Contract Closure and Review
Contract Closure and Review
MANAGEMENT
GUIDANCE NOTE ON PROCUREMENT
DECEMBER 2021
Abbreviationsvii
I. Introduction 1
Appendixes
Tra n s p a re n c y
Value for Money
The effective, efficient, and economic use of resources, which
requires an evaluation of relevant costs and benefits along with an
assessment of risks, nonprice attributes, and/or total cost of ownership
as appropriate
Fairness
Time
Time is an important element of VFM. When a project is delivered promptly or when a
process is completed rapidly, greater value is created for all stakeholders. For example, a
road project completed early provides economic benefit, security, or other value to the
community it serves. It increases the return on investment to the executing agency and
accelerates the project and payment cycle to the successful bidder. Likewise, a project
delivered late loses significant value.
Objective
This guidance note is intended to assist readers by elaborating on and explaining
ADB’s 2017 procurement policy and procurement regulations for borrowers
(including grant recipients).
This note identifies additional information for the reader to consider when applying ADB’s
procurement policy and procurement regulations to their circumstances.
Living Document
This guidance note is intended to be a living document and will be revised as required.
Be sure to check the ADB Business Center website for the latest version and updates,
https://www.adb.org/business/main.
The Reader
In many circumstances, readers are expected to use this guidance note in a manner unique
to their needs. For consistency throughout the suite of guidance notes, the following
assumption is made about the reader:
The reader is a professional involved in activities financed in whole or in part by an ADB loan
or grant, or by ADB-administered funds.
FAQs
Frequently asked questions, clarifications, examples, additional information, links to training,
and other useful resources will be made available on the ADB website.
Be sure to check the ADB Business Center website for more information,
https://www.adb.org/business/main.
In the event of any discrepancy between this guidance note and the procurement
regulations, the latter will prevail. The financing agreement governs the legal relationships
between the borrower and ADB. The rights and obligations between the borrower and the
provider of goods, works, or services are governed by the specific procurement document
issued by the borrower and by the contract signed between the borrower and the provider,
and not by this guidance note.
vii
ABBREVIATIONS
EXECUTIVE SUMMARY
Reduce Risk
• Anticipating what could go wrong, e.g., payment delays, right of access to
site.
• Putting in place mitigation measures to address any identified risks.
• Managing the closure of the project, ensuring that no pending issues or
obligations remain unaddressed.
1.1 The 2017 ADB procurement regulations recognize that one factor
contributing to achieving value for money (VFM) is effective contract
management. Contract management ensures that supplier, contractor, and/or
consultant deliverables are met as agreed under the contract.
1.3 This guidance note provides operational level guidance for borrowers,
through their executing and implementing agencies, on how contract management
should be applied in ADB-financed projects involving the procurement of goods,
works, and services.1
1.4 This guidance note assists users with contract management in the
procurement cycle as shown in Figure 1. The activities relating to the borrower’s
contract management are determined by decisions taken at the strategic
procurement planning stage and will later be implemented from contract award to
contract closure, to ensure that contract obligations are met and deliver VFM.
1
Borrowers, through their executing agencies, and any other party to a financing agreement shall
always act in accordance with the highest standard of ethics during any procurement process
(including contract management) subject to the procurement regulations and any use of funds,
resources, assets, and authority by such parties shall be in accordance with ADB’s Anticorruption
Guidelines and Integrity Principles and Guidelines (both as amended from time to time).
2 Contract Management
Country Partnership
Strategy
Country and Sector/Agency
Procurement Risk Assessment
y
Tran
Procurement Planning
Efficiency
sparency
Contract Management Project Procurement Risk
Contract Management Plan
CYCLE Assessment Rating,
Project Administration Manual
M alu e s
V
ne
s
o n fo r
ey Fa i r
Contract Award Bidding
Bidding Documents
Bid Evaluation
Evaluation Reports
Contract management
1.6 Figure 2 illustrates when the various contract management activities take
place throughout the project cycle.
1.7 This guidance note applies to contracts financed in whole or in part by ADB
loan or grant, or by ADB-administered funds, for the procurement of goods, works, or
services, including consulting services, to which the procurement regulations apply.2
2
In this guidance note, the term “Contractor” will be used to collectively designate a works
contractor, a supplier of goods, a consultant or other service provider. The terms “borrower” and
“employer” are used interchangeably.
Introduction 3
Supplier Meets
Requirements
Environmental
Probity
and Social
Benefits
Legislative Health
Compliance and Safety
2.3 Each of these benefits will impact on VFM, for two reasons:
3.1 Figure 4 describes the contract management process from the perspective
of the borrower, which comprises three stages: precontract award, contract
administration, and contract closure.3 Contract “implementation” describes the
contractor’s work within the contract and occurs concurrently with the borrower’s
stage of contract administration (i.e., the borrower administers the contract while
the contractor implements it).
A B C
Contract
Precontract Award Administration Contract Closure
3. Develop contract
3. Managing payment 3. Filing contract records
management plan
4. Managing changes
Reporting to ADB
3
The terms “contract management” and “contract administration” are sometimes
interchangeably used in the literature on management topics. To avoid ambiguity, in this
guidance note, contract management is used as encompassing all stages and activities aiming at
the overall goal of ensuring optimal contract outcomes. Contract administration designates one
stage of those activities focusing on the day-to-day interactions with the contractor as required
under the contract.
The Contract Management Process 7
3.2 These stages for the borrower follow a logical flow: the precontract award
stage is the design phase of contract management during which the strategy is defined;
the contract administration stage consists mainly in implementing this strategy by
performing a number of monitoring and control activities in interaction with the
contractor, starting from contract award; and the contract closure phase aims at
properly “exiting” the contract and drawing lessons for future projects. Each of these
stages is described below.
A. Pre-Contract Award
3.3 Contract management needs to be considered early in the procurement
process for it to be effective. Its starting point lies in Strategic Procurement Planning
stage which should be formulated early on between the project conceptualization
and project preparation stages.
3.4 Pre-contract award activities should include a risk assessment which will
translate, at contract level, some of the risks which were primarily identified at the
Country Partnership Strategy (CPS) stage through the Country/Sector Procurement
Risk Assessment (CSPRA) and later on, at the project conceptualization and
preparation phase through the Project Procurement Risk Assessment (PPRA)4,
which itself feeds into the risk assessment that is part of the strategic procurement
planning. Such risk assessment will lay the foundation of a contract strategy.
3.5 The contract strategy will then inform the contract management plan
(CMP) which will define activities and responsibilities to monitor the contractor’s
performance during contract implementation until contract closure. The CMP
shall be developed by the borrower at the time of preparation of the bidding
document. It shall subsequently be submitted to ADB for endorsement prior to
contract signature. It is a key tool of contract management which, during contract
implementation, should be updated on a monthly basis and be used to capture and
monitor all necessary information on physical progress, technical issues, financial
management, time management and other relevant aspects.
3.6 Many of these activities require the contractor and the borrower to
perform certain assigned tasks. Some of these tasks may have a cost implication to
the contractor and/or borrower, and many will need to be specified in the contract
to ensure that the responsibility is a contractual obligation. Therefore, contract
management arrangements need to be considered at the time of development of
the proposed contract to inform bidders of contractor’s obligations and costs.
3.7 To develop the contract and to prepare for its implementation, a risk
assessment should be conducted at an early stage of the procurement process
4
Further information on the general approach to risk management can be found in the Guidance
Note on Procurement Risk Framework. https://www.adb.org/sites/default/files/procurement-risk-
framework.pdf.
8 Contract Management
in the framework of the strategic procurement planning (SPP) stage, and more
particularly as part of the project procurement risk assessment (PPRA).
