 137 24-10-01 25-02-14 Soil Test (Owner's Scope)
C1T0002 Land filling/leveling (Owner's Scope) 151 24-10-01 25-02-28 Land filling/leveling (Owner's Scope)
Actual Critical Summary DEC & DR page 3 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1T1085 Temporary Jetty & Road Construction (Owner's Scope) 166 24-10-01 25-03-15 Temporary Jetty & Road Construction (Owner's Scope)
C1T0015 Mobilization 166 24-10-01 25-03-15 Mobilization
C1T0025 Concrete Supply (Batching plan or other ) 31 25-02-13 25-03-15 Concrete Supply (Batching plan or other )
C1T1010 Piling Test 61 25-03-16 25-05-15 Piling Test
C1T0020 Temp Camp & Office Construction 107 25-03-16 25-06-30 Temp Camp & Office Construction
C1T1091 Coal Unload Jetty Construction 304 25-05-01 26-02-28 Coal Unload Jetty Construction
Unit 1 & BOP 670 25-03-01 26-12-30 Unit 1 & BOP
Civil Works 630 25-03-01 26-11-20 Civil Works
Main Power Block 470 25-06-01 26-09-13 Main Power Block
Boiler Area 380 25-06-01 26-06-15 Boiler Area
Boiler 137 25-06-01 25-10-15 Boiler
C1T1015 Boiler Area Piling Work 30 25-06-01 25-06-30 Boiler Area Piling Work
C1T1020 Boiler Area Excavation 46 25-07-01 25-08-15 Boiler Area Excavation
C1T1030 Boiler Foundation Delivery for Install. 0 25-10-15 Boiler Foundation Delivery for Install.
C1T1025 Boiler Fundation Construction 87 25-07-21 25-10-15 Boiler Fundation Construction
Boiler Axuliary 350 25-07-01 26-06-15 Boiler Axuliary
C1T1074 Chimney Piling work 15 25-07-01 25-07-15 Chimney Piling work
C1T1058 ESP Piling work 16 25-07-16 25-07-31 ESP Piling work
C1T1062 IDF Piling work 10 25-08-01 25-08-10 IDF Piling work
C1T1079 Air Compressor House Piling work 21 25-08-11 25-08-31 Air Compressor House Piling work
C1T1185 Flue Gas Duct Supports Piling work 30 25-09-01 25-09-30 Flue Gas Duct Supports Piling work
C1T1060 ESP Foundation Construction 61 25-10-16 25-12-15 ESP Foundation Construction
C1T1070 PAF & FDF & IDF Foundation 61 25-12-16 26-02-14 PAF & FDF & IDF Foundation
C1T1180 Start-up Boiler House 90 25-12-16 26-03-15 Start-up Boiler House
C1T1265 Flue Gas Duct Supports Construction 90 25-12-16 26-03-15 Flue Gas Duct Supports Construction
C1T1080 Air Compressor House Construction 121 25-12-16 26-04-15 Air Compressor House Construction
C1T1075 Chimney Construction 243 25-10-16 26-06-15 Chimney Construction
T/H Area 440 25-07-01 26-09-13 T/H Area
MB 440 25-07-01 26-09-13 MB
C1T1031 MB Piling Work 46 25-07-01 25-08-15 MB Piling Work
C1T1032 MB Area Excavation 46 25-08-01 25-09-15 MB Area Excavation
C1T1035 MB Foundation Construction 91 25-09-01 25-11-30 MB Foundation Construction
C1T1040 Main Building Foundation up to 0m 0 25-11-30 Main Building Foundation up to 0m
C1T1045 MB Steel Structure Erection 77 25-12-01 26-02-15 MB Steel Structure Erection
C1T1050 MB Enclosing (TG house) 30 26-02-16 26-03-17 MB Enclosing (TG house)
C1T1195 HV &LV distribution room decoration 31 26-02-16 26-03-18 HV &LV distribution room decoration
C1T1205 bunker bay Floor Construction 90 26-02-16 26-05-16 bunker bay Floor Construction
