PC (7TH SEM)
PC (7TH SEM)
B.Tech,
SPINTRONIC TECHNOLOGY AND ADVANCE RESEARCH
Lecture Note
on
Prestressed Concrete
Prepared By:
Asst.Prof Prabhudatta Senapati
1 P.Senapati
Prestressed Concrete
B.Tech,
Module I:
Prestressing system, materials and codes: Basic concept, Losses of
prestress, analysis of prestress and bending stresses. Need for high
strength steel and concrete. Advantages and applications. Pre-
tensioning and post tensioning systems.
Module II: Design of beams : Analysis and design of section for bending
and shear, pressure line, concept of load balancing, cracking
moment, bending of cables, limit state analysis and design,
anchorage zone stresses, design of end block, Application to bridges.
Module III: Selection of prestress concrete members, short term and
long term deflections of uncracked members.
Module IV: Flexural strength of prestressed concrete
sections,Continuous beams, Design concept concordancy of cables,
Secondary design consideration
Module V: Design pre-tensioned and post tensioned beam.
2 P.Senapati
Prestressed Concrete
B.Tech,
1. Introduction
1.1 Background
The idea of prestressed concrete has been around since the latter decades of the 19th
century, but its use was limited by the quality of the materials at the time. It took until
the 1920s and ‘30s for its materials development to progress to a level where
prestressed concrete could be used with confidence. Freyssinet in France, Magnel in
Belgium and Hoyer in Germany were the principle developers.
The idea of prestressing has also been applied to many other forms, such as:
• Wagon wheels;
• Riveting;
• Barrels, i.e. the coopers trade;
In these cases heated metal is made to just fit an object. When the metal cools it
contracts inducing prestress into the object.
3 P.Senapati
Prestressed Concrete
B.Tech,
Basic Example
The classic everyday example of prestressing is this: a row of books can be lifted by
squeezing the ends together:
The structural explanation is that the row of books has zero tensile capacity. Therefore
the ‘beam’ of books cannot even carry its self weight. To overcome this we provide an
external initial stress (the prestress) which compresses the books together. Now they
can only separate if the tensile stress induced by the self weight of the books is greater
than the compressive prestress introduced.
Concrete
4 P.Senapati
Prestressed Concrete
B.Tech,
But we still get cracking, which is due to both bending and shear:
5 P.Senapati
Prestressed Concrete
B.Tech,
N A
N A
RC PSC
Smaller Deflections
The larger second moment of area greatly reduces deflections for a given section size.
Increased Spans
The smaller section size reduces self weight. Hence a given section can span further
with prestressed concrete than it can with ordinary reinforced concrete.
Durability
Since the entire section remains in compression, no cracking of the concrete can
occur and hence there is little penetration of the cover. This greatly improves the long-
term durability of structures, especially bridges and also means that concrete tanks can
be made as watertight as steel tanks, with far greater durability.
6 P.Senapati
Prestressed Concrete
B.Tech,
1.4 Materials
Concrete
You can see the importance creep has in PSC from this graph:
7 P.Senapati
Prestressed Concrete
B.Tech,
Steel
The steel used for prestressing has a nominal yield strength of between 1550 to 1800
N/mm2. The different forms the steel may take are:
• Wires: individually drawn wires of 7 mm diameter;
• Strands: a collection of wires (usually 7) wound together and thus having a
diameter that is different to its area;
• Tendon: A collection of strands encased in a duct – only used in post-
tensioning;
• Bar: a specially formed bar of high strength steel of greater than 20 mm
diameter.
Prestressed concrete bridge beams typically use 15.7 mm diameter (but with an area
of 150 mm2)7-wire super strand which has a breaking load of 265 kN.
8 P.Senapati
Prestressed Concrete
B.Tech,
9 P.Senapati
Prestressed Concrete
B.Tech,
Pre-tensioning
This is the most common form for precast sections. In Stage 1 the wires or strands are
stressed; in Stage 2 the concrete is cast around the stressed wires/strands; and in
Stage 3 the prestressed in transferred from the external anchorages to the concrete,
once it has sufficient strength:
10 P.Senapati
Prestressed Concrete
B.Tech,
In pre-tensioned members, the strand is directly bonded to the concrete cast around it.
Therefore, at the ends of the member, there is a transmission length where the strand
force is transferred to the concrete through the bond:
11 P.Senapati
Prestressed Concrete
B.Tech,
Post-tensioned
In this method, the concrete has already set but has ducts cast into it. The strands or
tendons are fed through the ducts (Stage 1) then tensioned (Stage 2) and then anchored
to the concrete (Stage 3):
The anchorages to post-tensioned members must distribute a large load to the concrete,
and must resist bursting forces as a result. A lot of ordinary reinforcement is often
necessary.