3.8 The first aspect of the risk assessment is to define a contract risk
allocation. This involves determining the best risk allocation between the borrower
and the contractor.5 The principle guiding this analysis should be that the party
in the best position to control and to manage the identified risk should bear
responsibility for that risk under the contract. A party being allocated a risk should
take all necessary preventive, mitigating, or corrective measures as deemed fit to
manage that risk, with the understanding that should the risk eventuate, this party
shall bear the financial consequences thereof (Box 1).
Box 1
Example of Contract Risk Allocation
The risks associated with the design of a complex water treatment plant, and
particularly the risk that the plant, once completed, be unfit for its intended purpose,
can be transferred to the contractor through the use of a design and build contract,
where the contractor holds ultimate responsibility for the design of the works based
on the employer’s requirements (preferably expressed in the form of performance
specifications). Under such contract, no specific design will be prescribed; instead,
the contract will stipulate a set of performance specifications that are to be achieved
by the facility (e.g. maximum energy consumption, maximum chemicals consumption,
plant production in m3/day, chemical contents, noise and odor levels, etc.). It will be
contractor’s responsibility to select the design most suited to meet these specifications,
to develop it and later to implement the works accordingly so that so that performance
of the facility conforms to the prescribed targets. This type of contract usually provides
for performance damages to which the contractor will be liable in case the prescribed
specifications are not met.
Source: Asian Development Bank.
3.9 This contract risk allocation should be based on a technical analysis and
a proper market analysis. Borrowers should, however, resist the temptation to
“dump” all (or most) allocated risks to the contractor. An unfair or unbalanced risk
allocation is likely to discourage competition, drive prices up, and lay the ground
for disputes during contract implementation—all circumstances being prejudicial
to obtaining VFM.
3.11 The second aspect of the risk assessment is intended to address the risks.
For the identified employer’s risks (e.g., delays in granting the contractor right of
5
This analysis may be fed by “high level” risks at country or sector level that are identified during
the project preparation phase (see the Guidance Note on Strategic Procurement Planning).
The Contract Management Process 9
access to the site, payment delays, etc.), an action plan needs to be prepared for their
mitigation (Box 2). For each risk identified, the action plan should define, for each risk
identified, preventive, mitigating, or corrective measures, and the party responsible
for implementing these measures along with a time frame. The borrower should be
aware of the contractor’s risks, even if he bears no responsibility towards such risks,
and monitor their potential impact on the project.
Box 2
Example of Employer’s Risk Management
In some countries, it is a requirement that a state-specialized body approve detailed designs
before any work is carried out. This issue may be of particular importance in a design and
build contract, since untimely approval is likely to delay the works and give rise to a claim by
the contractor. The borrower will thus have to determine a way to “manage” such risk, which
could for instance involve the appointment of an officer dedicated to follow-up the approval
process in liaison with the contractor and the state-specialized body.
Source: Asian Development Bank.
3.12 The consolidation of all such identified risks, including the associated
action plan, is usually referred to as the risk management plan (or contract
risk register). It should be managed throughout the contract implementation
period and updated as known risks change and new risks are identified. The risk
management plan is one component of the contract management plan.
3.15 Similarly to the risk assessment referred to above, the assessment of the
necessary human resources will be addressed during the strategic procurement
planning (SPP) stage, and more particularly as part of the project procurement risk
assessment (PPRA).
3.16 The borrower shall put in place a contract management team of the right
size and composition. This team may consist of a Project Management Unit (PMU)
or Project Implementation Unit (PIU) internal to the Implementation Agency. This
aspect is sometimes underestimated, with too much reliance on the works supervision
10 Contract Management
team on site. The size and composition of the borrower’s contract management
team should be commensurate to the scale and complexity of the project involved.
For example, an ordinary supply contract will not require the same resources as that
of a large-scale construction contract. The team should include skills in the relevant
technical field, contract management, and document administration (all the above
may be limited to one person for a small and/or simple project).
3.18 The borrower’s contract management team should have access to the
appropriate level of decision makers in their organization, so that relevant decisions
can be made promptly. Delays in making contract-related decisions have the
potential to greatly increase the cost and slow the completion of construction
projects (e.g., the approval of a small contract variation, if delayed, can lead to the
incurrence of substantial additional costs and time delays, as the contractor is not
authorized quickly enough to implement the action required).
3.21 The contract management plan (CMP) is the primary tool that manages
contractor performance. It is an internal document to the borrower and it is
not a contractual document. It comprises a set of documents, tables, graphs,
or flowcharts providing the relevant template that will be used to generate the
monthly project Progress Report with data from the site, designed to provide
all meaningful information on how the project is progressing. The CMP thus
constitutes the contract dashboard. It should enable the borrower to effectively
monitor the project, identify risks and take whatever mitigation or corrective
measures as may be required.
3.22 The CMP should be developed during the pre-contract award stage,
which will make it a useful tool that will inform the borrower of the characteristics
of the contract, the issues to look out for during the contract implementation
phase, and the measures against which contractor performance will be gauged.
3.24 For simple and low value contracts, the CMP may be limited to more
succinct items, which in accordance with the procurement regulations, may only
include the following:
3.25 For projects involving many contracts where it is not practical to have a
standalone CMP for each contract, it is suggested that one CMP can cover a group
of similar contracts of similar size. Individual CMPs ought to be prepared for large
contracts only. Executing agencies should engage with ADB in advance to discuss
the packaging of several contracts into a single contract management plan.
B. Contract Administration
6
Appendix 8, para 5, of the procurement regulations sets out the components that should be
included in any CMP for simple and lower-value contracts as well as for high-value, high-risk,
or complex contracts.
12 Contract Management
3.28 Contract administration is affected by the decisions that are taken early
during the project preparation phase (comprehensiveness of project documents,
choice of contract, formulation of project teams, robust short-listing and tender,
etc.) The borrower’s team must therefore be mindful of contract management
requirements from the start of project design and preparation.
Box 3
Example of Decisions and Actions Guided by Contract Management
• formally put the contractor on notice to increase mobilization and/or issuing instruction
to accelerate the rate of progress to preserve the targeted completion date,
• expedite the land acquisition process if still behind schedule,
• mobilize specialized contractors tasked with relocating utilities that may, if not timely
removed from the site, cause delays for the main contractor,
• require other contractors employed by the employer to revise their schedule if some
unforeseen factors will disrupt the way contractors are supposed to intervene on the site,
• if nothing can be undertaken to eliminate or even to mitigate adverse external factors
(e.g. climatic conditions, ground conditions, etc.), simply making sure that necessary
funding will be secured in due time to cope with the likely cost consequences thereof
(variations to be instructed by the engineer or claims from the contractor
Source: Asian Development Bank.
The Contract Management Process 13
1. Records Management
Box 4
Common Records to be Maintained through Records Management
• Key stakeholders
• Contract documents
• Insurance policies
• Bank guarantees and indemnities
• Permissions and approvals granted by the relevant authorities
• Plans and schedules
• Safety management plans
• Environmental management plans
• Variation schedules
• Project correspondence (in and out)
• Performance reviews (including contract performance reviews and reports)
• Meeting minutes
• Financial documents (interim payment certificates, invoices, purchase orders)
• Communications and claims and disputes
Source: Asian Development Bank.
2. Performance Management
3.35 For works contracts, the monthly progress report will provide the key data
to monitor progress. The monthly progress report, based on the template defined in
the CMP, will usually be prepared by the supervision engineer or other personnel of
the borrower (depending on the contract used), conducting regular site inspections
and tests (including tests on completion and, as applicable, tests after completion).
14 Contract Management
Progress reports will be based on the contractor’s own progress reports together
with other elements such as safeguard monitoring reports. The monthly progress
report will typically include, among other elements:7
7
If the borrower is using the Multilateral Development Bank Harmonized Edition (2010) of the
FIDIC Conditions of Contract for Construction, refer to sub-clause 4.21 (Progress Reports).