Actual Critical Summary DEC & DR page 4 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1T1255 Coal Bunkers 120 26-05-17 26-09-13 Coal Bunkers
Turbine Auxiliary 212 25-10-02 26-05-01 Turbine Auxiliary
C1T1055 TG Pedestal Construction 92 25-10-02 26-01-01 TG Pedestal Construction
C1T1240 Lubricating Oil foundation 15 26-02-16 26-03-02 Lubricating Oil foundation
C1T1260 Emergency Oil Pit 75 26-02-14 26-04-29 Emergency Oil Pit
C1T1245 MB 0m equipment foundation Construction 45 26-03-18 26-05-01 MB 0m equipment foundation Construction
Coal Handling & Fuel Oil Supply System 407 25-08-16 26-09-26 Coal Handling & Fuel Oil Supply Syste
C1T1086 Bucket wheel Stacker reclamer Foundation 120 25-08-16 25-12-13 Bucket wheel Stacker reclamer Foundation
C1T1250 Fuel Oil Tank Foundation 40 26-01-20 26-02-28 Fuel Oil Tank Foundation
C1T1105 Fuel Oil Pump House Construction 90 25-12-31 26-03-30 Fuel Oil Pump House Construction
C1T1088 Emergency Reclaim Hopper 90 26-01-03 26-04-02 Emergency Reclaim Hopper
C1T1096 Coal Control building 150 25-12-01 26-04-29 Coal Control building
C1T1097 Available Bottom Coal for Coal Yard 30 26-03-31 26-04-29 Available Bottom Coal for Coal Yard
C1T1095 Coal Transfer Tower Construction 119 26-01-15 26-05-13 Coal Transfer Tower Construction
C1T1090 Coal Crusher House Construction 150 25-12-31 26-05-29 Coal Crusher House Construction
C1T1089 Underground coal transportation corridor 150 26-01-03 26-06-01 Underground coal transportation corridor
C1T1100 Coal Conveyor Trestle Construction 121 26-02-13 26-06-13 Coal Conveyor Trestle Construction
C1T1087 Coal yard (Piling work of Dry coal shed) 210 25-12-14 26-07-11 Coal yard (Piling work of Dry coal shed)
C1T1252 Bulldozer house 120 26-05-30 26-09-26 Bulldozer house
Ash Handling System 268 26-01-19 26-10-13 Ash Handling System
H1010 Bottom Ash Silo Foundation 45 26-01-19 26-03-04 Bottom Ash Silo Foundation
H1005 Fly Ash Silo foundation 45 26-04-16 26-05-30 Fly Ash Silo foundation
H1015 CEMS room 60 26-06-16 26-08-14 CEMS room
H1000 Ash Yard 120 26-06-16 26-10-13 Ash Yard
Water Supply & Treatment System 344 25-10-01 26-09-09 Water Supply & Treatment System
Water Supply System 256 25-10-16 26-06-28 Water Supply System
C1T1109 Flocculating sedimentation pond 30 25-12-01 25-12-30 Flocculating sedimentation pond
C1T1111 Sea water Pond 30 25-12-31 26-01-29 Sea water Pond
C1T1106 CWP House lower structure (Piling work) 90 25-12-01 26-02-28 CWP House lower structure (Piling work)
C1T1115 Comprehensive water pump house (Piling work) 105 25-12-01 26-03-15 Comprehensive water pump house (Piling work)
C1T1275 Siphon Well 45 26-01-30 26-03-15 Siphon Well
C1T1108 CW Pipeline Excavation & Backfill 196 25-10-16 26-04-29 CW Pipeline Excavation & Backfill
C1T1107 CWP House Civil Structure & Enclosure 60 26-03-01 26-04-29 CWP House Civil Structure & Enclosure
C1T1112 Fresh Water Reservoir 90 26-01-30 26-04-29 Fresh Water Reservoir
C1T1113 Domestic water pond 30 26-04-30 26-05-29 Domestic water pond
