GO Transit Track Standards Revision 01 (May 2018)
GO Transit Track Standards Revision 01 (May 2018)
RC-0506-02TRK
May 2018
GO TRANSIT TRACK STANDARDS
RC-0506-02TRK
COPYRIGHT © 2018
Metrolinx,
an Agency of the Government of Ontario
PREFACE
This is revision 1 of the GO Transit Track Standards RC-0506-
02TRK May 2018. It is adapted from CN Engineering Track
Standards as per the agreement between Metrolinx and CN on
March 28, 2013. In accordance with the agreement, Metrolinx is
authorized to affix the name of Metrolinx/GO Transit to the CN
Standards, shall remove all references to CN and update/ modify
the standards to Metrolinx/GO Transit Standards.
Note
GENERAL REQUIREMENTS
1. The maintenance and construction standards and
practices contained herein shall apply to all track and
rights-of-way owned or operated by GO Transit (“the
Railway”), and UP Express, which are divisions of
Metrolinx, and are intended as the requirements but not
intended to replace or supersede the Transport Canada
Rules Respecting Track Safety.
2. Changes in railway standards or practices that do not
conflict with TC standards may be implemented on a
phased schedule or program, at the Corridor
Maintenance (CM), Senior Manager of Track and
Structures discretion.
3. All new or modified materials or equipment shall be
subjected to a service test, unless otherwise directed by
the CM Senior Manager of Track and Structures.
4. Under the requirements of these Standards, and where
appropriate, the CM Senior Manager of Track and
Structures may delegate their authority to a designated
individual.
5. Designated Authority, as described above, shall be
summarized at the end of this document.
6. The most current version of the GO Transit Track
Standards and all applicable bulletins shall be located on
the Metrolinx internal MYLINX intranet website at:
mylinx/sites/RailServ/en/Pages/Track-Standards.aspx,
under title “GO Transit Track Standards”.
TRACK STANDARD
RC-0506-02TRK May 2018 Revised: 2018-05-11
GO TRANSIT TRACK STANDARDS
CONTENTS
Section 1 Requirements ........................................................... 1-1
TRACK STANDARD
RC-0506-02TRK May 2018 Revised: 2018-04-10
GO TRANSIT TRACK STANDARDS
TRACK STANDARD
RC-0506-02TRK May 2018 Revised: 2018-04-10
GO TRANSIT TRACK STANDARDS
TRACK STANDARD
RC-0506-02TRK May 2018 Revised: 2018-04-10
GO TRANSIT TRACK STANDARDS
NOTES ....................................................................................... 85
TRACK STANDARD
RC-0506-02TRK May 2018 Revised: 2018-04-10
GO TRANSIT TRACK STANDARDS
Section 1 Requirements
1.1. General
1. The Standards, practices, and procedures contained
herein MUST be followed to ensure the safety of the
Railway and/or to comply with regulation, or action
MUST be taken to protect the condition, as in Section
1.2 below.
1.4. Miscellaneous
1. For all new track construction and track rehabilitation
projects, the horizontal and vertical deviation, and
geometry tolerances shall meet or exceed those found in
Appendix O – Minimum Construction Standards.
2. For all existing track, all track geometry maintenance
parameters shall meet or exceed the requirements of
Track Standard Section 16 Track Geometry.
3. Track and signals maintenance personnel require
access to the track, signals, and wayside infrastructure
with road vehicles. Emergency vehicles also require
access to the rail corridors at times. Where practical,
provision shall be made for roadway access in the layout
of track, utilities and railway related infrastructure, within
the rail corridors.
4. Tracks designated for maintenance use only (MOW)
should be considered in the design of track. A pocket
TRACK STANDARDS Page 1-2
RC-0506-02TRK May 2018 Revised: 2017-05-18
GO TRANSIT TRACK STANDARDS
Section 2 Definitions
74. Surfacing:
a. Spot Surfacing – Restoring of the track surface,
cross-level and alignment through short
stretches of track, not more than 19 ft. 6in (5.9
m) in length, when a continuous raise is not
necessary
b. Out-of-face Surfacing – The continuous raising
of track to restore track surface, cross-level, and
alignment.
75. Temperature
a. Ambient Temperature – the air temperature as
measured by a thermometer, not including
humidity or wind chill.
b. Rail Temperature – The temperature of the rail.
Rail temperature in cold weather is typically
equal to the ambient temperature. As a
guideline, in hot weather, the rail temperature is
equivalent to the ambient temperature plus 30ºF
(16ºC).
i. Note: Rail temperature must be
physically measured periodically
throughout the day with an approved
accurate thermometer, according to the
manufacturer’s specifications.
Measurements shall be taken away from
all sources of natural and artificial heat
and cold including but not limited to the
TRACK STANDARDS Page 2-10
RC-0506-02TRK May 2018 Revised: 2018-03-30
GO TRANSIT TRACK STANDARDS
3.7. Vegetation
1. Vegetation in electrified territory must be regularly
trimmed to meet electrical clearance requirements and
to maintain visibility of signage and access to rail
equipment and facilities at all times.
Section 4 Rail
4.1. Rail Identification
1. Rail branding is the raised letters and numbers along the
web of the rail. Rail stamping is on the opposite side of
the web and has indented letters and numbers.
2. Branding identifies the rail weight or section,
manufacturer, manufacturing method, year and month rolled.
Gauge in Gauge in
Degree of Curve inches mm
Maximum Maximum
Class of
Mismatch Mismatch on
Track
On top of Rail Gauge Side of Rail
1 1⁄4” (6 mm) 1⁄4” (6 mm)
2 and 3 3/16” (4.5 mm) 3/16” (4.5 mm)
4 and 5 1/8” (3 mm) 1/8” (3 mm)
Rail Size 141 lb. 136 lb. 132 lb. 115 lb. 100 lb. 100 HF 85 lb.
17 mm 14 mm 10 mm 8 mm 7 mm 6 mm 5mm
Rail
Wear 11/16” 9/16” 3/8” 5/16” 1/4” 1⁄4 3/16”
(0.6875) (0.5625) (0.375) (0.3125) (0.25) (0.25) (0.1875)
PRLT PRLTR
100 ºF 90 - 115 ºF
(37.7 ºC) (32.2 – 46.1 ºC)
PRLT 100°F
Current rail temperature Degrees 65°F (100-65°F)
NOTE: If the rail separates away from each other upon cutting more than 8.4 in.
the rail was at a stress free state at a temperature higher than the
PRLT.
Adjustment required: 8¼ in
When the ¼ inch of rail is removed and the 1” of weld material added, the rail
would be stress free when the rail temperature is at 100°F.
Example 2:
Rail anchored cold; rail ends
bypass
NOTE: If the rails bypass each other when the rail is cut or the gap is less than
8.4 in. the rail was in a stress free state at a temperature lower than 65°F
as identified in this example.
12¼ inches of rail will be cut off leaving a 9¼ inch gap. The rail is then to be
pulled back 8¼ inches and welded. (Note 1” gap is left for the weld)
This rail would now be stress free when the rail temperature is 100°F. (PRLT)
1/16
1/16
1/16
1/16
1/16
1/16
(in)
wear)
(Sum of both
Total Wear
sides plus
1/16
(in)
3/8
3/8
3/8
1/8
¼
One side Other side vertical
Flange Wear
0
(in)
3/16
1/16
1/8
¼
¼
Vertical Height
Loss of
3/16
3/16
1/16
1/16
(in)
1/8
¼
Min length
(ft.)
27
27
27
27
27
27
Rail Section Class
•
141RE
136RE
132RE
115RE
100RA
85
May 2018
132RE • 27 3/16 ¼ 0 3/8 1/16
TRACK STANDARDS
115RE • 27 1/8 3/16 0 ¼ 1/16
Revised: 2018-01-19
Page 4-49
GO TRANSIT RECOMMENDED METHODS
If... Then...
The end of the leg being
Unload the entire leg, OTHERWISE cut the
unloaded is near (i.e.
rail with an oxy-acetylene torch to the
only a short piece is left
required length.
on the train)
Travel at slow speed with rail in threader box,
Next unloading area is
to next location. Threader box must be tight
close (No greater than 1
against the threader car, and rail secured
mile away)
if possible.
Section 5 Joints
5.1. General Information
1. In conventional jointed track, each rail shall be bolted
with at least two bolts at each joint in Classes 2 through
5 tracks and with at least one bolt in Class 1 track.
2. In the case of Continuous Welded Rail (CWR) track,
each rail shall be bolted with at least two bolts at each
joint.
Rail
A B C D E Spacing
Size
2 11/16 8 3/16 13 11/16 1 3/16 2¾ 2 11/16 : 5 ½ : 5 ½
100ARA
(68.25) (8.25) (347.75) (30.25) (70) (68.25 : 140 : 140)
3½ 9½ 15 ½ 1 3/16 2 7/8 3½:6:6
115RE
(89) (241) (394) (30.25) (73) (89 : 152 : 152)
132RE 3½ 9½ 15 ½ 1 5/16 3 3/32 3½:6:6
136RE (89) (241) (394) (33.25) (78.5) (89 : 152 : 152)
1/8” (3.2mm) 35 to 59 1 to 15
1/16” (1.6mm) 60 to 85 15 to 30
0 Above 85 Above 30
3/16” (4.8mm) 26 to 45 -4 to 7
1/8” (3.2mm) 46 to 65 7 to 18
1/16” (1.6mm) 65 to 85 18 to 30
0 Above 85 Above 30
15. At the end of each shift, all of the rail laid must be bolted
and anchored per standard and each plate must be
spiked as per Track Standard Section 4.7.11.
16. Rail joints should be slotted to prevent flowed rail and
chipped joints.
17. When secured to wood ties with spikes, have spikes
driven so spike heads hold the toe of the joint bar.
18. Both sides of the joint shall be supported by the same
composition of tie (hardwood, concrete, or steel as
required) and shall be separated from a different tie
composition by at least four ties.
22. At insulated joints tie spacing shall not be less than 19½
in. (495 mm) for non-continuous insulated joints, and 18
in. (457 mm) for continuous insulated joints.
23. A series of eight 9 ft. (2.74 m) ties shall be used between
each pair of insulated joints.
a. This shall not be required within turnouts.
24. Insulated joints shall be staggered at a maximum of 4 ft.-
3 in. (1.3 m) for non-continuous insulated joints, and a
maximum 4 ft.-6 in. (1.37 m) for continuous insulated
joints. Final location of insulated joints shall be
confirmed with qualified signals personnel prior to
installation.
a. In electrified territory or in territory where stray
current is likely to be prevalent, insulated joints
shall be staggered a minimum of two (2) tie cribs
apart. A stagger of 39 in. (990 mm) is
recommended for continuously insulated joints
and 36 in. (914 mm) for non-continuously
insulated joints.
Rail Drills:
The various models of rail drills or approved equivalent are
recommended to be used on GO Transit territory may be
classified into two categories, as outlined below;
1. Gas Powered Drills (Supplied by Modern Track
Machinery)
a. Model PR8 c/w speed bit advance
i. engine speed – 3600 rpm
ii. spindle feed rate – 130 rpm
iii. feed rate:
• low: 0.002” (0.04mm)/rev
• medium: 0.0049” (0.125mm) /rev
• high: 0.0098” (0.25mm) / rev
b. Model PR3AA-2S High precision automatic
advance/stop
i. engine speed – 3600 rpm
ii. spindle feed rate – 130 rpm for standard rail and
80 rpm for hardened rail
iii. feed rate: 0.0051” (0.130mm) / rev
iv. drilling time will vary:
• Standard Carbon Rail (275-320 BHN) 60-90
seconds
• Premium rail (321-360 BHN) 90-120
seconds
v. Note: this model is equipped with a manual
“over-ride” which, when activated allows the
operator to manually feed the drill bit to the rail.
Manual operation is not recommended except in
the case of a mechanical problem.
2. Hydraulic Drills (Supplied by Stanley Tool Company)
a. Model RD11 Stanley Rail Drill – used with flat drill bit
Cutting Tips
Bit Holder
Lubrication:
When all other requirements for speed, feed and drilling times
are met, the expected life of a drill bit could be reduced by one
half, if proper lubrication is not provided. Lubrication must be
applied to the tip of the bit while drilling.
The model RD 12 hydraulic rail drill (see Figure 15) is used with
carbide tipped coring bits. The following practices shall be
observed:
1. Wipe all hose connections with a clean lint-free cloth
before making connections.
2. Connect the hoses from the hydraulic power source to
the hose couplers at the tool. It is a good practice to
connect the return hose first and disconnect it last to
minimize or avoid trapped pressure within the drill.
3. Observe flow indicators stamped on hose couplers to be
sure that oil flow is in the proper direction. The female
coupler is the inlet coupler.
4. The RD12 rail drill is equipped with a separate coolant
assembly that is used to deliver coolant to the drill bit.
Ensure this is operating properly before drilling.
5. Connect the coolant assembly to the rail drill using the
supplied quick- disconnect coupler.
6. Make sure the carbide inserts on the drill bit have good
cutting edges. If the surfaces are worn or chipped,
unscrew the retaining screw and rotate the insert to a
good cutting surface.
7. Install the drill bit into the piston assembly then turn
clockwise.
8. RD12 Drills must be used with rail templates and hole
guides.
9. The drilling machine must be properly aligned with the
proper rail guide. Never use joint bars as a guide.
10. Ensure drill is level and very tight
11. When clamping the drill to the rail, double check to
ensure clamping pressure. If loose, the drill will skid
down the rail and bits will be destroyed.
12. Drilling speed shall be set at the requirements set out by
the supplier. The spindle feed rate for the RD12 is 900
rpm @ 10 GPM.
13. Drilling speed and feed rates are very important. Drilling
speeds out of adjustment will affect the feed rate and
decrease the life of the carbide bit, increasing drilling
problems. Ensure drills are checked regularly for
recommended rpm’s, oil flow and pressures.
14. Feed rates are pre-set by the drilling speed. If drilling
speed is correct the feed rate will be correct as well.
15. Drilling must be closely timed using a stop watch or
other reliable method.
16. Watch the feed screw while the machine is drilling. If it
stops turning that means the drill bit is not cutting and
the machine should be stopped.
17. Drilling a hole with the RD 12 drills with carbide tipped
coring bits should take 40-60 seconds. Drilling times
longer than 60 seconds are generally a result of a dull or
chipped carbide bits and the bits should then be rotated.
18. Pay close attention to the drilling times previously
mentioned. The extra friction and heat produced by
exceeding the recommended drilling times can destroy
the cutting edge of the bit and result in poor surface
finishes and poor durability of the hole.
19. The tool bit holder must be inserted into the deepest
position of the chuck, properly seated and secured.
20. Do not run out of coolant. If this occurs, the drill bits will
only last approximately 10 seconds, the cutters will
break and the tool bit holder will be ruined and difficult to
remove.
21. Check cutters every 3 or 4 holes for condition. Cutters
should get approximately 30 holes before requiring
rotation.
22. Remove drill bit while in transit to avoid damage to the
cutters.
23. Remove tool holder out of spindle and place a rag in the
spindle for transit.
24. Use the correct template for the size of rail you are
drilling.
25. A qualified mechanic must check the condition of your
drilling machine at least once per year. Where a large
TRACK STANDARDS Page 5-14
RC-0506-02TRK May 2018 Revised: 2018-03-23
GO TRANSIT RECOMMENDED METHODS
Coolant Can
Handle
Coolant
Connection Piston Machine Assembly
Safety Precautions:
16. RD12 Rail drills and bits must have good lubrication, dry
drilling is not permitted.
17. Always ensure manufacturer’s recommendations are
followed.