The Contract Management Process 15
3. Managing Payments
4. Managing Changes
3.40 The contract should describe the process for initiating and getting
approval for variations. Such provisions should specify the scope of the engineer
(or contract manager or contract)’s authority to approve changes depending on
value and significance (in terms of quality, cost, and timing), and how initiation and
implementation of approved changes will take place.
3.41 Contract variations will translate into a change in the quantity, nature or
sequence of the works, goods or services to be provided. They can be motivated by
the reassessment of the employer’s needs or as the response to unforeseen events
occurring at the site (e.g. discovery of unforeseeable ground conditions).
(i) assess the reasons for the variation, and whether this may show an
emerging or actual performance problem;
(ii) assess the impact of the variation on the contract deliverables;
(iii) determine the effect the variation will have on the overall contract
price and schedule; and
(iv) follow the terms and conditions stated in the contract for review and
approval of variations.
3.44 When a matter cannot be resolved amicably and does crystallize into a
dispute, the parties should carefully comply with the dispute resolution mechanism
set forth in the contract. ADB’s preference is that borrowers use commercial
16 Contract Management
arbitration. For works contracts and supply and installation contracts, prior to
referring the dispute to arbitration, the matter should first be referred to a dispute
adjudication board or adjudicator designed to permit a speedier time bound and
on- site dispute settlement.
C. Contract Closure
1. Contract Close Out
3.47 Aside from termination, a contract closes when both parties have
discharged all their obligations. Where the contract is completed under its terms
and conditions, contract closure begins with:
(i) (i) the borrower confirming internally that the specified contract
deliverables have been completed and that there are no outstanding
matters or issues that remain unresolved; and
(ii) the borrower confirming to the contractor that the contract is
completed, apart from any agreed-upon, ongoing warranties
(or guarantees if applicable).
3.48 After the parties agree that the contract has been completed, the closure
process (particularly for more complex works) typically requires the parties to:
(ix) record the date and details of the final inspection at the end of
the defect notification period and issuance of the performance
certificate (in accordance with the specific procedures provided for
in the contract);
(x) record the end of the retention and guarantee periods, and the date
of release of retention monies and/or guarantees;
(xi) handle warranties, indemnities, and insurance;
(xii) summarize any claims made against or received from the contractor
by the executing agency;
(xiii) record final contract payments, and reconcile all payments; and
(xiv) record any transfer of assets, asset verification, and disposals.
2. Post-Contract Review
3.49 Best practice contract closure includes a post-closure contract review and
reporting of the review findings to ADB, comprising the following items:
3.50 The last task that needs to be carried out is the retention and secure filing
and storage of contract documentation and records (in physical and digital form).8
Such records as the as-built documents may be necessary to allow future works to
be done either on or in interface with the project.
3.51 For projects under post review procedure by ADB, another reason to keep
proper filing and securing of records is due to ADB’s right to conduct audits up to
2 years after the project closing date.
8
Depending on the nature of the document (contract, invoice, minutes, etc.) and the jurisdiction,
the minimum retention period for such records may be between 1 and 30 years.
IV. Reporting to and Requesting
No-Objection from ADB
4.3 Monthly progress reports will be reviewed by ADB as part of the project
review missions. The areas of particular attention will be the following:
Box 5
Summary of Borrower’s Responsibilities
• Planning contract management during the precontract award stage and incorporating contract
management requirements into the draft contract
• Developing a CMP prior to contract award
• Submitting a completed CMP to ADB prior to contract signing
• Implementing the CMP, to ensure that contract performance is satisfactory, appropriate
stakeholders are informed, and all contract requirements are met
• Submitting quarterly performance reports to ADB during contract implementation
• Requesting ADB’s no-objection where any modification would individually or in aggregate
increase the original contract price by over 15% (for contracts subject to post review)
• Preparing and submitting postcontract closure performance report
Source: Asian Development Bank.
V. Resources for Further Review
5.1 The following resources may be consulted for further information related
to contract management:
P. Bailly et al. 2015. Procurement Principles and Management. 11th ed. UK: Pearson.
Corbett & Co. International Construction Lawyers. 2017. FIDIC 2017, A Practical
Legal Guide. Edinburg: Corbett & Co
Government of the United Kingdom, Guidance by the National Audit Office. 2016.
Good Practice Contract Management. London.
J. A. Huse. 2013. Understanding and Negotiating Turnkey and EPC Contracts. 3rd ed.
UK: Sweet & Maxwell.
A-V Jaeger and G-S Hök. 2010. FIDIC—A Guide for Practitioners. Heidelberg:
Springer.
K. Lysons and B. Farrington. 2016. Procurement & Supply Chain Management. 9th ed.
UK: Pearson.
P. Marsh. 1998. Study Guide: Project and Contract Management. UK: Chartered
Institute of Purchasing and Supply.
P. Marsh. 2000. Contracting for Engineering and Construction Projects. 5th ed. UK:
Routledge–Gower Publishing.
Appendix 1: Typical Contract
Management Issues
A1.1 Those with experience managing contracts will be aware of issues that
arise during the contract implementation phase from their own experience.
A nonexhaustive list of typical issues is given below as a prompt for consideration by
contract managers, and as inputs into the contract risk assessment. Risk mitigation
actions resulting from any of the issues identified in the risk assessment should be
included in the Risk Management Plan, which is part of the contract management
plan (CMP). The Manual on Contract Management has substantial information on
CMP, including a CMP template describing a contract’s contents, and suggests how
the collected information may be interpreted. However, this CMP template is not
a “one-size-fits-all” template and should be adapted to the needs of each contract
considering its size, risks, and complexity and capacity constraints of executing
agencies and/or implementing agencies.
OVERVIEW
A3.2 In 2017, the Asian Development Bank (ADB) adopted the new
Procurement Policy and the Procurement Regulations for ADB Borrowers,
which are intended to improve business processes and change procurement from
a rules- based to a principles-based approach.
9
The term “contractors” also includes suppliers of goods or providers of consultancy or
nonconsultancy services.
10
The term “borrowers” also includes the recipient of grants. It applies to sovereign as well as
nonsovereign operations.
26 Appendix 3
INTRODUCTION
A3.6 The Procurement Regulations for ADB Borrowers (henceforth Procurement
Regulations) requires that a CMP acceptable to ADB should be developed
during contract creation; thus, it must be prepared at the time of bidding
document preparation and must be completed by the time of contract signing.
The Procurement Regulations further recommend that the borrower monitor the
performance and progress of the contracts in accordance with the CMP, and to
provide timely reports to ADB.11
I.
What is A Contract Management Plan
and Why Use It?
A3.8 The contract management plan (CMP) is a key tool that captures and
monitors all necessary information on a project’s physical progress, technical issues,
financial management, time management, safeguards, gender, and other relevant
aspects. It is to be maintained on a monthly basis.
A3.9 In more concrete terms, the CMP is a set of tables, schedules, graphs, and
photographs providing the guidance on content, procedures, and format to be used
in generating monthly project progress reports the purpose of which is to provide
all relevant information showing how the project is progressing. The CMP thus
constitutes the contract dashboard. It enables the employer to effectively monitor
the project; identify risks; and take whatever mitigation, preventive, or corrective
measures as may be required.
A3.10 This manual provides a template for the CMP, describes its contents,
and suggests how the collected information may be interpreted. This template
was designed for use in works contracts (including Design and Build contracts
or Design– Build– Operate contracts), although it can be adapted as well for
consultancy or nonconsultancy services—to a lesser extent for supply contracts
due to the lesser interaction between the client and the supplier of goods.