C1T1285 CW Outfall (Piling work) 90 26-03-16 26-06-13 CW Outfall (Piling work)
C1T1114 Reusing water pond 30 26-05-30 26-06-28 Reusing water pond
Actual Critical Summary DEC & DR page 5 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
WaterTreatment System 114 25-10-01 26-01-22 WaterTreatment System
C1T1126 Demineralized water storage tank Foundation 30 25-11-30 25-12-29 Demineralized water storage tank Foundation
C1T1120 Seawater desalination Plant Foundation 30 25-12-01 25-12-30 Seawater desalination Plant Foundation
C1T1121 Water Treatment Building Construction (Piling work) 114 25-10-01 26-01-22 Water Treatment Building Construction (Piling work)
Waste Water Treatment 234 26-01-19 26-09-09 Waste Water Treatment
C1T1127 Acid and Alkali Wastewater Pond 60 26-01-19 26-03-19 Acid and Alkali Wastewater Pond
C1T1128 Chlorine making house 107 26-03-01 26-06-15 Chlorine making house
C1T1130 Coal contained wastewater treatment plant 60 26-07-12 26-09-09 Coal contained wastewater treatment pl
C1T1290 Sanitary sewage treatment station 90 26-06-12 26-09-09 Sanitary sewage treatment station
C1T1132 Coal particle sedimentation pond 60 26-07-12 26-09-09 Coal particle sedimentation pond
Electrical System 396 25-03-01 26-03-31 Electrical System
C1T1155 150kV GIS Foundation & Building 122 25-09-01 25-12-31 150kV GIS Foundation & Building
C1T1150 Net Control building 122 25-09-01 25-12-31 Net Control building
C1T1157 Outside Truss 17 25-12-15 25-12-31 Outside Truss
C1T1135 Main TR Foundation (Piling work) 45 25-12-31 26-02-13 Main TR Foundation (Piling work)
C1T1145 Unit TR Foundation 45 25-12-31 26-02-13 Unit TR Foundation
C1T1160 Transmission Line construrction (Owner's Scope) 396 25-03-01* 26-03-31 Transmission Line construrction (Owner's Scope)
Axuiliary Plant 278 26-02-16 26-11-20 Axuiliary Plant
C1T1330 Foam fire extinguishing room 60 26-03-01 26-04-29 Foam fire extinguishing room
C1T1320 Storage Building 120 26-02-16 26-06-15 Storage Building
C1T1065 Administration Building Construction 151 26-02-16 26-07-16 Administration Building Construction
C1T1345 Plant Road 150 26-03-01 26-07-28 Plant Road
C1T1325 Guard House 60 26-06-16 26-08-14 Guard House
C1T1322 Fence Works & Gates 90 26-05-17 26-08-14 Fence Works & Gates
C1T1346 Parking Lot 30 26-07-29 26-08-27 Parking Lot
C1T1321 Workshop 120 26-06-16 26-10-13 Workshop
C1T1140 Operation & Maintenance House 166 26-05-17 26-10-29 Operation & Maintenance House
C1T1355 Landscaping 60 26-09-22 26-11-20 Landscaping
Installation Works 366 25-10-31 26-10-31 Installation Works
Main Power Block 365 25-11-01 26-10-31 Main Power Block
Boiler & Accessories 330 25-11-01 26-09-26 Boiler & Accessories
C1J1000 Boiler Steel Structure Install. Start 0 25-11-01 Boiler Steel Structure Install. Start
C1J1005 Boiler Steel Structure Install. 76 25-11-01 26-01-15 Boiler Steel Structure Install.
C1J1010 Boiler Drum Lifting & Postioned 3 26-01-16 26-01-18 Boiler Drum Lifting & Postioned
C1J1050 Induced Air Fan Install. 124 26-01-29 26-06-01 Induced Air Fan Install.
