PMP ATP Bootcamp Session 6
PMP ATP Bootcamp Session 6
BOOTCAMP
(2021 UPDATE)
Session 6
Instructor: Barb Waters, MBA, PMP
Class will begin at 11am EST
PMP® Exam Prep
This course will assist learners in preparing
for PMI’s PMP Exam (2021 Update)
If you are watching on replay, this slide deck
may have been modified to correct typos or
to make minor adjustments. If you notice a
difference it is intentional and not an
indication of exam changes.
TOPIC B:
SUPPORT TEAM
PERFORMANCE
2
Enablers
3
Deliverables and Tools
Deliverables Tools
Burnup charts
Earned Value
Throughput metrics
Cycle time
4
MONITORING AND CONTROLLING PROJECT WORK
Number of defects 3
Stakeholder issues 6
WORK PERFORMANCE INFORMATION
Number of
completed 8 7 +1 Met
activities
PV
AC
EV
400
300
$ (K)
200
100
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
19
Institute Inc., 2017.
Earned Value
EV* The measure of work performed expressed in terms of the budget authorized for
that work. EV = % work complete to date x budgeted cost
400
300
$ (K)
200
100
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
20
Institute Inc., 2017.
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
LATE
Project Schedule = 1 year Project Budget = $100,000
AC* The realized cost incurred for the work performed on an activity during a specific
time period.
400
300
$ (K)
200
100
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
26
Institute Inc., 2017.
Cost Variance, or CV, is the difference between what a project has earned
to date and what it has cost. It is the earned value minus the actual cost.
This tells you how well the project is performing in terms of costs.
Note: a negative CV shows that the project has earned less than has been spent. A positive
value means the project's cost performance is better than expected – for each dollar of value
earned, less than a dollar was spent.
Project Schedule = 1 year Project Budget = $100,000
EXAMPLE
EV = $75,000
AC = $70,000
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
30
Institute Inc., 2017.
DETERMINING PROJECT PERFORMANCE (EXAMPLE 1)
You have a budget of $20,000 to hire and train 10 new employees. Your schedule baseline is eight weeks. Four weeks
have passed and you have completely onboarded 4 employees. You have $13,500 left of your original budget.
ON TIME! Early!
LATE! LATE!
COMPLETION (EAC)
What if an EEF change affects many of our work packages?
What if we experience an unexpected risk event?
= $11,000
+
Surveys Focus Groups
$2,500 $7,500
+ +
Survey Creation Survey Analysis Meetings
$1,000 $1,500 $7,500
ESTIMATE AT
COMPLETION
Project Budget $1,000,000
Project Schedule = 1 year
Scenario: Assumes the same rate of spending will continue.
Budget = $1,000,000
Schedule = 1 year
CPI = 1.07
$1,000,000
$934,579 =
1.07
$1,000,000
$1,123,596 =
.89
Earned Value = $625,000
Actual Cost = $700,000 It’s too bad about that hurricane. If it
CPI = 0.89 wasn’t for the extra supply costs we
would be on budget. Good thing we are
back on track now.
ESTIMATE AT
COMPLETION
Project Budget $1,000,000
Project Schedule = 1 year
Scenario: Assumes we deviated from the budget, but it was an isolated
incident and now we are back to normal spending.
Budget = $1,000,000 Event: Hurricane
Schedule = 1 year Schedule = 1 year
Cost Variance = -$75,000
CPI = .89
ESTIMATE AT
COMPLETION
Project Budget $1,000,000
Project Schedule = 1 year
Scenario: Assumes poor cost performance and a firm completion deadline
Budget = $1,000,000
Schedule = 1 year
Estimate at Completion (EAC) = AC +
{ (BAC - EV)
(CPI * SPI) }
CPI = .79
SPI = .92
AC = $700,000
$1,319,152 = $700,000 +
{ ($1,000,000 - $550,000)
(0.79 * 0.92)
}
EV = $550,000
No
No
No
44
ESTIMATE TO COMPLETE (ETC)
Estimate to Complete (ETC) – The expected cost to finish all the remaining project work.
What information can we use to determine the ETC?
1. Project
360
Phase 1.1. 1.2. 1.3.
270
EAC = $934,579
AC = $700,000
47
BURN RATE
The burn rate is the rate at which you are spending money. This can
help you determine if you will stay within your budget.
BAC = $1,000,000
EAC = $934,579
A positive variance at completion means the project will come in under budget
TO COMPLETE PERFORMANCE INDEX (TCPI)
Scenario #1 Original budget can be achieved.
BAC = $1,000,000
EV = $750,000
AC = $700,000
Greater than one means you will have to spend more efficiently going forward
TO COMPLETE PERFORMANCE INDEX (TCPI)
Scenario #1 Original budget can be achieved.
