Cross Drainage: Topic 821 - General
Cross Drainage: Topic 821 - General
820-1
May 1, 2001
on spread footings with the streambed serving as the bottom of the culvert. Bridges are not designed to take advantage of submergence to increase hydraulic capacity even though some are designed to be inundated under flood conditions. For economic and hydraulic efficiency, culverts should be designed to operate with the inlets submerged during flood flows, if conditions permit. At many locations, either a bridge or a culvert will fulfill both the structural and hydraulic requirements of the stream crossing. Structure choice at these locations should be based on con0struction and maintenance costs, risk of failure, risk of property damage, traffic safety, and environmental and aesthetic considerations. Culverts are usually considered minor structures, but they are of great importance to adequate drainage and the integrity of the highway facility. Although the cost of individual culverts is relatively small, the cumulative cost of culvert construction constitutes a substantial share of the total cost of highway construction. Similarly, the cost of maintaining highway drainage features is substantial, and culvert maintenance is a large share of these costs. Improved service to the public and a reduction in the total cost of highway construction and maintenance can be achieved by judicious choice of design criteria and careful attention to the hydraulic design of each culvert.
820-2
June 26, 2006
basins having areas in excess of 1.3 km2 (130 ha) than for small basins.
these criteria need to be balanced against potential damage to the highway and adjacent properties upstream and downstream of the site. The selection of a design flood with a lesser or greater peak discharge may be warranted and justified by economic analysis. A more frequent design flood than a 4% probability of exceedance (25-year) should not be used for the hydraulic design of culverts under freeways and other highways of major importance. Alternatively, where predictive data is limited, or where the risks associated with drainage facility failure are high, the greatest flood of record or other suitably large event should be evaluated by the designer. When channels or drainage facilities under the jurisdiction of local flood control agencies or Corps of Engineers are involved, the design flood must be determined through negotiations with the agencies involved.
Although either of these alternatives may be used exclusive of the other, in actual practice both alternatives are often considered and used jointly to select the flood frequency for hydraulic design. For culverts and small bridges, apply the following general rules for first consideration in the process for ultimate selection of the design flood. (1) Bridges. The basic rule for the hydraulic design of bridges is that they should pass a 2% probability flood (50-year). Freeboard, vertical clearance between the lowest structural member and the water surface elevation of the design flood, sufficient to pass the 1% probability flood should be provided. Sixtenths meter of freeboard is often assumed for preliminary bridge designs. The effects of bedload and debris should be considered in the design of the bridge waterway. (2) Culverts. There are two primary design frequencies that should be considered: A 10% probability flood (10-year) without causing the headwater elevation to rise above the inlet top of the culvert and, A 1% probability flood (100-year) with-out headwaters rising above an elevation that would cause objectionable backwater depths or outlet velocities.
The designer must use discretion in applying the above criteria. Design floods selected on this basis may not be the most appropriate for specific project site locations or conditions. The cost of providing facilities to pass peak discharges suggested by
820-3
June 26, 2006
appreciably
change
the
outlet
(2) Tailwater. The term, tailwater, refers to the water located just downstream from a structure. Its depth or height is dependent upon the downstream topography and other influences. High tailwater could submerge the culvert outlet.
higher construction cost. On the other hand, retaining solids upstream from the entrance by means of a debris control structure often involves substantial maintenance cost and could negatively affect fish passage. An economic comparison which includes evaluation of long term maintenance costs should be made to determine the most reasonable and cost effective method of handling. (2) Interception. If it is not economical to pass debris, it should be retained upstream from the entrance by means of a debris control structure or the use of a debris basin when the facility is located in the vicinity of alluvial fans. If drift and debris are retained upstream, a riser or chimney may be required. This is a vertical extension to the culvert which provides relief when the main entrance is plugged. The increased head should not be allowed to develop excessive velocities or cause pressure which might induce leakage in the culvert. If debris control structures are used, access must be provided for maintenance equipment to reach the site. This can best be handled by coordination and field review with district maintenance staff. Details of a pipe riser with debris rack cage are shown on Standard Plan D93C. See FHWA Hydraulic Engineering Circular No. 9, "Debris-Control Structures" for further information. The use of an upstream debris basin and downstream concrete lined channels, has often been used by Local Agencies for managing flood flows on alluvial fans in urbanized areas. Experience has shown that this approach is effective, however, the costs of building and maintaining such facilities is high with a potential for sediment inflows greater than anticipated. The District Hydraulics Engineer should be consulted if a debris basin is being considered for interception in the vicinity of an alluvial fan.