C1J1055 FD Fan Install. 124 26-02-15 26-06-18 FD Fan Install.
C1J1065 ESP Install. 196 25-12-16 26-06-29 ESP Install.
Actual Critical Summary DEC & DR page 6 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1J1015 Boiler Heating Surface Install. 163 26-01-19 26-06-30 Boiler Heating Surface Install.
C1J1045 Coal Feeder Install. 77 26-04-17 26-07-02 Coal Feeder Install.
C1J1020 Boiler Hydraulic Test 2 26-07-01 26-07-02 Boiler Hydraulic Test
C1J1140 Coal Mill Install. 135 26-03-18 26-07-31 Coal Mill Install.
C1J1060 Primary Air Fan Install. 94 26-05-03 26-08-04 Primary Air Fan Install.
C1J1025 Boiler Painting and Insulating 75 26-07-03 26-09-15 Boiler Painting and Insulating
C1J1035 Boiler Pneumatic Test 3 26-09-16 26-09-18 Boiler Pneumatic Test
C1J1040 Boiler Chemical Cleaning 5 26-09-22 26-09-26 Boiler Chemical Cleaning
Turbine & Accessories 259 26-02-15 26-10-31 Turbine & Accessories
C1J1125 Overhead Crane Install. 30 26-03-03 26-04-01 Overhead Crane Install.
C1J1070 Turbine Deck-Plate Install. 30 26-04-02 26-05-01 Turbine Deck-Plate Install.
C1J1090 Generator Deck-Plate Positioning 31 26-05-02 26-06-01 Generator Deck-Plate Positioning
C1J1095 Generator Stator Lifting & Positioning 3 26-06-02 26-06-04 Generator Stator Lifting & Positioning
C1J1150 lubricating Oil System install. 60 26-04-17 26-06-15 lubricating Oil System install.
C1J1100 Generator Rotor Penetrating 15 26-07-18 26-08-01 Generator Rotor Penetrating
C1J1120 FW Pump Install. 92 26-05-02 26-08-01 FW Pump Install.
C1J1110 HP Bypass System Install. 77 26-06-01 26-08-16 HP Bypass System Install.
C1J1115 LP Bypass System Install. 77 26-06-01 26-08-16 LP Bypass System Install.
C1J1105 Condensor Assembly & Install. 197 26-02-15 26-08-30 Condensor Assembly & Install.
C1J1075 Turbine Proper Install. 122 26-05-02 26-08-31 Turbine Proper Install.
C1J1080 Turbine Casing-on 0 26-09-01 Turbine Casing-on
C1J1135 Main Steam Pipe Install. 180 26-03-18 26-09-13 Main Steam Pipe Install.
C1J1130 Boiler FW Pipe Install. 180 26-03-18 26-09-13 Boiler FW Pipe Install.
C1J1085 Turbine Oil Flushing 90 26-08-03 26-10-31 Turbine Oil Flushing
Coal Handling & Fuel Oil Supply System 198 26-01-13 26-07-29 Coal Handling & Fuel Oil Supply System
C1M1020 Fuel Oil Pump House Equip. & Piping Install. 90 26-03-31 26-06-28 Fuel Oil Pump House Equip. & Piping Install.
C1M1025 Stack Reclaimer Install. 180 26-01-13 26-07-11 Stack Reclaimer Install.
C1M1005 Coal Transfer Tower Equipment Install. 92 26-04-12 26-07-12 Coal Transfer Tower Equipment Install.
C1M1010 Coal Cushing Equipment Install. 60 26-05-30 26-07-28 Coal Cushing Equipment Install.
C1M1000 Coal Conveyor Belt System Install. 61 26-05-30 26-07-29 Coal Conveyor Belt System Install.
Ash Handling System 136 26-06-05 26-10-18 Ash Handling System
C1H1000 Slag Crusher Install. 136 26-06-05 26-10-18 Slag Crusher Install.
