OT(EST)
OT(EST)
NOTE : Attempt any 05 questions with legible handwriting and write answers of subparts of each
question in sequence with full justifications to support the answer.
1. (a) XYZ enterprises is having four plants that are manufacturing cars and are located at different locations.
The cars are being supplied from plant to three distribution centers and vary in transportation cost. The
transportation cost from each plant to each distribution center is given below: [1+4]
D1 D2 D3 Availability
P1 1 2 5 30
P lant P2 9 7 8 40
P3 4 5 2 20
P4 3 5 4 60
Requirement 40 50 60
(i) Find the initial BFS for the above transportation problem using Least Cost Method (LCM).
(ii) Using above initial BFS, calculate the Optimal transportation cost using UV-Method (Take u1 = 0).
(b) Solve the problem using Dual Simplex Method [3]
2. (a) Consider the following simplex tableau of a linear programming problem (maximization) at some iteration:
State all possible values/range of A, B, C, D, and E in each of the following so that the given statements
are true:
(a) The current solution is optimal but infeasible.
(b) The current solution is feasible but not optimal and the objective function value can be increased by
replacing x3 with x2 . [4]
(b) Perform two iterations of Steepest descent search method to minimize [4]
1 2
f (x1 , x2 ) = x + x22
2 1
with starting point X0 = (x1 , x2 ) = (2, 2).
3. (a) Determine how jobs should be assigned to machine when maximum time taken by a machine to do a job
is given in following table. [6]
Job
J1 J2 J3 J4 J5
M1 40 40 35 25 50
Machine M2 42 30 16 25 27
M3 50 48 40 60 50
M4 20 19 20 18 25
M5 58 60 59 55 53
(b) Find the values/range of α and β such that the given solution is optimal. (While checking the optimality,
take u1 = 0 for source 1) [2]
D-1 D-2 D-3 Supply
Source 1 4 α 9 50
20 30
Source 2 β 7 8 60
10 30 20
Demand 30 30 50
4. (a) Consider the following project with crash and normal durations as well as cost involved.
Activity Normal time (Weeks) Normal Cost (In $.) Crash Time (Weeks) Crash Cost (In $.)
1-2 4 130 1 220
1-3 3 130 1 150
1-4 3 200 1 210
2-5 5 100 2 190
3-6 2 50 1 80
4-6 10 150 9 180
5-6 7 200 5 250
(i) Determine the critical path, normal duration and normal cost of the project.
(ii) Determine the optimal cost of project duration if it is to be reduced by 2 Weeks. [3+2]
(b) Solve the Multi-objective Programming Problem: [3]
f (x1 , x2 ) = ex1 x2 + x2 .
(b) Find the extreme values of f (x1 , x2 ) = −2x21 + 4x1 x2 − 4x22 + 4x1 + 4x2 + 10, and hence find maxima or
minima of given function. [4]
————END———–
The Answer-sheets will be shown on June 06, 2024. The time & venue details will be added on LMS.