11
See Appendix 8, paragraph 3 of the Procurement Regulations for ADB Borrowers.
12
The Guidance Note on Contract Management was issued as part as a series of guidance notes to
elaborate on the Procurement Regulations.
Appendix 3 27
A Precontract
Award B Contract
Administration C Contract
Closure
1. Develop risk assessment 1. Record management 1. Contract close-out
2. Develop contract 2. Performance 2. Post contract review
management strategy management
3. Develop contract 3. Managing payment 3. Filling contract records
management plan 4. Managing changes
5. Claim and dispute
management
Reporting to ADB
A3.13 The CMP should be based, among other elements, on the project
risk assessment relevant to the contract. Section 3 of the CMP template
(risk management plan) includes a risk management matrix that should be
monitored throughout contract implementation. The nature and type of risks
that should be incorporated in the risk management plan of the CMP should be
derived and cascaded from the risk analysis conducted at the time of the project
procurement risk analysis and strategic procurement planning analysis.
28 Appendix 3
A3.15 The Procurement Regulations further require that the CMP be submitted
to ADB for clearance “at the time the contract is signed”, which in practice will
be after the bid evaluation is completed, and before (or at the same time as)
contract award. It shall be reviewed by an ADB project officer from the operations
department, with the support of the Procurement, Portfolio and Financial
Management Department (PPFD) procurement specialist if needed.
A3.16 Once the CMP has been designed and approved and once the
contract becomes effective,13 all relevant project data should be collected to
generate the monthly progress report, thus providing the implementing agency
(as “the Employer”) with a tool to monitor the progress of the works or services;
in other words, “to manage the contract.”
A3.17 The responsibility for generating the progress report should normally be
incumbent upon the supervision consultant designated as the “Project Manager”
or “Engineer” (hereinafter referred to as the Engineer). A primary source of
information should be the contractor’s progress report, which is usually submitted
on a monthly basis (Figure A3.2). Another source of information is the monitoring
reports prepared by the safeguard specialists or gender and/or social specialists who
are usually part of the supervision consultant’s team. These reports will cover the
monitoring of the environment management plan, including the health and safety
monitoring reports, and the social safeguards. The supervision consultant may also
have to collect information from the executing agency or implementing agency
with respect to obligations that are incumbent upon “the Client” or “the Employer,”
such as securing certain permits, processing the land acquisition and resettlement
plan, moving some utilities, etc.
13
Works contracts usually become effective upon the issuance of the letter of acceptance.
However, in some jurisdictions, the actual signature of a contract agreement may be required for
the contract to become effective.
Appendix 3 29
A3.19 The CMP and the monthly progress reports generated therefrom
should be a primary tool in the hand of the project management office (PMO)
or project implementation unit (PIU), or other entity in charge of the project
30 Appendix 3
within the implementing agency. The progress report, which is usually updated
monthly, provides all relevant information on how the project is progressing and
where potential risks may be. It thus informs any decision needed to be taken to
implement mitigating, preventive, or corrective measures.
A3.20 For instance, the lack of physical progress (lag between planned and
actual progress) reported in the monthly progress report may be ascribable to
several factors:
(i) the Contractor, because (for instance) it did not mobilize sufficient
resources, or because these resources are not properly used for the
contract;
(ii) the Employer, because (for instance) unencumbered access to site
could not be granted to the Contractor or because other contractors
employed by the employer hamper progress; and
(iii) other factors external to the Contractor or the Employer, such as
exceptionally adverse climatic conditions or unforeseeable ground
conditions delaying the contractor.
A3.21 Irrespective of how the contract allocates risks and which party should
eventually be liable for the consequences of such risks (in terms of time and cost), the
implementing agency should proactively manage such risks, and where possible and
relevant, take preventive or corrective measures. This may for instance consist of
A3.23 The use of the CMP and the monthly progress reports generated
therefrom should not however be seen as creating new and additional reporting
requirements for the executing agency. From the executing agency’s perspective,
the CMP and monthly progress report are tools for managing Contractors’
performance. Regardless of the scope and extent of reporting requirements to
ADB, to meet the loan or grant covenant, their use should thus be considered as
best practice for contract management.
Appendix 3 31
A3.27 For simple and low-value contracts, the CMP may be limited to more
succinct items, which in accordance with the procurement regulations, may only
include the following:
A3.28 For simple and low-value contracts, the CMP may cover only five
sections, as shown in Box A3.1. The five sections listed below are extracted from
the sections recommended for a full-fledged CMP, which is described in detail in
subchapter 4.2.
32 Appendix 3
Box A3.1
Elements of a Contract Management Plan for Simple
and Low-Value Contracts
Part A: Monthly Progress Report
Project Background
Executive Summary
Monthly Progress Update
• Section 4: Program Monitoring
• Section 6: Financial Management
• Section 8: Environment, Social, Health and Safety, Security-Related Obligations
• Section 9: Completion of Work and Contract Closure Activities
• Section 10: Recent Photographs of Site Activities
Project Background
A3.30 The project background is meant to provide key factual and descriptive
(and thus nonvariable) elements of the contract. It is usually laid on a one-page
schedule so as to give a “project at a glance” view of the contract. This description
will usually contain the following elements:
Executive Summary
A3.31 The executive summary provides the key conclusions tailored for decision
makers. Typically, the executive summary is a few paragraphs that briefly set out the
key issues together with recommendations for actions to be taken relating to the
reporting period. The following topics may be covered:
A3.33 This is the core and dynamic part of the progress report. A large part of the
information needed should be present in the Contractor’s monthly report from which
the Engineer can extract information to generate the progress report. The update is
divided into 10 sections, which are described in detail in subchapter 4.2.
A3.34 This descriptive part of the CMP contains all reference data and
information that are in principle invariant over the contract life, such as relevant
contract details, key points of contract, description of bank guarantees, and
insurances submitted by the Contractor. part B is divided into three sections,
which are described in subchapter 4.3.
A3.35 The project monthly update can be divided into the following 10 sections:
A3.36 This section lists all permits, licenses, and approvals that should be obtained,
either by the Employer or the Contractor before all or part of the works can start
(or shortly after). This may include (i) planning; (ii) zoning or building permits;
(iii) registration with the local engineering or contractor council; (iv) utilities removal or
relocation; (v) tax registration, for the purpose of setting up the Contractor’s in-country
subsidiary or branch office; and (vi) customs or tax exemptions. The final list should be
determined at the strategic procurement planning (SPP) stage.
A3.37 Some of these permits, licenses, and approvals should be obtained by the
Employer, others by the Contractor. It is therefore important to keep track of these
permits to make sure that they are secured in due time.
A3.38 Typically, when they are the responsibility of the Employer (e.g., customs
duties exemptions), failure to timely obtain such permits, licenses, or approvals
will entitle the Contractor to claim compensation for cost and/or time extension.
Besides, implementing agencies should be aware that even when the Contractor
is responsible for obtaining such permits, licenses, or approvals, the contract may
stipulate that the Employer should be responsible for providing assistance to the
Contractor in obtaining them, and failure to provide such assistance may thus also
be grounds for a Contractor’s claim.
A3.39 Therefore, keeping track of the process for securing all such permits,
licenses, or approvals, and the recording of any variance between due dates, and
actual dates and their reasons, will be key to avoiding or at least limiting administrative
impediments to the proper progress of the works. If needed, additional resources within
the implementing agency, or possibly assistance from another government entity or
department, should be considered for troubleshooting.
A3.40 This section contains three tables listing all activities that should take
place from the issuance of the letter of acceptance by the Employer to the selected
bidder until 28 days after the commencement date (or such other period that
Appendix 3 35
the contract may specify). The contract typically sets out a number of critical
obligations for the parties during this period:
A3.41 Each of these activities is critical for the proper start of the project and
corresponds to specific obligations of either party (as well as the Engineer) under
the contract.