18. Ensure any burrs, fins and sharp edges are removed
after each drilling operation using an approved tool.
Quality Assurance:
If for any reason it is felt that a quality issue exists with new drill
bits ensure the following:
1. Drill (machine) is functioning properly.
2. Proper procedures have been followed.
3. Good lubrication has been provided.
4. Drill bit has not been damaged through rough handling.
5. Ensure hydraulic pump drive belt is properly adjusted.
If the above has been followed and problems still exist contact
your immediate supervisor.
10. The distance from the end of rail to the nearest edge of
any drilled hole in the rail shall not be less than 4 in. (102
mm).
11. The Month, Year, Welder ID, and weld number of each
weld shall be identified with a tag or written with a paint
marker on the gauge side of the web within 3 ft. (914
mm) of the weld.
12. For the welding of insulated joints, standard joint bars
shall be applied on only one joint at a time. (Note that
when the insulated joint is on the closure rail, the
installation of standard joint bars may short the track
circuit).
13. Rail pullers MUST be used on all closure welds if the rail
temperature is at or below the PRLT.
a. Rail pullers must not be removed until the weld
has cooled below 700°F (372°C).
14. NO welding of switch points or stock rails on Class 3
track and above with the following exception:
a. In cases of emergency: Welding will be allowed,
following proper welding procedures and limiting
the speed over the weld repair to Class 2 track
until component is replaced.
i. Switch point welding must be conducted
by a qualified welding foreman as
determined by the CM Senior Manager
of Track and Structures.
ii. In NO case shall switch points be
welded if the defective area requires a
repair to exceed 12 in. (305 mm).
iii. Where welding is necessary and the
weld repair is equal to or greater than 4
in. (102 mm) in length, the total number
of times the switch point can be welded
is once.
iv. Where welding is necessary and the
weld repair is less than 4 in. (102 mm),
there is no restriction on the number of
times a point can be welded.
Tolerance
Measurement Dimension Thermite FBW
(in.) (in.)
Crown: peak of rail at the 0.030 0.060
A
weld (0.76 mm) (1.52 mm)
Vertical Offset: Addition of
0.060
crown and vertical height A+C 0
(1.52 mm)
difference
Dip Camber 0 0
Horizontal Offset: head 0.015 0.040
B
difference on side of rail (0.38 mm) (1.01 mm)
0.030 0.030
Indent –Kink to field side D
(0.76 mm) (0.76 mm)
Indent – Crown inward 0.030 0.060
D
(peak) toward track center (0.76 mm) (1.52 mm)
20. All track work nearby shall be stopped during the drop
and for the first 5 minutes following.
a. If the weld is near a crossing, road traffic should
be stopped for the same timeline as above.
21. Only trained, qualified, and certified personnel will be
allowed to weld.
22. Temporary bonds or rail bypass cables shall be applied
around a cut within a crossing circuit, as per Track
Standards section 22.3, to prevent the requirement for
deactivation and/or nuisance ringing.
Section 9 Ties
9.1. Timber Tie Installation and Maintenance
1. Timber ties shall be made from hardwood and:
a. No. 1 Grade, 7 in x 9 in x 8 ft. 6 in (178 mm x
229 mm x 2591 mm) treated hardwood with
100% end plating on all main lines spaced at 20
3/8 in (517 mm) on center
b. No. 2 Grade, 6 in x 8 in x 8 ft. 6 in (152 mm x
203 mm x 2591 mm) treated hardwood with
100% end plating for spurs, industry and yard
tracks at a minimum and spaced at 21 ¼ in.
(540 mm) on center.
c. Installed perpendicular (square) with the rail and
centered with the track, with the end of the tie
approximately 18 ½ in (470 mm) from the field
edge of the rail base.
2. Crossing ties in CWR territory replaced as part of
crossing rehabilitation may all be changed in a single
pass provided that the:
a. Crossing surface is replaced immediately
following tie renewal;
b. Crossing approaches are restored and are of
sound condition;
c. The appropriate speed restriction is applied for
out-of-face surfacing;
d. Crossing ties should extend for 5 ties beyond
the end of the crossing surface;
3. Crossing ties shall be composed of 9 ft. (2.7 m) long
hardwood ties 100 % end plated unless otherwise
approved by the CM Senior Manager of Track and
Structures and shall be spaced at 18” (457 mm)
throughout the crossing.
# of Consecutive Ties
Tangent track up to
Greater than 2º
2º curves
With a Junior or
5 4
Production Tamper
With Hand tamping
3 2
or Hydraulic Tools
* Note that if more than 4 consecutive ties are renewed, the track will
also require gauging.
12. For new construction of jointed rail track, rail anchors will
be installed in a box pattern on every other tie.
13. Turnouts should be fully anchored to the extent possible
in both jointed and CWR track.
14. In all CWR track, rail anchors will be installed in a box
pattern on every other tie except:
a. At permanent joints within CWR (joints that will
not be welded), then every tie will be box
anchored for a minimum distance of 200 ft. (61
m) each direction from the joint.
b. When jointed rail abuts CWR, a minimum of 200
ft. (61 m) of rail on either side immediately
adjacent to the joint will have every tie boxed
anchored.
c. At turnouts, non-glued insulated joints, diamond
crossing frogs, and/or a lift rail system, every tie
will be box anchored for a minimum distance of
200 ft. (61 m) each way from the turnout or joint.
d. At location of an open-deck bridge, every tie will
be box anchored 200 ft. (61 m) of rail in each
direction from the abutments
e. At locations where steel or concrete ties adjoin
hardwood ties, every tie will be box anchored
200ft. (61 m) of rail in the direction of the
hardwood ties.
f. At road crossings every tie will be box anchored
for a minimum distance of 200 ft. (61 m) each
direction unless the track through the crossing is
fully anchored.
15. When CWR is installed on a bridge with an open deck
span, the requirements outlined in Table 21 will be used,
where practical.
a. The CM Manager of Bridges & Structures to
identify fixed ends of spans prior to installing
CWR.
b. Prior to anchoring CWR on open deck steel
TPG, TT, and DT spans, the Manager of Bridges
TRACK STANDARDS Page 10-4
RC-0506-02TRK May 2018 Revised: 2017-03-27
GO TRANSIT TRACK STANDARDS
Length of
Continuous Open Individual Rail Anchor Sliding Joint
Deck Portion Span Length Requirements Requirements
(ft.) (ft.)
100 ft.
(30.5 m) or All Spans No anchors None required
Less
Box anchor
None required
every second tie*
100 ft.
(30.5 m) or Or
Less
Sliding joint(s)
No anchors
required
Greater than
100 ft. Box anchor
(30.5 m) every second tie
None required
for 100’ from fixed
Greater than end of span*
100 ft.
(30.5 m) Or
Sliding joint(s)
No anchors
required
* Box anchors are to be applied only to ties that are hook bolted to the
span (generally every second tie). Box anchor spacing may be
extended to every third tie if required to match the bolt spacing. If rail
clips are used, every non-hook bolted tie should have a rail clip
without longitudinal restrain.
10.3. Derails
1. Derails must be installed:
a. Where there is any possibility of equipment that
has been left standing on tracks other than main
tracks or designated sidings, may be moved by
39’-0”
12 m EC
Return Curve
39’-0”
12 m
Spike Pattern D
BC
Spike Pattern D
Point of Switch
39’-0”
12 m
Section 11 Ballast
11.1. Ballast Conditions
1. Track must be supported by material which will promote
drainage of the track structure, and restrain the track
laterally and vertically under dynamic loads imposed by
railroad equipment and thermal stress exerted by the
rails.
2. Ballast must conform to the current version of the GO
Transit Crushed Rock Track Ballast Specification.
11.2. Ballasting
1. Ballast cross sections for new construction shall conform
to Standard Plan GTS-2205. For ballast on rail bridges
or structures refer to Metrolinx General Guidelines for
Design of Railway Bridges and Structures.
2. For all new construction, place and proof-roll a minimum
of 6 inch (152 mm) of pre-ballast.
3. For the unloading of track ballast using rail equipment or
hi-rail trucks, Recommended Method 3706-2: Ballast
Unloading shall be followed.
4. Ballast cross section shall have:
a. In wood tie territory, cribs filled to a minimum of
1 in. (25 mm) below the top of tie.
b. In concrete tie territory, cribs filled to a minimum
of 1 in. (25 mm) below the top of tie ends.
i. Ballast shall be up to 1 in. (25mm)
above the centre of the concrete tie.
c. No ballast left on top of track or turnout ties,
fasteners and tie plates, except as noted in
Track Standards section 11.2.4.b.i.
d. Shoulder ballast for jointed rail track to be
maintained to a minimum of 6 in. (152 mm) out
from the end of the tie before sloping at 2:1.
TRACK STANDARDS Page 11-1
RC-0506-02TRK May 2018 Revised: 2018-01-12
GO TRANSIT TRACK STANDARDS
11.3. Clearances
1. For any work which will reduce the allowable clearances,
such as ballast stockpiling, permission must be obtained
from the CM Manager of Track
2. Any lifts or realignment that may affect clearances to
adjacent or overhead structures or OCS wiring must
receive prior approval from the CM Senior Manager of
Track and Structures, and when warranted, operational
bulletins issued restricting train movements.
3. Prior to releasing the track for railway movements the
OCS clearances shall be measured and confirmed with
the CM Senior Manager of Track and Structures.
a. In some instances, OCS adjustment and
realignment may be required prior to releasing
track.
11.4. Bridges
1. If bridges are within the section of track planned for re-
ballasting, plans must be made to undercut each bridge
approach for a sufficient distance to permit a safe and
smooth runoff.
2. Ballast on train crew walkways is to be removed to avoid
a tripping hazard and to protect the safe passage of the
public and traffic under the bridge.
3. Provide from the end of the train crew walkway a well
graded transition zone to the ballasted section
4. On ballast deck bridges, provide temporary barriers to
protect the public and traffic under the bridge from falling
ballast, during ballasting operations.
5. When ballasting adjacent to open deck bridges, care
shall be taken to prevent ballast from falling on or
collecting around the bridge seats.
11.6. Undercutting
1. Take all necessary precautions to avoid track buckling.
Pay close attention to the temperature when planning to
use under-track plows, sleds, and other specialized
undercutting equipment. Fill cribs and restore shoulders
with new ballast as soon as possible, but must be
completed before train operation.
2. Prior to conducting an undercutting program a tie
condition survey shall be completed and all defective ties
shall be replaced.
3. The transitions or runoff off gradients must be made on
tangent track and must be fully tamped and level to
provide a smooth transition from newly ballasted track to
old ballast. In no case can the rate of runoff be more
than described in Track Standard Section 16.2.8.
4. Following an undercutting program, the track disturbed
shall be destressed including 200 ft. (61 m) in either
direction away from the disturbed section.
Level Action
Pre-project planning (weeks to months prior to job)
• emergencies (safety)
1 • work environment
• ballast requirements
• project impediments
• etc.
Pre-job planning (done days ahead of the job)
• emergencies (safety)
2 • work environment
• ballast requirements
• production impediments
• etc.
Pre-block planning (done hours before the job)
Step Action
Ensure unloading employees are provided with proper
1
breathing apparatus
Provide train crew with list of unloading sites (should be pre-
2
marked in the field)
Ensure that there is enough ballast on hand to complete the
proposed work.
3
If enough ballast is unavailable, prioritize where unloading will
be done.
Job briefing by the unloading foreman, including:
• locations and how much ballast will be unloaded at
each
• obstructions
• direction of unloading
• whether you will be unloading centres, shoulders,
4 or both
• speed of unloading
• signals for shaking cars
• where employees will meet to leave the site and be
in the clear of trains.
• etc.
note: this should be done at each unloading site
Job briefing by train crew, including:
• the time available to unload ballast
• where trains will be cleared
5
• how track gradients may affect unloading process
• etc.
Note: this should be done at every unloading site
3. Unloading Ballast
The following is a general outline to follow when unloading ballast
from railcars.
Step Action
Ensure proper unloading bars/cranks available for old/new cars
1
Crack doors on Morrison/Knudsen ballast cars
Move ballast train into position ensuring that train is marshalled so
that:
• same car types are marshalled (should be done prior to
2 obtaining work block)
• only loaded cars will move over flooded track
• spreader is next to unit and train is “pushed” during
unloading (where possible)
TRACK STANDARDS Page 11-6
RC-0506-02TRK May 2018 Revised: 2018-01-12
GO TRANSIT RECOMMENDED METHODS
Unload:
• between rails first
• on shoulder only after centres have been unloaded if
applicable
If using older enterprise cars, clean all ballast off centre doors and
6
close them, then clean side doors prior to closing.
12.3. Precautions
1. If possible, surface away from the fixed location and not
towards it.
a. If not possible, destress the both rails
immediately following the surfacing work. Follow
the requirements of Track Standards section
4.9, 13.3, and 14.5 for destressing.
2. When surfacing operations are required in a curve, the
entire curve must be surfaced from tangent to tangent.
3. Before surfacing and lining a curve on main tracks, the
curve must be staked if it is more than 3° or if the rail
temperature is more than 50°F or 28°C below the
preferred rail laying temperature, or is expected to be in
the next 24 hours.
4. Compound curves shall be staked prior to surfacing.
TRACK STANDARDS Page 12-5
RC-0506-02TRK May 2018 Revised: 2018-01-12
GO TRANSIT TRACK STANDARDS
Crank Eye
Throw
Adjustment
± 1/32” (0.8 mm) ± 1/16” (1.6 mm)
4½” (114 mm) 2-1/16” (52 mm)
4-5/8” (117 mm) 2-3/16” (56 mm)
4¾” (121 mm) 2¼” (57 mm)
4-7/8” (124 mm) 2-5/16” (59 mm)
Example
A number 12 - 136 lb. turnout is replaced in track. A length of 200 ft. of
track is removed. The reference marks were 3/4” further apart after the
panel was installed. At the time of de-stressing the rail temperature was
70°F (21°C) and that the PRLT is 100°F. How much expansion is
required at both the point and frog end of the turnout?
(141*30*.00008/2)
Adjustment for half the
0.169 in. (for table use 150 ft. and divide by 2:
length of #12 turnout
3/8 divide 2 is 3/16)
Add length of weld and total (0.48 +0.48 + 0.169+1) 1 weld is 1 in.
2.129 in.
adjustment (for table 1/2+1/2+3/16+1 = 2-3/16”)
Cut rail at trailing end of turnout at 200ft away from turnout and remove
anchors.
Cut 2.129” or 2-3/16” of the rail depending on calculation method used,
and pull or heat to a 1 in. gap for final welding. Weld and re-anchor.
Cut rail at facing end of turnout at 200ft away from turnout and remove
anchors.
Cut 2.129” or 2-3/16” of the rail depending on calculation method used,
and pull or heat to a 1 in. gap for final welding. Weld and re-anchor.
1“ 1¼” 1-3/8”
Size of Bolt
(25 mm) (32 mm) (35 mm)
Torque
840 1675 2500
(ft.-lbs)
Torque
1140 2270 3390
(N-m)
3. Make sure the spike holes are plugged and the frog
base plate is resting flat and solid. If not, adze or replace
ties as necessary to provide a flat solid support under
the entire frog. Make sure tie spacing is correct for the
size of frog being installed.
4. Guard rails are extremely important. They provide
protection and ensure the proper operation of the spring
wing rail. Make sure the frog is properly gauged (56 ½
inches), and that the guard check gauge and the guard
face gauge measurements are greater than or equal to
the minimums shown by the class of track in the
Transport Canada Rules Respecting Track Safety.
5. Care must be taken when lifting the frog with a tamper
as the rail base hooks may bend the frog base plate.