12 P.Senapati
Prestressed Concrete
B.Tech,
13 P.Senapati
Prestressed Concrete
B.Tech,
Losses
From the time the prestress is applied, the prestress force gradually reduces over time
to an equilibrium level. The sources of these losses depend on the method by which
prestressing is applied.
In both methods:
• The member shortens due to the force and this relieves some of the prestress;
• The concrete shrinks as it further cures;
• The steel ‘relaxes’, that is, the steel stress reduces over time;
• The concrete creeps, that is, continues to strain over time.
In post-tensioning, there are also losses due to the anchorage (which can ‘draw in’ an
amount) and to the friction between the tendons and the duct and also initial
imperfections in the duct setting out.
For now, losses will just be considered as a percentage of the initial prestress.
14 P.Senapati
Prestressed Concrete
B.Tech,
15 P.Senapati
Prestressed Concrete
B.Tech,
2.1 Background
The codes of practice limit the allowable stresses in prestressed concrete. Most of the
work of PSC design involves ensuring that the stresses in the concrete are within the
permissible limits.
Since we deal with allowable stresses, only service loading is used, i.e. the SLS case.
For the SLS case, at any section in a member, there are two checks required:
At Transfer
This is when the concrete first feels the prestress. The concrete is less strong but the
situation is temporary and the stresses are only due to prestress and self weight.
At Service
The stresses induced by the SLS loading, in addition to the prestress and self weight,
must be checked. At service stage, the concrete has its full strength but losses will have
occurred and so the prestress force is reduced.
The ultimate capacity at ULS of the PSC section (as for RC) must also be checked. If
there is insufficient capacity, you can add non-prestressed reinforcement. This often
does not govern.
16 P.Senapati
Prestressed Concrete
B.Tech,
Notation
We have:
The ratio of prestress after losses (service) to prestress before losses, (transfer).
17 P.Senapati
Prestressed Concrete
B.Tech,
Allowable Stresses
Concrete does have a small tensile strength and this can be recognized by the designer.
In BS 8110, there are 3 classes of prestressed concrete which depend on the level of
tensile stresses and/or cracking allowed:
18 P.Senapati
Prestressed Concrete
B.Tech,
Theoretical Example
A B
C
L
VA VB
wL2
MC =
8
d
bd 3
A = bd I=
12 2
bd 2 bd
Zt = Zb =
6 6
MC MC
t = =
Z b
Z
t b
19 P.Senapati
Prestressed Concrete
B.Tech,
Case I
If we take the beam to be constructed of plain concrete (no reinforcement) and we
neglect the (small) tensile strength of concrete ( ft = 0 ), then, as no tensile stress can
occur, no load can be taken:
wI = 0
Case II
We consider the same beam, but with centroidal axial prestress as shown:
P P
A B
C
L
VA VB
P MC P MC
+
A Zt A Zt
+
+ + =
P MC P MC
−
A Zb A Zb
20 P.Senapati
Prestressed Concrete
B.Tech,
For failure to occur, the moment caused by the load must induce a tensile stress
P
greater than . Hence, just prior to failure, we have:
A
M C P wL2
= =
Zb A 8Zb
8Z P
wII = b
L2 A
Case III
In this case we place the prestress force at an eccentricity:
e e
P P
C
A B
L
VA VB
Using an equilibrium set of forces as shown, we now have three stresses acting on the
section:
e
N.A.
= P
P
M = Pe
21 P.Senapati
Prestressed Concrete
B.Tech,
P Pe MC P MC − Pe
+ Zt
A Zt Zt A Zt
+
+ + + =
+
P Pe MC P MC Pe
− +Z
A Zb Zb A Zb b
M C P Pe
= +
Zb A Zb
8Z P Pe
w = b +
L A Z b
2
III
d
If, for example, we take e = , then:
6
P
8Zb P
Pd 6 16Zb = 2 w
w = + =
III II
L2 A bd 2 6 L2 A
So the introduction of a small eccentricity has doubled the allowable service load.
22 P.Senapati
Prestressed Concrete
B.Tech,
Prestress force (at transfer), P = 2500 kN. Losses between transfer and SLS = 20%.
Check stresses. Permissible stresses are:
ftt = -1 N/mm2 ftc = 18 N/mm2
fst = 0 N/mm2 fsc = 22 N/mm2
The section is rectangular, 300 wide and 650 mm deep. It is simply supportedspanning
12 m with dead load equal to self weight and a live load of 6 kN/m (unfactored). The
prestress force is applied at the centroid.
x=h/2
A = 300650
= 195 000 mm2 h
I = 3006503/12
= 6866106 mm4
Section modulus for the top fibre, Zt, is I/x. For a rectangular section 650 mm deep, the
centroid is at the centre and this is:
(some people use the formula for rectangular sections, Zt = bh2/6 which gives the same
answer).
