Determination of Concrete Setting Time Using Electrical
Determination of Concrete Setting Time Using Electrical
Resistivity Measurement
Zongjin Li1; Lianzhen Xiao, Ph.D.2; and Xiaosheng Wei3
Abstract: The hydration process of fresh concretes with different proportions was studied using electrical resistivity measurement. The
minimum point 共Pm兲 and the transition point 共Pt兲 were identified on the electrical resistivity development curves. The time tm at which Pm
Downloaded from ascelibrary.org by New York University on 02/12/15. Copyright ASCE. For personal use only; all rights reserved.
occurred, represented the time when the curve dropped to a minimum and before increasing as a result of the onset of hydration. The time
tt at which Pt occurred, marked the time when the kinetics of hydration transition changed from the setting to the hardening stage. To
evaluate the significance of tm and tt in terms of the setting process, they were compared to the initial setting time 共ti兲 and final setting time
共t f 兲 measured with the traditional penetration resistance method. The quantitative relationships between the setting time of concrete and
the electrical resistivity critical points were developed. The equations can be used to estimate the setting times of concrete as an alternative
method.
DOI: 10.1061/共ASCE兲0899-1561共2007兲19:5共423兲
CE Database subject headings: Concrete; Penetration resistance; Measurement; Electrical resistivity.
Introduction regular intervals. Moreover, the test results can be largely affected
by the skill of operators. For these reasons, there have been at-
Concrete setting time is a crucial parameter for construction tempts to use alternative techniques, such as the impact-echo
progress and concrete quality control. When the setting time is method 共Pessiki and Carino 1988兲 and ultrasonic measurement
known, the times of mixing, transporting, casting and finishing 共Ozturk et al. 1999; Subramaniam et al. 2005; Lee et al. 2004;
can be regulated and the effectiveness of various set-controlling Voigt et al. 2005兲 to determine the setting time for concretes. The
admixtures can be decided. Typically, the initial and final setting impact-echo method defines the setting time of concrete as the
time of concrete are measured by the penetration method that has condition when the wave velocity begins to increase. However, it
been standardized in ASTM C 403 共1995兲. ASTM C 403 defines is hard to be applied to early age concrete and is thus not practi-
two points as the initial setting time and the final setting time, cal. The ultrasonic method is based on the generation, transmis-
corresponding approximately to the point at which the concrete sion and reflection of mechanical waves in concrete. Preliminary
will no longer be plastic under compaction, and the concrete studies have shown good correlation between the measured wave
strength has increased to a value gain of about 0.7 MPa, respec- reflection factor and the hydration process. Electrical resistivity
tively. The initial and final setting of concrete are determined by measurement is another nondestructive technique for monitoring
the times at which the penetration resistance reaches 3.5 and the setting and hardening process of fresh concrete 共McCarter et
27.6 MPa, when a designated needle penetrates 25.4 mm into the al. 2003; Gu et al. 1994b; Gu and Beaudoin 1997; Tumidajski
mortar, which has been sieved from the fresh concrete. It is hard 2005; Li et al. 2003; Wei and Li 2005兲, and has the potential to
work to remove the mortar fraction through a 4.75 mm sieve from determine the setting time of concrete. The setting time of cement
fresh concrete, especially for concretes with poor fluidity. Addi- was studied with electrodes as early as the 1930s 共Michelsen
tionally, for concrete having a retarder incorporated it probably 1933兲. The retardation effect of setting due to the incorporation of
takes an operator more than 10 h to finish the test, working at superplasticizers, using impedance spectros, was observed by Gu
and Torrents 共Gu et al. 1994a; Torrents et al. 1998兲. The results
1 obtained from these alternative methods for the interpretation of
Professor, Dept. of Civil Engineering, The Hong Kong Univ. of
Science and Technology, Clear Water Bay, Kowloon, Hong Kong. the setting behavior mentioned above, were compared with the
E-mail: [email protected] conventional penetration method. However, no quantitative rela-
2
Visiting Scholar, Dept. of Civil Engineering, The Hong Kong Univ. tionship between the ultrasonic response or electrical response
of Science and Technology, Clear Water Bay, Kowloon, Hong Kong. and conventional setting time was proposed.
E-mail: [email protected] In this paper, the noncontacting electrical resistivity response
3
Associate Professor, Dept. of Civil Engineering, Huazhong Univ. of is used to determine the setting time of concrete, based on mini-
Science and Technology, 1037 Luoyu Rd., Wuhan, 430074, China. mum point 共Pm兲 and the transition point 共Pt兲 of a resistivity curve.