BAC = $1,000,000
EV = $750,000
AC = $700,000
✓
.83 = work
($1,000,000 – $700,000)
MONEY
Greater than one means you will have to spend more efficiently going forward
TO COMPLETE PERFORMANCE INDEX (TCPI)
Scenario #2 Assumes original budget cannot be achieved.
BAC = $1,000,000
EAC = $1,075,000
EV = $700,000
AC = $775,000
(BAC – EV) “work left”
To Complete Performance Index (TCPI) =
(EAC – AC) “money left”
($1,000,000 – $700,000)
1=
($1,075,000 – $775,000)
ACTIVITY: USING
EARNED VALUE
MANAGEMENT
54
Page 214 of PMP Exam Prep Student PDF.
Activity 4-2:
Using Earned
Value
Management.
Page 215 of PMP Exam Prep Student PDF.
Activity 4-2:
Using Earned
Value
Management.
TOPIC G:
MANAGE PROJECT
ISSUES
59
Enablers
60
Deliverables and Tools
Deliverables Tools
61
Issues
Issue: A current condition or situation that may have an impact on the project
objectives. In other words, it is an action item that the project team must address.
63
Issue Log
Issue log: A document where information about issues is recorded and monitored. It
is used to track problems, inconsistencies, or conflicts that occur during the life of the
project and require investigation in order to work toward a resolution.
64
Issue Resolution
65
Guidelines to Resolving Issues
• Use your organization’s Issue Log template, or in the absence of one, create an
Issue Log.
• Train project team members to promptly report potential issues to the project
manager, who will determine if they belong in the Issue Log.
• Enter the issue into the Issue Log and assign an owner and a due date.
• Monitor progress and discuss each open issue at every project status meeting.
• Develop a response (also known as a workaround) to the issue.
• Assess the impact of the response.
• Approve the response.
• Close the issue.
66
ACTIVITY: MANAGING
PROJECT ISSUES
67
Page 191 of PMP Exam Prep Student PDF.
Activity 3-8:
Managing
Project Issues.
Guidelines to Recommend, Plan, and Facilitate Change
• Establish a single way changes are requested with a description of the proposed
change, the business value of the change, any risk and risk mitigation
recommendations, and the likely cost of the change.
• Ensure that a CCB can assess the change cost, risk, and value, other potential
impacts to the project, and make recommendations.
• The size of the change and the project’s tolerances will determine if the project
manager can approve the change or is required to escalate the change for review
and approval to the project’s governing board.
• Follow organizational change management best practices, including build a
compelling case for change, get buy-in and commitment of key stakeholders,
communicate the change vision, and enable other stakeholders to engage.
• Ensure changes are properly aligned and updates to other project artifacts, such as
the project plan, training plans, training artifacts, and software configurations or
demonstrations.
70
TOPIC H:
ENSURE KNOWLEDGE
TRANSFER FOR
PROJECT CONTINUITY
71
Enablers
72
Deliverables and Tools
Deliverables Tools
73
MANAGE PROJECT KNOWLEDGE
Purpose
• Leverage knowledge
• Improve project outcomes
• Share knowledge
Types of Knowledge
• Explicit
• easy to share
• obtained through words, pictures, or numbers
• examples: a math formula, or step-by-step instructions for doing something
• Tacit
• difficult to share
• obtained through unique experiences, expertise, thoughts, and insights
• Examples: learning to drive or learning to play an instrument
Types of Knowledge
Explicit knowledge* Knowledge that can be codified using symbols such as words,
numbers, and pictures.
• This type of knowledge can be documented and shared with others.
Tacit knowledge* Personal knowledge that can be difficult to articulate and share
such as beliefs, experience, and insights.
• This type of knowledge is essential to provide the context of the explicit knowledge.
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
75
Institute Inc., 2017.
LESSONS LEARNED
Knowledge gained during the project which is used during the current project and stored
for use in future projects.
Lessons Learned Register: used to record knowledge during the current project
Lessons Learned Repository: historical information that records knowledge from past
projects and is updated for use in future projects
77
Lessons-Learned Register
• Considerations:
• Scheduling lessons learned
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
78
Institute Inc., 2017.
Knowledge Management
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
79
Institute Inc., 2017.
Considerations of Lessons Learned
80
Lessons-Learned Register
Project A
Project B
Project A
Project C
Lessons-Learned Register Lessons-Learned Repository
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
81
Institute Inc., 2017.
Project Responsibilities Within the Team
• Leadership to communicate the organization’s vision and inspire the project team
to focus on the goals of the project.
• Facilitation to effectively guide a group to a successful solution to a problem.
• Political awareness to keep the project manager aware of the organization’s
political environment.
• Networking to facilitate relations among project stakeholders so that knowledge is
shared at all levels.