23 P.Senapati
Prestressed Concrete
B.Tech,
The only applied loading at transfer is the self weight which is (density of concrete)
(area). Hence:
wl2/8
The total loading at SLS is this plus the imposed loading, i.e.:
The prestress causes an axial stress of P/A = 2500103 / 195 000 = 12.8 N/mm2:
24 P.Senapati
Prestressed Concrete
B.Tech,
12.8
At transfer, the stress due to prestress applies and, after the beam is lifted, the stress
due to self weight. The self weight moment at the centre generates a top stress of:
+ =
-4.2 8.6 ✓
At SLS, the prestress has reduced by 20%. The top and bottom stresses due to applied
load (Ms) are 195.8106/21.12106 = 9.3 N/mm2. Hence the SLS check is:
+ =
-9.3 0.9 ✓
As per the previous example, but the prestress force is P = 1500 kN at 100 mm below
the centroid.
P P
0.1m
P P
0.1P 0.1P
7.7
26 P.Senapati
Prestressed Concrete
B.Tech,
-7.1
+
7.1
As the moment is hog, the stress at the top is tension, i.e., negative. Similarly the
stress at the bottom fibre is +7.1
0.6
Hence the total distribution of stress due to PS is:
+ =
27 P.Senapati
Prestressed Concrete
B.Tech,
At SLS, the prestress has reduced by 20% (both the P/A and the Pe/Z components are
reduced by 20% as P has reduced by that amount). The stress distribution due to applied
load is as for Example 1. Hence the SLS check is:
11.8 -9.3
2.5 ✓
28 P.Senapati
Prestressed Concrete
B.Tech,
3.1 Basis
Sign Convention
In order to derive equations that enable design, we maintain a rigid sign convention:
• Moment:
Positive sag;
• Eccentricity of prestress:
Positive above centroid;
• Section Modulus:
Negative for the bottom of the member;
• Stress:
Positive compression.
P Pe MC
A Zt Zt t
+
+ + + =
+
P Pe MC b
A Zb Zb
29 P.Senapati
Prestressed Concrete
B.Tech,
P Pe MC
= + +
Top fibre:
t
A Zt Zt
P Pe MC
Bottom fibre: = + +
b
A Zb Zb
and;
• the Pe Z term is negative for Z t since Zt is positive and e is negative and the
Governing Inequalities
Given the rigid sign convention and the allowable stresses in the concrete, and noting
that the losses are to be taken into account, the stresses are limited as:
Transfer
Top fibre – stress must be bigger than the minimum allowable tensile stress:
t ftt
P Pe M t (1)
+ + ftt
A Zt Zt
30 P.Senapati
Prestressed Concrete
B.Tech,
Bottom fibre – stress must be less than the maximum allowable compressive stress:
31 P.Senapati
Prestressed Concrete
B.Tech,
b ftc
P Pe M t (2)
+ + ftc
A Zb Zb
Service
Top fibre – stress must be less than the maximum allowable compressive stress:
t fsc
P Pe M s (3)
+ + f
sc
A Zt Zt
Bottom fibre – stress must be bigger than the minimum allowable tensile stress:
b fst
P Pe M s (4)
+ + f
st
A Z b Zb
32 P.Senapati
Prestressed Concrete
B.Tech,
Top Fibre
The top fibre stresses must meet the criteria of equations (1) and (3). Hence, from
equation (1):
P Pe Mt
+ + ftt
A Zt Zt
P Pe Mt f
+ +
A Z tt
t
Zt
P Pe
− A + Z Mt
+ − ftt
t Z t
P Pe M P Pe Mt
+ + s
−
+ + f − f
A Z Z A Z Z sc tt
t t t t
Ms Mt
− f − f
sc tt
Zt Zt
Hence:
33 P.Senapati
Prestressed Concrete
B.Tech,
M −
t
(5)
f sc tt
34 P.Senapati
Prestressed Concrete
B.Tech,
Bottom Fibre
The bottom fibre stresses must meet equations (2) and (4). Thus, from equation (2):
P Pe Mt
+ + ftc
A Zb Zb
P Pe
+ t f
M
+
tc
A Z b Z b
P + Pe
− A Z Mt
+ − ftc
b Zb
P Pe M P Pe Mt
+ + s
−
+ + f − f
A Z Z A Z Z st tc
b b b b
Ms Mt
− f − f
st tc
Zb Zb
Hence:
M −
(6)
ftc − fst
b
Note that in these developments the transfer moment is required. However, this is a
function of the self weight of the section which is unknown at this point. Therefore a
trial section or a reasonable self weight must be assumed initially and then checked
once a section has been decided upon giving the actual Zt and Zb values.