A3.42 As per ADB guidelines and procedures, the LARP should be implemented
before the commencement of the works. However, for “linear” projects, such as
road construction and/or rehabilitation, installation of power transmission lines, or
water distribution networks, it may be difficult to have the LARP fully implemented
before the commencement of works. The LARP may thus be processed in
sections14 and the corresponding site areas may be handed over to the Contractor
section by section.
A3.43 Under such scenario, if the works start on some sections while others are
still not yet under the full control of the Employer, it is crucial that the remaining LARP
processing activities be monitored very carefully. The “sectional” handover of the site
to the Contractor would also need to be carefully described in the contract, with the
understanding that noncompliance with the agreed milestones for site access would
likely result in claims for extension of time and additional payment.
14
The word “section” is used in this context to describe the various parts in which the LARP may be
processed. It is not to be confused with the concept of “Section” used in the FIDIC contract to
describe “a part of Works specified in the Contract Data as a Section (if any).”
36 Appendix 3
Due Actual
Clause Action Responsible Date Date Comment
GCC Provision of insurances (See Contractor
18.1 Section 6)
GCC Appointment of dispute board Employer
20.2 and signing of the Dispute and
Agreement(s) by the parties Contractor
[Insert any other start-up related
obligations added for the particular
contract]
ADB = Asian Development Bank, APG = advance payment guarantee, FIDIC = Fédération
Internationale des Ingénieurs-Conseils (International Federation of Consulting Engineers),
GCC = General Conditions of Contract, ITB = Instructions to Bidders, PCC = Particular
Conditions of Contract.
Note: All ITB clause numbers refer o Section 1 of the ADB Standard Bidding Document in the
User’s Guide to Procurement of Works (June 2018). GCC or PCC clause numbers refer to FIDIC
Contract MDB Harmonized Edition (June 2010).
Sources: ADB. User’s Guide to Procurement of Works (June 2018). Manila; International Federation
of Consulting Engineers. 2010. FIDIC Contract MDB Harmonized Edition (June 2010). Geneva.
A3.45 All the activities above are usually embedded in various instructions
to bidders (for the first three items) or contract provisions (for all the others),
which provide the specific timeframe for the responsible party (e.g., submission
of the performance security). Noncompliance with any of these obligations
in the prescribed timeframe will usually give entitlement to the other party for
some remedies: extension of time; additional cost (e.g., in case of failure to grant
full access and unobstructed possession of the site); or financial charges (e.g., in
case of delayed payment of the advance payment) for the Contractor. In certain
(extreme) situations, it can lead to contract termination for cause, triggered
either by the Contractor (e.g., in case of nonsubmission by the Employer of its
financial arrangements) or by the Employer (e.g., in case of nonsubmission of the
performance security).
A3.47 The above activities are incumbent upon the Contractor and should be
carefully monitored by the Engineer. Although the mobilization of the Contractor
is expected to commence as soon as practicable after the issuance of the letter
acceptance, the Contractor will usually wait to receive the advance payment in order to
limit its financial exposure.15
15
Under certain forms of contract such as the FIDIC MDB Harmonized Edition (June 2010),
the payment of the advance payment is a condition precedent to the notification of the
commencement date, which means that the Contractor is likely to delay its mobilization until
that time.
16
Further reference on the general approach to risk management can be found in ADB.
Guidance Note on Procurement Risk Framework. Manila. https://www.adb.org/sites/default/files/
procurement-risk-framework.pdf.
Appendix 3 39
A3.50 The risk management approach contained in the CMP (and if needed,
reflected and commented later in each progress report) is thus the outcome of this
global process. The risks identified at this stage are primarily those derived from the
PPRA as cascaded into the strategic procurement planning process. Additional risks
may nonetheless be identified at this stage depending on the project detailed
engineering design or on the particular circumstances arising at the time of contract
preparation or negotiation.
A3.51 A typology of all such risks sorted by the various stages of the project
implementation is presented in Box A3.2.
Box A3.2
Categories of Risks in Project Implementation
A3.52 Risk analysis has three steps: risk identification, risk assessment, and risk
mitigation. These are consolidated in a contract risk management plan, also called
contract risk register.
Risk Identification
A3.53 Following the typology as suggested in Box A3.2, the identified risks can be
monitored through the contract risk register or risk matrix, which is used as a live
project management and decision-making support tool. The register should be
updated every time risk mitigation measures are implemented, until such time that
the level of residual risk is considered as acceptable by the implementing agency.
This matrix should be used during contract implementation to make sure that risks
remain monitored and controlled. Box A3.3 shows the different fields
recommended in a contract risk matrix.
Box A3.3
Contract Risk Register
Risk reference
• Risk category (cross-cutting risk, Procurement risk, Design risk, etc.)
• Risk name
• Date identified
• Risk owner, i.e., the person or entity in charge of managing that risk
Risk details
• Risk description
• Risk potential cause
• Risk impact if it occurs
Risk assessment
• Risk probability of occurrence score, split into five levels, from Very Low (VL) to
Very High (VH), or 1 to 5
• Risk impact score split into five levels, from VL to VH, or 1 to 5
• Risk score, being the multiplication of probability score by impact score, i.e., ranging from
1 to 25; the higher the score, the higher the need to mitigate the risk
Source: Asian Development Bank (Procurement, Portfolio and Financial Management Department).
Risk Assessment
The risk scoring system and associated color code can be based on the following
matrix (Table A3.5):
Appendix 3 41
Source: Asian Development Bank (Procurement, Portfolio and Financial Management Department).
Risk Mitigation
A3.56 Upon implementation of the risk mitigation measure, the risk owner shall
decide whether to declare the status of the residual risk as either of the following:
A3.57 It should be noted that the above addresses risks that have direct cost
and time implications. There might be other characteristics of risk that do not
necessarily translate into direct cost and time impact, such as reputational risks.
The implementing agency shall assess such kind of risks by using the same risk
matrix but defining risk impact score using terms other than direct time and
monetary costs.
A3.59 This section is a key part of the progress report, which should provide
a reliable picture of the progress achieved at a given month versus the planned
progress. The source of information is the time schedule, as updated monthly,
which the Contractor will submit to the supervision engineer as part of its own
monthly progress report. The contents, format, and sometimes the software will
typically be described in the contract specifications.
A3.62 A sample of level 1 and level 2 program and illustrative charts and
commentary is shown in Box A3.4.
Appendix 3 43
Box A3.4
Sample Level I and Level 2 Programs
It will be up to the Engineer to extract the relevant information from the Contractor’s
monthly time schedule to provide a meaningful picture of the situation.
17
Claims may, however, also be initiated by the Employer, usually in response to noncompliance
by the Contractor of some of its obligations (e.g., failure to complete the works or services as per
the agreed time for completion, giving entitlement for delay damages for the employer subject to
making a claim).
44 Appendix 3
4.2.5.1 Variations
18
Per FIDIC Contract MDB Harmonized Edition (June 2010), sub-clause 13.1 [Right to Vary].
19
Per ENAA form of International Contract for Process Plant Construction, sub-clause 39.2
[Changes Originating from Employer].
Appendix 3 45
A3.68 Finally, executing and implementing agencies should bear in mind that
for ADB- funded projects, for contracts subject to prior review, variations should
be submitted to ADB for no-objection. No-objection shall be issued by a different
level of authority within ADB whether the variation represents more than 15% of
the accepted contract amount but less than $50 million (in the aggregate with all
previous variations), or above $50 million. A memo shall be submitted to ADB
setting out the rationale for the variation, the basis of its valuation, and the possible
impact on the time for completion. The executing and/or implementing agency
will have to agree with ADB on the funding of the variation, which may involve
reallocation of provision of price and/or quantity contingency under the loan
agreement, as well an extension of the loan closing date if required.