820-4
June 26, 2006
822.3 Economics
Debris problems do not occur at all suspected locations. It is often more economical to construct debris control structures after problems develop. An assessment of potential damage due to debris clogging if protection is not provided should be the basis of design.
Therefore, culverts should be placed at each defined swale to limit carryover of drainage from one watershed to another.
820-5
June 26, 2006
the fill. Where settlement is anticipated, provisions should be made for camber. (c) In steep sloping areas such as on hillsides, the overfill heights can be reduced by designing the culvert on a slope flatter than natural slope. However, a slope should be used to maintain a velocity sufficient to carry the bedload. A spillway or downdrain can be provided at the outlet. Outlet protection should be provided to prevent undermining. For the downdrain type of installation, consideration must be given to anchorage. This design is appropriate only where substantial savings will be realized.
820-6
June 26, 2006
barrel. However, it is possible for the culvert to function with an unsubmerged outlet under outlet control where flow passes through critical depth in the vicinity of the outlet. For each type of control, different factors and formulas are used to compute the hydraulic capacity of a culvert. Under inlet control, the cross sectional area of the culvert, inlet geometry, and elevation of headwater at entrance are of primary importance. Outlet control involves the additional consideration of the tailwater elevation of the outlet channel and the slope, roughness and length of the culvert barrel. A discussion of these two types of control with charts for selecting a culvert size for a given set of conditions is included in the FHWA Hydraulic Design Series No. 5, "Hydraulic Design of Highway Culverts."
elevation. In cases where the headwater elevation is greater then the top elevation of the roadway embankment, an overtopping analysis is done in which flow is balanced between the culvert discharge and the surcharge over the roadway. In the cases where the culvert is not full for any part of its length, open channel computations are performed.
Familiarity with culvert hydraulics and traditional methods of solution is necessary to provide a solid basis for designers to take advantage of the speed, accuracy, and increased capabilities of hydraulic design computer programs. The hydraulic design calculator and computer programs available from the FHWA are more fully described in HDS No. 5, "Hydraulic Design of Highway Culverts." The HY8 culvert hydraulics program provides interactive culvert analysis. Given all of the appropriate data, the program will compute the culvert hydraulics for circular, rectangular, elliptical, arch, and user-defined culverts. The logic of HY8 involves calculating the inlet and outlet control headwater elevations for the given flow. The elevations are then compared and the larger of the two is used as the controlling
820-7
June 26, 2006
(3) Headwalls and Wingwalls. This end treatment may be required at the culvert entrance for the following reasons: To improve hydraulic efficiency. To retain the embankment and reduce erosion of slopes. To provide structural stability to the culvert ends and serve as a counterweight to offset buoyant or uplift forces.
(4) Rounded Lip. This treatment costs little, smoothes flow contraction, increases culvert capacity, and reduces the level of ponding at the entrance. The box culvert and pipe headwall standard plans include a rounded lip. The rounded lip is omitted for culverts less than 1200 mm in diameter; however, the beveled groove end of concrete pipe at the entrance produces an effect similar to that of a rounded lip. (5) Mitered End. A mitered culvert end is formed when the culvert barrel is cut to conform with the plane of the embankment slope. Mitered entrances are not to be used. They are hydraulically less efficient than either flared end sections or headwalls, and they are structurally unstable. (6) Entrance Risers. At a location where the culvert would be subject to plugging, a vertical pipe riser should be considered. Refer to Index 822.2 for discussion on debris-control structures.