35 P.Senapati
Prestressed Concrete
B.Tech,
Example
Problem
The single-span, simply-supported beam shown below carried the loads as shown.
Taking the losses to be 25% and:
• permissible tensile stresses are 2.5 N/mm2 at transfer and 2.0 N/mm2 in
service;
• permissible compressive stresses are 20 N/mm2 at transfer and at service.
Determine an appropriate rectangular section for the member taking the density of
prestressed concrete to be 25 kN/m3.
Solution
We will check the requirements at the critical section which is at mid-span. To
determine an approximate initial transfer moment, M t , we estimate the section depth
based on a span depth ratio of, say, 15:
9000
d = = 600 mm
trial
15
Try this with a width of 250 mm, which is a practical minimum. Hence, the sefl
weight load is:
36 P.Senapati
Prestressed Concrete
B.Tech,
wL2 3.75 92
Mt = = = 38 kNm
8 8
Ms = = = 291 kNm
8 8
Ms −Mt
Zt
f sc − f tt
291 − 0.75 38
Zt
20 − 0.75(−2.5)
Zt 12.0 106 mm3
M −M
Z b sf − f t
tc st
291 − 0.75 38
Zb
0.75(20) − (−2.0)
Zb 15.4 106 mm3
37 P.Senapati
Prestressed Concrete
B.Tech,
Z = Z and so the requirement for Zb
If the section is to be rectangular, then b t
governs:
bh 2
Z= 15.4 106
6
250h2
15.4 106
6
6 (15.4 106 )
h
250
h 609 mm
Note that this changes the self weight and so the calculations need to be performed
again to verify that the section is adequate. However, the increase in self weight is
offset by the larger section depth and hence larger section modulii which helps reduce
stresses. These two effects just about cancel each other out.
Verify This
38 P.Senapati
Prestressed Concrete
B.Tech,
Taking the governing equation for tensile stress at transfer, equation (1), we have:
P Pe Mt
+ + ftt
A Zt Zt
1
P + e Mt
f −
A Z tt
t Zt
Zt
ftt − M t since e Z is negative
P
1 A + e Zt
t
1
t
P ftt − M t Z t
Hence:
1 1 Zt 1A
f −M Z
P ftt − M t Z t
(7)
tt t t
This is a linear equation in 1 P and e. Therefore a plot of these two quantities will give
a region that is acceptable and a region that is not acceptable, according to the
inequality.
39 P.Senapati
Prestressed Concrete
B.Tech,
40 P.Senapati
Prestressed Concrete
B.Tech,
1
P + e Mt
f −
A Z tc
b Zb
1 1A
1 Zb
Z b f Z b
(8)
ftc t tc t
Another linear equation which gives the feasible region graphed as:
41 P.Senapati
Prestressed Concrete
B.Tech,
1
P + e Ms
f −
A Z sc
t Zt
1 Zt A
Z t Z t
(9)
f sc s f sc s
This equation can again be graphed to show the feasible region. However, this line can
have a positive or negative slope. When the slope is negative, 1 P must be under the
line; when the slope is positive, 1 P must be over the line. A simple way to
remember this is that the origin is always not feasible. Both possible graphs are:
42 P.Senapati
Prestressed Concrete
B.Tech,
43 P.Senapati
Prestressed Concrete
B.Tech,
Lastly, we have equation (4) which governs for tension at the bottom fibre during
service. This gives:
1
P + e Ms
f −
A Z st
b Zb
Which gives:
1 Zb A
Z b f Z b
(10)
f st st
44 P.Senapati
Prestressed Concrete
B.Tech,
Magnel Diagram
A Magnel Diagram is a plot of the four lines associated with the limits on stress. As
can be seen, when these four equations are plotted, a feasible region is found in which
points of 1 P and e simultaneously satisfy all four equations. Any such point then
satisfies all four stress limits.
Added to the basic diagram is the maximum possible eccentricity – governed by the
depth of the section minus cover and ordinary reinforcement – along with the
maximum and minimum allowable prestressing forces. For economy we usually try
to use a prestressing force close to the minimum.
The geometric quantities Zt A and Zb A are known as the upper and lower kerns
45 P.Senapati
Prestressed Concrete
B.Tech,
Example
Problem
A beam, 200 mm wide × 350 mm deep spans 10 m and carries 3 kN/m live load in
addition to its dead weight. The concrete is grade 40 and the prestress is transferred at
32 N/mm2 cube strength. Take prestress losses to be 20%. The member is to be a Class
1 member.