A3.69 Sound contract management practice dictates that variations are kept
track of and monitored on a monthly basis. Since variations will usually impact the
final contract price, the cost consequences of variations, and the funding thereof,
should be monitored closely.
4.2.5.2 Claims
A3.72 Unless they are misused by a Contractor, claims should not necessarily be
considered as an act of hostility toward the Employer.
46 Appendix 3
A3.73 The claim process relies on strict processes. For the Contractor, the claim
process is usually a multitier process including, depending on the form of contract,
early warning notice and/or notice of claim, and submission of detailed and
substantiated claim. Each of these steps are usually framed within strict time limits,
noncompliance with which will elicit claim rejection. Under the FIDIC and ENAA
forms of contract, the notice of claim should be served “as soon as practicable, and
not later than 28 days after the Contractor became aware, or should have become
aware, of the event or circumstance.20”
A3.74 For his or her part, the Engineer is also bound to a strict timeframe for
conducting analysis and determination of the claim. It is worth underlining that
under most common forms of construction contracts such as FIDIC and ENAA,
the Engineer is empowered to perform certain determination and/or certifier
functions under the contract which requires a certain degree of impartiality
and fairness.
A3.75 As for variations, it would be useful if the CMP includes a diagram of all
steps needed for claim submission and claim determination under the contract.
20
Under FIDIC First Edition (1999), sub-clause 20.1 [Contractor’s Claims]; FIDIC Second
Edition (2017), sub-clause 20.2.1 [Notice of Claim]; and ENAA form of International Contract
for Process Plant Construction, sub-clause 44.1 [Contractor’s Claims.]
Appendix 3 47
Event or
circumstance
<
DAYS
Account of
fully detailed
claim
<
DAYS
Engineer’s
initiative Response of
the Engineer
on the
principle
The Engineer
certifies
amount in
IPC
A3.77 Since claims, as for variations, are likely to have an impact the final
contract price, the cost consequences of claims and the funding thereof should be
monitored closely.
A3.79 The table below shows what information the Claim Register show include:
21
ADB recommends that for contracts the duration of which is expected over 18 months contain a
price adjustment clause to address the risk inflation.
50 Appendix 3
A3.84 The contract final price will therefore be usually different from the
accepted contract amount that the parties have agreed on the date of signing, as
illustrated below:
Month 2
………
Month n
Appendix 3 51
60,000,000
50,000,000
40,000,000
30,000,000
20,000,000
10,000,000
A3.87 This simple approach may however be misleading if the actual (physical)
progress does not reflect the actual payments made to date: this may be the case
for instance because the remeasured quantities have been significantly in excess
of the estimated quantities as per the bills of quantities or because of unexpected
conditions (e.g. underground soil condition) which led to claims and, consequently,
to an increase in cost.
A3.89 As shown in the graph below, three parameters will then be assessed:
60,000,000
50,000,000
40,000,000
30,000,000
20,000,000
10,000,000
A3.90 Good contract management may prevent, or at least limit, the occurrence
of disputes. Some disputes may however be inevitable and therefore require
a careful management considering the cost and time impact they will have on
the project.
A3.92 ADB funded works contracts provide for three-tier dispute resolution
system such as illustrated below:
A3.94 Among the cases usually referred to arbitration are disputes concerning
contract termination. The cases are particularly prone to costly and protracted
arbitration procedures. Executing/implementing agencies considering
terminating a contract should bear in mind that for ADB-financed projects,
ADB no- objection should be granted before triggering termination. A memo
should be submitted to ADB explaining the facts and contractual grounds for
termination; Executing/ implementing agencies should also comment on the way
for completing the works covering mainly the issues of valuation of remaining
works, procurement arrangements for selecting a new contractor, impact on
funding arrangement and loan closing date.
A3.95 Environment, social, and health and safety (ESHS) safeguards, as well as
security management (if applicable in the country) are important contractor obligations
that need to be carefully monitored. Although, they may not necessarily impact on
the cost, time and quality of the works, proper compliance with these obligations lies
at the heart of ADB’s mandate. In addition to the obvious potential damage or harm
to the environment, the local population and to workers on site, it must be stressed
that compliance is required in line with legal covenants and ADB Safeguards Policy
Statement (2009). Noncompliance with any of these obligations carry considerable
reputational risks to the implementing and executing agencies as well as to ADB.
A3.96 There are two primary sources of information for such data: (i) the
Contractor’s monthly progress report; it is therefore important to make sure that,
at bidding document preparation stage, the corresponding reporting obligations are
duly stipulated in the works contract,22 (ii) the reports that should be prepared by
the Engineer’s safeguards team and other experts (social and/or gender specialists).
22
Under FIDIC Contract MDB Harmonized Edition (June 2010), sub-clause 4.21; FIDIC Second
Edition (2017), sub-clause 4.20; and ENAA form of International Contract for Process Plant
Construction, sub-clause 18.3.
Appendix 3 55
A3.97 The tables below show the suggested format to be used in the CMP as
a template (to be updated in each progress report):
Compensation of temporary
impacts (structures, trees, income)
during construction.
Unanticipated impacts during
construction (i.e., additional land
requirements, unidentified land/assets
owners, land borrowing, etc.)
LTIFR = number of lost-time injuries (LTIs) within a given accounting period, relative to the
total number of hours worked in that period. The formula measures the number of LTIs per
million hours worked during an accounting period and is as follows:
FAI = number of injuries that requires a single first aid treatment and a follow up visit for
subsequent observation involving only minor injuries, and for which the person would typically
return immediately to their normal activities.
MTI = number of injuries or disease that resulted in a certain level of treatment given by a
physician or other medical personnel under standing orders of a physician other than on-site
first aid treatment.
SNM = number of unplanned events that did not result in injury, illness, or damage – but had
the potential to do so (i.e. ‘Close-Call’, ‘Nearly a Collision’, ‘Near Hit’).
TRIFR = number of injuries (excluding fatalities) requiring medical treatment per million hours
worked within an organization. The formula is as follows:
(Number of recordable injuries in accounting period) / (Number of hours worked by all staff
in the same accounting period) x 1,000,000.
58 Appendix 3
A3.99 Although most forms of contract provide for security measures to be taken
by the Contractor for the site operation 23 (fencing, lighting, signage), in some specific
countries the prevailing political situation and/or social instability mandates that specific
(and additional) security measures to be taken by the Contractor on site. This may
include designing specific operational procedures related to crisis management,
mobilizing dedicated personnel, and hiring specialized experts.
A3.102 The tables below show the suggested format to be used in the CMP as a
template (to be updated in each progress report):
23
Under FIDIC Contract MDB Harmonized Edition (June 2010), sub-clause 4.22; FIDIC Second
Edition (2017), sub-clause 4.21; and ENAA form of International Contract for Process Plant
Construction, sub-clause 22.4.
Appendix 3 59
A3.103 Good contract management mandates that not only the implementation
phase of the contract be monitored, but also that the “clean” and proper closure
contract be managed. This is important for both parties
• The Contractor will seek to receive from the Employer a statement that,
apart ongoing warranties (if applicable), all of its obligations have been
completed in accordance with the contract (the performance certificate).
The Contractor will also have to report to its bank(s) that outstanding
guarantees (performance guarantee, retention guarantee or others) were
returned so that they can be written off the books. The Contractor will have
to report to its insurers that the periods of coverage for the various policies
issued have lapsed (contractor’s all risks, workmen’s compensation and
employer’s liability, third party liability, professional indemnity, etc.).