82
Knowledge Management
Level Description
• Each team member needs to know how to perform their work in accordance with each
assigned task’s scope, schedule, and cost.
• Required knowledge can be acquired by:
Individual
• Research
• Collaborating with team members
• Examining the project’s or organization’s knowledge repository
• The focus is on achieving the goals of the current project.
• Project manager solicits knowledge about other projects that can be applied to the current
project.
Project
• Project Management Office (PMO) is an excellent source of knowledge, as it exists for the
purpose of defining and maintaining standards for project management within an
organization.
• The focus is on managing programs or portfolios.
Organization • The program manager or portfolio manager seeks information from peers who manage
other programs or portfolios, in an effort to adapt this knowledge to their specific need.
83
Working Environment Expectations
• Knowledge is not constant: what we knew yesterday can change based on what we did
today.
• Continuously evaluate the project environment for new risks and follow the risk
management plan to proactively address them before they become issues that will affect
the project objectives.
• Don't hoard knowledge; follow the communications management plan and inform
stakeholders of changes affecting their work.
• Use appropriate tools to share knowledge with stakeholders:
• Face-to-face during formal meetings
• Face-to-face during informal meetings and discussions
• Telephone
• Email
• Wikis
• Intranet
• Printed documents
84
Knowledge Transfer Approach
• Meetings, seminars, and various other types of in-person and virtual events that
encourage people to interact and exchange ideas and knowledge.
• Training that involves interaction between attendees.
85
Guidelines to Maintain Team and Knowledge Transfer
86
ACTIVITY: ENSURING
KNOWLEDGE
TRANSFER FOR
PROJECT CONTINUITY
87
Page 197 of PMP Exam Prep Student PDF.
Activity 3-9:
Ensuring
Knowledge
Transfer for
Project
Continuity.
TOPIC D:
SUPPORT
ORGANIZATIONAL
CHANGE
90
Enablers
91
Deliverables and Tools
Deliverables Tools
92
Change Management Plan
93
CHANGES TO THE ORGANIZATION
“Enterprise”
• Inside the organization
• Organizational structure
• Organizational policies Human Resources Organizational
Culture or Structure
• Technology
“Environment” 100%
VERIFIED
100%
VERIFIED
103
Enablers
104
Deliverables and Tools
Deliverables Tools
105
Change Management Plan
Change Management Plan* A component of the project management plan that
establishes the change control board, documents the extent of its authority, and
describes how the change control system will be implemented.
Answers the following questions:
• Who can propose a change?
• What exactly constitutes a change?
• What is the impact of the change on the project's objectives?
• What steps are necessary to evaluate the change request before approving or
rejecting it?
• When a change request is approved, what project documents must be amended to
record the actions necessary to effect the change?
• How will these actions be monitored to confirm that they have been completed
satisfactorily?
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
106
Institute Inc., 2017.
UNCONTROLLED
CHANGES AND RISK
Change requests may affect:
• Project documents
• Deliverables
• Baselines
• Project management plan
SCOPE CREEP
• Uncontrolled increase
in scope
Project scope
• Some changes seem boundary
minor
INFORMAL
CHANGE I found a way to reduce
We need more help to
REQUESTS
complete this activity on
the number of defects.
time. Can we hire more
Check out this idea.
people?
CHANGE
REQUESTS
FROM
LEADERSHIP
Project Manager Sponsor
CHANGE REQUESTS
May originate from
New rules and regulations
Organizational changes
Customer request
Project team request
Project needs Time
Request Though initial specifications called for Contract affected Network upgrade contract.
description security codes four characters in length,
these codes must be at least seven Risks Some current data on system may be lost if user
characters in length for security reasons. profiles are changed.
Reason for Current security settings are too easily Triple constraints This will add to the duration and therefore the costs of
request cracked. impacted the project. However, this is necessary to ensure the
quality of the final product.
Risks, if not The information on our computer
implemented systems could be stolen if we do not Project manager’s Proceed
tighten security. recommendation
Specification changes
New regulations
Missed requirements
113
CHANGE CONTROL PROCESS
• Set a standard for changes
• Benchmark best practices
• Utilize subject matter experts
• Document and track changes
• Communicate with stakeholders
Change Control Systems
Change control system* A set of procedures that describes how modifications to the
project deliverables and documentation are managed and controlled.
Change Control Board (CCB)* A formally chartered group responsible for reviewing,
evaluating, approving, delaying, or rejecting changes to the project, and for recording
and communicating such decisions.
These definitions are taken from the Glossary of Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management
115
Institute Inc., 2017.
EXPERT JUDGMENT/MEETINGS
Analyzing the
Change Change Course of Updating
impact of the
identification documentation action related plans
change
117
Approved Change Requests
Approved change requests: Requests that have been received and approved in
accordance with the integrated change control plan and are ready to be scheduled for
implementation.
