4 Blower Testing and Commissioning Checklist

This document is a checklist for the testing and commissioning of regenerative ring blowers used in aeration and ventilation systems. It outlines the necessary inspections, preparations, and tests to ensure compliance with contract requirements and safety regulations. The checklist includes sections for inspection data, preparation, inspection preliminaries, and sign-offs by competent personnel.

Uploaded by

zhawn70
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
375 views3 pages

4 Blower Testing and Commissioning Checklist

This document is a checklist for the testing and commissioning of regenerative ring blowers used in aeration and ventilation systems. It outlines the necessary inspections, preparations, and tests to ensure compliance with contract requirements and safety regulations. The checklist includes sections for inspection data, preparation, inspection preliminaries, and sign-offs by competent personnel.

Uploaded by

zhawn70
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

REMARKS:

BLOWER TESTING &


COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)

 All ITR documents to be completed & witnessed by competent person/s


 Compliance to be achieved to contract requirements and all latest versions of applicable standards

1. REFERENCE INFORMATION

NUMBER OF AERO TUBE GRID:


INSPECTION DATA

PROJECT NAME: MANUFACTURER / MODEL:

LOCATION: BLOWER ELEC. SPECS [Volts / Phase / Hertz / Kw]:

STP DESIGN CAPACITY: BLOWER MECH. SPECS. [Hp / Max Airflow / Max Pressure /
TDH]:

ATTENDEES: SERIAL NUMBER:

2. INSPECTION PREPARATION

Verify that the model, HP or KW, voltage, phase and hertz on the motor nameplate match the installation
requirements.

Verify that the power supply voltage, hertz, and phase capacity match motor requirements.

Check that the Blower lead assembly is not damaged.

Check that the electrical installation and controls meet all safety regulations and match the motor
requirements, including fuse or circuit breaker size and motor overload protection.

Blower installed as per drawing Layout / approved drawings.

Piping Installed properly - Pipe Fittings, Valves, and Pipe Supports etc.

Aero Tube Grid with Hose and Connector done.

Assemble all pipe joints as tightly as practical, to prevent unscrewing from motor torque.

Base frame Blower Properly Installed and Fabricated.

3. INSPECTION PRELIMINARIES YES NO N/A COMMENTS/DETAILS


“Punchlist” reviewed and free of significant
1
defects preventing asset commissioning?
Hazard identification and risk assessment
2
for asset pre-commissioning complete?
Electrical construction and pre-
3
commissioning ITRs complete?
Mechanical and Electrical site-specific pre-
4
requisite ITRs complete?

Page 1 of 3
REMARKS:
BLOWER TESTING &
COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)

4. INSPECTION YES NO N/A COMMENTS/DETAILS


ROTATION
Blower running freely by hand without rub,
1
noise or obvious out of balance?
ANCILLARY AND TEMPORARY EQUIPMENT
All ancillary systems available and on-line?
2 (e.g. external seal water, lube oil, cooling
water, room ventilation systems)
Temporary instruments (if required)
3 installed? (e.g. vibration transducers, flow
meters, pressure gauges)
CONTROL AND PROTECTION SYSTEMS
All electrical / instrument control and
4
protection systems available and on-line?
BLOWERS
Blower discharge pipe fixed connected to
5
the blower and aero tube grid?
Blower properly mounted to the frame
6
bracket.

7 All Blower gate valves installed?

ACCESS

Area around Blower, free of debris and


8 barricaded off from other works (if
required)?
9 Emergency stop pushbutton accessible?

5. TEST YES NO N/A COMMENTS/DETAILS

AIR FLOW TEST


With the suction and discharge isolation
1 valves opened, Air Flow test to the
maximum line.
BLOWER PRE-RUN CHECKS
Check wirings are correct prior to start the
2
blower.
Ensure suction pipe is freely open /
3
installed filter before starting the blower
PERFORMANCE ASSESSMENT
Pitch and level of noise emanating from
4
Blower acceptable?
Blower and pipework connections properly
5
tight (no leaks)?

Page 2 of 3
REMARKS:
BLOWER TESTING &
COMMISSIONING CHECKLIST
AERATION – REGENERATIVE RING BLOWER – VENTILATION
INSPECTION & TEST RECORD (ITR)

ACTION TARGET
6. REMARKS / REMEDIAL / FOLLOW UP ACTIONS STATUS
BY DATE

7. SIGNOFFS
NAME (PRINT) COMPANY / ROLE SIGNATURE DATE

NAME (PRINT) COMPANY / ROLE SIGNATURE DATE

NAME (PRINT) COMPANY / ROLE SIGNATURE DATE

Page 3 of 3