Hand jacks MUST be utilized on the outside rails of the
turnout to assist in lifting the frog
6. Where hand tamping of ties is performed, only 16” on
either side of the rail is to be tamped; the centre of the
tie must not be tamped except on steel tie turnouts.
7. Before leaving the work site, clean the spring wing rail
plates. Apply a lubricant to the base plates. Check the
operation of the wing rail to ensure that the base plate
has not restricted the horn clearance. Check to make
sure the wing rail closes without sticking.
8. Maintenance of spring frogs includes:
a. Good tie condition and surface under the frog
toe to keep the horns from impacting the
housings.
TRACK STANDARDS Page 13-19
RC-0506-02TRK May 2018 Revised: 2018-01-12
GO TRANSIT TRACK STANDARDS
hole. Lift and move the guard bar to the left or right
depending on which adjustment is being made and
insert bolts into these holes. Check that the distance
from the gauge face of the stock rail is between 4” to
4-1/8”. If so re-bolt the 2 bolts that hold the guard
bar in place and recheck the stock rail to guard face
dimension.
c. Note:
The Abex or (ABR rail) switch point guards have 2
adjustments of 1/4” each after the initial installation.
Adjustment beyond that is not possible and a new
wear bar will be required.
Section 14 Crossings
14.1. At-Grade Rail-to-Rail Crossings
1. For railway diamonds, follow the same procedure for
turnouts in Track Standards Section 13
2. Crossings will be installed according to the plans
supplied for each crossing.
3. Install continuously insulating joints at all diamond
crossings.
4. Jack and lifting slings should be used under the diamond
insert, not under the legs.
5. Avoid damage to the diamond insert when handling,
placing and lifting.
6. Installation of guard rails in advance of the rail crossing
will be at the discretion of the CM Senior Manager of
Track and Structures.
7. Subgrade under rail crossings must be well drained.
Clean crushed rock ballast will be kept well tamped so
that the surface of the frog is maintained at a uniform
grade with the approaches. Only approved ballast shall
be used.
8. Rail crossings must be fully bolted. All bolts will be
provided with spring or hardened flat steel washers and
will be kept tightened to the torque shown in Table 27
and Table 28 of Track Standard Section 13.4. Use the
correct diameter and bolt length. See Track Standards
Sections 13.2 and 13.3 for further details.
9. Manganese castings will:
a. Be ground and slotted as per Track Standard
Section 13.4.17. Product warranty requires that
this be documented.
b. Be welded if the tread is worn down 3/8 in. (10
mm) or more below the original contour
19. When preparing the rail for the crossing, ensure that the
bonded insulated glued joints are welded to this rail in
order to remove a joint from the vicinity of the crossing
and prevent pumping per item 16.
20. The rail weight and section to be installed shall be the
same as the rail section for that portion of the
subdivision. However, in no case should the weight of
rail installed in a crossing be less than 115 lb. RE.
21. Tie plates shall be forged type (such as MSR) for the full
crossing surface and fully spiked and lagged.
a. Approval from the CM Senior Manager of Track
and Structures can be given to use 14-inch
double shoulder plates.
i. Plates shall be fully spiked as per Track
Standard Section 10.4, spiking pattern
number D (Appendix R – Spiking
Patterns) for the full crossing panel
length.
• The gauge side pin track spike
may be removed to
accommodate the proper
seating of the rail seal.
ii. The track shall be anchored as per
Track Standard Section 10.2 including
through the crossing.
22. The appropriate rubber rail seal shall be used to
accommodate the rail anchors. Tie plates shall conform
to Track Standard Section 10.1 and 14.3.21.When using
rail clips the appropriate rubber rail seal shall be used.
The manufacturer’s instructions should be followed for
the installation of this flange-way (rail seal) material.
23. Where asphalt crossing surfaces are used, the rubber
rail seal product shall be secured to the rail via an
approved fastening device in every tie crib. Rail seal
shall be ended in a crib area, clipped, and the ends
sealed in with asphalt. Asphalt shall extend to the edge
of the rail seal.
24. Where spikes are used they shall be six inches in length
(152 mm).
TRACK STANDARDS Page 14-8
RC-0506-02TRK May 2018 Revised: 2018-05-11
GO TRANSIT TRACK STANDARDS
25. Where timber tie screws are used they shall be as per
Standard Plan GTS-1315, 6-1/2 in. (165 mm) in length
and heat-treated.
26. Cellular confinement (sometimes called geowebs and
geogrids) may be used where the subgrade of the
crossing is particularly soft and is prone to pumping,
such as swamp or muskeg locations. They may also be
used in other locations where the bearing capacity of the
soil is insufficient to sustain the applied highway and
railway loading. This can be determined by indications
of either excessive water in the soil or if a heel can be
pressed into the subgrade. Consideration should then
be given to using cellular confinement cells. The CM
Senior Manager of Track and Structures should be
contacted for advise on where and which type to use.
27. Filter fabrics are not recommended for grade crossings
except in exceptional cases, as directed by the CM
Senior Manager of Track and Structures. Research has
shown than most fines in ballast are either air borne,
washed in by water or simply the result of ballast
degradation under load. Having a filter fabric under the
ballast traps the fines in the ballast.
28. There are five categories of crossing surface length
dimensions. The following are the minimum lengths of
crossing surface, as measured at right angles to the
centre line of the roadway. Note that the travelled portion
of the roadway includes sidewalks.
a. Where the traveled portion of the roadway has
no shoulders then the crossing surface must
extend 20 in. (0.5 m) beyond the traveled portion
of the roadway on both ends of the crossing.
b. Where there is a shoulder (paved or unpaved)
beyond the traveled portion of the roadway then
the crossing surface must extend 20 in (0.5 m)
beyond the shoulder on both ends of the
crossing
c. Where there is sidewalk within 3 ft. (1 m) of the
vehicular portion of the roadway (with or without
curbs) then the crossing surface must extend 20
in. (0.5 m) beyond the sidewalk on both ends of
the crossing.
TRACK STANDARDS Page 14-9
RC-0506-02TRK May 2018 Revised: 2018-05-11
GO TRANSIT TRACK STANDARDS
Travelled portion of
(0.5m)
Sidewalk
roadway
shoulder
20”
Shoulder
shoulder where applicable
Crossing surfaces may be
applicable
Notes:
1. The minimum width of grade crossing surface for public
roads for vehicle use is 26 ft. (8 m) measured at a right
angle to the centreline of the roadway.
2. The minimum width of the grade crossing surface for a
sidewalk, path, trail, or any other route for a pedestrian,
or for use by a pedestrian using an assistive device is 5
ft. (1.5 m) measured at right angles to the centreline of
the sidewalk, path, trail, or route.
10. Cut and pull halfway through the 400 ft. (122 m) section,
at the x marks in the preceding figure, with all anchors
removed on the main track; leave all anchors and clips
on crossing.
Example
A crossing is being rehabilitated and new rail panel installed through the
crossing. 110 ft. of rail will be replaced, in a location where the CM Sr.
Manager of Track and Structures has determined that only 1 side is
required. The rail temperature at time of destressing the crossing rail
was 60°F. The reference marks are now 1/4” further apart. What is the
required rail expansion?
(200*40*0.00008)
Adjustment for 200 ft. gap 0.64 in.
(use 5/8 in. for tables)
Adjustment for crossing 110 ft. > 100 ft. therefore use 110 ft.
0.352 in.
length (For table 3/8 in.)
Total adjustment required is 400 ft. for the unanchored zone (200 ft. +
200 ft.) plus add the greater of the length of the crossing or 100 ft. In
this case the length of the crossing panel is 110 ft. therefore we use a
total of 510 ft.
Cut 2.882 in. or 2-7/8 in. of the rail depending on calculation method
used, and pull or heat to a 1 in. gap for final welding. Weld and re-
anchor.
Example:
Assume that a crossing on a line carrying 10 MGT annually
requires rehabilitation. The road authority advises that the
average daily vehicle count for this crossing is 10,000 vehicles
per day of which 1,000 are trucks. Find the most appropriate
crossing surface for this crossing.
Rail
a Areas with high numbers of fatigue related rail defects
b Rail defects protected by joint bars
c Rail damage which has been alleviated by grinding
d Areas approaching urgent limits for wear. Where rail
wear is at the increased monitoring limit, the underside
of the rail-head must be physically inspected.*
e Locations prone to overstressed rail, such as:
i. areas where rail repairs have been made (too little
or too much rail installed)
ii. curves
iii. areas of severe rail corrugation
iv. areas of heavy brake application
(e.g. approaches to PSO locations) – moving rail.
v. areas of buffer rails or any joints adjoining CWR
vi. areas of steep grades and sags
vii. areas of insufficient or damaged rail anchors, or
significant rail movement
viii. derailment sites or derailment damaged rail
f Signs of rail moving through anchors
g Short misalignment and kinks in tangent track.
Joints
a Cracked or broken joint bars, especially where this is a
high occurrence of such
b Gauge or top of rail mismatch between rails.
1
Rail Joint Condition Action
Visible cracks in joint bar Replace bar
Loose bolts Tighten bolts
Bent bolts Replace bolts*
Missing bolts2 Replace bolts
Tie(s) not effectively supporting Tamp tie(s)
joint Replace or repair tie(s)*
Broken or missing tie plate(s) Replace tie plate(s)
Deteriorated insulated joint Replace/repair joint*
Rail end batter (greater than
5/16 in. (8 mm) in depth and
Repair by welding joint or
more than 6 in. (152 mm) in
length measured with a 36 in. removing rail*
(914 mm) straight-edge)
Rail end mismatch reaches
limits specified by TC Rules
Respecting Track Safety, Part II,
Replace rail weld or grind
Subpart D, IV (see table below)
Adjust rail anchors, tighten
Longitudinal rail movement
greater than 2 inches (51 mm)
bolts, add or remove rail at
appropriate time
Wide rail gap greater than ½ in. Adjust rail gap and secure
(13 mm) joint*
Joint vertical movement (profile)
that exceeds 75% of the
allowable threshold for the
Surface joint*
designated class of track3
Fouled4 ballast present in
conjunction with joint vertical
Surface joint and provide
movement (profile) that exceeds
75% of the allowable threshold drainage*
for the designated class of track
1
Action may also consist of placing a speed restriction or
removing the track from service.
2
A minimum of 2 bolts per rail must be in place at each joint.
3
Joint vertical movement is the apparent visible movement
measured at the joint.
4
Fouled ballast is defined as ballast that is so contaminated
with fines that it contains standing water within the track
structure at joints
* Or conduct follow-up inspections every other week until the
defects are repaired or removed
15.10. Derails
1. Derails shall be inspected on foot and operated and
must conform to the requirements in Track Standards
Section 10.3.
2. Derail inspection frequency is dictated by Table 46 in
Appendix B – Track Inspection Frequencies.
3. When conducting an inspection of a derail the following
should be noted:
a. Derail is of the proper size, type, and fit;
b. The ties under the derail are sound, fasteners
intact, and the tie fully supports the derail;
c. Lock is present and applied to the derail;
d. Derail is painted yellow, and clearly visible; and
e. Derail signs, where required are in place and
visible.
a. Non-signalled territory.
b. Jointed and/or gas welded rail.
c. Rail of 115 RE weight or lighter subject to rail
car gross weight of 286,000 lbs.
d. Rail with a history of frequent defects.
3. Additional track inspections should also be considered
during the first “cold snap” of the season.
4. During winter, at times of snow accumulations, watch for
signs of screw spike / cut spike failure on curves
equipped with rolled plates and 16 inch modified
eccentric plates with welded e-clip shoulders.
Disturbance of the snow may be evidence of lateral
movement of the tie plates due to weaken fasteners and
may be accompanied by lifting/canting of the plate.
Ditches or culverts
Drainage Ditches or culverts blocked,
blocked, beaver activity, High water
beaver activity, high water
high water
Slides Slides, rock falls Slides, rock falls Slides, rock falls
Damaged, open gates, Damaged, open gates, Damaged, open gates,
Fencing
livestock on R.O.W. livestock on R.O.W. livestock on R.O.W.
Vertical & horizontal
Clearances Restricted clearances -
restricted clearances
Loose, missing or high
Missing or high planks
planks or other surface
or other surface
material, high spikes,
material, high spikes, Ride quality, restricted
obstructed flange-ways,
obstructed flange-ways, visibility
restricted sight lines
restricted sight lines
Highway and
Warning devices -
Farm Crossings Warning devices - damaged
damaged or missing Warning devices -
or missing gates, lenses,
gates, lenses, bulbs, damaged or missing
bulbs, signs, masts, 1-800
signs, masts, 1-800 gates, inoperable
number label, power “off” or
number label
“on” lights
Power light.
Height of
Rail Section Base Gauge ΔDesign
Section
53¾” 7 5/16” 2¾”
136 RE (70 mm)
(1,365 mm) (185.75 mm)
53 7/8” 7 1/8” 2 5/8”
132 RE (66.7 mm)
(1,368.5 mm) (181 mm)
54” 6 5/8” 2½”
115 RE (63.5 mm)
(1,371.5 mm) (168.25 mm)
4. Alignment
a. The maximum allowable deviations for
alignment related defects are listed in Appendix
D – Urgent Defects.
b. The measurement for alignment shall be the
maximum mid-ordinate (positive or negative) in
inches, of a 62 ft. (18.9 m) or 31 ft. (9.5 m) chord
measured at the gauge point.
i. On curved track, the high (outside) rail
shall be used as the line rail. On tangent
track, either rail may be used as the line
rail but the same rail must be used
throughout the tangent.
ii. The line rail for a turnout for the
diverging route is the curved closure rail
between the switch point and the frog.
TRACK STANDARDS Page 16-5
RC-0506-02TRK May 2018 Revised: 2018-03-30
GO TRANSIT TRACK STANDARDS
6. Surface
a. The maximum allowable deviations for surface
related defects are listed in Appendix D – Urgent
Defects.
b. The measurement for SURFACE shall be the
maximum positive or negative mid-ordinate, in
inches or mm, of a 62 ft. (18.9m) chord
measured along the top surface of the rail.
c. The maximum mid-ordinate shall be established
by centring visible peaks or sags on the chord.
7. Cross Level
a. The maximum allowable deviations for cross
level related defects are listed in Appendix D –
Urgent Defects.
b. The measurement for cross-level shall be the
difference in elevation, in inches or mm,
between the grade rail and the adjacent rail,
measured at right angles with a level board or
approved track gauge.
c. Designated elevation at any point on a curve is
determined by averaging the elevation of 11
points (the point of concern plus 5-points on
either side) over a 155 ft. (47.2 m) track
segment at 15 ft. 6 in. (4.72 m) spacing. If the
TRACK STANDARDS Page 16-8
RC-0506-02TRK May 2018 Revised: 2018-03-30
GO TRANSIT TRACK STANDARDS
16.4. Responsibility
1. The Track Supervisor or designate is responsible for:
a. Checking the deterioration in track geometry
between IRIS tests;
b. Ensuring that track geometry is maintained with
the track geometry standards, or providing
appropriate track protection; and,
c. Accompanying the IRIS testing vehicle when it is
testing primary and secondary main lines in their
respective territory.
½” Point of Frog
4½”
¼” – 5/16”
(114 mm)
Items to
TS Requirements
Check
• Cribs not less than three quarters full
Ballast and
• Ballast shoulder not less than 10 in. (254 mm)
Drainage
• No standing water or indications of it.
Line, gauge,
surface, and • Per Track Standard Section 16
cross level
• Sound and holding spikes and fasteners
Ties • Stops and shoulders firmly welded to plate
• not worn in excess of 1/8 in. (3mm)
• None broken or cracked
Plates • None missing.