Draw the Magnel diagram for the mid-span section and determine an economic
prestressing force and its corresponding eccentricity.
Solution
The self weight is:
wsw = 25(0.2 0.35) = 1.75 kN/m
Ms = = = 59.4 kNm
8 8
The allowable stresses are, for a Class 1 member, from the previous table:
Hence:
1 1 4.083106 1 70 103
P
−6.37 e + −6.37
106
−0.0385e − 2.243
P
47 P.Senapati
Prestressed Concrete
B.Tech,
Hence:
48 P.Senapati
Prestressed Concrete
B.Tech,
1 1 −4.083106 1 70 103
P
21.37 e + 21.37
106
−0.0115e + 0.668
P
Hence:
1 0.8 4.083106 0.8 70 103
−1.24 e + −1.24
P
106
−0.158e − 9.21
P
Hence:
49 P.Senapati
Prestressed Concrete
B.Tech,
Notice that the 106 has been brought to the left so that we are working with larger
numbers on the right hand sides. To plot these lines, note that the vertical intercepts
are known and the x-axis values are also known to be:
50 P.Senapati
Prestressed Concrete
B.Tech,
−Z t −4.083106
= = −58.33 mm
A 70 103
−Z b − ( −4.083106 )
= = +58.33 mm
A 70 10 3
We plot the lines using these sets of points on each of the axes:
ftt
106/P (106/N)
10 ftc
fsc
8
fst
6
0
-150 -100 -50 0 50 100 150
-2
Eccentricity (mm)
-4
-6
-8
-10
51 P.Senapati
Prestressed Concrete
B.Tech,
ftt
106/P (106/N)
3 ftc
fsc
fst
2.5
1.5
0.5
Eccentricity (mm)
0
-150 -100 -50 0 50 100 150
So from this figure, the minimum prestressing is the highest point in the region (or
maximum y-axis value) permissible, which is about 2.4. Hence:
106
= 2.4
P
106
P=
2.4
= 416 103 N
= 416 kN
Obviously these values can be worked out algebraically, however such exactitude is
not necessary as prestress can only be applied in multiples of tendon force and
eccentricities are to the nearest 10 mm practically.
52 P.Senapati
Prestressed Concrete
B.Tech,
Thus far we have established an appropriate section and chosen a value for P, which
remains essentially constant along the length of the span. We have also found a value
for the eccentricity at the critical location.
Since the moments change along the length of a beam, we must change some aspect of
the prestress also. The only remaining variable is the eccentricity. As we wish to limit
possible tensile stresses, we only examine equations (1) and (4) correspondingto
tension on the top at transfer and tension on the bottom in service.
P Pe Mt
+ + ftt
A Zt Zt
Zt ftt Zt M t
e
P − A+ P
Zt Zt ftt − M t
elower − + (11)
A P
53 P.Senapati
Prestressed Concrete
B.Tech,
P Pe M s
+ + f st
A Z b Zb
e b st − Zb + M s
Zf
P A P
Zb Zb fst − M s
eupper − + (12)
A P
Since the upper and lower kerns (the Zt A and Zb A quantities) are constant for
constant geometry, and since P is also constant, it can be seen that the cable limits
follow the same profile as the bending moment diagrams at transfer and in service.
54 P.Senapati
Prestressed Concrete
B.Tech,
Example
Problem
For the beam of the previous example, sketch the upper and lower eccentricities
given a prestress of 450 kN.
Solution
In the previous example, the kerns were found to be
−Z t
= −58.33 mm
A
−Zb = +58.33 mm
A
=−
Zt Zt ftt − M t
e +
lower
A P
−4.083 − M t , x
= −58.33 +
450
M
= −58.33 −1.02 − t , x
450
M
= −59.35 − t ,x
450
55 P.Senapati
Prestressed Concrete
B.Tech,
Zb Zb fst − M s
eupper = − +
A P
0−M
= 58.33 + s,x
0.8 450
M
= 58.33 − s , x
360
Knowing the values of the bending moments at positions along the beam, we can now
plot the eccentricity limits:
200
150
100
50
0
0.00 2.00 4.00 6.00 8.00 10.00
Distance Along Beam (m)
In this figure the upper and lower eccentricities are very close at the critical section.
This is because the chosen prestress is very close to the minimum possible from the
permissible region. A higher prestress would give ‘looser’ limits.
56 P.Senapati
Prestressed Concrete
B.Tech,
Debonding
Notice from the eccentricity limits of the previous example that a straight cable/tendon
profile will not work. Yet we know from the discussion on factory precasting of
prestressed sections that straight tendons are preferable.
