PRINCE2 7th Edition Foundation Exam Cram
PRINCE2 7th Edition Foundation Exam Cram
PRINCE2 ®
7 Edition
th
Foundation
Exam Cram
By Dave Litten
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Copyright
The Swirl logo™ is a trademark of AXELOS Limited, used under permission of AXELOS Limited.
All rights reserved.
PRINCE2® is a registered trademark of AXELOS Limited, used under permission of AXELOS Limited.
All rights reserved.
Based upon AXELOS® PRINCE2® materials. Material is used under licence from AXELOS Limited.
All rights reserved.
All rights reserved. No part of this book may be reproduced in any form or by any electronic or
mechanical means, including information storage and retrieval systems – except for brief
quotations in articles or reviews – without permission in writing from its publisher, David
Geoffrey Litten.
All brand names and product names used in this book are trademarks, registered trademarks,
or trade names of their respective holders.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 2
FOUNDATION EXAM CRAM PRINCE2 7th Edition
There are five characteristics of a project that distinguish it from business as usual:
temporary: projects are temporary in nature. When the desired change has been
implemented, business as usual resumes (in its new form), and the need for the
project is removed.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 3
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 4
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 5
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Benefits: who are we doing it for? The project management team must have a clear
understanding of the purpose of the project and what needs to be achieved to
justify its investment.
Costs: many factors can affect the cost/budget available or may lead to (potential)
underspend or overspend against the cost budget. The project must be affordable.
Time: when will the project start, when will the key products be delivered, and
when will the project finish?
Quality: finishing on time and within budget is not much consolation if the result of
the project is not as specified or does not work. What is delivered by the project
must be fit for purpose.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 6
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 7
FOUNDATION EXAM CRAM PRINCE2 7th Edition
PR CE E E
PRINCE2
e inte r ted ele ents
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 8
FOUNDATION EXAM CRAM PRINCE2 7th Edition
PRINCE2 processes: these seven processes in PRINCE2 provide the set of activities
required to direct, manage, and deliver a project successfully:
▪ starting up a project
▪ directing a project
▪ initiating a project
▪ controlling a stage
▪ managing product delivery
▪ managing a stage boundary
▪ closing a project.
The project context: PRINCE2 has been designed so it can work within any context
including organizational and commercial context, delivery method, sustainability
requirements, and project scale.
The principles, practices, and processes are applied by the people involved to ensure
that the method is fit for the project context.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 9
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 10
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 11
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 12
FOUNDATION EXAM CRAM PRINCE2 7th Edition
There may be users who specify the desired outputs (referred to as products in
PRINCE2), suppliers who will provide the resources and expertise to deliver the
products, and business decision-makers who will ensure that the project
investment can be justified and remains justified through the project lifecycle.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 13
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Manage by stages
A PRINCE2 project is planned, monitored, and controlled on a stage-by-stage basis.
Manage by exception
A PRINCE2 project establishes limits of delegated authority by defining tolerances
for performance against its plans.
Focus on products
A PRINCE2 project focuses on the definition and delivery of products, in particular
their user quality expectations and requirements.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 14
FOUNDATION EXAM CRAM PRINCE2 7th Edition
People in PRINCE2
People are central to the PRINCE2 method.
The purpose of a project is to deliver change, which will affect people in their
business as usual (BAU) activities, routines, and responsibilities.
How well the change is implemented, and therefore how well the project performs,
depends on the capabilities of the project team, the strength of the relationships
between them, and the people impacted by the change.
In PRINCE2, ‘people’ covers those who are working on a project and the
relationships between them, as well as those impacted by a project.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 15
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Organizational
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 16
FOUNDATION EXAM CRAM PRINCE2 7th Edition
This means that project teams require a different style of management and
leadership than that used for established business teams, as it can be more
challenging for a temporary leader or manager to exercise their authority.
ecosystem
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 17
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ Bringing teams together and building social cohesion within teams that are
co-located or have virtual or hybrid working arrangements. S
Ecosystem
Intersection/Interaction
Communication
Communication is important to avoid misconceptions and unnecessary barriers in
implementing changes.
PRINCE2 addresses communication in a communication management approach.
This defines and describes the means and frequency of communication with and
receiving feedback from across the project ecosystem, supporting alignment and
shaping of the project.
How project teams communicate will also depend on whether they are co-located,
remote, or hybrid.
Main project stakeholder
groups
Relationships
People or groups
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 18
FOUNDATION EXAM CRAM PRINCE2 7th Edition
PRINCE2 practices
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 19
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 20
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Organizing practice
The purpose of the organizing practice is to define and establish the project’s
structure of accountability and responsibilities (the ‘who’).
