Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
MH-BL.B.B1 GROUND FLOOR
[Link] 03 Concrete Work
[Link] 03.1 CONCRETE FORMWORK
03.1.01 -379 03.1.02 -151
To elevation Column 5 To stair case and landing. 2
5 2
14-Jul-25 18-Jul-25 12-Jul-25 14-Jul-25
[Link] 03.2 STEEL CONCRETE REINFORCEMENT
03.2.01 -379 03.2.02 -151
To elevation Column 2 To stair case and landing. 1
2 1
11-Jul-25 12-Jul-25 11-Jul-25 11-Jul-25
[Link] 03.3 CAST-IN-PLACE CONCRETE
[Link] 03.3.1 C-25 concrete
[Link] -151
In stair case and landing. 1
1
15-Jul-25 15-Jul-25
[Link] 03.3.2 C-30 concrete
[Link] -379 [Link] -158
In Elevation Column 4 In Façade Shear Wall 7
4 7
19-Jul-25 23-Jul-25 16-Jul-25 23-Jul-25
[Link] 04 Masonry Work
04.02 -299
400x200x100mm thick 7
Class B, H.C.B. wall 7
24-Nov-25 01-Dec-25
04.01 -228
400x200x200mm thick 30
Class B, H.C.B. wall 30
10-Sep-25 16-Oct-25
[Link] 08 Openings
MH BL B B1 Di i i 08 1 D
Activity ID
Activity Name
Total
Original Page 1 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
MH-BL.B.B1 GROUND FLOOR
[Link] 03 Concrete Work
[Link] 03.1 CONCRETE FORMWORK
[Link] 03.2 STEEL CONCRETE REINFORCEMENT
[Link] 03.3 CAST-IN-PLACE CONCRETE
[Link] 03.3.1 C-25 concrete
[Link] 03.3.2 C-30 concrete
[Link] 04 Masonry Work
[Link] 08 Openings
MH BL B B1 Di i i 08 1 D
Activity ID
Activity Name
Total
Original Page 2 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
[Link] 08.1 Doors
08.1.02 -318 08.1.01 -320
Assembly 5 Production 12
5 12
27-Jan-26 31-Jan-26 21-Jan-26 03-Feb-26
[Link] 08.2 Windows
08.2.02 -328 08.2.01 -328
Assembly 5 Production 10
5 10
07-Feb-26 12-Feb-26 02-Feb-26 12-Feb-26
[Link] 08.3 Toilet partitions
08.3.01 -316
Assembly 5
5
24-Jan-26 29-Jan-26
[Link] 09 Finishes
[Link] 09.1 PLASTERING
09.1.01 -299
Two coats plastering to 20
internal partition wall 20
02-Dec-25 24-Dec-25
09.1.03 -298 09.1.02 -313
fine coat cement plaster 8 3mm thick final coat of 15
8 gypsum plaster 15
29-Dec-25 06-Jan-26 08-Jan-26 26-Jan-26
[Link] 09.2 TILING
09.2.02 -379 09.2.01 -299
3mm thick self leveling 20 40mm thick rough Cement 12
chemical & abrasion 20 sand screed 12
25-Feb-26 19-Mar-26 25-Dec-25 08-Jan-26
09.2.04 -347 09.2.07 -347
20mm thick high quality 18 Porcelain Skirting 5
porcelain floor tile 18 5
09-Feb-26 28-Feb-26 02-Mar-26 06-Mar-26
09 2 05 -354 09 2 06 -354
Activity ID Total
Activity Name Original Page 3 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
[Link] 08.1 Doors
[Link] 08.2 Windows
[Link] 08.3 Toilet partitions
[Link] 09 Finishes
[Link] 09.1 PLASTERING
[Link] 09.2 TILING
Activity ID Total
Activity Name Original Page 4 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
09.2.05 354 09.2.06 354
10 mm thick quality wood 15 Wooden Skirting 5
parquet flooring 15 5
20-Feb-26 09-Mar-26 10-Mar-26 14-Mar-26
09.2.11 -315 09.2.08 -315
30 mm thick marble tile 2 Marble Skirting 2
flooring 2 2
24-Jan-26 26-Jan-26 27-Jan-26 28-Jan-26
09.2.10 -294 09.2.09 -322 09.2.03 -314
Granite window sill 7 Granite tile flooring(stair 12 20mm thick non-slippery 8
7 case) 12 ceramic floor tile 8
25-Dec-25 01-Jan-26 23-Jan-26 05-Feb-26 17-Jan-26 27-Jan-26
[Link] 09.3 WALL FINISHES
09.3.02 -349 09.3.01 -323
wooden or equivalent 15 300x300x8mm thick glazed 15
acoustic panel wall cladding 15 ceramic wall 15
20-Feb-26 09-Mar-26 21-Jan-26 06-Feb-26
[Link] 09.4 CEILINGS
09.4.02 -317 09.4.01 -304
Perforated wooden acoustic 10 suspended ceiling from 7
panel Ceiling 10 plastic panels 7
20-Jan-26 30-Jan-26 06-Jan-26 14-Jan-26
[Link] 09.5 PAINTING
09.5.01 -370
three coats of approved 13
quality plastic emulsion 13
12-Mar-26 26-Mar-26
09.5.02 -315
polymer modified Quartz 10
pain 10
16-Jan-26 28-Jan-26
[Link] 10 Specialities
[Link] 10.1 12mm thick high quality Moisture-resistant compact laminated (HPL); Toilet cubicles
10.1.01 -319
Assembly 3
3
30-Jan-26 02-Feb-26
Activity ID Total
Activity Name Original Page 5 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
[Link] 09.3 WALL FINISHES
[Link] 09.4 CEILINGS
[Link] 09.5 PAINTING
[Link] 10 Specialities
[Link] 10.1 12mm thick high quality Moisture-resistant compact laminated (HPL); Toilet cubicles
Activity ID Total
Activity Name Original Page 6 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
[Link] 10.2 Pre-fabricated Movable Wall Partitions
10.2.01 -314
Assembly 3
3
24-Jan-26 27-Jan-26
[Link] 10.3 Reflective Thermoplastic marking paint
10.3.01 -379 10.3.02 -379
Road line marking 3 To basement floor columns 3
3 to the height of 1500mm 3
07-Apr-26 09-Apr-26 10-Apr-26 13-Apr-26
[Link] 10.4 SIGNAGE
10.4.1 -370
signs laminated 6
photopolymer face sheet 6
27-Mar-26 02-Apr-26
[Link] 32 Exterior Improvement
[Link] 32.1 Grean Area
32.1.01 -226 32.1.03 -219
Bulk excavation in ordinary 3 Cart away excavated 3
soil to a depth not 3 material 3
03-Oct-25 06-Oct-25 03-Oct-25 06-Oct-25
32.1.02 -226
Fill under pavement with 5
quarry waste 5
09-Oct-25 14-Oct-25
32.1.04 -343
Natural grass lawn bedded 5
on well prepared soil. 5
25-Feb-26 02-Mar-26
Activity ID Total
Activity Name Original Page 7 of 8 © Oracle Corporation
emaining
Start Finish
Construction of Multipurpose hall Classic Schedule Layout 10-Feb-25 00:38
[Link] 10.2 Pre-fabricated Movable Wall Partitions
[Link] 10.3 Reflective Thermoplastic marking paint
[Link] 10.4 SIGNAGE
[Link] 32 Exterior Improvement
[Link] 32.1 Grean Area
Activity ID Total
Activity Name Original Page 8 of 8 © Oracle Corporation
emaining
Start Finish