E-mail: [email protected] Meanwhile, the penetration resistance is measured as specified in
Note. Associate Editor: Carl Liu. Discussion open until October 1, ASTM C 403 as a parallel investigation. From comparison and
2007. Separate discussions must be submitted for individual papers. To
regression, quantified setting time equations are proposed as a
extend the closing date by one month, a written request must be filed with
the ASCE Managing Editor. The manuscript for this paper was submitted function of the critical points 共tm and tt兲 to determine the initial
for review and possible publication on September 13, 2005; approved on setting time and final setting time of concrete.
March 28, 2006. This paper is part of the Journal of Materials in Civil In summary, the scope of the current investigation is: 共1兲 to
Engineering, Vol. 19, No. 5, May 1, 2007. ©ASCE, ISSN 0899-1561/ measure concrete electrical resistivity using a noncontacting elec-
2007/5-423–427/$25.00. trical resistivity device; 共2兲 to obtain the critical points on the
Setting Time
The setting time of concrete was obtained by means of penetra-
tion resistance measurements, in accordance with ASTM C 403.
curve then becomes linear again with a much steeper slope than
that of the first part. There is a transition point 共Pt兲 for each mix
located at the maximum curvature of the transition region, de-
scribing the transition of fresh concrete from conditions of setting
to hardening, and indicating a gain in strength of the concrete.
The times of occurrence of transition point 共tt兲 for Mixes 1, 3, and
10 were 305 min 共5.08 h兲, 706 min 共11.77 h兲 and 462 min
共7.70 h兲 after mixing. Comparing Mixes 1 and 10, the higher
W / C ratio 共Mix 10兲 shows a later transition time, corresponding
to a later start of solidification. And comparing Mixes 1 and 3, the
incorporation of superplasticizer in Mix 3 leads to the longest
Fig. 2. Electrical resistivity response of concretes: 共a兲 minimum time to reach its transition point.
point Pm and three development periods on curves – t; 共b兲 transition The values of tm and tt of the all 11 mixes, are given in Table
point Pt on curves – t 共log scale兲 2. It can be seen that tm and tt are obviously related to the different
setting processes caused by W / C, incorporated admixtures or ce-
ment type. The experimentally observed changes in the electrical
development with time 共 – t兲 for the control concrete 共Mix 1兲, the response can be further analyzed. The electrical resistivity re-
concrete containing a superplasticizer 共Mix 3兲 and concrete with a sponse of concrete can be divided into three different develop-
higher water cement ratio 共Mix 10兲 are plotted in Figs. 2共a and b兲. ment periods based on Pm and Pt, as shown Fig. 2共a兲, and the
Fig. 2共a兲 shows the resistivity change with time up to 400 min characteristics of each period are described as follows.
and the critical points, Pm, are marked as solid dots on the curves. The dissolving period 共I兲 occurs from the start of mixing to
Fig. 2共b兲 shows the resistivity change up to 1,440 min on a point Pm. Bulk resistivity 共t兲 deceases largely due to the increase
logarithmic scale and the second critical points Pt, are identified of ions in the liquid phase during this period. After water is added
on the curves. to the cement, the dissolution of ions from the cement takes place
As shown in Fig. 2共a兲, the electrical resistivity response 共 – t兲 and mobile ions, such as potassium 共K+兲, sodium 共Na+兲, calcium
exhibits a minimum point, Pm, in the first stage after mixing. Pm 共Ca2+兲, hydroxyl ions 共OH−兲, sulfate 共SO2− 4 兲 are released. These
represents a maximum conducting point corresponding to each free mobile ions favor the conductivity of the matrix solution. The
mix, indicating the solution in the hydration system reaches satu- variable admixtures, the W / C, or the cement type can cause
ration with dissolution progress, suggesting the onset of hydra- changes in the ion concentration or composition of the liquid
tion. The occurrence times of the minimum point 共tm兲 for Mixes phase 共Li et al. 2003; Torrents et al. 1998; Wei and Li 2005兲. The
1, 3, and 10 were 20 min 共0.33 h兲, 56 min 共0.93 h兲, and 37 min time to reach the saturation point for each mix is therefore af-
共0.62 h兲, respectively. As compared to Mix 1, the higher W / C of fected by the W / C, the type and dosage of the admixture, and the
Mix 10 leads to a longer time to reach saturation, which agrees to cement type.
the results observed by Li et al. 共2003兲. Moreover, an obviously The setting period 共II兲 is from point Pm to the transition point
delayed Pm in Mix 3 shows the effect of the incorporation of a Pt. In this period, the electrical resistivity gradually increases with
superplasticizer. time, indicating a decrease in porosity and increase in tortuosity.