C1H1005 Fly Ash Handling Equipment & Piping Install. 136 26-06-05 26-10-18 Fly Ash Handling Equipment & Pip
Water Supply & Treatment System 319 25-10-31 26-09-14 Water Supply & Treatment System
C1S1010 WTP Equipment Install. 77 26-01-23 26-04-09 WTP Equipment Install.
C1S1015 Service Water Pump House Equip. Install. 60 26-03-16 26-05-14 Service Water Pump House Equip. Install.
C1S1005 CW Pipe Install. 222 25-10-31 26-06-09 CW Pipe Install.
Actual Critical Summary DEC & DR page 7 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C1S1020 Start-up Boiler Install. 107 26-03-16 26-06-30 Start-up Boiler Install.
C1S1000 CW Pump House Equipment Install. 91 26-04-30 26-07-29 CW Pump House Equipment Install.
C1S1030 Chlorine making system Install. 60 26-06-16 26-08-14 Chlorine making system Install.
C1S1025 Fire Fighting System Install. 121 26-05-17 26-09-14 Fire Fighting System Install.
Electrical System 200 26-01-01 26-07-19 Electrical System
C1D1015 DC System Install. & Battery Test 46 26-01-01 26-02-15 DC System Install. & Battery Test
C1D1025 UPS Install. & Adjustment 61 26-01-01 26-03-02 UPS Install. & Adjustment
C1D1040 150kV GIS Install. equipment and Cable Install. 76 26-01-01 26-03-17 150kV GIS Install. equipment and Cable Install.
C1D1045 Net Control equipment & Cable Install. 76 26-01-01 26-03-17 Net Control equipment & Cable Install.
C1D1030 Main TR Install. and Oil Polishing. 60 26-02-14 26-04-14 Main TR Install. and Oil Polishing.
C1D1035 Unit TR Install. and Oil Polishing. 60 26-02-14 26-04-14 Unit TR Install. and Oil Polishing.
C1D1055 Power back feeding 0 26-04-16 Power back feeding
C1D1050 Common Electrical system Comm. 30 26-03-18 26-04-16 Common Electrical system Comm.
C1D1000 No-Segregated Bustduct Install. 62 26-02-27 26-04-29 No-Segregated Bustduct Install.
C1D1020 Electrial Equipment & Cable Install. inside CCR & T/H 57 26-03-19 26-05-14 Electrial Equipment & Cable Install. inside CCR & T/H
C1T1165 Coal handling system electrical Instal. 60 26-04-30 26-06-28 Coal handling system electrical Instal.
C1D1005 IPBD Install. 30 26-06-05 26-07-04 IPBD Install.
C1D1010 IPBD Unit TR Branch Install. 15 26-07-05 26-07-19 IPBD Unit TR Branch Install.
Instrument & Control System 160 26-03-26 26-09-01 Instrument & Control System
C1K1020 DCS Equipment Install. 15 26-04-17 26-05-01 DCS Equipment Install.
C1K1015 WTP I&C Install. 60 26-03-26 26-05-24 WTP I&C Install.
C1K1025 Cabling & Wiring relevant to DCS Power-on 54 26-05-07 26-06-29 Cabling & Wiring relevant to DCS Power-on
C1K1000 Common Control System Install. in CCR 60 26-05-02 26-06-30 Common Control System Install. in CCR
C1K1030 DCS Power-on 2 26-07-01 26-07-02 DCS Power-on
C1K1005 Boiler Part I&C Install. 77 26-05-17 26-08-01 Boiler Part I&C Install.
C1K1035 Coal Handling System I&C Install. 62 26-06-13 26-08-13 Coal Handling System I&C Install.
C1K1010 Turbine Part I&C Install. 108 26-05-17 26-09-01 Turbine Part I&C Install.