• The Employer (implementing agency) will must ensure that all defects notified
at the taking over (snag list) and during the defect notification period were duly
remedied, all operation and maintenance manuals (if applicable) and as-built
drawings and documents were submitted in full and proper order, all due
payments were effected in line with the Contractor’s final statement and that
proper discharge therefor was given by the Contractor.
Due Actual
Clause Action Responsible Date Date
A3.110 This is the descriptive (or static) part of the CMP. It contains all
descriptive elements of the contract which will normally not vary over the duration
of the contract, or perhaps only in limited circumstances (e.g. replacement of
one key stakeholder such as the Engineer or the Contractor’s representative).
These elements will nonetheless provide a useful source of reference information.
A3.113 The tables hereinafter show the format that may be used for these elements:
24
Under the FIDIC contract MDB Harmonized Edition (June 2010), changes may however
occur to the performance security during the contract implementation period since the
contract conditions (sub-clause 4.2) provide that its amount should be increased or decreased
whenever the contract price increase or decrease by more than 25% due to a change in cost
(price adjustment), change in legislation or a variation.
62 Appendix 3
Sections (Yes/No).
If yes provide details.
Time for Completion (days)
Defects Notification Period (days)
Location of the Site
A3.114 The following table lists the main points of contact under the Contract
Community / [e.g. as per [e.g. as per project’s [insert date] [insert date]
stakeholder meeting project’s CCP] CCP]
ADB Oversight [e.g. every Quarter] [insert date] [insert date]
meeting
ADB = Asian Development Bank, CCP = community communication plan
25
Numbers inserted refer to individuals started in Table 2.1 above.
64 Appendix 3
A3.115 A summary list of items that may be discussed at the meetings stated
above is contained in Appendix B. All meetings to be documented with minutes
shared to all attendees.
4.3.2.3 Reporting
Name of Bank
Correspondent Bank,
if applicable
Amount of security [currency]
4.3.3.2 Insurances
Insurer
Policy no.
Amount of Insurance
PART A
[Most of this information will not change throughout the project’s life cycle. Insert once
and do not change unless necessary. Add further items if you think it is required.]
[This part should be updated monthly and only contain major items. Examples follow:]
[List all Permits, Licenses, and Approvals and update each month if required. These should be
country-specific requirements such as development consent/environmental license, certificate
for imported materials and equipment, materials permit, quarry permit, water discharge
permit etc].
a. LARP Processing
Clearance of LARP
Compliance report
Section Implementation
Definition status Due Date Actual Date Comments
A3.119 The items below are only examples and additional items may be needed
to be added and/or deleted depending on the particular project.
Due Actual
Clause Action Responsible Date Date Comments
Residual Tender Stage Actions
ITB 42.1 Issuance of Letter of Acceptance Employer
(LoA)
ITB 19.6 Return Bid Security to Contractor Employer
ITB 43.2 Contract Agreement Signature Employer and
Contractor
Contract Requirements
GCC 4.2 Provision of Performance Security Contractor
GCC 2.4 Evidence of the Employer’s Financial Employer
Arrangements
GCC 4.13 Effective Access to and Possession Employer
of the Site
GCC 14.2 Provision of Advance Payment Contractor
Guarantee
68 Appendix 3
Due Actual
Clause Action Responsible Date Date Comments
GCC 14.2 Submission and certification of Contractor
and 14.6 application for Advance Payment
GCC 14.7 Payment of Advance Payment Employer
PCC 4.18 Preparation and submission of Contractor
the Contractor’s Environmental
Management Plan
GCC 8.1 Commencement Date Engineer
Contract Activities required within 28 days of Commencement Date
GCC 8.3 Submission of Detailed Program Contractor
GCC 18.1 Provision of Insurances Contractor
(See Section 6)
GCC 20.2 Appointment of Dispute Board Employer and
and signature of the Dispute Contractor
Agreement(s) by the parties
ITB = instructions to bidders, GCC = General Conditions of Contract, PCC = Particular Conditions
of Contract.
Note: GCC clause numbers refer to FIDIC Contract MDB Harmonized Edition (June 2010).
Sources: ADB. User’s Guide to Procurement of Works (June 2018). Manila; International Federation
of Consulting Engineers. 2010. FIDIC Contract MDB Harmonized Edition (June 2010). Geneva.
c. Mobilization Activities
The items below are only examples and additional items may need to be added or
deleted depending on the particular project.
Scheduled Actual
Clause Action Reference Date Date Variance
GCC Establishment of Site boundaries, Program
4.22/6.6 compound, offices etc.
GCC Mobilization of Contractor’s Program
1.1.5.1/4.17 Equipment
GCC Mobilization of Contractors Program
1.1.2.7/6.9 Personnel
GCC = General Conditions of Contract.
Note: GCC clause numbers refer to FIDIC Contract MDB Harmonized Edition (June 2010).
Source: International Federation of Consulting Engineers. 2010. FIDIC Contract MDB Harmonized
Edition (June 2010). Geneva.
Appendix 3 69
A3.120 This table is updated monthly and should only contain risks that are
considered high and would have a serious impact on the project. This is a very
important part of the report and all major risks should be stated and have proposed
mitigation measures. A description of how to categorize risk has been included in
Appendix A. Please note that a full project risk register should be attached to the
CMP as an appendix.
A3.121 This Sub-Chapter is updated monthly and should contain the items
below. If the program is experiencing delays, then this needs to be highlighted and
mitigation measures stated.
• Level 2* program
• Tabular form of progress – planned dates, actual dates, variances
• Graphical form – line graph illustrating actual verses planned progress
• Pie chart – overall progress (%), time elapsed, time remaining
• One month look ahead table with target dates
• Short paragraph on critical path
* A Level 2 Schedule is a high-level integrated project schedule for the
entire project time frame that is used for high level internal and external
management This schedule shows the project milestones of engineering,
procurement, construction, and start-up activities.
A3.122 These tables are to be updated monthly and contain all claims and
variations submitted.
a. Payment Schedule
A3.123 This table records all payments related to the contract – including
contractor, PMC, consultants, etc.
A3.124 This table records the impacts of variations, claims, disputes, etc. It shows
why the contract cost has increased or decreased.
[Insert a graph illustrating the difference between planned payments (cashflow) and actual
payments. If there is a significant difference, then a comment should be made explaining why.]
70 Appendix 3
b. Earned Value
[Insert a graph that illustrates the Earned Value. If there is a significant difference, then a
comment should be made explaining why.]
5.3.7 Disputes
LTIFR = number of lost-time injuries (LTIs) within a given accounting period, relative to the
total number of hours worked in that period. The formula measures the number of LTIs per
million hours worked during an accounting period and is as follows:
(Number of LTIs in accounting period) / (Total hours worked in accounting period) x 1,000,000
FAI = number of injury that requires a single first aid treatment and a follow up visit for
subsequent observation involving only minor injuries, and for which the person would typically
return immediately to their normal activities.
MTI = number of injuries or disease that resulted in a certain level of treatment given by a
physician or other medical personnel under standing orders of a physician other than on-site
first aid treatment.
SNM = number of unplanned events that did not result in injury, illness, or damage – but had
the potential to do so (i.e. ‘Close-Call’, ‘Nearly a Collision’, ‘Near Hit’).
TRIFR = number of injuries (excluding fatalities) requiring medical treatment per million hours
worked within an organization. The formula is as follows:
(Number of recordable injuries in accounting period) / (Number of hours worked by all staff in
the same accounting period) x 1,000,000.
72 Appendix 3
d. Security Monitoring
A3.127 Only add photos taken in period that the report covers.
PART B
A3.128 A majority (but not all) of part B can be completed once and would not
need updating.