• Not worn in excess of 1/8 in. (3 mm).
Rails • Note rail condition such as rust streaks, ordinary
(Including switch breaks, vertical or horizontal split heads, engine
rails, closure burns, broken bases, crushed heads, bolt-hole
rails, stock rails, breaks, etc.
TRACK STANDARDS Page 17-16
RC-0506-02TRK May 2018 Revised: 2018-01-12
GO TRANSIT TRACK STANDARDS
and frog rails) • End batter or mismatch not exceeding 0.040 in. (1
mm)
• Fully spiked (except hook twin tie plates which will
have only one spike per plate end) or fastened with
Fasteners tie screws and Rail clips.
• Spikes fully driven or timber tie screws drawn down.
• Rail clips in place and shoulders not broken
• No breaks or cracks in manganese inserts
• No breaks in blocks or rail braces, etc.
• If the tread portion of a casting is worn down more
Castings than 3/8in. (10 mm) below the original contour,
operating speed over that crossing may not be
greater than 10 mph
• Metal flow ground off
• None loose, broken or missing.
• All tight (torque per Track Standard Section 13.4)
Bolts • Spring washers, flat washers or cotter pins present as
required
• Bolts are of correct strength, length , and diameter
• On main track or in CWR territory:
o Fully box anchored on both tracks through diamond
o Fully box anchored for 200 ft. (61 m) in both
Rail Anchors
directions beyond the diamond.
• On other tracks, sufficient number of rail anchors to
prevent movement of diamond
• In place and functional
Insulation
• not visibly damaged
• Clear of foreign objects.
• Not less than 1-1/2” (38 mm) deep for Class 2
Flange-ways through 5. Not less than 1 3/8” (35 mm) deep for
class 1.
• Not less than 1-3/4” (44 mm) wide.
• Guard check gauge – not less than that dimension in
Guard Check
Table 36 in Track Standard section 17.5
Gauge / Guard
Face Gauge • Guard face gauge - not less than that dimension in
Table 36 in Track Standard section 17.5
Joints • Joints from the outer signals on all routes
Introduction
This Recommended Method describes typical switch layout
problems encountered at power operated switch locations that
have a direct impact on the reliability of turnouts. Also described
are appropriate corrective actions.
The intent of this Recommended Method is to provide a
guideline for use by Track Foreman, Track Supervisors, S&C
Supervisors, and Signal Maintainers when conducting switch
layout inspections.
At least twice annually, it is recommended that switch layouts
should be inspected jointly by Track and S&C maintainers.
References:
GI-329, GI-409 and appropriate turnout plans
Inspection Criteria
The following tables identify some of problems typically
encountered at power switch layouts, the probable causes
and/or preventative maintenance procedures that can mitigate
them, and the impacts on the switch machine.
RC-0506-02TRK
Switch points are askew machine throw, lock and detector
replacement of the switch point or
in relation to one another connecting rods including internal
closure rail
components. This often results in loss
of correspondence. Thimbles in the heel casing are
Replace thimble in heel casting
worn
Switch points does not Prevents the point from seating, Lips on point and/or stock rail Grind off visible lip
fully close beyond switch causing switch machine adjustment
Inspect stock rail to ensure properly
tip difficulties Stock rail braces over driven
seated, adjust braces if necessary
The switch point should fit flush against Improper adjustment of switch Adjust rods ensuring gauge and
May 2018
the stock rail for the full length of the rods or helper rod (where so flange-way clearance are
Switch point does not fully head cut in the closed position. If it equipped) maintained
TRACK STANDARDS
close beyond switch tip. does not, the switch point may move
under traffic causing component wear Track not properly gauged If significant, turnout stock rail may
and loss of correspondence. need to be re-gauged.
those few plates, which will scrape off It is not unusual for a turnout to not
most of the lubrication the first time the ride evenly on all plates. However, if
Switch points not riding on
switch is thrown, where normally problem is severe, tamp or surface
all plates
lubrication may last for 1-2 months low spots. Installation of rollers also
without replacement. The end result is Bowed switch point recommended.
Revised: 2018-01-12
Page 17-20
higher friction causing the switch
machine motor to overload.
Problem Impact on Switch Machine Probable Cause Corrective Action
RC-0506-02TRK
Switch plates are not friction between points and plates and Graphite or lubricate switch.
approved lubricant.
properly lubricated. overloads the switch machine motor.
(turnouts with Schwihag
rollers do not require
Using engine oil or grease gathers dirt, Remove excess oil and grit and
lubrication) Switch has been lubricated
filings and other grit contributing to lubricate with approved product
using engine oil or grease.
friction. (graphite or WL191 lube).
Sand on switch plates increases Remove excess oil and grit and
Sand on switch plates. friction and causes the switch machine Locomotive sanders. lubricate with approved product
motor to overload. (graphite or WL191 lube).
May 2018
Rail grindings become magnetized due
TRACK STANDARDS
to grinding action and grinding deposits
Rail grindings from switch
Rail grindings on switch adhere to switch plates and rods
grinders not properly removed Clean switch area.
plates and in crib. bypassing the insulation and short out
after grinding.
the OS track circuit, resulting in a
signal system outage
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-21
Problem Impact on Switch Machine Probable Cause Corrective Action
RC-0506-02TRK
MJS clips which are adjusted too tight
and / or not lubricated will result in
higher friction during switch movement Lubricate MJS clips immediately.
causing overloading of the switch
machine.
Worn, improperly adjusted MJS clips are not properly
or dry MJS clips. Worn MJS clips contribute to switch installed or lubricated. Ensure MJS clips are lubricated
point misalignment and loss of
regularly in accordance with GI-409.
correspondence.
May 2018
Note: Rocker clips are used in newer
TRACK STANDARDS
turnouts instead of MJS clips, and Check and replace shims
require no lubrication.
Broken or fatigued insulators on
front rods, switch rods, gauge Replace insulators.
Failed insulators will short out the OS
rods, gauge plates, insulated
Failed insulator. track circuit, resulting in a signal
joints, and insulated ductwork.
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-22
Problem Impact on Switch Machine Probable Cause Corrective Action
RC-0506-02TRK
switch machine connecting rods Promptly replace all missing
Loose rail braces. Loose resulting in loss of correspondence. hardware. When hardware is missing
or missing clips, spikes, Lack of switch maintenance. it results in overloading of remaining
bolts or anchors. components resulting in premature
Allows excessive rolling of the stock wear and failure.
rail head resulting in point movement
and loss of correspondence.
May 2018
to overload.
TRACK STANDARDS
Ensure that switch points are flush
Fluctuating temperatures causes rails
with head block tie during initial
to run and contributes to misalignment
Switch is not properly installed. installation.
of the front rod and 1st switch rods
resulting in loss of correspondence. Ensure every tie is box anchored
The front rod or the 1st
through the turnout and on either side
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-23
machine. Check tie spacing and readjust as
necessary.
Problem Impact on Switch Machine Probable Cause Corrective Action
This results in the fastening bolts Replace head block ties as required.
securing the switch machine and Consideration should be given to
Damaged or worn head
RC-0506-02TRK
extended gauge plate to the head Lack of switch maintenance. installing new gauge plates with the
block ties.
blocks to loosen resulting in loss of attached switch
switch machine adjustment. machine plate (Standard Plan GTS-520)
May 2018
Misalignment of ties results in rods
TRACK STANDARDS
Tie straps at switch or Switch not properly installed.
eventually rubbing against the ties, Re-install straps and tighten lag screws
helper crank loose or not
causing the switch machine motor to ASAP.
in place. Lag screws pulled loose.
overload.
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-24
Problem Impact on Switch Machine Probable Cause Corrective Action
RC-0506-02TRK
points and therefore higher motor Track machines and other
Damaged helper rod Replace or repair damaged
current which can result in switch heavy work equipment drive
assembly. components ASAP.
machine motor overload. This may over helper rods.
also lead to additional switch point
wear.
May 2018
Ensure bolts are inspected regularly
TRACK STANDARDS
Lack of switch machine
in accordance with GI- 329(a) and
maintenance.
Loose fastening bolts Results in loss of switch machine adjust immediately.
securing switch machine. adjustment.
Damaged or worn head block
Install new switch plates
ties (see above).
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-25
Problem Impact on Switch Machine Probable Cause Corrective Action
RC-0506-02TRK
accordance with GI-329(a) is
point lugs, rod bushings, points and switch machine throw rod,
performed regularly and
bear paws, clevises, bent lock rod, or point detector rod can Lack of switch maintenance.
necessary adjustments or
point detector or lock result in loss of correspondence, or
replacements are performed
rods. failure to properly detect an open point.
ASAP.
May 2018
of correspondence.
TRACK STANDARDS
Ensure nozzles are correctly
Snow clearing device nozzles must be
Snow clearing device installed and inspected regularly.
installed with 2 to 3 in. (51 -76 mm) of
nozzles obstructing Improperly installed nozzles.
clearance to the point. Failure to do so
points. Plan for refurbishment of SCDs
can result in unreliable switch locking.
as required.
Ensure regular inspections of
GO TRANSIT RECOMMENDED METHODS
Revised: 2018-01-12
Page 17-26
GO TRANSIT RECOMMENDED METHODS
tread may not contact the open 3/8 in. (9 mm) at the
gauge side of a spring half inch point).
wing rail. • When spring wing rail is
• The toe of each wing rail open, the opening
must be solidly tamped between wing and point
and fully and tightly rail must not be less than
bolted. 1 ¾ in. (44 mm) at any
• Each (spring) frog with a point.
bolt hole defect or head- • No broken, loose or
web separation must be missing hold down bolts
replaced. • Retarder, where installed,
allows for full closure of
TC Rules Respecting Track wing rail in greater than 1
Safety Part II - D XIV but less than 3 minutes.
• The raised guard rail on a
self-guarded frog shall not
be worn more than 3/8 in.
(9.5 mm).
• If repairs are made to a
• Self-guarded frogs must
self-guarded frog without
Self-Guarded not be used on turnouts
Frogs removing it from service,
where speeds will exceed
the guarding face must be
15 mph.
restored before rebuilding
the point.
(𝐸𝐸𝐴𝐴 + 𝐸𝐸𝑢𝑢 )
𝑉𝑉𝑚𝑚𝑚𝑚𝑚𝑚 = � (2)
0.0007 ∙ 𝐷𝐷
Check Vmax:
Using Equation 2:
Vmax2= 66 MPH
Vmax4= 76 MPH
Vmax6= 85 MPH
The allowable speeds are good for each type of traffic.
Example 2
Check Vmax:
Using Equation 2:
Vmax2= 40 MPH
Vmax4= 46 MPH
L = 194 ft.
The minimum Spiral shall be the greater of the 2.
Spiral Length = 293 ft.
Example 3
Example 4
Determine Superelevation:
1. Freight
From Appendix N – Curve and Vmax Tables,
balanced Superelevation = 6 1/8”
Imbalance allowed = 3”
Superelevation = 3 1/8”
2. GO Train
From Appendix N – Curve and Vmax Tables,
balanced Superelevation = 7 3/8”
Imbalance allowed = 4”
Superelevation = 3 3/8”
Based on the above calculations the maximum superelevation
that meets the criteria for each type of traffic is 5” (based on
freight and maximum design tolerances set by this Track
Standard. The minimum superelevation that meets the criteria is
3 3/8”.
Apply the minimum allowable Superelevation
Superelevation = 3 3/8”
Check Vmax:
Using Equation 2:
Vmax2= 50 MPH
Vmax4= 57 MPH
The allowable speeds are good for each type of traffic.
This falls beneath the physical limitation of 300 ft. The spiral
length of 300 ft. can be used provide the superelevation is runoff
appropriately.
By the freight torsion formula, the superelevation must be runoff
over at least 209 ft. Since the GO Train/passenger speed is
below 60mph, up to 25% percent of the superelevation can be
runoff on the tangent. As this is below the physical restriction,
there is no need to runoff the superelevation in the tangent.
20.2. Monitoring
1. Monitoring of excavations, shoring walls, and other
construction works adjacent or under a railway corridor
can be found in the Metrolinx General Guidelines for
Design of Railway Bridges and Structures.
2. A ground movement monitoring or a shoring wall
monitoring plan for both vertical and horizontal
settlement is required for any excavation works
TRACK STANDARDS Page 20-3
RC-0506-02TRK May 2018 Revised: 2018-03-30
GO TRANSIT TRACK STANDARDS
21.5. Clearances
1. Every structure over or beside a railway track, shall
afford the minimum clearances set out in Appendix X –
GO Transit Heavy Rail Clearance Envelopes.
a. Standard clearances and train envelopes have
been provided for the most common cases to be
encountered
b. For cases of tunnels, and other structures not
mentioned refer to AREMA or the governing
Metrolinx Standard.
Section 23 Platforms
Vertical
Gauge Face to Vertical
Location Clearance
Edge of Platform† Clearance ATR†
Tolerance
915mm 127mm - 25 mm
Mixed Use Corridors
(36”) (5”) (- 1”)
GO Transit Use
915mm* 254mm** ± 25 mm
Only (Restricted
(36”) (10”) (± 1”)
Clearance) Corridors
1,073 mm to edge
of concrete
UP Express Use 1,220 mm ± 13 mm
(42 ¼“)
Only Corridors‡ (48”) (± ½“)
1013 mm to edge
of rubber (39 7/8”)
1086 mm to edge
of concrete 1,220 mm
UP Mixed Use (42 ¾“) (48”) ± 13 mm
Corridors‡ 1036 mm to edge 1,207 mm (USRC) (± ½“)
of rubber (47 3/8”)
(40 ¾“)
Accessibility 1,270 mm 533 mm ± 25 mm
Platform (50”) (21”) (± 1”)
* 807mm (31 ¾“) permitted for existing platforms in the USRC. All new platforms to be
designed based on Table 41 above.
** 203mm (8”) permitted for existing platforms in the USRC. All new platforms to be
designed based on Table 41 above.
† For platforms on curved (super-elevated) track, clearances shall be determined
through design to ensure safe boarding and de-boarding of passengers on both regular
and accessible platform. For reference the height of floor of a GO consist ATR is
635mm (25”).
‡ UP platform horizontal measurements can be confirmed by measuring the gap
between the train and the platform at the doors. At Pearson station the gap should be
49 mm (15/16 in.). At all other stations, the gap should be 121 mm (4 ¾ in.).
NOTE: The CM Sr. Manager of Track and Structures can request the use of
an HGIV instead of and LGIV based on location.