118
CHANGE LOG
• Once a change is approved and built, the project manager needs to plan for its
successful implementation.
• Roll out plans enable the project manager to define the knowledge transfer,
training, and readiness activities required to implement the change.
• Depending on the size, scope, and nature of the change, the plan details might
include:
• Project team and the affected customer and user stakeholders
120
Training Plan
• Changes to the project plan will likely impact the training plan.
• Changes might include:
• Scope of the training and knowledge transfer required
• Training timelines
121
Training Artifacts
Changes to the plan and deliverable set necessitates changes to the training
artifacts, including:
• Changes to training courseware
• Changes to lab configurations and exercises
• Changes to knowledge requirements and potentially to credentials if certification of
skills is expected
• Training updates for the trainers to gain the necessary knowledge transfer required
to deliver the updated training
122
Project Management Plan Updates
• Based on the scope of changes, the project management plan may need
substantial updates.
• Updates might include:
• Scope
• Timelines
• Work packages
123
PRINCIPLES FOR EFFECTIVE
Change Request
CHANGE CONTROL
Yes
Change
request Rejected
passes
filter?
Accepted
Deliverable No
affected?
Yes
Minor impact PM Moderate impact PM & Major impact PM, sponsor, &
reviews stakeholder review stakeholder review
Rebalance the project
PM Plan
Monitor and Perform • Changes to Baselines
Control Project Integrated
Work Baselines should only show changes
Change Control
from the current time
forward
• Past performance cannot be
changed
• This protects the integrity of
the baselines and the
historical data of past
Direct and
Manage Project performance
Work
We may have to use some reserve funds. What
decisions require approval? When do I have to
make a change request? When do I have to go
to my sponsor? What does the Change Control
plan indicate?
Project Manager
PROJECT
Management
Reserve
Budget
MANAGER’S
Baseline
AUTHORITY
Cost Contingency
Baseline Reserve
Work Package
Cost
Estimates
Validating Changes
Did the change do what it was supposed to?
Change Request
(iterate integrated
X
change control)
Change
Cost of Changes
• Development methodologies find
defects early
• Verify and validate often
agile
Time
Guidelines to Manage Project Changes
133
Page 187 of PMP Exam Prep Student PDF.
Activity 3-7:
Managing
Project
Changes.
TOPIC I:
PLAN AND MANAGE
PROJECT / PHASE
CLOSURE
136
Enablers
137
Deliverables and Tools
Deliverables Tools
Validate work
138
CLOSING THE PROJECT OR PHASE
Contract
@
Contracts Invoices Archived communications Schedules Past project documents
FINAL REPORT
Summary of project or phase
Project objectives
• Criteria used for evaluation
• Verification that criteria were met
• Evaluation of unmet criteria
Confirmation that deliverables achieved the business
needs or will meet needs in the future
Summary of risks encountered during the project
ETHICS IN CLOSING
• Ensure deliverables have been completed based on documented and agreed-
upon requirements
• Protect the organization from additional costs or charges after completion
• Communicate transparently with stakeholders regarding lessons learned in
final project report
• Contribute to the development and growth of other project professionals
through the capture of comprehensive lessons learned EEF and OPA updates
• Evaluate customer and end-user satisfaction and enhance future relationships
• Formally close the project or phase
Close Project or Phase
143
Close Project or Phase Criteria
• The requirements changed during execution to the point where the project is no
longer feasible.
• Adequate funding is no longer available to complete the requirements.
• Significant risks are encountered that make the successful completion of the
project impossible.
• The organization no longer needs the project deliverables.
• External factors arise that do away with the need for the project. Examples of these
factors include:
• Change in laws or regulations.
144
Transition Planning Artifacts
• Coordination and strategy about how to best deliver and transition the product and
other deliverables is needed.
• Releasing and deploying deliverables in the most suitable manner ensures end-
user awareness and increases the proper usages and adoption of outputs.
• Preparation of artifacts includes:
• Training
• Documentation
• Communication
• Support
145
Transition Readiness
• Releasing, delivering, and deploying the project’s work into an environment that is
not ready may negate its value.
• Project teams must examine the readiness of all parties and prepare them for
delivery, including:
• End users
• The business
• The physical resources
• The project team
• Most critical in situations where there is an upgrade or improvement to an existing
product or service.
• Assess the readiness of all parties, implement the transition plans accordingly, and
capture lessons learned for the next release or project.
146
Close-Out Meetings
147
Guidelines to Close a Project or Phase
149
Page 144 of PMP Exam Prep Student PDF.
Activity 2-11:
Closing a
Project or
Phase.
DAILY BOOTCAMP SURVEY
At the end of each Bootcamp session please let us know how we are doing. Your feedback helps us to offer the best possible
Bootcamp experience.