KURIAN ESTIMATE
KURIAN ESTIMATE
Page 1
Laterite Masonry in 1:6 for super
structure wall up to 3m height
4 using good quality dressed laterite
including all material and labour
charge etc. Complete
Ground Floor
Outer wall 1 50.65 0.60 0.60 18.23
Cross wall 1 3.20 0.60 0.60 1.15
Cross wall 1 2.00 0.60 0.60 0.72
Cross wall 1 1.60 0.60 0.60 0.58
Cross wall 2 1.20 0.60 0.60 0.86
Cross wall 2 2.20 0.60 0.60 1.58
Cross wall 1 4.70 0.60 0.60 1.69
First Floor
Outer wall 1 48.50 0.60 0.60 17.46
Cross wall 2 3.20 0.60 0.60 2.30
Cross wall 2 2.00 0.60 0.60 1.44
Cross wall 1 1.60 0.60 0.60 0.58
46.60
Deductions
D 1 1.20 0.20 2.10 0.50
D1 4 0.90 0.20 2.10 1.51
W1 6 0.60 0.20 1.80 1.30
W2 4 1.50 0.20 1.60 1.92
W3 4 1.80 0.20 1.70 2.45
W4 1 2.50 0.20 1.70 0.85
W5 1 2.90 0.20 1.70 0.99
W6 1 3.00 0.20 1.70 1.02
W7 1 3.20 0.20 1.70 1.09
W8 1 3.10 0.20 1.70 1.05
KW1 1 0.70 0.20 1.10 0.15
KW2 1 1.20 0.20 1.10 0.26
V 4 0.60 0.20 0.45 0.22
Total deductions 13.31
Total less deductions 33.29
Page 2
R.C.C Work 1:2:4 using mix
20mm size broken stone for r.c.c
5 work including cost of all
material and labour charge etc.
Complete
Ground Floor
Lintel 1 62.81 0.20 0.15 1.88
Sunshade 1 20.15 0.80 0.08 1.29
Beam 2 6.20 0.20 0.30 0.74
Beam 1 4.70 0.20 0.30 0.28
Beam 1 1.40 0.20 0.30 0.08
Pillar 2 0.20 0.20 2.10 0.17
Pillar 3 0.20 0.20 2.55 0.31
Steps 20 1.00 0.25 0.18 0.90
Roof slab 1 11.40 6.75 0.10 7.70
Roof slab 1 9.50 6.50 0.10 6.18
Roof slab 1 2.20 3.30 0.10 0.73
First Floor
Lintel 1 40.50 0.20 0.15 1.22
Sunshade 1 15.85 0.80 0.08 1.01
Beam 1 6.20 0.20 0.30 0.37
Beam 1 4.70 0.20 0.30 0.28
Pillar 2 0.20 0.20 2.10 0.17
Roof slab 1 11.40 6.75 0.10 7.70
Roof slab 1 6.00 4.50 0.10 2.70
Roof slab 1 2.20 3.30 0.10 0.73
34.43
Say 35 M³ @ 8500 / M³ 297500
Supplying and fixing of fully
paneled Door, windows and
ventilators using best quality
6 Teak wood as per standard size
and shutters including cost and
conveyance of all material and
labour charge etc. Complete
D 1 1.20 2.10 2.52
D1 4 0.90 2.10 7.56
W1 6 0.60 1.80 6.48
W2 4 1.50 1.60 9.60
W3 4 1.80 1.70 12.24
W4 1 2.50 1.70 4.25
W5 1 2.90 1.70 4.93
Page 3
W6 1 3.00 1.70 5.10
W7 1 3.20 1.70 5.44
W8 1 3.10 1.70 5.27
KW1 1 0.70 1.10 0.77
KW2 1 1.20 1.10 1.32
V 4 0.60 0.45 1.08
Total 66.56
Say 67 M² @ Rs 7000/M² 469000
Ground Floor
Outer wall 1 50.65 3.00 151.95
Living 1 13.00 3.00 39.00
Bed 1 14.06 3.00 42.18
Bed 1 13.80 3.00 41.40
Toilet 2 7.50 3.00 45.00
Toilet 1 6.30 3.00 18.90
Dining 1 11.10 3.00 33.30
Kitchen & WA 1 9.80 3.00 29.40
Open space 1 12.50 3.00 37.50
First Floor
Outer wall 1 48.50 3.00 145.50
Bed 1 14.06 3.00 42.18
Bed 1 13.80 3.00 41.40
Toilet 2 7.50 3.00 45.00
Hall 1 13.50 3.00 40.50
Open space 1 13.50 3.00 40.50
793.71
Total deductions same as Item No.6 66.56
Total less deductions 727.15
Page 4
Floor finishing with good quality
Italian Marble including cost of
8
all materials and labour charge,
etc. Completes
Ground Floor
Sitout 1 3.10 1.50 0.00 4.65
Living 1 3.80 3.00 0.00 11.40
Bed 1 3.20 3.60 0.00 11.52
Bed 1 3.20 3.40 0.00 10.88
Dining 1 6.20 4.00 0.00 24.80
Kitchen & WA 1 5.80 4.50 0.00 26.10
Open space 1 6.00 4.00 0.00 24.00
First Floor
Balcony 1 2.00 3.30 0.00 6.60
Bed 1 3.20 3.60 0.00 11.52
Bed 1 3.20 3.40 0.00 10.88
Hall 1 3.50 3.80 0.00 13.30
Open space 1 4.50 5.00 0.00 22.50
178.15
Say 179 M² @ Rs 8500 / M² 1521500
Ceiling plastering in cement
mortar 1:4, 12mm thick, cost to
9 inside, including cost of all
materials and labour charge etc.
Completes
Ground Floor
Sitout 1 3.10 1.50 0.00 4.65
Living 1 3.80 3.00 0.00 11.40
Bed 1 3.20 3.60 0.00 11.52
Bed 1 3.20 3.40 0.00 10.88
Toilet 2 2.20 2.00 1.00 8.80
Toilet 1 1.80 2.00 2.00 3.60
Dining 1 6.20 4.00 3.00 24.80
Kitchen & WA 1 5.80 4.50 4.00 26.10
Open space 1 6.00 4.00 5.00 24.00
First Floor 6.00 0.00
Balcony 1 2.00 3.30 7.00 6.60
Bed 1 3.20 3.60 8.00 11.52
Bed 1 3.20 3.40 9.00 10.88
Toilet 2 2.20 2.00 10.00 8.80
Page 5
Hall 1 3.50 3.80 11.00 13.30
Open space 1 4.50 5.00 12.00 22.50
199.35
Say 200 M² @ Rs 3200 / M² 640000
Plumbing and Sanitary
10 LS 375000
arrangement
Total 6000000
Owner Engineer
Page 6