RC-0506-02TRK
Freight (mph) 10 25 40 60 80 N/A N/A
May 2018
3-3/4” 2-1/4” 1-3/8” 1-1/8” 3/8” 3/8” 3/8”
Alignment Tangent 62 ft. (18.9 m)
(95) (57) (35) (28) (10) (10) (10)
TRACK STANDARDS
3-3/4” 2-1/4” 1-3/8” 1-1//8” 1/2” 3/8” 3/8”
Alignment Curve/Spiral 62 ft. (18.9 m)
(95) (57) (35) (28) (13) (10) (10)
GO TRANSIT TRACK STANDARDS
Revised: 2018-01-12
Page 6
Track Class
PRIORITY DEFECTS
1 2 3 4 5 6 7
RC-0506-02TRK
Passenger (mph) 15 30 60 80 95* 110 125
Freight (mph) 10 25 40 60 80 N/A N/A
May 2018
TRACK STANDARDS
2- 1-3/4” 1-1/2” 1-3/8” 1-1/8” 3/4” 3/4”
Warp 62 ft. (18.9 m)
1/4”(57) (44) (38) (35) (29) (19) (19)
GO TRANSIT TRACK STANDARDS
Revised: 2018-01-12
Page 7
Track Class
URGENT DEFECTS
1 2 3 4 5 6 7
Passenger (mph) 15 30 60 80 95* 110 125
RC-0506-02TRK
Freight (mph) 10 25 40 60 80 N/A N/A
May 2018
5” 3” 1-3/4” 1-1/2” 3/4” 5/8” 1/2”
Alignment Tangent 62 ft. (18.9 m)
(127) (76) (44) (38) (19) (16) (13)
TRACK STANDARDS
Alignment Curve / Spiral 62 ft. 5” 3” 1-3/4” 1-1/2” 5/8” 1/2" 1/2"
(18.9 m) (127) (76) (44) (38) (16) (13) (13)
GO TRANSIT TRACK STANDARDS
Revised: 2018-01-12
Page 8
Track Class
URGENT DEFECTS
1 2 3 4 5 6 7
Passenger (mph) 15 30 60 80 95* 110 125
RC-0506-02TRK
Freight (mph) 10 25 40 60 80 N/A N/A
May 2018
3” 2-1/4” 2” 1-3/4” 1-1/2” 1” 1”
Warp 62 ft. (18.9 m)
(76) (57) (51) (44) (38) (25) (25)
TRACK STANDARDS
3” 2” 1-3/4” 1-1/4” 1” 7/8” 7/8”
Cross-Level from Design
(76) (51) (44) (32) (25) (22) (22)
GO TRANSIT TRACK STANDARDS
Revised: 2018-01-12
Page 9
GO TRANSIT TRACK STANDARDS
NOTE:
Wide Gauge: The distance between the gauge points of the rails 5/8” (16 mm)
below the top of the rail may not be more than:
Narrow Gauge: The distance between the gauge points of the rails 5/8” (16 mm)
below the top of the rail may not be less than:
Alignment 62 Tangent: The deviation of the mid-offset from a 62 ft. (18.9 m)
chord may not be more than:
Alignment 62 Curve: The deviation of the mid-ordinate from a 62 ft. (18.9 m)
chord may not be more than:
Alignment 31: The deviation of the mid-ordinate from a 31 ft. (9.45 m) chord
may not be more than:
Surface: The deviation from uniform profile on either rail at the mid-ordinate of a
62 ft. (18.9m) chord may not be more than:
Warp 31: The difference in cross level between any two points within 31ft. (9.45
m) apart in spirals may not be more than:
Warp 62: The difference in cross level between any two points within 62 ft.
(18.9m) apart may not be more than:
Cross-level from Design: Deviation from zero cross-level at any point on
tangent track or from designated cross-level or reverse elevation on curves and
spirals may not be more than:
Runoff: The runoff in any 31ft. (9.45 m) of rail at the end of a raise may not be
more than:
RC-0506-02TRK
Class Passenger Warp 62 ft. Cross-
of Train Alignment Alignment Alignment Warp 31ft. (18.9 m) Level Cross- Runoff at
Wide
Track Speed Tangent 62 Curve 62 ft. Curve 31 ft. Surface (9.45 m) Tangents, Tangents Level End of
Gauge
ft. (18.9 m) (18.9 m) (9.45 m) Spirals Spirals, and and Spirals Raise
Curves Curves
May 2018
57-5/8 3 3 2-3/4 1-3/4 2 2 1-1/2 3
30 No Limit
TRACK STANDARDS
(1464) (76) (76) (70) (44) (51) (51) (38) (76)
57-5/8 2-3/8 2-3/8 1-1/4 2-1/2 1-1/2 1-7/8 1-7/8 1-3/8 2-1/2
45
(1464) (60) (60) (31) (63) (38) (47) (47) (35) (63)
57-5/8 2-1/8 2-1/8 1-1/4 2-3/8 1-3/8 1-13/16 1-13/16 1-5/16 2-5/16
50
(1464) (54) (54) (31) (60) (35) (46) (46) (33) (58)
GO TRANSIT TRACK STANDARDS
3
57-5/8 1-15/16 1-15/16 1-1/4 2-5/16 1-5/16 1-3/4 1-3/4 1-1/4 2-1/8
55
(1464) (49) (49) (31) (58) (33) (44) (44) (31) (54)
57-5/8 1-3/4 1-3/4 1-1/4 2-1/4 1-1/4 1-3/4 1-3/4 1-1/4 2
60
(1464) (44) (44) (31) (57) (31) (44) (44) (31) (51)
Revised: 2016-06-12
Page 11
APPENDIX E – ALLOWABLE TSO FOR IRIS
Defect inch (mm)
RC-0506-02TRK
Passenger Warp 62 ft.
Class of Alignment Alignment Alignment Warp 31 ft. (18.9 m) Cross-Level Cross- Runoff at
Train
Track Surface (9.45 m) Tangents, Tangents Level End of
Speed Wide Gauge Tangent 62 ft. Curve 62 ft. Curve 31 ft.
(18.9 m) (18.9 m) (9.45 m) Spirals Spirals, and and Curves Spirals Raise
Curves
57-5/8 1-11/16 1-11/16 1-3/16 2-3/16 1-3/16 1-5/8 1-5/8 1-3/8 1-7/8
65
(1464) (43) (43) (30) (55) (30) (41) (41) (35) (48)
57-5/8 1-5/8 1-5/8 1-1/8 2-1/8 1-1/8 1-1/2 1-1/2 1-1/8 1-3/4
70
(1464) (41) (41) (28) (54) (28) (38) (38) (28) (44)
4
57-9/16 1-9/16 1-9/16 1-1/16 2-1/16 1-1/16 1-3/8 1-3/8 1-1/16 1-5/8
75
(1462) (39) (39) (27) (52) (27) (35) (35) (27) (41)
May 2018
57-1/2 1-1/2 1-1/2 1 2 1 1-1/4 1-1/4 1 1-1/2
80
TRACK STANDARDS
(1460) (38) (38) (25) (51) (25) (31) (31) (25) (38)
57-1/2 1-1/4 1-3/16 13/16 1-3/4 7/8 1-1/8 1-1/8 7/8 1-5/16
85
(1460) (31) (30) (21) (44) (22) (28) (28) (22) (33)
57-1/2 1 7/8 5/8 1-1/2 13/16 1-1/16 1-1/16 13/16 1-1/8
5 90
(1460) (25) (22) (16) (38) (21) (27) (27) (21) (28)
GO TRANSIT TRACK STANDARDS
Revised: 2016-06-12
Page 12
Defect inch (mm)
RC-0506-02TRK
of Train Alignment Alignment Alignment Warp 31 ft. (18.9 m) Cross-Level Cross- Runoff at
Wide
Track Speed Tangent 62 Curve 62 ft. Curve 31 ft. Surface (9.45 m) Tangents, Tangents Level End of
Gauge
ft. (18.9 m) (18.9 m) (9.45 m) Spirals Spirals, and and Curves Spirals Raise
Curves
May 2018
57-5/8 3 3 2-3/4 1-3/4 2 2 1-1/2 3
25 N/A
(1464) (76) (76) (70) (44) (51) (51) (38) (76)
TRACK STANDARDS
57-5/8 2-1/2 2-1/2 1-1/4 2-9/16 1-9/16 1-7/8 1-7/8 1-3/8 2-5/8
30
(1464) (63) (63) (31) (65) (40) (48) (47) (35) (66)
TRUCK DEFECTS – FREIGHT
57-5/8 2-1/8 2-1/8 1-1/4 2-3/8 1-3/8 1-13/16 1-13/16 1-5/16 2-5/16
3 35
(1464) (54) (54) (31) (60) (35) (46) (46) (33) (59)
GO TRANSIT TRACK STANDARDS
Revised: 2016-06-12
Page 13
APPENDIX F – ALLOWABLE TSO FOR IRIS
Defect inch (mm)
RC-0506-02TRK
of Train Alignment Alignment Alignment Warp 31 ft. (18.9 m) Cross-Level Cross- Runoff at
Track Speed Wide Gauge Tangent 62 ft. Curve 62 ft. Curve 31 ft. Surface (9.45 m) Tangents, Tangents and Level End of
(18.9 m) (18.9 m) (9.45 m) Spirals Spirals, and Curves Spirals Raise
Curves
57-5/8 1-11/16 1-11/16 1-3/16 2-3/16 1-3/16 1-5/8 1-5/8 1-3/8 1-7/8
45
(1464) (43) (43) (30) (55) (30) (41) (41) (35) (48)
57-5/8 1-5/8 1-5/8 1-1/8 2-1/8 1-1/8 1-1/2 1-1/2 1-1/8 1-3/4
50
(1464) (41) (41) (28) (54) (28) (38) (38) (28) (44)
4
57-9/16 1-9/16 1-9/16 1-1/16 2-1/16 1-1/16 1-3/8 1-3/8 1-1/16 1-5/8
55
(1462) (39) (39) (27) (52) (27) (35) (35) (27) (41)
57-1/2 1-1/2 1-1/2 1 2 1 1-1/4 1-1/4 1 1-1/2
May 2018
60
(1460) (38) (38) (25) (51) (25) (31) (31) (25) (38)
57-1/2 1-5/16 1-1/4 7/8 1-13/16 15/16 1-3/16 1-3/16 15/16 1-3/8
TRACK STANDARDS
65
(1460) (33) (32) (22) (46) (24) (30) (30) (24) (35)
57-1/2 1-1/8 1-1/16 ¾ 1-5/8 7/8 1-1/8 1-1/8 7/8 1-1/4
70
(1460) (29) (27) (19) (41) (22) (29) (29) (22) (32)
5
57-1/2 15/16 13/16 5/8 1-7/16 13/16 1-1/16 1-1/16 13/16 1-1/8
75
GO TRANSIT TRACK STANDARDS
(1460) (24) (21) (16) (37) (21) (27) (27) (21) (28)
57-1/2 ¾ 5/8 ½ 1-1/4 ¾ 1 1 ¾ 1
80 (13) (32) (19)
(1460) (19) (16) (25) (25) (19) (25)
Note: These tables are used for when speed related track geometry defects are detected during track geometry (IRIS) truck inspections. The tables may be
used to determine the maximum Temporary Slow Order speed to be applied for the seventy-two (72) hour period.
Revised: 2016-06-12
Page 14
TABLE A: RAIL WEAR LIMITS
Rail Size 141 lbs. 136RE 132RE 115RE 100ARA 100 lbs. HF 85lbs.
RC-0506-02TRK
Increased 19 mm 17 mm 14.5 mm 12 mm 7 mm 5 mm 4 mm
Monitoring 3/4 “ 5/8” 9/16” 1/2” 1/4” 3/16” 1/8”
Rail Size 141 lbs. 136RE 132RE 115 RE 100ARA 100 lbs. HF 85lbs.
6 mm
May 2018
Increased 12 mm 9.5 mm 8 mm
Monitoring 1/2" 3/8” 5/16” 1/4"
TRACK STANDARDS
16 mm 13 mm 11 mm 8 mm
Urgent
5/8” 1/2" 7/16” 5/16”
Rail Size 141 lbs. 136RE 132RE 115 RE 100ARA 100 lbs. HF 85lbs.
Increased 24 mm 22 mm 18 mm 16 mm 10.5 mm 8 mm 6 mm
Monitoring 15/16” 7/8” 11/16” 5/8” 3/8” 5/16” 1/4”
Urgent 32 mm 28.5 mm 24 mm 21 mm 14 mm 11 mm 8 mm
Revised: 2017-08-01
Page 15
1-1/4” 1-1/8” 15/16” 13/16” 9/16” 7/16” 5/16”
TABLE B: RAIL WEAR LIMITS ON BRIDGES, OVERPASSES, AND TUNNELS
Rail Size 141 lbs. 136RE 132RE 115RE 100ARA 100 lbs. HF 85lbs.
RC-0506-02TRK
Increased 14.5 mm 13 mm 11 mm 9 mm 5.5 mm 4 mm 3 mm
Monitoring 9/16” 1/2" 7/16” 3/8” 3/16” 1/8” 1/8”
Urgent 19 mm 17 mm 14.5 mm 12 mm 7 mm 5 mm 4 mm
3/4 “ 5/8” 9/16” 1/2” 1/4” 3/16” 1/8”
Rail Size 141 lbs. 136RE 132RE 115 RE 100ARA 100 lbs. HF 85lbs.
4.5 mm
May 2018
Increased 9 mm 7 mm 6 mm
Monitoring 3/8” 1/4” 1/4” 3/16”
TRACK STANDARDS
12 mm 9.5 mm 8 mm 6 mm
Urgent
1/2" 3/8” 5/16” 1/4"
Rail Size 141 lbs. 136RE 132RE 115 RE 100ARA 100 lbs. HF 85lbs.
Urgent 24 mm 22 mm 18 mm 16 mm 10.5 mm 8 mm 6 mm
Revised: 2017-08-01
Page 16
15/16” 7/8” 11/16” 5/8” 3/8” 5/16” 1/4”
GO TRANSIT TRACK STANDARDS
Appearance in Track:
An oval or round dark area on the
running surface of the rail where
damaged metal breaks out forming a
cavity. There are usually several
marks. Sometimes they match on
both rails. Others are located on the
same rail and spaced at a distance
corresponding to the spacing of the
locomotive wheels.
Shelly Rail
Appearance in Track:
1. Dark spots irregularly spaced on
the gauge side of the running
surface.
2. Longitudinal separations at one or
more levels in the upper gauge
corner
3. It occurs most frequently on
curves.
Appearance in Track:
Bleeding cracks in the web
Appearance in Track:
1. A dark streak in the running
surface.
2. Widening of the head for the
length of the split.
3. One side of the head may show
signs of sagging, causing a rust
streak to appear on the fillet under
the head
4. In advanced stages a bleeding
crack will appear at the fillet under
the head.
Head-Web Separation
(HWJ, HWO)
Appearance in Track:
1. In earlier stages, wrinkled lines
appear along the fillet under the
head.
2. In later stages, a small crack
appears along the fillet under the
head on either side. These cracks
grow longitudinally with slight
irregular turns upward and
downward.
3. In advanced stages, bleeding
cracks will extend downward from
the longitudinal crack.
Appearance in Track:
Cracks in the web extending radially
from a bolt hole.
Appearance in Track:
1. A flattening and widening of the
head with the entire head
sagging,
2. Small cracks in the depression of
the running surface.
3. In advanced stages, a bleeding
crack may appear in the fillet
under the head.
Appearance in Track:
1. Bulging of the web on either or
both sides. There may be shallow
cracks apparent on the sides of
the bulge.
2. A slight sinking of the rail head in
the area above the pipe with no
other deformation of the head.
Appearance in Track:
1. A hairline crack running
completely around the rail, usually
accompanied by bleeding.
2. A separation of rail at the break
with one or both ends battered.
3. The faces of the rail are rough
and granular with no sign of a
defect.
Appearance in Track:
1. A crack starting near the junction
of the base and the web
extending outward to the edge of
the base.
2. A longitudinal crack along the
junction of the base and the web.
3. A half-moon break in the base.
Appearance in Track:
1. Change in grain structure, likely
near the base of the rail.
2. Discoloration
Battered End
Appearance in Track:
3. Flattening and widening of the head of the rail at the end.
4. The underside of the head is not affected in any way.
Mill Defect
Appearance in Track:
1. A deformation of the rail head that can cause wheels to batter the rail
severely.
2. Broken out inclusions that leave cavities in the side or top of the head.
3. Inclusion of foreign material in the rail.
4. Vertical rust marks at regular intervals along the side of the rail web.
Appearance in Track:
A transverse or longitudinal crack or separation in any portion of the weld or the
rail within six inches of the weld.
