MSE 3,4,5 unit end questions
MSE 3,4,5 unit end questions
1.A supermarket sells 20,000 packets of wheat at Rs 20 per packet annually. Delivery costs are Rs 50
per order and the cost of holding a unit in stock is 15 per cent of the total cost. Determine EOQ also
find the number of orders to be placed.
2.What do you understand by acceptance sampling? Explain the concepts of single and double
sampling plans.
4.What is statistical process control? Describe the objectives and advantages of statistical process
control.
5.Compute control limits for the following four days and state whether the percentage defective falls
within the control limits for each day.
Date Number of TV components Number of
inspected defectives
Aug 3 100 15
Aug 8 160 14
Aug 13 200 19
Aug 23 170 21
6.You are given the values of sample means (average) and sample Range for 10 samples of size 5 each.
Draw the charts for the X-bar chart and R- chart.Find out is there any samples following beyond the
control limits of the above charts and write your comment.
Sample 1 2 3 4 5 6 7 8 9 10
No
Mean 43 49 40 44 45 38 51 46 42 48
Range 5 6 5 7 6 4 8 6 4 6
For n=5, Consider A2 =0.577; D3=0; D4=2.11
7.Compute control limits for the following four days and state whether the percentage defective falls
within the control limits for each day.
Date Number of TV components Number of
inspected defectives
Aug 3 100 15
Aug 8 160 14
Aug 13 200 19
Aug 23 170 21
10.The following data gives the readings for 8 samples of size 6 each in the production of a certain
product. Find the control limits using mean chart.
Sample 1 2 3 4 5 6
mean 300 342 351 319 326 333
range 25 37 20 28 30 22
11.Determine the various stock control levels with the following information:
Normal usage — 5000 units per day
Minimum usage — 2400 units per day
Maximum usage — 7700 units per day
Lead time — 10–20 days
EOQ — 8,000 units
12.The following information is about the shock absorbers used by an automobile workshop:
Annual demand: 4800 units
Unit price: Rs 300
Cost of placing an order: Rs 50
Storage cost: 3 per cent per annum
Interest rate: 15 per cent per annum
Calculate EOQ and also find the number of orders to be placed.
13.The following data represents the number of defects found on each sewing machine cabinet
inspected.
Plot a control chart with control limits. Comment on the chart
Sample No. 1 2 3 4 5 6 7 8 9 10
No.of 8 10 7 9 6 7 8 9 4 5
defects
UNIT-4
4. An engineering project consists of six activities. The three time estimates in number days
for each activity are given below.
Activity 1-2 2-3 3-5 5-6 1-4 4-5
to 4 3 2 9 5 4
tm 7 3 8 9 5 10
tp 10 3 20 9 5 16
Calculate the values of expected time(te), Standard Deviation and variance.
Duration 10 12 6 8 8 10 6
(days)
i)draw the network diagram ii) determine the critical path and project duration
7. A small engineering project consists of six activities. The three time estimates in number
days for each activity are given below.
Activity 1-2 2-3 3-5 5-6 1-4 4-5
to 2 1 0 7 3 2
tm 5 1 6 7 3 8
tp 8 1 18 7 3 14
i)Calculate the values of expected time(te), Standard Deviation and variance.
ii) Draw the network diagram and mark te on each activity
iii) Identify the critical path and mark on the network diagram
iv) Find the probability of completing project in 25 days
8. The details of activities and the project duration are given below
Activity A B C D E F G H I
Preceding -- -- A A B C, D D D, E F,G,H
activity
duration 2 3 3 5 5 9 3 3 5
i)Draw the network diagram ii) identify the critical path and mark on the network diagram
iii) calculate EST and LFT and mark them on the network diagram.
Duration 8 10 4 6 6 8 4
(days)
i)Draw the network ii) Find EST, LST, EFT and LFT
iii) Mark the critical path on network and calculate project completion time
10. A small engineering project consists of 6 activities namely ABCDE & F with duration of
4, 6, 5, 4, 3 and 3 days respectively.
Activity A B C D E F
Preceding activity - A B A D C, E
duration 4 6 5 4 3 3
i) Draw the network diagram and calculate EST, LST, EFT, LFT and floats. Mark the
critical path and find total project duration
11. Draw the network for the following project and number the activities:
event A B C D E F G H J K L M
Pre. - A B B D B E G, E D, F, H C, J K J
event