Commissioning 220 26-05-25 26-12-30 Commissioning
System & Sub-System Commissioning 175 26-05-25 26-11-15 System & Sub-System Commi
C1C1005 WTP Commissioning 30 26-05-25 26-06-23 WTP Commissioning
C1C1014 Fuel Oil System Commissioning 15 26-07-29 26-08-12 Fuel Oil System Commissioning
C1C1015 Start-up Boiler Commissioning 15 26-08-13 26-08-27 Start-up Boiler Commissioning
C1C1010 CW System Commissioning & Flushing 20 26-08-15 26-09-03 CW System Commissioning & Flushing
C1C1030 Coal Handling System Comm. 61 26-07-30 26-09-28 Coal Handling System Comm.
C1C1020 Boiler & Auxiliary System Comm. 61 26-07-31 26-09-30 Boiler & Auxiliary System Comm.
C1C1035 Boiler Firing & Steam Blowing 15 26-10-17 26-10-31 Boiler Firing & Steam Blowing
C1C1025 Turbine & Auxiliary System Comm. 61 26-09-16 26-11-15 Turbine & Auxiliary System Com
Actual Critical Summary DEC & DR page 8 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Integral Start-up & Test Run 45 26-11-16 26-12-30 Integral Start-up & Test R
C1C1040 Steam Admission & Initia l Synchronization 5 26-11-16* 26-11-20 Steam Admission & Initia l Syn
C1C1045 Unit Test in Low Load 10 26-11-21 26-11-30 Unit Test in Low Load
C1C1060 COD of Unit 1 0 26-12-15* COD of Unit 1
C1C1050 Unit Restart & up to Full Load Comm 15 26-12-01 26-12-15 Unit Restart & up to Full Lo
C1C1070 SLO Preparation and Process of Certificate 10 26-12-06 26-12-15 SLO Preparation and Pro
C1C1065 Test After COD (such as RB, FCB, AGC, PT, etc) 15 26-12-16 26-12-30 Test After COD (such as
Unit 2 592 25-08-16 27-03-30 Unit 2
Civil Works 485 25-08-16 26-12-13 Civil Works
Main Power Block 485 25-08-16 26-12-13 Main Power Block
Boiler Area 273 25-08-16 26-05-15 Boiler Area
Boiler 138 25-08-16 25-12-31 Boiler
C2T1005 Boiler Area Piling Work 31 25-08-16 25-09-15 Boiler Area Piling Work
C2T1010 Boiler Area Excavation 46 25-09-16 25-10-31 Boiler Area Excavation
C2T1050 Boiler Foundation Delivery for Install. 0 25-12-31 Boiler Foundation Delivery for Install.
C2T1030 Boiler Fundation Construction 87 25-10-06 25-12-31 Boiler Fundation Construction
Boiler Axuliary 242 25-09-16 26-05-15 Boiler Axuliary
C2T1020 ESP Piling work 15 25-09-16 25-09-30 ESP Piling work
C2T1025 IDF Piling work 10 25-10-01 25-10-10 IDF Piling work
C2T1000 Flue Gas Duct Supports Piling work 30 25-10-11 25-11-09 Flue Gas Duct Supports Piling work
C2T1055 ESP Foundation Construction 45 26-01-01 26-02-14 ESP Foundation Construction
C2T1070 PAF & FDF & IDF Foundation 61 26-02-15 26-04-16 PAF & FDF & IDF Foundation
C2T1075 Flue Gas Duct Supports Construction 90 26-02-15 26-05-15 Flue Gas Duct Supports Construction
T/H Area 454 25-09-16 26-12-13 T/H Area
MB 454 25-09-16 26-12-13 MB
C2T1015 MB Piling Work 46 25-09-16 25-10-31 MB Piling Work
C2T1035 MB Area Excavation 46 25-11-01 25-12-16 MB Area Excavation
C2T1040 MB Foundation Construction 91 25-11-16 26-02-14 MB Foundation Construction