820-8
June 26, 2006
entrance using air blown mortar, concreted riprap, sacked concrete or slope paving. Straight flared wingwalls and warped wingwalls aid in maintaining the approach velocity, align and guide drift, and funnel the flow into the culvert entrance. To insure enough velocity to carry drift and debris through the culvert or increase the velocity and thereby increase the entrance capacity, a sloping drop down apron at the entrance may be used. To minimize snagging drift, the standard plans require wingwalls to be flush with the culvert barrel. The flare angle may range from 30 to 75 degrees; the exact angle is based on the alignment of the approach channel banks and not the axis of the culvert. Greater efficiency is obtained when the top of the wingwall is the same elevation as the headwall. Whether warped or straight flared wingwalls are used depends on the shape of the approach channel. Straight flared wingwalls are appropriate for well defined channels with steep banks. Warped wingwalls are more suited to shallow trapezoidal approach channels. Usually it is more economical to transition between the stream section and the culvert by means of straight flared wingwalls or warped wingwalls than to expand the culvert barrel at entrance. For a very wide channel, this transition may be combined with riprap, dikes, or channel lining extending upstream to complete the transition. (2) Transitions. Elaborate transitions and throated openings for culverts may be warranted in special cases. Generally a highly developed entrance is unnecessary if the shape of the culvert fits the approach channel. In wide flat channels where ponding at entrance must be restricted, a wide shallow structure or multiple conduit should be used if drift and debris are not a problem. Throated or tapered barrels at entrance are more vulnerable to clogging by debris. They are not economical unless they are used for corrective measures; for example, where there is a severe restriction in right of way width and
it is necessary to increase the capacity of an existing culvert structure. For further information refer to HEC-9, "Debris-Control Structures" and HDS 5, "Hydraulic Design of Highway Culverts"
820-9
June 26, 2006
Integrated Computer Program System, provides designs for energy dissipators and follows the HEC-14 method for design. Culvert outlet design should provide a transition for the 100-year flood or design event from the culvert outlet to a section in the natural channel where natural stage, width, and velocity will be restored, or nearly so, with consideration of stability and security of the natural channel bed and banks against scour. If an outfall structure is required for transition, typically it will not have the same design as the entrance. Wingwalls, if intended for an outlet transition (expansion), generally should not flare at an angle (in degrees) greater than 46 divided by the outlet velocity in meters per second. However, transition designs fall into two general categories: those applicable to culverts in outlet control (subcritical flow) or those applicable to culverts in inlet control (supercritical). The procedure outlined in HEC-14 for subcritical flow expansion design should also be used for supercritical flow expansion design if the culvert exit Froude number (Fr) is less than 3, if the location where the flow conditions desired is within 3 culvert diameters of the outlet, and if the slope is less than 10 percent. For supercritical flow expansions outside these limits, the energy equation can be used to determine flow conditions leaving the transition. Warped endwalls can be designed to fit trapezoidal or U-shaped channels, as transitions for moderateto-high velocity (3-5.5 m/s). For extreme velocity (exceeding 5.5 m/s) the transition can be shortened by using an energydissipating structure.
828.3 Length
The length of pipe culvert to be installed is determined as follows: (a) Establish a theoretical length based on slope stake requirements making allowance for end treatment. (b) Adjust the theoretical length for height of fill by applying these rules: For fills 4 m or less, no adjustment is required. For fills higher than 4 m, add 0.3 m of length at each end for each 3 m increment of fill height or portion thereof. The additional length should not exceed 2 m on each end. In cases of high fills with benches, the additional length is based on the height of the lowest bench.
(c) Use the nearest combination of commercial lengths which equal or exceed the length obtained in (b) above.
820-10
June 26, 2006
The allowable overfill heights for concrete arches, structural plate arches, and structural plate vehicular undercrossings are based on existing soil withstanding the soil pressures indicated on the Standard Plans. A foundation investigation should be made to insure that the supporting soils withstand the design soil pressures for those types of structures. (2) Method of Installation. Under ordinary conditions, the methods of installation described in the Standard Specifications and shown on the Standard Plans should be used. For any predictable settlement, provisions for camber should be made. Excavation and backfill details for circular concrete pipe, reinforced box and arch culverts, and corrugated metal pipe and arch culverts are shown on Standard Plans A62-D, A62DA, A62-E, and A62-F respectively. (3) Height of Cover. There are several alternative materials from which acceptable culverts may be made. Tables of maximum height of cover recommended for the more frequently used culvert shapes, sizes, corrugation configurations, and types of materials are given in Chapter 850. Not included, but covered in the Standard Plans, are maximum earth cover for reinforced concrete box culverts, reinforced concrete arches, and structural plate vehicular undercrossing. For culverts where overfill requirements exceed the limits shown on the tables a special design must be prepared. Special designs are to be submitted to the Division of Structures for review, or the Division of Structures may be directly requested to prepare the design. Under any of the following conditions, the Division of Structures is to prepare the special design: Where foundation material will not support footing pressure shown on the Standard Plans for concrete arch and structural plate vehicular undercrossings. Where foundation material will not support footing pressures shown in the Highway Design Manual for structural plate pipe arches or corrugated metal pipe arches.
