Method statement for Diesel Generator & Tank
Method statement for Diesel Generator & Tank
1.0 PURPOSE
The Demolition of Diesel Generator Building and Tank in front of existing MTC to
accommodate augmentation of new MTC.
2.0 SCOPE
This method statement covers all processes related to the demolition of the Diesel
generator and Tank, including:
This procedure must be read in conjunction with the relevant Inspection and Test Plan
(ITP), outlining the responsibilities and quality verification to be performed by various
parties.
3.0 REFERENCES
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.1 Safety
Ensure all personnel are trained in demolition work and aware of the risks
associated with live MEP services.
Use appropriate PPE (Personal Protective Equipment) at all times.
Barricade the demolition area and display warning signs.
Isolate live electrical systems and ensure all electrical panels and DBs are de-
energized before demolition.
Conduct a pre-demolition safety briefing for all workers.
1. Pre-Demolition Inspection:
o Inspect the building structure and identify live MEP services.
o Isolate and protect live electrical systems, plumbing lines, and the septic
tank.
o Verify that all utilities (water, electricity, gas) are disconnected or isolated.
2. Demolition Sequence:
o Start demolition from the top (roof) and proceed downward to the ground
floor.
o Use the excavator with a demolition attachment to break down the
structure.
o Remove debris using dump trucks and dispose of it at an approved landfill
site.
3. Protection of MEP Services:
o Identify and mark all live electrical cables, control panels, and DBs.
o Protect plumbing stack lines and ensure the septic tank remains
operational.
o Use portable cutting tools to carefully remove electrical cables and
plumbing lines.
4. Debris Removal:
o Sort debris into recyclable and non-recyclable materials.
o Transport debris to the designated disposal site.
5. Final Inspection:
o Inspect the site to ensure all debris has been removed.
o Verify that the septic tank and surrounding area are intact and
operational.
8.0 ATTACHMENTS
This method statement ensures that the demolition of the building is carried out safely,
efficiently, and in compliance with all relevant regulations and project requirements. All
personnel involved must adhere to the outlined procedures and safety measures to
minimize risks and ensure the successful completion of the project.
This draft follows the same structure and format as the provided method statement,
ensuring consistency and clarity. Adjustments can be made based on specific site
conditions or additional requirements.