Appearance in Track:
A transverse crack across the rail head and progressing down into the web
usually originating at the surface in the area of the cad weld. The weld area will
often have grinding marks from where the cad weld has been ground off. It may
appear to be a bolt hole crack, but originates from the cad weld and not the bolt
hole.
Note: The defect grows in the area of a heat zone created by the weld that is
very brittle. Because of the brittleness, any severe blow, such as a flat spot on a
wheel, can cause sudden rupture.
Appearance in Track:
A hairline crack at right angles to the running surface that may display bleeding
or rust on the side of the head. The crack will be perpendicular to the rail and is
often vertical without the “lean” of 20 degrees common in transverse defects.
Breaks will occur in the middle of the weld and will appear as a transverse defect
with a black nucleus.
Note: Welds may be in track for many years before a defect develops but defect
growth can be very rapid.
Appearance in Track:
1. Flattening and widening of the head of the rail, other than at the end.
2. The underside of the head is not affected in any way.
Damaged Rail
Appearance in Track:
Any rail broken or injured by wrecks, broken, flat, or unbalanced wheels, slipping,
or similar causes.
Appearance in Track:
Nicks, cuts, dents or scars on any part of the surface of the rail.
Damage by Derailment
Appearance in Track:
Rail that has been broken, bent, nicked or otherwise damaged by derailment of
equipment. Rail defects caused by derailments will have defect codes which
reflect the type of defect the derailment created, i.e.: BBJ, BRO, TDT…etc.
Rail wear is
Rail Wear is less Remedial Action
greater than the
the increased
increased
monitoring limits
monitoring limits
Limit operating
3/16” to 5/16” 1/8” to 3/16” speed to 30 mph
(5mm) to (8mm) (3mm) to (5mm) and repair or
replace
Limit operating
greater than 5/16” greater than 3/16” speed to 10 mph
(8mm) (5mm) and repair or
replace
Corrective
Condition Depth Remedial Action
action
Crack-out Limit train operations
in the to not more than
10mph and visually
upper
N/A supervise each Change out rail
fillet movement until the
under the defective rail is
rail head removed
Grind with local
welding forces,
Corrugati switch & crossing
All depths Record Location
on grinder or grinding
train if possible, or
change rail
Grind with local
welding forces,
Flaking N/A Record Location switch & crossing
grinder or grinding
train
Grind with local
Record Location and
welding forces,
check for escalation
≤ 3mm (1/8”) switch & crossing
of defect once per
grinder or grinding
month
train
Record Location and
> 3mm (1/8” ) check for crack-out
Change out rail
≤ 5 mm (3/16“) under head once per
Spalling week
Limit train operation to
and
not more than 60mph
Shelling >5 mm (3/16“)
and check for crack- Change out rail
≤7mm ( ¼“)
out under head once
per week
Limit train operations
to not more than
30mph and check for
>7mm ( ¼ ”) Change out rail
crack-out under head
on each routine
inspection
NOTE: If a crack-out condition exists in the upper fillet area under the
rail head, trains and engines must not be allowed over this rail condition
until the defective rail is changed-out, unless the person assigned to
visually supervise the movement is on-site, in constant communication
with the locomotive engineer, and the movement is restricted to a speed
not exceeding 10 mph.
Equipment 50,000
Tonnage 8,000 Tons
(empty / AW0 loading) Tons
APPENDIX K – AUTHORIZING
MOVEMENTS OVER RAIL BREAKS
YES NO
RC-0506-02TRK
Difference 200 (61) 400 (122) 600 (183) 800 (244) 1000 (305) 1200 (366) 1400 (427) 1482 (452)
from PRLT
°F °C CWR MOVEMENT in. (mm)
5 2 1/8 (3) 1/8 (3) 1/4 (6) 3/8 (10) 3/8 (10) 1/2 (13) 1/2 (13) 5/8 (15)
10 5 1/8 (3) 3/8 (10) 1/2 (13) 5/8 (15) 3/4 (20) 1 (25) 1-1/8 (29) 1-1/8 (29)
15 7 1/4 (6) 1/2 (13) 3/4 (20) 1 (25) 1-1/4 (32) 1-1/2 (38) 1-5/8 (41) 1-3/4 (44)
20 9 3/8 (10) 5/8 (15) 1 (25) 1-1/4 (32) 1-5/8 (41) 1-7/8 (48) 2-1/4 (57) 2-3/8 (60)
25 11 3/8 (10) 3/4 (20) 1-1/4 (32) 1-5/8 (41) 2 (51) 2-3/8 (60) 2-3/4 (75) 3 (76)
May 2018
30 13 1/2 (13) 1 (25) 1-1/2 (38) 1-7/8 (48) 2-3/8 (60) 2-7/8 (73) 3-3/8 (84) 3-1/2 (89)
TRACK STANDARDS
35 16 1/2 (13) 1-1/8 (29) 1-5/8 (41) 2-1/4 (57) 2-3/4 (75) 3-3/8 (84) 3-7/8 (98) 4-1/8 (105)
40 18 5/8 (15) 1-1/4 (32) 1-7/8 (48) 2-1/2 (64) 3-1/4 (83) 3-7/8 (98) 4-1/2 (114) 4-3/4 (121)
45 20 3/4 (20) 1-1/2 (38) 2-1/8 (54) 2-7/8 (73) 3-5/8 (92) 4-3/8 (111) 5 (127) 5-3/8 (137)
GO TRANSIT TRACK STANDARDS
50 22 3/4 (20) 1-5/8 (41) 2-3/8 (60) 3-1/4 (83) 4 (102) 4-3/4 (121) 5-5/8 (143) 5-7/8 (149)
55 24 7/8 (23) 1-3/4 (44) 2-5/8 (67) 3-1/2 (89) 4-3/8 (111) 5-1/4 (133) 6-1/8 (156) 6-1⁄2 (165)
RAIL THERMAL EXPANSION CHART
60 27 1 (25) 1-7/8 (48) 2-7/8 (73) 3-7/8 (98) 4-3/4 (121) 5-3/4 (146) 6-3/4 (171) 7-1/8 (181)
in the Table must be calculated using the formula provided.
Revised: 2018-03-26
Page 38
Determination of rail expansion for lengths between those shown
APPENDIX L – CONTINUOUS WELDED
TEMP. LENGTH OF CWR ft. (m)
RC-0506-02TRK
Difference
from PRLT 200 (61) 400 (122) 600 (183) 800 (244) 1000 (305) 1200 (366) 1400 (427) 1482 (452)
May 2018
85 38 1-3/8 (35) 2-3/4 (70) 4-1/8 (105) 5-1/2 (140) 6-3/4 (171) 8-1/8 (206) 9-1/2 (241) 10-1/8 (257)
90 40 1-1/2 (38) 2-7/8 (73) 4-3/8 (111) 5-3/4 (146) 7-1/4 (184) 8-5/8 (219) 10-1/8 (257) 10-5/8 (270)
TRACK STANDARDS
95 42 1-1/2 (38) 3 (76) 4-1/2 (114) 6-1/8 (156) 7-5/8 (194) 9-1/8 (232) 10-5/8 (270) 11-1/4 (286)
100 44 1-5/8 (41) 3-1/4 (83) 4-3/4 (121) 6-3/8 (162) 8 (203) 9-5/8 (244) 11-1/4 (286) 11-7/8 (302)
105 47 1-5/8 (41) 3-3/8 (86) 5 (127) 6-3/4 (171) 8-3/8 (213) 10-1/8 (257) 11-3/4 (298) 12-1/2 (318)
GO TRANSIT TRACK STANDARDS
110 49 1-3/4 (44) 3-1/2 (89) 5-1/4 (133) 7 (178) 8-3/4 (222) 10-1/2 (267) 12-3/8 (314) 13 (330)
MOVEMENT (in) = RAIL LENGTH (ft.) x TEMP DIFF FROM PRLT (°F) x 0.00008
MOVEMENT (mm) = RAIL LENGTH (m) x TEMP DIFF FROM PRLT (°C) x 0.0145
Revised: 2018-03-26
Page 39
GO TRANSIT TRACK STANDARDS
1⁄2(13) 1 (25) 1-1⁄2(38) 2 (51) 2-1⁄2(64) 3 (76) 3-1⁄2(89) 4 (102) 4-1⁄2(108) 5 (127) 5-1⁄2(140) 6 (152)
RC-0506-02TRK
EFFECTIVE RAIL LENGTH ADDED TO CURVE PER 1000 ft. OF CURVE in. (mm)
0º 30’ 0 1/8(3) 1/8(3) 1/8(3) 1/4(6) 1/4(6) 1/4(6) 3/8(10) 3/8(10) 3/8(10) 1/2(13) 1/2(13)
1º 00’ 1/8(3) 1/8(3) 1/4(6) 3/8(10) 1/2(13) 1/2(13) 5/8(16) 3/4(19) 3/4(19) 7/8(22) 1(25) 1(25)
1º 30’ 1/8(3) 1/4(6) 3/8(10) 1/2(13) 5/8(16) 3/4(19) 7/8(22) 1(25) 1-1/8(29) 1-1/4(32) 1-1/2(38) 1-5/8(41)
2º 00’ 1/8(3) 3/8(10) 1/2(13) 3/4(19) 7/8(22) 1(25) 1-1/4(32) 1-3/8(35) 1-1/2(38) 1-3/4(44) 1-7/8(48) 2-1/8(54)
2º 30’ 1/4(6) 3/8(10) 5/8(16) 7/8(22) 1-1/8(29) 1-1/4(32) 1-1/2(38) 1-3/4(44) 1-7/8(48) 2-1/8(54) 2-3/8(60) 2-5/8(67)
3º 00’ 1/4(6) 1/2(13) 3/4(19) 1(25) 1-1/4(32) 1-5/8(41) 1-7/8(48) 2-1/8(54) 2-3/8(60) 2-5/8(67) 2-7/8(73) 3-1/8(79)
May 2018
3º 30’ 1/4(6) 5/8(16) 7/8(22) 1-1/4(32) 1-1/2(38) 1-7/8(48) 2-1/8(54) 2-1/2(64) 2-3/4(70) 3-1/8(79) 3-3/8(79) 3-5/8(92)
DEGREEOF CURVE
4º 00’ 3/8(10) 3/4(19) 1(25) 1-3/8(35) 1-3/4(44) 2-1/8(54) 2-1/2(64) 2-3/4(70) 3-1/8(79) 3-1/2(89) 3-7/8(98) 4-1/4(108)
TRACK STANDARDS
4º 30’ 3/8(10) 3/4(19) 1-1/8(29) 1-5/8(41) 2(51) 2-3/8(60) 2-3/4(70) 3-1/8(79) 3-1/2(89) 3-7/8(98) 4-3/8(111) 4-3/4(121)
5º 00’ 1/2(13) 7/8(22) 1-1/4(32) 1-3/4(44) 2-1/8(54) 2-5/8(67) 3(76) 3-1/2(89) 3-7/8(98) 4-3/8(111) 4-3/4(121) 5-1/4(133)
GO TRANSIT TRACK STANDARDS
When a curve chords inward, it is equivalent to adding rail into the track. The effective amount of rail added into a curve is
based on the amount the curve has shifted, or chorded inward, which can be calculated by the table above.
Revised: 2018-03-14
Page 41
ADDED FOR CURVES CHORDING INWARD
APPENDIX M – EFFECTIVE LENGTH
DISTANCE CURVE HAS CHORDED INWARD in. (mm)
RC-0506-02TRK
1⁄2(13) 1 (25) 1-1⁄2(38) 2 (51) 2-1⁄2(64) 3 (76) 3-1⁄2(89) 4 (102) 4-1⁄2(108) 5 (127) 5-1⁄2(140) 6 (152)
EFFECTIVE RAIL LENGTH ADDED TO CURVE PER 1000 FT. OF CURVE in. (mm)
5º 30’ 1/2(13) 1(25) 1-1/2(38) 1-7/8(78) 2-3/8(60) 2-7/8(73) 3-3/8(86) 3-7/8(98) 4-1/4(108) 4-3/4(121) 5-1/4(133) 5-3/4(146)
6º 00’ 1/2 (13) 1(25) 1-5/8(41) 2-1/8(54) 2-5/8(67) 3-1/8(79) 3-5/8(92) 4-1/8(105) 4-5/8(117) 5-1/4(133) 5-3/4(146) 6-1/4(159)
6º 30’ 5/8(16) 1-1/8(29) 1-3/4(45) 2-1/4(57) 2-7/8(73) 3-3/8(86) 4(102) 4-1/2(114) 5(127) 5-5/8(143) 6-1/4(159) 6-3/4(172)
7º 00’ 5/8(16) 1-1/4(32) 1-7/8(48) 2-1/2(64) 3(76) 3-5/8(92) 4-1/4(108) 4-7/8(124) 5-1/2(140) 6-1/8(156) 6-3/4(172) 7-3/8(187)
May 2018
7º 30’ 5/8(16) 1-1/4(32) 2(51) 2-5/8(67) 3-1/4(83) 3-7/8(98) 4-5/8(117) 5-1/4(133) 5-7/8(149) 6-1/2(165) 7-1/4(184) 7-7/8(200)
TRACK STANDARDS
8º 00’ 3/4(19) 1-3/8(35) 2-1/8(54) 2-3/4(70) 3-1/2(89) 4-1/4(108) 4-7/8(124) 5-5/8(143) 6-1/4(159) 7(178) 7-5/8(194) 8-3/8(213)
8º 30’ 3/4(19) 1-1/2(38) 2-1/4(57) 3(76) 3-3/4(95) 4-1/2(114) 5-1/4(133) 5-7/8(149) 6-5/8(168) 7-3/8(187) 8-1/8(206) 8-7/8(225)
DEGREE OF CURVE
GO TRANSIT TRACK STANDARDS
9º 00’ 3/4(19) 1-1/2(38) 2-3/8(60) 3-1/8(79) 3-7/8(98) 4-3/4(121) 5-1/2(140) 6-1/4(159) 7(178) 7-7/8(200) 8-5/8(219) 9-3/8(238)
9º 30’ 7/8(22) 1-5/8(41) 2-1/2(64) 3-3/8(86) 4-1/8(105) 5(127) 5-3/4(146) 6-5/8(168) 7-3/8(187) 8-1/4(210) 9-1/8(232) 10(254)
10º 00’ 7/8(22) 1-3/4(45) 2-5/8(67) 3-1/2(89) 4-3/8(111) 5-1/4(133) 6-1/8(156) 7(178) 7-3/4(197) 8-3/4(222) 9-5/8(245) 10-1/2(267)
Revised: 2018-03-14
Page 42
GO TRANSIT TRACK STANDARDS
Example:
Per the Table, for a 4 degree curve and 3 inches (76 mm) of
movement, it is equivalent to adding 2-1/8 in. (54 mm) of rail per
1000 ft. (305 m) or a reduction in the Neutral rail temperature by
30°F (13°C). For a 2,000 ft. (610 m) curve the effective rail
length added would therefore be 4¼ in. (108 mm).