By changing the prestress force along the length of the beam, we can find a solution
to this problem. From the previous example the new eccentricity limits are:
200
Distance from Soffit (mm)
150
100
50
0
0.00 2.00 4.00 6.00 8.00 10.00
Distance Along Beam (m)
Note that it appears that there remains a problem at the ends of the beam. However, the
cable force gradually increases in reality due to the transmission zone (i.e. the bond
between the tendon and concrete). Hence the stresses will be acceptable in this zone
also.
57 P.Senapati
Prestressed Concrete
B.Tech,
700
600
500
Prestress (kN)
400
300
200
100
0
0.00 2.00 4.00 6.00 8.00 10.00
Distance Along Beam (m)
Note that the maximum prestress has been increased from 450 kN to 600 kN. Even
thought he extra strand is an added expense; it is offset by the constructability of the
member.
Note that the prestress steps up in units of 200 kN at two points. Imagine there to be 3
tendons acting, each of 200 kN prestress:
• From 0 to 1.5 m only 1 tendon is to act;
• From 1.5 to 3 m 2 tendons are to act;
• From 3 to 5 m all 3 tendons are to act
(Note that the prestress is symmetrical.)
58 P.Senapati
Prestressed Concrete
B.Tech,
In a factory setting, all 3 tendons will be present and yet some are not to act.
Therefore the bond between the concrete and tendon is broken by using plastic tubing
over the required length. Hence for our beam, the layout will look like:
Briefly then for post-tensioned members in general, the section properties, the
bending moments, and the prestress all may change along the length of a member:
Mt and Ms
Mt and Ms
Hogging
Sagging
Mt = Ms = 0
In such beams, the governing stress limits must be checked at ‘every’ point along the
length of the beam.
59 P.Senapati
Prestressed Concrete
B.Tech,
4. Prestressing Losses
• After-transfer losses are the difference between the transfer force, P and the force
at SLS, P = P .
s t
Notation
fc = stress in concrete;
= strain;
sh = strain in concrete due to shrinkage;
= creep strain in concrete an infinite time after prestressing at SLS;
60 P.Senapati
Prestressed Concrete
B.Tech,
= creep strain per unit of sustained stress.
61 P.Senapati
Prestressed Concrete
B.Tech,
In pre-tensioning, the strands are stressed before the concrete is cast. Therefore, after
jacking ( Pjack ) has been applied, at a level y, the concrete is subjected to the stress:
Pjack ( P e) y
jack M y
fc, y = + + o
Ag Ig Ig
At the level of the strands, y = e . Hence, the stress in the concrete at that level is:
P P e2 Me
f c,e = jack
+ jack
+ o
Ag Ig Ig
And the concrete at the level of the strands has a strain of:
fc,e
c,e =
Ec
Since the strands are bonded to the concrete, they undergo a loss of strain of the same
amount, c,e , with associated stress and force losses of E p c,e and Ap E p c,e . Hence:
AE P P e2 M e
P = E
A + I + It
p p jack jack
c g g g
The concrete never feels the full jacking force since the strands shorten as the
62 P.Senapati
Prestressed Concrete
B.Tech,
concrete strains. Hence, elastic shortening loss in pre-tensioning is ‘before-transfer’.
63 P.Senapati
Prestressed Concrete
B.Tech,
2. Shrinkage Loss
Concrete shrinks as it sets and for a period afterwards. The amount of shrinkage
depends on the humidity and the surface area to volume ratio. Once again, as the strands
are bonded to the concrete they undergo the same strain. Hence the loss of prestress is:
P = A E
sh p p sh
3. Relaxation Loss
When maintained at a constant strain, prestressing strand gradually loses its stress with
time (like a guitar going out of tune). It is due to a realignment of the steel fibres and is
the same phenomenon as creep. Depending on the quality of the steel, relaxation losses
can vary in the range of 3% to 8%.
Stress
= constant
time
Relaxation is ‘after-transfer’.
64 P.Senapati
Prestressed Concrete
B.Tech,
4. Creep Loss
Creep is the ongoing increase in strain with time, when stress is kept constant:
Strain
= constant
time
Creep causes a strain in the concrete adjacent to the strands and over a long time is:
= f c,e
The creep factor depends on a number of things such as concrete quality and its
age when loaded. Thus the strands slacken as before, and the loss of force is:
P =AE
creep p p
= Ap E p f c,e
P Pe 2 M e
= A E t + t + perm
p p
Ag Ig I g
M perm is the moment due to the permanent loads such as the prestress, dead load and
superimposed dead loads such as such as parapets and road pavement). As creep loss
contributes to , an exact calculation is iterative. Creep is long term, hence it is an
‘after-transfer’ loss.