As shown in Fig. 2共b兲, the – t 共log scale兲 relationship of each The hydrate nuclei form from the saturated solution, consuming
mix exhibits a similar distinctive feature, dividing the curve into the ions in the solution and at the same time reducing the porosity.
three parts. The first part, at earlier ages, has a linear pattern with The hydration progress results in a percolation of the matrix, and
a very slight upward slope, and is followed by a transition region the fluid concrete then transits to a rigid state. From point Pm to a
in which the slope starts to increase in a curved manner. The time of about 2 h, for the control sample, the change in resistivity
mixing.
Hardening period 共III兲: This period commences from point Pt
onwards, which indicates a change in the rate of increase of 共t兲.
The hydration progress leads to the matrix having more tortuosity
and the resistivity continually increases with time. The reaction
rate decreases, controlled by ion-diffusion when the thicker hy-
drates on the cement particle surface form 共Mindess et al. 2003兲.
Lee, H. K., Lee, K. M., Kim, Y. H., Yim, H., and Bae, D. B. 共2004兲.
Fig. 4. Variation of setting time in the measured and calculated “Ultrasonic in-situ monitoring of setting process of high-performance
values concrete.” Cem. Concr. Res., 34共4兲, 631–640.
Li, Z., Wei, X., and Li, W. 共2003兲. “Preliminary interpretation of Portland
cement hydration process using resistivity measurements.” ACI Mater.
J., 100共3兲, 253–257.
McCarter, W. J., Chrisp, T. M., Starrs, G., and Blewett, J. 共2003兲. “Char-
considerable applications to assess the setting time and strength acterization and monitoring of cement-based systems using intrinsic
development trend and provide in situ information to determine electrical property measurements.” Cem. Concr. Res., 33共2兲, 197–206.
the demolding time and control quality. Michelsen, S. 共1933兲. “Beitrag zur bindezeit bsestimmung.” Zement,
22共3兲, 457–461.
Mindess, S., Young, J. F., and Darwin, D. 共2003兲. Concrete, 2nd Ed.,
Conclusions Prentice-Hall, Upper Saddle River, N.J.
Ozturk, T., Rapoport, J., Popovics, J. S., and Shah, S. P. 共1999兲. “Moni-
toring the setting and hardening of cement-based materials with ultra-
The following conclusions may be drawn from this study.
sound.” Concr. Sci. Eng., 1共2兲, 83–91.
1. Two critical points, Pm and Pt, are found on the electrical Pessiki, S. P., and Carino, N. J. 共1988兲. “Setting time and strength of
resistivity curve of fresh concrete. concrete using the impact-echo method.” ACI Mater. J., 85, 389–399.
2. The physical meaning of Pm is that it is the onset of hydra- Subramaniam, K. V., Lee, J., and Christensen, B. J. 共2005兲. “Monitoring
tion; and that of Pt is the gain of notable strength. The time the setting behavior of cementitious materials using one-sided ultra-
of occurrence of point Pt is linearly proportional to the final sonic measurement.” Cem. Concr. Res., 35共5兲, 850–857.
setting time. Torrents, J. M., Roncero, J., and Gettu, R. 共1998兲. “Utilization of imped-
3. The following two equations have been developed and can ance spectroscopy for studying the retardation effect of a superplasti-
be used to estimate the initial setting time and the final set- cizer on the setting of cement.” Cem. Concr. Res., 28共9兲, 1325–1333.
ting time for concrete mixes, respectively, ti = 1.8807tm Tumidajski, P. J. 共2005兲. “Relationship between resistivity, diffusivity and
microstructural descriptors for mortars with silica fume.” Cem. Concr.
+ 0.4429tt and t f = 0.9202tt + 0.2129.
Res., 35共7兲, 1262–1268.
Voigt, T., Ye, G., Sun, Z., Shah, S. P., and Van Breugel, K. 共2005兲. “Early
age microstructure of Portland cement mortar investigated by ultra-
sonic shear waves and numerical simulation.” Cem. Concr. Res.,
Acknowledgments 35共5兲, 858–866.
Wei, X., and Li, Z. 共2005兲. “Study on hydration of Portland cement with
The support from the Grants of HKUST 6272/03E and fly ash using electrical measurement.” Mater. Struct., 38共277兲, 411–
NSFC50578142 is gratefully acknowledged. 417.