C2T1060 Main Building Foundation up to 0m 0 26-02-14 Main Building Foundation up to 0m
C2T1065 MB Steel Structure Erection 92 26-02-15 26-05-17 MB Steel Structure Erection
C2T1080 MB Enclosing (TG house) 31 26-05-18 26-06-17 MB Enclosing (TG house)
C2T1090 bunker bay Floor Construction 90 26-05-18 26-08-15 bunker bay Floor Construction
C2T1105 Coal Bunkers 120 26-08-16 26-12-13 Coal Bunkers
Turbine Auxiliary 198 25-12-17 26-07-02 Turbine Auxiliary
C2T1045 TG Pedestal Construction 92 25-12-17 26-03-18 TG Pedestal Construction
C2T1100 MB 0m equipment foundation Construction 45 26-05-18 26-07-01 MB 0m equipment foundation Construction
C2T1095 Lubricating Oil foundation 15 26-06-18 26-07-02 Lubricating Oil foundation
Actual Critical Summary DEC & DR page 9 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Ash Handling System 90 26-04-04 26-07-02 Ash Handling System
C2T1130 Bottom Ash Silo Foundation 45 26-04-04 26-05-18 Bottom Ash Silo Foundation
C2T1110 Fly Ash Silo foundation 45 26-05-19 26-07-02 Fly Ash Silo foundation
Electrical System 122 26-02-15 26-06-16 Electrical System
C2T1120 Unit TR Foundation 61 26-02-15 26-04-16 Unit TR Foundation
C2T1125 Main TR Foundation (Piling work) 61 26-04-17 26-06-16 Main TR Foundation (Piling work)
Installation Works 366 26-01-16 27-01-16 Installation Works
Main Power Block 366 26-01-16 27-01-16 Main Power Block
Boiler & Accessories 338 26-01-16 26-12-19 Boiler & Accessories
C2J1000 Boiler Steel Structure Install. Start 0 26-01-16 Boiler Steel Structure Install. Start
C2J1005 Boiler Steel Structure Install. 75 26-01-16 26-03-31 Boiler Steel Structure Install.
C2J1010 Boiler Drum Lifting & Postioned 3 26-04-01 26-04-03 Boiler Drum Lifting & Postioned
C2J1030 Induced Air Fan Install. 137 26-04-01 26-08-15 Induced Air Fan Install.
C2J1035 FD Fan Install. 137 26-04-17 26-08-31 FD Fan Install.
C2J1015 Boiler Heating Surface Install. 163 26-04-04 26-09-13 Boiler Heating Surface Install.
C2J1020 Boiler Hydraulic Test 2 26-09-14 26-09-15 Boiler Hydraulic Test
C2J1025 ESP Install. 196 26-03-18 26-09-29 ESP Install.
C2J1045 Coal Feeder Install. 77 26-07-17 26-10-01 Coal Feeder Install.
C2J1050 Primary Air Fan Install. 94 26-07-17 26-10-18 Primary Air Fan Install.
C2J1040 Coal Mill Install. 135 26-06-18 26-10-31 Coal Mill Install.
C2J1055 Boiler Painting and Insulating 80 26-09-16 26-12-04 Boiler Painting and Insulatin
C2J1060 Boiler Pneumatic Test 3 26-12-05 26-12-07 Boiler Pneumatic Test
C2J1065 Boiler Chemical Cleaning 7 26-12-13 26-12-19 Boiler Chemical Cleaning
Turbine & Accessories 244 26-05-18 27-01-16 Turbine & Accessories
C2J1110 Turbine Deck-Plate Install. 30 26-06-18 26-07-17 Turbine Deck-Plate Install.
C2J1120 Generator Deck-Plate Positioning 31 26-07-18 26-08-17 Generator Deck-Plate Positioning
C2J1125 Generator Stator Lifting & Positioning 3 26-08-18 26-08-20 Generator Stator Lifting & Positioning
C2J1080 lubricating Oil System install. 60 26-07-03 26-08-31 lubricating Oil System install.
