BLOWER TESTING &
COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)
All ITR documents to be completed & witnessed by competent person/s
Compliance to be achieved to contract requirements and all latest versions of applicable standards
1. REFERENCE INFORMATION
NUMBER OF AERO TUBE GRID:
INSPECTION DATA
PROJECT NAME: MANUFACTURER / MODEL:
LOCATION: BLOWER ELEC. SPECS [Volts / Phase / Hertz / Kw]:
STP DESIGN CAPACITY: BLOWER MECH. SPECS. [Hp / Max Airflow / Max Pressure /
TDH]:
ATTENDEES: SERIAL NUMBER:
2. INSPECTION PREPARATION
Verify that the model, HP or KW, voltage, phase and hertz on the motor nameplate match the installation
requirements.
Verify that the power supply voltage, hertz, and phase capacity match motor requirements.
Check that the Blower lead assembly is not damaged.
Check that the electrical installation and controls meet all safety regulations and match the motor
requirements, including fuse or circuit breaker size and motor overload protection.
Blower installed as per drawing Layout / approved drawings.
Piping Installed properly - Pipe Fittings, Valves, and Pipe Supports etc.
Aero Tube Grid with Hose and Connector done.
Assemble all pipe joints as tightly as practical, to prevent unscrewing from motor torque.
Base frame Blower Properly Installed and Fabricated.
3. INSPECTION PRELIMINARIES YES NO N/A COMMENTS/DETAILS
“Punchlist” reviewed and free of significant
1
defects preventing asset commissioning?
Hazard identification and risk assessment
2
for asset pre-commissioning complete?
Electrical construction and pre-
3
commissioning ITRs complete?
Mechanical and Electrical site-specific pre-
4
requisite ITRs complete?
Page 1 of 3
REMARKS:
BLOWER TESTING &
COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)
4. INSPECTION YES NO N/A COMMENTS/DETAILS
ROTATION
Blower running freely by hand without rub,
1
noise or obvious out of balance?
ANCILLARY AND TEMPORARY EQUIPMENT
All ancillary systems available and on-line?
2 (e.g. external seal water, lube oil, cooling
water, room ventilation systems)
Temporary instruments (if required)
3 installed? (e.g. vibration transducers, flow
meters, pressure gauges)
CONTROL AND PROTECTION SYSTEMS
All electrical / instrument control and
4
protection systems available and on-line?
BLOWERS
Blower discharge pipe fixed connected to
5
the blower and aero tube grid?
Blower properly mounted to the frame
6
bracket.
7 All Blower gate valves installed?
ACCESS
Area around Blower, free of debris and
8 barricaded off from other works (if
required)?
9 Emergency stop pushbutton accessible?
5. TEST YES NO N/A COMMENTS/DETAILS
AIR FLOW TEST
With the suction and discharge isolation
1 valves opened, Air Flow test to the
maximum line.
BLOWER PRE-RUN CHECKS
Check wirings are correct prior to start the
2
blower.
Ensure suction pipe is freely open /
3
installed filter before starting the blower
PERFORMANCE ASSESSMENT
Pitch and level of noise emanating from
4
Blower acceptable?
Blower and pipework connections properly
5
tight (no leaks)?
Page 2 of 3
REMARKS:
BLOWER TESTING &
COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)
ACTION TARGET
6. REMARKS / REMEDIAL / FOLLOW UP ACTIONS STATUS
BY DATE
7. SIGNOFFS
NAME (PRINT) COMPANY / ROLE SIGNATURE DATE
NAME (PRINT) COMPANY / ROLE SIGNATURE DATE
NAME (PRINT) COMPANY / ROLE SIGNATURE DATE