Manpower and Equipment Histogram

The document outlines the project timeline and manpower requirements for the design and build of the Environmental and Radiation Laboratories under contract number C2024/30. It includes a detailed histogram of manpower allocation from August 2024 to October 2026, indicating a gradual increase in manpower over the project duration. Additionally, it presents equipment requirements and projections for the same period.

Uploaded by

qaqc-engr-farley
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

Manpower and Equipment Histogram

The document outlines the project timeline and manpower requirements for the design and build of the Environmental and Radiation Laboratories under contract number C2024/30. It includes a detailed histogram of manpower allocation from August 2024 to October 2026, indicating a gradual increase in manpower over the project duration. Additionally, it presents equipment requirements and projections for the same period.

Uploaded by

qaqc-engr-farley
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT: DESIGN AND BUILD OF THE

CONTRACT NUMBER : C202

EQUIP

MONTH Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25


MANPOWER 3 3 3 3 3 4 5 5

30

25

20
MANPOWER in Number

15

10

5 5 5
5 4
3 3 3 3 3

0
Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25
GN AND BUILD OF THE ENVIRONMENTAL AND RADIATION LABORATORIES
TRACT NUMBER : C2024/30 PROJECT ID : BP 2023 C 025 S

EQUIPMENT HISTOGRAM

Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26
5 27 27 27 26 28 27 28 27 25

EQUIPMENT HISTOGRAM

28 28
27 27 27 27 27
26
25 25
24

5 5 5

Feb-25 Mar-25 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26

MONTH
DATE : 30 OCT 24

Feb-26 Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26


25 24 27 23 25 20 12 3 4

27

25 25 25
24
23

20

12

4
3

Jan-26 Feb-26 Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26
PROJECT: DESIGN AND BUILD OF THE ENVIRONMENTAL AND RADIATION LABORATORIES
CONTRACT NUMBER : C2024/30 PROJECT ID : BP 2023 C 025 S

DIRECT MANPOWER HISTOGRAM


DATE : 30 OCT 24

MONTH Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26
MANPOWER 16 17 16 17 17 26 26 26 36 85 91 227 227 256 267 369 379 383 382 389 389 384 381 382 288 56 32

DIRECT MANPOWER HISTOGRAM


450

400 389 389


383 382 384 381 382
379
369

350

300 288

267
MANPOWER in Number

256
250
227 227

200

150

100 91
85

56
50 36 32
26 26 26
16 17 16 17 17

0
Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26

MONTH