Business:
User:
The products of a project should provide benefits to a defined set of users who
support both defining the requirements of the product and ensuring these
requirements are met.
Users can sit within the business as end users, be impacted by the project, or have
a role in operating or maintaining the products. Users can also sit outside of the
business as end users or be impacted by the outputs of the project.
PRINCE2 defines a senior user role to represent user interests on the project.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 21
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Supplier:
Projects require people with the necessary skills and knowledge to collaborate to
deliver the products. They may come from within the organization, or external
suppliers may be used for their skills and knowledge. PRINCE2 defines a senior
supplier role to represent supplier interest on the project.
Appointed by the business as the single point of accountability for the project, the
executive is ultimately accountable for the success of the project. This
accountability cannot be delegated.
The project executive secures funding for the project and is responsible for the
business case and the continued business justification of the project.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 22
FOUNDATION EXAM CRAM PRINCE2 7th Edition
They are responsible for effectively governing the project in a way that is aligned to
the business strategy, including ensuring longer-term thinking on topics such as
environmental, social, and economic impacts.
There cannot be more than one project executive and the role cannot be combined
with the project manager.
Represents the user community and is accountable for the approach taken to
capture user requirements and for the specification of benefits aligned to the
business case. The role is responsible for:
▪ monitoring products against the requirements in line with the business case
Depending on the scale and complexity of the user community, more than one
person may represent users.
Represents the supplier community that is involved in all aspects of delivering the
project products and must ensure sufficient ongoing commitment of people and
resources from the supplier to support the project work.
The senior supplier is accountable for the quality of the products delivered by the
suppliers and for the technical integrity of the project. Depending on the scale and
complexity of the supplier community, more than one person may represent
suppliers.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 23
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Accountable to the business for the success of the project and has authority and
responsibility for the project within the project tolerances set by the business, often
captured in a project mandate.
They are responsible for creating the right environment for the project to succeed,
including:
▪ ensuring business strategy and objectives are reflected in the business case
▪ ensuring the project and its management approaches are aligned to the
business’ environmental, social, and governance (ESG) commitments
▪ governing the project and determining the rules, constraints, shared values,
and perspectives needed to guide decision-making at all levels
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 24
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Has the authority to run the project on behalf of the project board within the
agreed project tolerances and constraints. They are responsible for day-to-day
management of a project, including:
▪ managing and delegating the work to the team managers or team members
▪ setting the work package tolerances and constraints for the team managers
and project support roles to work within
▪ ensuring decisions are being made in line with the project board guidance
and tolerances
▪ monitoring and supporting the safety and well-being of team members and
the sustainability of the project approach.
Depending on scale, complexity, skill and capacity, the project manager may also
perform the team manager and project support roles or delegate these directly to
team members.
Responsible for delivering the work allocated to them within the tolerances and
constraints agreed with the project manager, through:
▪ setting the tolerances and constraints for team members to work within
▪ ensuring team decisions are in line with the project manager’s guidance and
the tolerances
▪ managing relationships both within their team and any interfaces with others
▪ monitoring and supporting the safety and wellbeing of team members and
the sustainability of the team’s approach.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 25
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Project board members are accountable for the assurance of their respective areas
of concern. The project board is responsible for establishing how project assurance
will be undertaken, ensuring clarity in the roles and responsibilities and how those
appointed to assurance roles will interact with each other.
Although the role is the responsibility of the project manager, it can be delegated to
suppliers, individuals, or groups within the business or to other team members.
Project support must be kept separate from project assurance roles to maintain the
independence of assurance.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 26
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Organizational levels
The project management structure has four levels, three of which represent the
project management team and a fourth that sits outside the project.
Directing layer
The project board has representations from the business, user, and supplier
communities and is accountable for the success of the project. It is also responsible
for the overall direction and management of the project within the constraints
established by the commissioning party.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 27
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Managing layer
The project manager is responsible for the day-to-day management of the project
within the constraints established by the project board.
Delivering layer
Team managers and members are responsible for the day-to-day management and
decision-making for their element of the project within the constraints established
by the project manager, co-creating where required with other team members
from across the project ecosystem.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 28
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Plans practice
The purpose of the plans practice: is to facilitate communication and control by
defining the products to be delivered (the ‘what’) and the means to deliver them
(the ‘who’, the ‘how’, the ‘where’, and estimates of the ‘when’ and for ‘how much’) to
satisfy the project business case (the ‘why’).