65 P.Senapati
Prestressed Concrete
B.Tech,
This loss only occurs in post-tensioning when there is more than one tendon.
Two Tendons
As a simple example, take the following beam with two tendons:
Tendon 1 is stressed first. The operator applies prestress until the gauge indicates the
required prestress force is applied. The beam shortens during this process but this is
compensated for, as it is jacked until the required prestress force is applied. Hence there
is no elastic shortening loss to be allowed for at this stage.
Tendon 1 is anchored and Tendon 2 is stressed. This causes strain at the level of Tendon
1, resulting in a prestress loss in Tendon 1. The stress due to Tendon 2 is:
P2 ( P2e2 ) y
fc ,2 = +
Ag Ig
Note that the actual properties are approximated with the gross properties, Ag and I g .
The strain due to the stressing of Tendon 2, in the concrete adjacent to Tendon 1, is:
66 P.Senapati
Prestressed Concrete
B.Tech,
1 P ( P2e2 ) e1
c,2 = +
2
Ec Ag I g
This is the amount of strain lost in Tendon 1. Hence the loss of prestress force is:
P = Ap1 E p P + ( P2 e2 ) e1
2 2
Ec Ag Ig
The stressing of Tendon 2 does not cause any losses in Tendon 2 – it only causes
losses in tendons that have already been anchored.
Multiple Tendons
Similar calculations can be made for any arrangement of tendons. For 4 tendons:
1. stressing the first tendon does not cause any losses;
2. stressing the 2nd causes a loss in the 1st;
3. stressing the 3rd causes losses in the 1st and 2nd;
4. stressing the 4th causes losses in the 1st, 2nd and 3rd.
Hence the first tendon has losses due to the stressing of Tendons 2, 3 and 4, the
second due to the stressing of 3 and 4 and the third due to the stressing of 4 giving:
3 4
2 3 4
2−4
Ec Ag Ig Ec Ag Ig
Ap 3 E p P ( P4e4 ) e3
+ +
4
Ec Ag Ig
2. Shrinkage Loss
3. Relaxation Loss
4. Creep Loss
When the jacking force is applied, there is a friction between the tendon and the duct
that prevents the interior parts of the beam/slab from feeling the full force:
Pjack
P = P −P
fric jack l
= Pjack (1 − e− )
68 P.Senapati
Prestressed Concrete
B.Tech,
where is the aggregate change in angle from the jack (in radians) (the sum of the
absolute values of each change in angle) and is the roughness (friction) coefficient.
Pjack
P1 = Pjacke -
Dead
Jack
Anchor
2 C
Pjack
1 3
A B
At A: loss = Pjack (1 − e− ) 1
At B: loss = Pjack (1 − e− ( + ) )
1 2
At C: loss = Pjack (1 − e− ( + + ) )
1 2 3
Friction curvature loss happens between the jack and a-section. Therefore the section
never feels the full jacking force and this loss is ‘before transfer’.
69 P.Senapati
Prestressed Concrete
B.Tech,
This loss is due to ‘unintentional variation of the duct from the prescribed profile’:
wobbly duct
tendon
friction
This loss increases with distance from the jack and is given by:
P =P (1 − e )
− kx
wobble jack
70 P.Senapati
Prestressed Concrete
B.Tech,
7. Draw-In Loss
Anchors consist of wedges that ‘draw in’ when the jack ceases to be applied:
wedges wedge
draw in
strand
Jack
The draw in of the wedges can be up to 10 mm but the loss is generally local:
Force
Friction losses
Pjack (curvature + wobble)
Draw in losses are not transmitted more than about 5-10 m from the live anchor.
Formulas are available which give the extent and magnitude of the draw in loss.
71 P.Senapati
Prestressed Concrete
B.Tech,
The following diagram shows the strain diagram at three stages of loading:
Stage 1
This is the strain diagram at transfer. The strain in the concrete at steel level is
compressive, with magnitude of:
1
= Pt Pe2
+
E A I
ct
c
72 P.Senapati
Prestressed Concrete
B.Tech,
f
f pt = Pt pt = Ept
A
p p
Stage 2
The applied moment is sufficient to decompress the concrete at the steel level.Provided
there is a bond between the steel and concrete, the change in strain in the prestressing
steel is equal to that of the concrete at the steel level. Hence the strain in the prestressing
steel is now + . pt ct
Stage 3
This is the strain diagram at the ultimate load. The concrete strain at the steel level,
cpu , is related to the concrete strain at the top of the section by similar triangles:
= dp − x
cu
x
cpu
The change in strain in the prestressing steel is, by compatibility, the same as cpu .