C2J1085 HP Bypass System Install. 77 26-06-18 26-09-02 HP Bypass System Install.
C2J1095 LP Bypass System Install. 77 26-06-18 26-09-02 LP Bypass System Install.
C2J1105 FW Pump Install. 92 26-07-02 26-10-01 FW Pump Install.
C2J1130 Generator Rotor Penetrating 15 26-10-03 26-10-17 Generator Rotor Penetrating
C2J1115 Turbine Proper Install. 122 26-07-18 26-11-16 Turbine Proper Install.
C2J1140 Turbine Casing-on 0 26-11-17 Turbine Casing-on
C2J1070 Condensor Assembly & Install. 197 26-05-18 26-11-30 Condensor Assembly & Insta
C2J1145 Turbine Auxiliary Pipe Instal. 167 26-06-18 26-12-01 Turbine Auxiliary Pipe Instal.
C2J1090 Main Steam Pipe Install. 180 26-06-18 26-12-14 Main Steam Pipe Install.
Actual Critical Summary DEC & DR page 10 of 11
Remain Milestone
Master Schedule of Tanjung Sauh 2x150MW Smart Energy Power Plant
Activity ID Activity Name Original Start Finish 2025 2026 2027
Duration O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
C2J1100 Boiler FW Pipe Install. 180 26-06-18 26-12-14 Boiler FW Pipe Install.
C2J1135 Turbine Oil Flushing 90 26-10-19 27-01-16 Turbine Oil Flushing
Ash Handling System 136 26-08-19 27-01-01 Ash Handling System
C2H1010 Slag Crusher Install. 136 26-08-19 27-01-01 Slag Crusher Install.
C2H1015 Fly Ash Handling Equipment & Piping Install. 136 26-08-19 27-01-01 Fly Ash Handling Equipm
Electrical System 155 26-05-15 26-10-16 Electrical System
C2D1005 Electrial Equipment & Cable Install. inside CCR & T/H 61 26-05-15 26-07-14 Electrial Equipment & Cable Install. inside CCR
C2D1010 IPBD Install. 30 26-08-21 26-09-19 IPBD Install.
C2D1015 IPBD Unit TR Branch Install. 15 26-09-20 26-10-04 IPBD Unit TR Branch Install.
C2D1000 Main TR Install. and Oil Polishing. 122 26-06-17 26-10-16 Main TR Install. and Oil Polishing.
Instrument & Control System 108 26-07-31 26-11-15 Instrument & Control System
C2K1000 Boiler Part I&C Install. 77 26-07-31 26-10-15 Boiler Part I&C Install.
C2K1005 Turbine Part I&C Install. 108 26-07-31 26-11-15 Turbine Part I&C Install.
Commissioning 151 26-10-31 27-03-30 Commission
System & Sub-System Commissioning 93 26-10-31 27-01-31 System & Sub-Syste
C2C1000 Boiler & Auxiliary System Comm. 61 26-10-31 26-12-31 Boiler & Auxiliary System
C2C1010 Boiler Firing & Steam Blowing 15 27-01-10 27-01-24 Boiler Firing & Steam
C2C1005 Turbine & Auxiliary System Comm. 61 26-12-02 27-01-31 Turbine & Auxiliary S
Integral Start-up & Test Run 45 27-02-14 27-03-30 Integral Star
C2C1015 Steam Admission & Initia l Synchronization 5 27-02-14 27-02-18 Steam Admission
C2C1020 Unit Test in Low Load 10 27-02-19 27-02-28 Unit Test in Low
C2C1035 COD of Unit 2 0 27-03-15* COD of Unit 2
C2C1025 Unit Restart & up to Full Load Comm 15 27-03-01 27-03-15 Unit Restart &
C2C1030 SLO Preparation and Process of Certificate 10 27-03-06 27-03-15 SLO Preparat
C2C1040 Test After COD 15 27-03-16 27-03-30 Test After CO
Actual Critical Summary DEC & DR page 11 of 11