820-11
June 26, 2006
Where a culvert will be subjected to unequal lateral pressures, such as at the toe of a fill or adjacent to a retaining wall.
829.4 Joints
The possibility of piping being caused by open joints in the culvert barrel may be reduced through special attention to the type of pipe joint specified. For a more complete discussion of pipe joint requirements see Index 853.1. The two pipe joint types specified for culvert installations are identified as "standard" and "positive". The "standard" joint is adequate for ordinary installations and "positive" joints should be specified where there is a need to withstand soil movements or resist disjointing forces. Corrugated metal pipe coupling band details are shown on Standard Plan sheets D97A through D97G and concrete pipe joint details on sheet D97H. If it is necessary for "standard" or "positive" joints to be watertight they must be specifically specified as such. Rubber "O" rings or other resilient joint material provides the watertight seal. Corrugated metal pipe joints identified as "downdrain" are watertight joint systems with a tensile strength specification for the coupler.
Special designs usually require that a detailed foundation investigation be made. (4) Minimum Cover. When feasible, culverts should be buried at least 0.3 m. For construction purposes, a minimum cover of 150 mm greater than the thickness of the structural cross section is desirable for all types of pipe. The minimum thickness of cover for various type culverts under rigid or flexible pavements is given in Table 854.9.
829.3 Piping
Piping is a phenomenon caused by seepage along a culvert barrel which removes fill material, forming a hollow similar to a pipe. Fine soil particles are washed out freely along the hollow and the erosion inside the fill may ultimately cause failure of the culvert or the embankment. The possibility of piping can be reduced by decreasing the velocity of the seepage flow. This can be reduced by providing for watertight joints. Therefore, if piping through joints could become a problem, consideration should be given to providing for watertight joints. Piping may be anticipated along the entire length of the culvert when ponding above the culvert is expected for an extended length of time, such as when the highway fill is used as a detention dam or to form a reservoir. Headwalls, impervious materials at the upstream end of the culvert, and anti-seep or cutoff collars increase the length of the flow path, decrease the hydraulic gradient and the velocity of flow and thus decreases the probability of piping developing. Anti-seep collars usually consist of bulkhead type plate or blocks around the entire perimeter of the culvert. They may be of metal or concrete, and, if practical, should be keyed into impervious material. Piping could occur where a culvert must be placed in a live stream, and the flow cannot be diverted. Under these conditions watertight joints should be specified.
829.5 Anchorage
Refer to Index 834.4(5) for discussion on anchorage for overside drains. Reinforced concrete pipe should be anchored and have positive joints specified if either of the following conditions is present: (a) Where the pipe diameter is 1500 mm or less, the pipe slope is 33 percent or greater, and the fill over the top of the pipe less than 1.5 times the outside diameter of the pipe measured perpendicular to the slope. (b) Where the pipe diameter is greater than 1500 mm and the pipe slope is 33 percent or greater, regardless of the fill over the top of the pipe. Where the slopes have been determined by the geotechnical engineer to be potentially unstable, regardless of the slope of the pipe, as a minimum, the pipes shall have positive joints. Alternative pipes/anchorage systems shall be investigated when there is a potential for substantial movement of the soil.
820-12
June 26, 2006
Where anchorage is required, there should be a minimum of 450 mm cover measured perpendicular to the slope. Typically buried flexible pipe with corrugations on the exterior surface will not require anchorage, however, a special detail will be required for plastic pipe without corrugations on the exterior surface.
(a) Reinforced Concrete Pipe - Reinforced concrete pipe with joint seals is generally satisfactory. For heads over 6 m, special consideration should be given to hydrostatic pressure. (b) Corrugated Metal Pipe - corrugated metal pipe must be of the thickness and have the protective coatings required to provide the design service life. Field joints must be watertight. The following additional treatment is recommended. When the head is more than 3 m and the flow is continuous or is intermittent and of long duration, pipe fabricated by riveting, spot welding or continuous helical lockseam should be soldered. Pipe fabricated by a continuous helical welded seam need not be soldered. If the head is 3 m or less and the flow is intermittent and lasts only a few days, as in storm flows, unsoldered seams are permissible.
820-13
June 26, 2006
plugging of the cross drain could lead to high pressures on the upstream side of the fill, creating seepage through the fill and/or increased potential for piping. The requirements for submitting information to the FHWA Division Office in Sacramento as described in Index 805.6 are not affected by the regulations mentioned above.