1. CONTRACT DETAILS
b. Meeting Schedule
(ii) Once agreed, only update when required.
c. Reporting
(iii) Once agreed, only update when required.
b. Insurances
SCHOOL PROJECT
MONTHLY PROGRESS REPORT
Reporting Period: 1–31 MAY 2021
PART A
Due Actual
Clause Action Responsible Date Date Comments
Residual Tender Stage Actions
ITB 42.1 Issuance of letter of Employer 1/5/2020 1/5/2020
acceptance
ITB 19.6 Return bid security to Employer 1/5/2020 1/5/2020
Contractor
ITB 43.2 Contract agreement Employer 1/6/2020 1/6/2020
signature and
Contractor
Contract requirements
GCC 4.2 Provision of performance Contractor 1/7/2020 30/6/2020
security
GCC 2.4 Evidence of the Employer 1/7/2020 30/6/2020
employer’s financial
arrangements
GCC 4.13 Effective access to and Employer 1/8/2020 1/8/2020
possession of the site
GCC 14.2 Provision of advance Contractor 1/7/2020 1/7/2020
payment guarantee
GCC 14.2 Submission and Contractor 8/7/2020 8/7/2020
and 14.6 certification of application
for advance payment
GCC 14.7 Payment of advance Employer 1/8/2020 1/8/2020
payment
PCC 4.18 Preparation and Contractor 1/8/2020 1/8/2020
submission of
the Contractor’s
environmental
management plan,
including health and
safety management plan
GCC 8.1 Commencement date Engineer 1/8/2020 1/8/2020
Contract Activities Required Within 28 Days of Commencement Date
GCC 8.3 Submission of detailed Contractor 1/9/2020 1/9/2020
program
Due Actual
Clause Action Responsible Date Date Comments
GCC 18.1 Provision of insurances Contractor 1/9/2020 1/9/2020
(see section 6)
GCC 20.2 Appointment of dispute Employer 1/9/2020 1/8/2020
board and signature of and
the dispute agreement(s) Contractor
by the parties
ITB = Instructions to Bidders, GCC = General Conditions of Contract, PCC = Particular
Conditions of Contract.
Note: All ITB clause numbers refer to Section 1 of the ADB Standard Bidding Document in the
User’s Guide to Procurement of Works (June 2018). GCC/PCC clause numbers refer to FIDIC
Contract MDB Harmonized Edition (June 2010).
Sources: ADB. User’s Guide to Procurement of Works (June 2018). Manila; International Federation
of Consulting Engineers. 2010. FIDIC Contract MDB Harmonized Edition (June 2010). Geneva.
A4.3 The following section highlights the main risks related to this reporting
period. Two risks were identified in the project risk register and one risk is new.
Risk Owner
Risk (person
Reference Risk Description Level Mitigation Measure responsible)
12 Building Permit Block B: High Meeting has been Contractor
The Contractor has not arranged (June 23)
yet been able to obtain the with the municipality
permit to pour the last slab. to discuss what was
It is now 2 weeks overdue. required to obtain
approval. Once permit is
obtained, the Contractor
will work night shifts to
make up the lost time
New Façade Specifications: High Design consultant will Design
Due to a change in fire propose an updated Consultant
regulations, the façade specification to the
specification will need to be Contractor. PMC will
changed. This could have request Employer
cost and time implications. sign-off with respect to
aesthetics.
14 Level difference between High The Contractor will Contractor
site and existing road. request municipal
The actual road height is surveyor to check height
different from what is stated and update municipal
on the municipal records. records.
This is delaying approval on
the final site access points.
PMC = project management consultant.
Updated Updated
Recovery Program Program
Program – Rev 0. – Rev 0.
– Milestone Forecast Forecast Variance Variance
Completion April 16 May 16 Total Period
# Description (a) (b) (c) (a-c) (b-c)
1 Issuance of Building Permit 27 Feb 2021 27 Feb 2021 27 Feb 2021 0 Days 0 Days
Completion of structural
3 30 April 2021 19 May 2021 29 May 2021 –29 Days –10 Days
steel for superstructure
Connection availability
4 for main services (water, 1 June 2021 1 June 2021 1 June 2021 0 Days 0 Days
power, drainage)
5 Wild air availability 15 June 2021 9 July 2021 12 July 2021 –27 Days –3 Days
6 Completion of lift works 27 June 2021 19 July 2021 29 May 2021 29 Days 51 Days
7 Completion of facade works 28 June 2021 24 July 2021 2 Aug 2021 –35 Days –9 Days
Temporary permanent
8 4 July 2021 26 July 2021 4 Aug 2021 –31 Days –9 Days
power
Completion of external
10 18 July 2021 7 Aug 2021 22 Aug 2021 –35 Days –15 Days
works
Issuance of building
11 completion certificate 23 Aug 2021 14 Sept 2021 25 Sept 2021 –33 Days –11 Days
(BCC)
13 School opens 28 Aug 2021 19 Sept 2021 29 Sept 2021 –32 Days – 10 Days
Time Elapsed
Overall Progress
Time Remaining
A4.5 The critical path is moving through the “wet” trades (plastering);
mechanical, electrical, and plumbing (MEP) trades; and finishes for the
second- floor block D. The local electricity authority inspection, power on,
and testing and/ or commissioning are also on the critical path.
Appendix 4 83
Days to Completion 84
Target Variance 15
A4.6 The project was budgeted to have incurred costs of $50 million up until
the end of May 2021. It has currently incurred costs of $47 million. The payments
to date are outlined below.
4.10. Disputes
A4.10 There was one workplace incident involving concrete burn injury on
26 May 2021. The concerned worker was given medical treatment at a nearby
clinic and was off- work for 5 days before allowed to resume light activities on
site. Incident report with details on the event cause, actions, and lesson learned
was circulated to the site team on 27 May 2021, and a specific toolbox briefing on
concrete work safety was held on 28 May 2021.
(i) setting up the site to be ready for carrying out work in the monsoon
season, and
(ii) community liaison group meeting June 2021.
LTIFR = number of lost-time injuries (LTIs) within a given accounting period, relative to the
total number of hours worked in that period. The formula measures the number of LTIs per
million hours worked during an accounting period and is as follows:
(Number of LTIs in accounting period) / (Total hours worked in accounting period) x 1,000,000
FAI = number of injury that requires a single first aid treatment and a follow up visit for
subsequent observation involving only minor injuries, and for which the person would typically
return immediately to their normal activities.
MTI = number of injuries or disease that resulted in a certain level of treatment given by a
physician or other medical personnel under standing orders of a physician other than on-site
first aid treatment.
SNM = number of unplanned events that did not result in injury, illness, or damage – but had
the potential to do so (i.e., ‘Close-Call’, ‘Nearly a Collision’, ‘Near Hit’).
TRIFR = number of injuries (excluding fatalities) requiring medical treatment per million hours
worked within an organization. The formula is as follows:
(Number of recordable injuries in accounting period) / (Number of hours worked by all staff in
the same accounting period) x 1,000,000
N/A
Appendix 4 89
PART B
1 Employer
5 Contractor’s Representative
6 H&S Officer
7 Engineer’s Representative
11
12
13
14
15
PMU = project management unit, H&S = health and safety, ADB = Asian Development Bank,
HQ = headquarters.
Contract Management
Guidance Note on Procurement
This guidance note provides operational-level guidance for borrowers, through their
executing agencies, on how contract management should be applied in projects
during the procurement cycle for a contract financed in whole or in part by an ADB
loan or grant, or by ADB-administered funds, for the procurement of goods, works,
and services. Contract management encompasses three stages: preparation and
planning activities prior to contract award, contract administration during contract
implementation, and contract closure. Effective contract management ensures that
supplier, contractor, and/or consultant deliverables and obligations are met as agreed
under the contract. In addition, more efficient and effective contract management
promotes increased and more timely loan disbursements.