Plan: is a proposal that outlines what, where, when, how, and who of the project as
a whole (or a subset of its activities). In PRINCE2, there are the following types of
plan:
▪ project plan
▪ stage plan
▪ team plan
▪ exception plan
Project plan: a high-level plan showing the major products of the project and
when, how, and at what cost they will be delivered.
Stage plan: a detailed plan used as the basis for project management control
throughout a stage.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 29
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Team plan: a plan used as the basis for organizing and controlling the work of a
team when executing a work package. Team plans are optional in PRINCE2.
Exception plan: a plan that follows an exception report and explains how the
project will respond to the exception within the stage.
Combined with the focus on products principle, managing by stages helps the
project management team to plan and deliver what is required when it is required.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 30
FOUNDATION EXAM CRAM PRINCE2 7th Edition
The number of stages can vary, based on the nature of the products and the
necessary delivery activities.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 31
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Quality practice
The purpose of the quality practice: to document the user’s requirements of the
project products and to establish how they will be met.
User’s quality expectations: a statement about the quality expected from the
project product, captured in the project.
Acceptance criteria: a prioritized list of criteria that the project product must meet
before the user will accept it.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 32
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Quality planning: the capturing of quality specifications for the project products
and generating the associated product descriptions and quality management
approach.
Quality control: the procedures to monitor the specific products of a project and
their development or delivery activities to determine whether they comply with
relevant standards and identify ways to minimize causes of unsatisfactory
performance.
Quality assurance: a planned and systematic activity that provides confidence that
products will meet their defined quality specifications when tested under quality
control.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 33
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Risk practice
The purpose of the risk practice: to identify, assess, and control uncertainties that
would affect the project’s objectives, and, as a result, improve the ability of the
project to succeed.
A risk: an uncertain event or set of events that, should they occur, will affect the
achievement of objectives. A risk is measured by a combination of the probability of
a perceived threat or opportunity occurring and the magnitude of its impact on
objectives.
The risk management approach: describes how risk will be managed on the
project. This includes the specific procedures, techniques, standards, and
responsibilities to be applied.
The risk register: maintains a record of identified risks related to the project,
including their status and history.
Risk owner: the person who must take responsibility for responding to a risk.
Risk action owner: the person who is the nominated owner of agreed actions to
respond to a risk. This role is also known as the risk actionee.
Risk probability: the estimated chance that a risk will occur. Probability is often
estimated by considering the probability or frequency of occurrence of a risk.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 34
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Risk velocity: how quickly a risk would have an impact on objectives should it
occur.
Risk exposure: the degree to which a particular objective is ‘at risk’. Risk exposure
is a neutral concept as exposure can be positive or negative.
Risk appetite: the amount and type of risk that the business is willing to take in
pursuit of its objectives.
Risk response: each response to risks will depend on the particular situation and
type of risk. Different responses may be appropriate for threats and opportunities:
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 35
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 36
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Identify: review the plan’s context and objectives so that threats and opportunities
can be identified.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 37
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Issues practice
The purpose of the issues practice is to collect and assess issues and control
changes to the project’s baseline.
▪ An event external to the project: that may impact the project in some way.
Change budget is the money or authorized constraints set aside in a plan to cover
changes. It is allocated by those with delegated authority to deliver authorized
changes.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 38
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ change budget: the money set aside in a plan to cover changes, allocated by
those with delegated authority to deliver authorized changes.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 39
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ Change control: the process by which changes that may affect the project
baseline are identified, assessed, and then approved, rejected, or deferred.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 40
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ escalating
▪ using data.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 41
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Time: the degree to which a project is permitted to deliver later or earlier than an
agreed target completion date.
Quality: how much something can vary from agreed quality criteria.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 42
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Types of control
PRINCE2 provides two types of progress control throughout the life of a project:
Event-driven control
A control that occurs when a specific event occurs. For example:
▪ organizational events that may affect the project, such as financial year end.
Time-driven control
A management control that occurs at predefined periodic intervals. For example:
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 43
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Escalating exceptions
An exception is a situation where it can be forecast that there will be a deviation
beyond the tolerance levels agreed between the project manager and the project
board (or between the project board and business layer).
Step 1
From the work package data, the team manager forecasts that one or more of the
products in the work package will take the work package outside one of its
tolerances. At this point, an issue is raised for the attention of the project manager.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 44
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Step 2
If the issue will affect the stage (or project) tolerances to the point that they are
forecast to be breached, an exception report is created by the project manager
detailing the situation with resolution options and a recommendation.
The exception report is sent to the project board or project executive at the
directing level, along with any other relevant data to assist in their decision.
Step 3
The project board or project executive have several options that they could take.