RC-0506-02TRK
0°45' 0 0 1/8 1/4 3/8 1/2 5/8 7/8 1 1/8 1 3/8 1 5/8 1 7/8 2 1/4 2 5/8 3 3 3/8 3 3/4 4 1/4 4 3/4 5 1/4
1° 00' 0 1/8 1/8 1/4 1/2 5/8 7/8 1 1/8 1 3/8 1 3/4 2 1/8 2 1/2 3 3 3/8 4 4 1/2 5 5 5/8
1° 30' 0 1/8 1/4 3/8 5/8 1 1 1/4 1 5/8 2 1/8 2 5/8 3 1/8 3 3/4 4 3/8 5 1/8 5 7/8
2° 00' 0 1/8 3/8 1/2 7/8 1 1/4 1 3/4 2 1/4 2 7/8 3 1/2 4 1/4 5 5 7/8
2° 30' 0 1/8 3/8 3/4 1 1/8 1 5/8 2 1/8 2 3/4 3 1/2 4 3/8 5 1/4
3° 00' 0 1/4 1/2 7/8 1 3/8 1 7/8 2 5/8 3 3/8 4 1/4 5 1/4
3° 30' 0 1/4 1/2 1 1 1/2 2 1/4 3 3 7/8 5
4° 00' 1/8 1/4 5/8 1 1/8 1 3/4 2 1/2 3 3/8 4 1/2 5 5/8
4° 30' 1/8 3/8 3/4 1 1/4 2 2 7/8 3 7/8 5
5° 00' 1/8 3/8 3/4 1 3/8 2 1/4 3 1/8 4 1/4 5 5/8
5° 30' 1/8 3/8 7/8 1 1/2 2 3/8 3 1/2 4 3/4
6° 00' 1/8 3/8 1 1 5/8 2 5/8 3 3/4 5 1/8
6° 30' 1/8 1/2 1 1 7/8 2 7/8 4 1/8 5 5/8
7° 00' 1/8 1/2 1 1/8 2 3 1/8 4 3/8 6
May 2018
7° 30' 1/8 1/2 1 1/8 2 1/8 3 1/4 4 3/4
8° 00' 1/8 1/2 1 1/4 2 1/4 3 1/2 5
8° 30' 1/8 5/8 1 3/8 2 3/8 3 3/4 5 3/8
TRACK STANDARDS
9° 00' 1/8 5/8 1 3/8 2 1/2 4 5 5/8
E= 0.0007 D S2
9° 30' 1/8 5/8 1 1/2 2 5/8 4 1/8 6 E = Superelevation (in)
10° 00' 1/8 3/4 1 5/8 2 3/4 4 3/8 D = Degree of curvature (decimal degrees)
10° 30' 1/8 3/4 1 5/8 3 4 5/8 S = Speed (mph)
11° 00' 1/4 3/4 1 3/4 3 1/8 4 7/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 44
1" Imbalanced Superlelevation (CP Freight)
Degree of Speed (MPH)
Curve 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0°15' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 5/8 3/4
0°30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1 1/4 1 1/2 1 7/8 2 1/8 2 1/2
0°45' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 5/8 7/8 1 1/4 1 5/8 2 2 3/8 2 3/4 3 1/4 3 3/4 4 1/4
RC-0506-02TRK
1° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1/8 1 1/2 2 2 3/8 3 3 1/2 4 4 5/8 5 3/8 6
1° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 5/8 1 1/8 1 5/8 2 1/8 2 3/4 3 3/8 4 1/8 4 7/8 5 3/4
2° 00' 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1/4 1 7/8 2 1/2 3 1/4 4 4 7/8 5 7/8
2° 30' 1/2 1/2 1/2 1/2 1/2 5/8 1 1/8 1 3/4 2 1/2 3 3/8 4 1/4 5 1/4
3° 00' 1/2 1/2 1/2 1/2 1/2 7/8 1 5/8 2 3/8 3 1/4 4 1/4 5 3/8
3° 30' 1/2 1/2 1/2 1/2 1/2 1 1/4 2 2 7/8 4 5 1/8
4° 00' 1/2 1/2 1/2 1/2 3/4 1 1/2 2 3/8 3 1/2 4 5/8 6
4° 30' 1/2 1/2 1/2 1/2 1 1 7/8 2 7/8 4 5 3/8
5° 00' 1/2 1/2 1/2 1/2 1 1/4 2 1/8 3 1/4 4 5/8
5° 30' 1/2 1/2 1/2 1/2 1 3/8 2 1/2 3 3/4 5 1/8
6° 00' 1/2 1/2 1/2 5/8 1 5/8 2 3/4 4 1/8 5 3/4
6° 30' 1/2 1/2 1/2 7/8 1 7/8 3 1/8 4 5/8
7° 00' 1/2 1/2 1/2 1 2 1/8 3 3/8 5
May 2018
7° 30' 1/2 1/2 1/2 1 1/8 2 1/4 3 3/4 5 3/8
8° 00' 1/2 1/2 1/2 1 1/4 2 1/2 4 5 7/8
8° 30' 1/2 1/2 1/2 1 3/8 2 3/4 4 3/8
TRACK STANDARDS
9° 00' 1/2 1/2 1/2 1 1/2 3 4 5/8
9° 30' 1/2 1/2 1/2 1 5/8 3 1/8 5
E= 0.0007 D S2 - 1
10° 00' 1/2 1/2 5/8 1 3/4 3 3/8 5 1/4
10° 30' 1/2 1/2 5/8 2 3 5/8 5 5/8
11° 00' 1/2 1/2 3/4 2 1/8 3 7/8 5 7/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 45
2" Imbalanced Superlelevation (CN Freight)
Degree of Balanced Speed (MPH)
Curve 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0°15' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 7/8 1 1/8 1 1/2
0°45' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 5/8 1 1 3/8 1 3/4 2 1/4 2 3/4 3 1/4
RC-0506-02TRK
1° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1 3/8 2 2 1/2 3 3 5/8 4 3/8 5
1° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 5/8 1 1/8 1 3/4 2 3/8 3 1/8 3 7/8 4 3/4 5 5/8
2° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 7/8 1 1/2 2 1/4 3 3 7/8 4 7/8 5 7/8
2° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1/2 2 3/8 3 1/4 4 1/4 5 3/8
3° 00' 1/2 1/2 1/2 1/2 1/2 1/2 5/8 1 3/8 2 1/4 3 1/4 4 3/8 5 1/2
3° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1 1 7/8 3 4 1/8 5 3/8
4° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1 3/8 2 1/2 3 5/8 5
4° 30' 1/2 1/2 1/2 1/2 1/2 7/8 1 7/8 3 4 3/8 5 7/8
5° 00' 1/2 1/2 1/2 1/2 1/2 1 1/8 2 1/4 3 5/8 5 1/8
5° 30' 1/2 1/2 1/2 1/2 1/2 1 1/2 2 3/4 4 1/8 5 3/4
6° 00' 1/2 1/2 1/2 1/2 5/8 1 3/4 3 1/8 4 3/4
6° 30' 1/2 1/2 1/2 1/2 7/8 2 1/8 3 5/8 5 1/4
7° 00' 1/2 1/2 1/2 1/2 1 1/8 2 3/8 4 5 7/8
May 2018
7° 30' 1/2 1/2 1/2 1/2 1 1/4 2 3/4 4 3/8
8° 00' 1/2 1/2 1/2 1/2 1 1/2 3 4 7/8
8° 30' 1/2 1/2 1/2 1/2 1 3/4 3 3/8 5 1/4
E= 0.0007 D S2 - 2
TRACK STANDARDS
9° 00' 1/2 1/2 1/2 1/2 2 3 5/8 5 3/4
9° 30' 1/2 1/2 1/2 5/8 2 1/8 4
10° 00' 1/2 1/2 1/2 3/4 2 3/8 4 1/4
10° 30' 1/2 1/2 1/2 1 2 5/8 4 5/8
11° 00' 1/2 1/2 1/2 1 1/8 2 7/8 4 7/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 46
3" Imbalanced Superlelevation (Passenger Trains)
Degree of Balanced Speed (MPH)
Curve 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0°15' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°45' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1/4 1 3/4 2 1/4
RC-0506-02TRK
1° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1 1/2 2 2 5/8 3 3/8 4
1° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 3/8 2 1/8 2 7/8 3 3/4 4 5/8 5 1/2
2° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 2 2 7/8 3 7/8 4 7/8 6
2° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 3/8 2 1/4 3 1/4 4 3/8 5 5/8
3° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 2 1/4 3 3/8 4 1/2 5 7/8
3° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 7/8 2 3 1/8 4 3/8 5 7/8
4° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/2 2 5/8 4 5 1/2
4° 30' 1/2 1/2 1/2 1/2 1/2 1/2 7/8 2 3 3/8 4 7/8
5° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 2 5/8 4 1/8 5 3/4
5° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1 3/4 3 1/8 4 3/4
6° 00' 1/2 1/2 1/2 1/2 1/2 3/4 2 1/8 3 3/4 5 1/2
6° 30' 1/2 1/2 1/2 1/2 1/2 1 1/8 2 5/8 4 1/4
7° 00' 1/2 1/2 1/2 1/2 1/2 1 3/8 3 4 7/8
May 2018
7° 30' 1/2 1/2 1/2 1/2 1/2 1 3/4 3 3/8 5 3/8
8° 00' 1/2 1/2 1/2 1/2 1/2 2 3 7/8 6
8° 30' 1/2 1/2 1/2 1/2 3/4 2 3/8 4 1/4
E= 0.0007 D S2 - 3
TRACK STANDARDS
9° 00' 1/2 1/2 1/2 1/2 1 2 5/8 4 3/4
9° 30' 1/2 1/2 1/2 1/2 1 1/8 3 5 1/8
10° 00' 1/2 1/2 1/2 1/2 1 3/8 3 1/4 5 5/8
10° 30' 1/2 1/2 1/2 1/2 1 5/8 3 5/8 6
11° 00' 1/2 1/2 1/2 1/2 1 7/8 3 7/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 47
4" Imbalanced Superlelevation (GO Trains and UP Express DMUs)
Degree of Balanced Speed (MPH)
Curve 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0°15' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°45' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 1/4
RC-0506-02TRK
1° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1 5/8 2 3/8 3
1° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/8 1 7/8 2 3/4 3 5/8 4 1/2 5 1/2
2° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1 7/8 2 7/8 3 7/8 5
2° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 2 1/4 3 3/8 4 5/8 5 7/8
3° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 2 3/8 3 1/2 4 7/8
3° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 2 1/8 3 3/8 4 7/8
4° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 5/8 3 4 1/2
4° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 2 3/8 3 7/8 5 1/2
5° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 5/8 3 1/8 4 3/4
5° 30' 1/2 1/2 1/2 1/2 1/2 1/2 3/4 2 1/8 3 3/4 5 5/8
6° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1 1/8 2 3/4 4 1/2
6° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1 5/8 3 1/4 5 1/4
7° 00' 1/2 1/2 1/2 1/2 1/2 1/2 2 3 7/8 5 7/8
May 2018
7° 30' 1/2 1/2 1/2 1/2 1/2 3/4 2 3/8 4 3/8
8° 00' 1/2 1/2 1/2 1/2 1/2 1 2 7/8 5
8° 30' 1/2 1/2 1/2 1/2 1/2 1 3/8 3 1/4 5 1/2
E= 0.0007 D S2 - 4
TRACK STANDARDS
9° 00' 1/2 1/2 1/2 1/2 1/2 1 5/8 3 3/4
9° 30' 1/2 1/2 1/2 1/2 1/2 2 4 1/8
10° 00' 1/2 1/2 1/2 1/2 1/2 2 1/4 4 5/8
10° 30' 1/2 1/2 1/2 1/2 5/8 2 5/8 5
11° 00' 1/2 1/2 1/2 1/2 7/8 2 7/8 5 3/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 48
6" Imbalanced Superlelevation (LRC)
Degree of Balanced Speed (MPH)
Curve 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0°15' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
0°45' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2
RC-0506-02TRK
1° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1
1° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 1 5/8 2 1/2 3 1/2 4 1/2
2° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 7/8 1 7/8 3 4 1/8 5 3/8
2° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 3/8 2 5/8 3 7/8 5 1/4
3° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/2 2 7/8 4 1/4 5 7/8
3° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 3/8 2 7/8 4 3/8 6
4° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 2 1/2 4 1/8 5 7/8
4° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 7/8 3 1/2 5 3/8
5° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/8 2 3/4 4 5/8
5° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 3/4 3 5/8 5 5/8
6° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 3/4 2 1/2 4 1/2
6° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 3 1/4 5 3/8
7° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 1 7/8 3 7/8
May 2018
7° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1/2 2 3/8 4 5/8
8° 00' 1/2 1/2 1/2 1/2 1/2 1/2 7/8 3 5 3/8
8° 30' 1/2 1/2 1/2 1/2 1/2 1/2 1 1/4 3 1/2 6
TRACK STANDARDS
9° 00' 1/2 1/2 1/2 1/2 1/2 1/2 1 3/4 4 1/8
E= 0.0007 D S2 - 6
9° 30' 1/2 1/2 1/2 1/2 1/2 1/2 2 1/8 4 5/8
10° 00' 1/2 1/2 1/2 1/2 1/2 1/2 2 5/8 5 1/4
10° 30' 1/2 1/2 1/2 1/2 1/2 5/8 3 5 3/4
11° 00' 1/2 1/2 1/2 1/2 1/2 7/8 3 3/8
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-14
Page 49
Vmax3
Degree of
Measured Superelevation (in.)
Curve
0 1/4 1/2 3/4 1 1 1/4 1 1/2 1 3/4 2 2 1/4 2 1/2 2 3/4 3 3 1/4 3 1/2 3 3/4 4 4 1/4 4 1/2 4 3/4 5 5 1/4 5 1/2 5 3/4 6
0°15' 131 136 141 146 151 156 160 165 169 173 177 181 185 189 193 196 200 204 207 210 214 217 220 224 227
0°30' 93 96 100 104 107 110 113 116 120 122 125 128 131 134 136 139 141 144 146 149 151 154 156 158 160
0°45' 76 79 82 85 87 90 93 95 98 100 102 105 107 109 111 113 115 118 120 121 123 125 127 129 131
RC-0506-02TRK
1° 00' 65 68 71 73 76 78 80 82 85 87 89 91 93 94 96 98 100 102 104 105 107 109 110 112 113
1° 30' 53 56 58 60 62 64 65 67 69 71 72 74 76 77 79 80 82 83 85 86 87 89 90 91 93
2° 00' 46 48 50 52 53 55 57 58 60 61 63 64 65 67 68 69 71 72 73 74 76 77 78 79 80
2° 30' 41 43 45 46 48 49 51 52 53 55 56 57 59 60 61 62 63 64 65 67 68 69 70 71 72
3° 00' 38 39 41 42 44 45 46 48 49 50 51 52 53 55 56 57 58 59 60 61 62 63 64 65 65
3° 30' 35 36 38 39 40 42 43 44 45 46 47 48 49 51 52 52 53 54 55 56 57 58 59 60 61
4° 00' 33 34 35 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 53 54 55 56 57
4° 30' 31 32 33 35 36 37 38 39 40 41 42 43 44 45 45 46 47 48 49 50 50 51 52 53 53
5° 00' 29 30 32 33 34 35 36 37 38 39 40 41 41 42 43 44 45 46 46 47 48 49 49 50 51
5° 30' 28 29 30 31 32 33 34 35 36 37 38 39 39 40 41 42 43 43 44 45 46 46 47 48 48
6° 00' 27 28 29 30 31 32 33 34 35 35 36 37 38 39 39 40 41 42 42 43 44 44 45 46 46
6° 30' 26 27 28 29 30 31 31 32 33 34 35 36 36 37 38 39 39 40 41 41 42 43 43 44 44
May 2018
7° 00' 25 26 27 28 29 29 30 31 32 33 34 34 35 36 36 37 38 38 39 40 40 41 42 42 43
7° 30' 24 25 26 27 28 28 29 30 31 32 32 33 34 35 35 36 37 37 38 38 39 40 40 41 41
TRACK STANDARDS
8° 00' 23 24 25 26 27 28 28 29 30 31 31 32 33 33 34 35 35 36 37 37 38 38 39 40 40
8° 30' 22 23 24 25 26 27 28 28 29 30 30 31 32 32 33 34 34 35 36 36 37 37 38 38 39
9° 00' 22 23 24 24 25 26 27 27 28 29 30 30 31 31 32 33 33 34 35 35 36 36 37 37 38
9° 30' 21 22 23 24 25 25 26 27 27 28 29 29 30 31 31 32 32 33 34 34 35 35 36 36 37
10° 00' 21 22 22 23 24 25 25 26 27 27 28 29 29 30 30 31 32 32 33 33 34 34 35 35 36
GO TRANSIT TRACK STANDARDS
10° 30' 20 21 22 23 23 24 25 25 26 27 27 28 29 29 30 30 31 31 32 32 33 34 34 35 35
11° 00' 20 21 21 22 23 23 24 25 25 26 27 27 28 28 29 30 30 31 31 32 32 33 33 34 34
11° 30' 19 20 21 22 22 23 24 24 25 26 26 27 27 28 28 29 29 30 31 31 32 32 32 33 33
12° 00' 19 20 20 21 22 22 23 24 24 25 26 26 27 27 28 28 29 29 30 30 31 31 32 32 33
Revised: 2018-03-14
Page 50
Vmax = Maximum Speed (mph)
𝐸𝐸𝐴𝐴 + 3
𝑉𝑉𝑚𝑚𝑓𝑓𝑚𝑚 =
0.0007 ∙ 𝐷𝐷
Degree of Vmax4
Curve Measured Superelevation (in.)