Final
The final strain in the prestressing steel at ultimate load is thus:
pu = pt + ct + cpu
In this equation, it is only cpu that is not known. This can be obtained once a depth of
Example
Problem
Determine the ultimate moment capacity of the section shown. The steel tendon has a
transfer prestress of 1200 kN and the area of the strand is 1000 mm 2. The elastic
modulus for the prestressing steel is 195 kN/mm2 and the concrete is 45 N.
350 0.45fcu
cu
Fc
x
750 650 s = 0.9x
Ap
cpu Pu
Solution
The initial strain in the tendon due to the prestress is:
=
P
= 1200 103
t
= 0.00615
pt
Ep Ap (195 103 )(1000)
1
= Pt Pe2
+
E A I
ct
c
1 1200 103
=
74 P.Senapati
Prestressed Concrete
B.Tech,
75 P.Senapati
Prestressed Concrete
B.Tech,
650 − x
cpu = 0.0035
x
650 − x
pu = 0.00655 + 0.0035
x
P =AE
650 − x
u p p pu
At the correct depth to the neutral axis we will have horizontal equilibrium of forces,
Pu = Fc . Hence we iteratively try to find this value of x:
76 P.Senapati
Prestressed Concrete
B.Tech,
x Fc Pu Difference
M u = P uz
= Pu ( d p − 0.45x )
= 2005771 (650 − 0.45 314.4)
= 1020 kNm
77 P.Senapati
Prestressed Concrete
B.Tech,
Background
The shear design procedure for PSC is quite different from ordinary RC. It varies
significantly from code to code. However, there is one issue with PSC that can have a
significant influence on shear design. This is the vertical component of the prestress
force which can have a significant beneficial effect.
P sin
P
P
Bearing
Also, the shear capacity depends on whether or not the section has cracked under the
ultimate flexural moments at the section.
Note that nominal links are required in PSC members, similarly to ordinary
reinforced members.
78 P.Senapati
Prestressed Concrete
B.Tech,
V = 1 − 0.55 f ps v b d + M o V 0.1b d
fcu
f c v M
cr v
pu
In which:
M is the moment acting at the section;
V is the shear acting at the section;
M0 is the moment required to remove 0.8 of the compressive stress at the level of
the prestress:
I
M 0 = 0.8 f c,e
e
where:
Ps Pe 2
fc,e = + s
Ag Ig
f ps is the stress in the tendon at SLS;
f pu
is the ultimate tensile strength of the tendon;
79 P.Senapati
Prestressed Concrete
B.Tech,
A section is uncracked if the applied moment is less than M 0 . In such section, the
fcu
principal tensile stress in the web is limited to f t = 0.24 . Based on a Mohr’s
f t 2 + 0.8 ft fcp
Vco = 0.67bh +V
p
In which:
fcp is the compressive stress due to prestress at the centroidal axis:
Ps
fcp =
A
Vp is the vertical component of prestress at the section, resisting the applied shear;
80 P.Senapati
Prestressed Concrete
B.Tech,
Shear Design
Uncracked: Vc = Vco
Cracked: Vc = min Vco ,Vcr
Asv 0.4bv
=
sv 0.87 f yv
Asv V − Vc
=
sv 0.87 f yvdt
Where:
Asv is the link area;
sv is the link spacing;
f yv is the characteristic strength of the links;
dt is the depth to the furthest steel, ordinary or prestressed, from the compression
face.
81 P.Senapati
Prestressed Concrete
B.Tech,
Example
Problem
A Y-beam, as shown, has rib width of 200 mm and a depth of 1000
mm. Its area is 310 × 103 mm2 and its second moment of area is 36 ×
109 mm4. The area of prestressing steel is 1803 mm 2 which has
strength of 1750 N/mm2 and is stressed to 60% of its strength in
service at an eccentricity of 290 mm. The concrete is grade 50.
Solution
First determine the following:
82 P.Senapati
Prestressed Concrete
B.Tech,
f ps
= 0.6 given
f pu
2
Ps Pe
fc,e = + s
Ag Ig
1893103 (189310 ) ( 290 )
3 2
= +
310 103 36 109
= 10.52 N/mm2
I
M 0 = 0.8 f c,e
e
= 36 109
0.8(10.52) 290
= 1046 kNm
0.79 100 A 0.33 400 0.25 f 0.33
v =
s
cu
1.25 bvd d 25
c
=
1.25 200 790 790 25
= 0.78 N/mm2
Hence:
V = 1 − 0.55 f ps v b d + M o V 0.1b d
fcu
f c v M
cr v
pu
83 P.Senapati
Prestressed Concrete
B.Tech,
The section is uncracked since M M and so the design shear strength is 547.3 kN
0
which is greater than the applied 400 kN. Therefore, use nominal links.
84 P.Senapati