They may:
▪ reallocate the overall project tolerances to resolve the breach of the stage
tolerance
▪ reprioritize the requirements to bring the stage back within tolerance (de-
scoping or re-scoping the product)
▪ inform the project manager that they require more time to consider their
options
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 45
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ implement the exception report and request an exception plan from the
project manager
▪ implement the exception report by escalating to the business layer for advice
and direction, if the exception will take the project outside one or more of its
project level tolerances
▪ the business layer will provide direction to the project board, which will then
direct the project manager accordingly.
Step 4
The project manager ceases the current stage and introduces a stage boundary to
create the exception plan and adjust any other related information in the project
initiation documentation.
An end stage report may also be produced where the stage has progressed to a
point where this would be useful data for the decision.
Step 5
The project board or project executive will assess the exception plan and may take
several options. They may:
▪ reject the exception plan and request amendments from the project
manager reject the exception plan and direct the project manager to
continue with the stage (this may require minor adjustments to the current
stage)
▪ approve the exception plan and return it to the project manager for further
action.
Step 6
The exception plan will be received by the project manager with a direction to
implement it as a new stage plan. In effect, the exception plan becomes the new
stage plan.
The project manager authorizes the next set of work packages for the delivering
level to recommence, taking into consideration the issue that triggered the
exception.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 46
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Starting up a project
The purpose of the process of starting up a project is to ensure that the
prerequisites for initiating a project are established by answering the question, ‘do
we have a viable and worthwhile project?’.
The decision to start the project must be explicit, as the activities within the process
of starting up a project happen before this decision.
The project brief ensures that the project has a commonly understood and well-
defined starting point.
▪ all the necessary authorities exist for initiating the project (for example, to
assign people and secure resources)
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 47
FOUNDATION EXAM CRAM PRINCE2 7th Edition
▪ individuals are appointed who will undertake the work required in the
initiation stage or take significant project management roles during the
project
▪ the work required for the initiation stage (documented in a stage plan) is
planned
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 48
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Directing a project
The purpose of the process of directing a project is to enable the project board
to be accountable for the project’s success by making key decisions and exercising
overall control while delegating day-to-day management of the project to the
project manager.
▪ plans for realizing the post-project benefits are managed and reviewed.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 49
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Initiating a project
The purpose of the process of initiating a project is to establish solid
foundations for the project, enabling the business to understand the work that
needs to be done to deliver the project product before committing to any
significant expenditure or resources.
The objectives of the process of initiating a project are to ensure that there is
common understanding of:
▪ the reasons for doing the project, the benefits expected, and the associated
risks (documented in a full business case)
▪ how and when the products will be delivered and at what cost
The full business case will be used by the project board to authorize the project
and provides the basis of the ongoing check that the project remains viable.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 50
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 51
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Controlling a stage
The purpose of the process of controlling a stage is to assign work, monitor such
work, handle issues, report progress to the project board, and take corrective
actions to ensure that the stage remains within the tolerances set by the project
board.
▪ the agreed stage products meet the agreed quality expectations and are
accepted
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 52
FOUNDATION EXAM CRAM PRINCE2 7th Edition
The objectives of the process of managing product delivery are to ensure that:
▪ team managers and their teams are clear as to what is to be produced and
what is the expected effort, cost, and timescales are
▪ the planned products are delivered to quality expectations and within the
tolerances
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 53
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Therefore, this process should be executed at, or close to, the end of each stage.
▪ assure the project board that all products in the current stage plan have
been completed and approved
▪ provide the information needed for the project board to assess the
continuing viability of the project
▪ record any information or lessons that can help later stages of this project or
other projects
For exceptions, the objectives of the process of managing a stage boundary are
similar to those listed above but include preparing an exception plan and seeking
approval to replace the project or current stage plan with the exception plan.
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 54
FOUNDATION EXAM CRAM PRINCE2 7th Edition
Closing a project
The purpose of the process of closing a project is to provide a fixed point at
which acceptance of the project product is confirmed.
It also provides a point to recognize that the objectives or the approved changes to
the objectives, as established in the project initiation documentation, have been
achieved.
Where there is a cause for a premature close, this process ensures the project is
closed in an orderly way.
▪ ensure that the business can support the products when the project is closed
▪ assess any benefits that have already been realized, and update the benefits
management approach to include any post-project benefit reviews
▪ ensure provision has been made to address all open issues and risks, with
follow-on action recommendations
▪ ensure the project is closed in an orderly way and not simply abandoned (in
the case of a premature close)
------------------------------------------------------------------------------
Projex Academy |PRINCE2 7th Edition exam cram|© david geoffrey litten Page | 55