7.3 Process Flow - Pressure Vessel Fabrication

The document outlines a detailed process flow for a commercial project, starting from project award to final delivery. It includes various stages such as engineering review, material requisition, inspections, and production activities. Each step involves checks and approvals to ensure quality and compliance before moving to the next phase.

Uploaded by

mridhwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views1 page

7.3 Process Flow - Pressure Vessel Fabrication

The document outlines a detailed process flow for a commercial project, starting from project award to final delivery. It includes various stages such as engineering review, material requisition, inspections, and production activities. Each step involves checks and approvals to ensure quality and compliance before moving to the next phase.

Uploaded by

mridhwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Process

Process Flow
Entity

Commercial
Start

Project award

Engineering &
QA/QC Document and procedure
review

IFC Drawing Issuance

MTO

Raise Material Requisition /


Purchase Requisition

Check material
Yes
availaibility

Supply Chain No
Management

Raise Purchase Order Reject Material inspection

Sent back to
Material receive
supplier

Reject Inspection

Production
Accept Accept
Team - Shop
Fabrication

Mark & Cut

Reject
Inspection

Accept

Shell can rolling, nozzel pre-


fab, Slips, supports & Other
misc. items Pre-fab, & fit-up

Reject

Inspection

Accept
Production
Team - Field
Assembly & Assembly & Fit-up
Fabrication

Reject

Inspection

Accept

Welding activity

Reject
Inspection /
NDT

Reject
Accept

PWHT
NDT
(if require)

Hydrotest

Accept

Blasting painting

Reject
Final
Inspection

Accept

Packing / preservation &


Delivery

End