0 1/4 1/2 3/4 1 1 1/4 1 1/2 1 3/4 2 2 1/4 2 1/2 2 3/4 3 3 1/4 3 1/2 3 3/4 4 4 1/4 4 1/2 4 3/4 5 5 1/4 5 1/2 5 3/4 6
0°15' 151 156 160 165 169 173 177 181 185 189 193 196 200 204 207 210 214 217 220 224 227 230 233 236 239
0°30' 107 110 113 116 120 122 125 128 131 134 136 139 141 144 146 149 151 154 156 158 160 163 165 167 169
0°45' 87 90 93 95 98 100 102 105 107 109 111 113 115 118 120 121 123 125 127 129 131 133 135 136 138
RC-0506-02TRK
1° 00' 76 78 80 82 85 87 89 91 93 94 96 98 100 102 104 105 107 109 110 112 113 115 116 118 120
1° 30' 62 64 65 67 69 71 72 74 76 77 79 80 82 83 85 86 87 89 90 91 93 94 95 96 98
2° 00' 53 55 57 58 60 61 63 64 65 67 68 69 71 72 73 74 76 77 78 79 80 81 82 83 85
2° 30' 48 49 51 52 53 55 56 57 59 60 61 62 63 64 65 67 68 69 70 71 72 73 74 75 76
3° 00' 44 45 46 48 49 50 51 52 53 55 56 57 58 59 60 61 62 63 64 65 65 66 67 68 69
3° 30' 40 42 43 44 45 46 47 48 49 51 52 52 53 54 55 56 57 58 59 60 61 61 62 63 64
4° 00' 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 53 54 55 56 57 57 58 59 60
4° 30' 36 37 38 39 40 41 42 43 44 45 45 46 47 48 49 50 50 51 52 53 53 54 55 56 56
5° 00' 34 35 36 37 38 39 40 41 41 42 43 44 45 46 46 47 48 49 49 50 51 51 52 53 53
5° 30' 32 33 34 35 36 37 38 39 39 40 41 42 43 43 44 45 46 46 47 48 48 49 50 50 51
6° 00' 31 32 33 34 35 35 36 37 38 39 39 40 41 42 42 43 44 44 45 46 46 47 48 48 49
6° 30' 30 31 31 32 33 34 35 36 36 37 38 39 39 40 41 41 42 43 43 44 44 45 46 46 47
May 2018
7° 00' 29 29 30 31 32 33 34 34 35 36 36 37 38 38 39 40 40 41 42 42 43 43 44 45 45
7° 30' 28 28 29 30 31 32 32 33 34 35 35 36 37 37 38 38 39 40 40 41 41 42 43 43 44
TRACK STANDARDS
8° 00' 27 28 28 29 30 31 31 32 33 33 34 35 35 36 37 37 38 38 39 40 40 41 41 42 42
8° 30' 26 27 28 28 29 30 30 31 32 32 33 34 34 35 36 36 37 37 38 38 39 39 40 40 41
9° 00' 25 26 27 27 28 29 30 30 31 31 32 33 33 34 35 35 36 36 37 37 38 38 39 39 40
9° 30' 25 25 26 27 27 28 29 29 30 31 31 32 32 33 34 34 35 35 36 36 37 37 38 38 39
10° 00' 24 25 25 26 27 27 28 29 29 30 30 31 32 32 33 33 34 34 35 35 36 36 37 37 38
GO TRANSIT TRACK STANDARDS
10° 30' 23 24 25 25 26 27 27 28 29 29 30 30 31 31 32 32 33 34 34 35 35 35 36 36 37
11° 00' 23 23 24 25 25 26 27 27 28 28 29 30 30 31 31 32 32 33 33 34 34 35 35 36 36
11° 30' 22 23 24 24 25 26 26 27 27 28 28 29 29 30 31 31 32 32 32 33 33 34 34 35 35
12° 00' 22 22 23 24 24 25 26 26 27 27 28 28 29 29 30 30 31 31 32 32 33 33 34 34 35
Revised: 2018-03-14
Page 51
Vmax = Maximum Speed (mph)
𝐸𝐸𝐴𝐴 + 4
𝑉𝑉𝑚𝑚𝑓𝑓𝑚𝑚 =
0.0007 ∙ 𝐷𝐷
Description Class 4 and Above Class 2 and 3 Class 1, Yard
Per Appendix P – Rail Usage Guidelines or as specified by the CM Senior Manager of Track
Rail Weight
and Structures
RC-0506-02TRK
Rail
CWR CWR Jointed or CWR
(CWR or Jointed)
STANDARDS
100% ties plated per Track Standard Section 10.1 and Appendix S – Recommended Tie Plate
Tie Plates
Usage
Improved Fair Type Anchors or approved equivalent
Rail Anchors
Per Track Standard Section 10.2
Elastic Fasteners (Rail Clips) Elastic Fasteners (Rail Clips)
Fasteners
6” Cut Spikes 6” Cut Spikes
6 hole bars, punched for alternating oval-head bolts
May 2018
Joint Bars
per Standard Plan TS-1202
Track Tie Spacing
TRACK STANDARDS
Concrete 24“ (609 mm) (2640/mile)
Hardwood Grade 1 20 3/8” (518 mm) (3110/mi) 21¾” (552 mm) (2980/mi)
GO TRANSIT TRACK STANDARDS
Revised: 2018-03-30
Page 52
APPENDIX O – MINIMUM CONSTRUCTION
Description Class 4 and Above Class 2 and 3 Class 1, Yard
Concrete, Insulated Steel, or
Track Ties Concrete Concrete or Hardwood**
Hardwood
Hardwood Grade 1 or Insulated
Turnout / Crossing Ties Hardwood Grade 1, or Concrete**
Steel
GO Spec Class 1 – Main track
RC-0506-02TRK
Ballast GO Spec Class 2 – Non-main track
GO Transit Spec Class 1 –Main-line ballast
Crushed Rock only
AREMA Class 4A (For steel ties)
Minimum Depth Below
12 inch (305 mm) 9 inch (230 mm)
Bottom of Tie
Shoulder Width CWR 12inch (305 mm)
Sub-Ballast**
12 inch (305 mm)
Minimum Depth
May 2018
Top Width 22 ft. (6.7 m) – Single Track
Turnouts #12 RBM (GTS-271)
TRACK STANDARDS
Hardwood Tie Turnouts #20 RBM 136RE (GTS-278)
#10 RBM (GTS-267)
#12 RBM 136RE (GTS-271)
#8 RBM** (GTS-9)
Narstco #12 RBM
Steel Tie Turnouts N/A Narstco #10 RBM
GO TRANSIT TRACK STANDARDS
Narstco #8 RBM**
Concrete Tie Turnouts As directed by the CM Sr. Manager of Track and Structures
Revised: 2018-03-30
Page 53
* Where walking ballast is required, it shall be applied in a minimum 4” (102 mm) thick layer
** Only when authorized in writing by the CM Senior Manager of Track and Structures
GO TRANSIT TRACK STANDARDS
* 100 ARA and 132 RE rail may be used for maintenance only.
All mainline 100 ARA rail shall be scheduled for upgrade
to the appropriate rail section above.
Note: Any rail section smaller than 100 ARA shall be scheduled
for upgrade to the appropriate rail size.
High Rail
Low Rail
RC-0506-02TRK
Non-Main
X X X X
Track
A
0-20 X
0-20 X X
May 2018
0-20 X
TRACK STANDARDS
C
>20 X X
GO TRANSIT TRACK STANDARDS
>20 X
APPENDIX R – SPIKING PATTERNS
NOTE: When Forged Plates (e.g. MSR Plates) are used, ALL holes
19.
Revised: 2017-08-11
Page 59
5½” (140mm) Rail Base, 1:40 Canted Rail Seat*
Annual
Class of
Tonnage 14” (356mm) DS plate
Track
(MGT) MSR 16” (406mm) and 18” (457mm) Plates
USAGE
RC-0506-02TRK
All
All Yard (Existing 11” DS Tie plates and Rolled Plates* shall be replaced through routine
maintenance)
May 2018
Degree of Curve
TRACK STANDARDS
≤5 1-5 0º - 6º > 6º N/A
*1:20 Canted Rail Seat is permitted for Galt Sub Maintenance only
3-5 0º - 2º >2º - 4º > 4º
Revised: 2017-08-11
Page 60
APPENDIX S – RECOMMENDED TIE PLATE
GO TRANSIT TRACK STANDARDS
Bituminous (Asphalt) 6
The above average crossing surface life spans are based on 3,000 to 5,000
vehicles per day and 120 to 175 GO trains per day over the crossing.
* Not typically used on GO Transit operated corridors.
APPENDIX V – TEMPORARY
CONSTRUCTION CROSSINGS
Notes:
Key-in Benching
Limit advanced excavation into the existing fill to only a few days
in advance of road bed construction backfill (ideal <3 days). Only
key in to the slope the thickness of the fill layer which is going to
the placed (eg. 1 ft. (305 mm) thick layer of granular fill or 2 ft.
(610 mm) layer of rock fill). Vertical faces for the benches should
then be limited to < 2 ft. (610 mm) or as accepted in writing by
the geotechnical engineer (depending on soil and slope stability
conditions).
NOTE: for use with tangent track only. For curve corrections refer to Track
Standards Section 19.3.3.
NOTE: For use with tangent track only. For curve corrections refer to Track
Standards Section 19.3.3. Refer to Metrolinx General Guidelines for Design of
Bridges and Structures for full details on design requirements.
NOTE: For use with tangent track only. For curve correction, consult the CM
Senior Manager of Track and Structures. Refer to Metrolinx General Guidelines
for Design of Bridges and Structures for full details on design requirements and
tunnel clearances.
NOTE: For use with tangent track only. For curve correction, consult the CM
Senior Manager of Track and Structures. Refer to Metrolinx General Guidelines
for Design of Bridges and Structures for full details on design requirements.
Horizontal clearances to signal bungalows shall be as per the current approved
Metrolinx SCP.
Ability to Maximum
Maximum
Ability to Ability to handle length of
allowable
Make / handle handle Rail 136RE Rail
load on
Model Ties Rail by grasped approved
grapple
(wood) tine tips in grapple for handling
(lbs)
arms ft. (m)
Heiden
yes yes no 6000 39
HC20-B3
Heiden
yes yes no 6000 39
HC20-B4
Heiden
yes yes no 6000 39
HC20-A3
Heiden
yes yes yes 6500 39
HC20-AHR3
Heiden
yes yes yes 6500 39
HC20-AHR4
Heiden
yes yes no 6000 39
HC20-BP-3
Heiden
yes yes no 6000 39
HC20-BLT-3
Kinshofer
yes yes yes 6600 50
632-2-R
Kinshofer
yes yes yes 6600 50
632-R
Kinshofer
yes yes yes 9900 50
C12VE
Kinshofer
yes yes yes 9900 50
C25VE
Moley MPB1 yes yes yes 4400 50
Moley MPB2 yes yes yes 4400 50
Moley MPB3 yes yes yes 4400 50
Moley MPB
yes yes no 4400 50
1C
Moley MPB
yes yes no 4400 50
2C
Moley MPB
yes yes no 4400 50
3C
Rotobec
4550RA- yes yes yes 32000 60
RT252
Rotobec
yes no yes 25000 N/A
4642-RT252
Rotobec
4642RA- yes yes yes 25000 60
RT252
Ability to Maximum
Maximum
Ability to Ability to handle length of
allowable
Make / handle handle Rail 136RE Rail
load on
Model Ties Rail by grasped approved
grapple
(wood) tine tips in grapple for handling
(lbs)
arms ft. (m)
Rotobec
6007BT- yes yes no 14000 60
RT142
Rotobec
6007RA- yes yes yes 14000 60
RT222
Rotobec
6606HDRA- yes yes yes 21000 60
RT252
Rotobec
6806RA- yes yes yes 14000 60
RT142
yes
Rotobec
(individua yes no 8800 60
5805BT- A
l)
Rotobec
yes yes yes 8800 60
5805RA
Rototilt
yes no yes 18250 N/A
MG60
Rototilt
yes no yes 26460 N/A
MG80
yes
Serco
(individua yes yes 16000 39
5006137
l)
Serco
yes yes no 9000 39
5006139
Serco
yes yes no 16000 39
5006141
Serco
yes yes yes 16000 39
5013215
Serco
yes yes no 9000 39
5013329
Serco 5206
C/R S/P yes yes no 32000 39
Log
Serco
yes yes no 32000 39
680A899
Serco
yes yes no 9000 39
5006143
Serco
yes yes no 9000 39
5006145
Serco
yes yes no 9000 39
5013255
MISCELLANEOUS RECOMMENDED
METHODS
Recommended Method 3708-1: Application of Granular Salt
1 inch = 25.4 mm
1 mm = 0.0394 inch
1m = 3.28 ft.
1 ft. = 304.8 mm
1 mi. = 5280 ft.
1 mi. = 1.6 km
1m = 1,000 mm
1 kg = 2.2 lbs
1 ton = 2,000 lbs
1 ton = 907 kg
1 tonne = 1,000 kg
1 tonne = 2,200 lbs
1 tonne = 1.1 ton
1 gal = 3.78 L
Ballast
1 m ≈ 1.71 tonnes
3
50 50
𝑅𝑅 (𝑓𝑓𝑓𝑓) = 𝐷𝐷 𝐷𝐷𝑐𝑐 = 2 ∙ sin−1 � �
sin� 𝑐𝑐�2� 𝑅𝑅
DESIGNATED AUTHORITY
1. Areas of responsibility where the CM Senior Manager of
Track and Structures has delegated authority are located
in Table 58.
2. Table 58 indicates only the sections where authority has
been delegated. For all other inquiries, the CM Senior
Manager of Track and Structures is the designated
authority.
NOTES
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
TRACK STANDARDS Page 86
RC-0506-02TRK May 2018 Revised: 2017-08-03
GO TRANSIT TRACK STANDARDS
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
TRACK STANDARDS Page 87
RC-0506-02TRK May 2018 Revised: 2017-08-03