btk methodstatement

This document is a Construction Method Statement for the Rehabilitation of Road Package A in Timor-Leste, detailing the project's execution plan, including coordination, materials, equipment, and safety measures. The project is expected to last 12 months and involves various construction stages such as earthworks, drainage, and bridge construction. It emphasizes the use of local materials and outlines a waste management strategy to ensure environmental compliance.

Uploaded by

finus marcal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

btk methodstatement

This document is a Construction Method Statement for the Rehabilitation of Road Package A in Timor-Leste, detailing the project's execution plan, including coordination, materials, equipment, and safety measures. The project is expected to last 12 months and involves various construction stages such as earthworks, drainage, and bridge construction. It emphasizes the use of local materials and outlines a waste management strategy to ensure environmental compliance.

Uploaded by

finus marcal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

METHOD STATEMENT

Bid Date : January 29, 2025


Tender ID Nu. Bid No.: TENDER/176/MOP-2024

To: Ministry Of Public Work


EXECUTIVE SUMMARY

This report has been commissioned by BQ Corperation Unip Lda. to prepare a Construction Method
Statement in support of a detailed planning application for the Rehabilitation of Road Package A
(Municipio Manufahi), National Road (Arterial A14) Same Luak-Betano, L = 10 Km (Part II, 5.05
km)This report outlines how this project, will be constructed efficiently, under controlled
environmental conditions. This method statement describes how we propose to achieve good quality
of the works, complete within the schedule and to avoid accident.m

A. PRELIMINARIES
Before begins project, first have to be done is signing contract & PO with the
Ministry of Public Work , Timor – Leste.
❖ Early Coordination
Coordination Between the parties involved in implementing this
activity such as the leader of activities, and contractors is needed in this
preparation stage.
Coordination of work is needed to facilitate the implementation of work and
the achievement of the best work.
This initial coordination phase is the next process during the period of
implementation.
❖ Evaluation of contract Document
The next stage of this preparatory work is to check in detail the
complete date that well be used as a reference for implementing supply such
as:
• Requirement contract
• Technical contract
• Design Schedule to Completion works

B. PROGRAMME OF WORKS

The total duration for the whole works is estimated to be 12 months and will comprise the following
key stages:
NO ITEM OF WORK
1 GENERAL REQUIREMENTS
2 EARTHWORKS
3 SUBBASE AND BASE COURSE
4 SURFACE COURSES
5 BRIDGE CONSTRUCTION
6 DRAINAGE AND SLOPE PROTECTION STRUCTURES
7 MISCELLANEOUS STRUCTURES
Our 8 BIOENGINEERING
constructio n
methodology statement which follows explains how this will be achieved.

C. MATERIALS AND RESOURCE USE


All materials available locally for the construction will be used.
Sand = Betano (Local Material)
Gravel, Rocks and Boulders = Vemasse, Jonize, Jova, Suai Indah, Beduku/Liquica River (Local Material)Beduku Quarry
(Local Material)
Embankment = Near Source (Local Material) Water Supply = Near Source (Local
Material) Reinforcing Steel Bars = Imported from Indonesia Cement = Imported
from Indonesia

PRELIMINARY

Mobilization of equipment, Tools and Personnel will be followed by the setting of site office, warehouse and survey or the
measuring and marking at site.

All Temporary Facilities will be use in the Project shall be complete mobilized and on site with-in 2 Weeks.
CONSTRUCTION
Estimates of key construction materials are listed below:
Cement = ± 320 tons
Reinforcing Steel Bars = ± 45 tons
Gravel = ± 210 cu.m.
Rock and Boulders = ± 157 cu.m.
Sand = ± 212 cu.m.
Asphalt = ± 65 Ton

A specialist waste management organization will be employed during construction works with
specific responsibility for the coordination of the disposal of all surplus materials and the management
of an effective document control system to track and confirm that the proper procedures have been
followed.

The location of the waste handling site that the materials will be taken to will vary dependent upon
their specific make up but we anticipate that sites in Same Luak-Betano, will be used amongst others
as appropriate. Wherever possible, materials will be recycled and re-used either onsite, or provided
for use elsewhere.

Plant Material and Equipment


Consideration has been given to the types of plant that are likely to be used on-site during the
preliminary and construction phases of the Proposed Development. The plant and equipment
associated with each key element of the construction process is set out in Table 1.& 2

Table 1: Estimated of Material Resources SUPPLIER

Material Supplier Resource


Reinforcing Steel Bar Lay Shop Dili
Cement Lay Shop Dili
Crushed Aggregate, Near Source In Own Production
Stone
Sand Near Source Betano
Embankment Material Near Source Betano
Safety Equipment and Lay Shop
Dili
Tools
D. EQUIPMENT

Consideration has been given to the types of equipment that are likely to be used on-site during the
preparation and construction phases of the Proposed Development.
Table 2: Estimated Types of Equipment during the Demolition and Construction Phase

Equipment Preliminary Foundation Structure/Install Asphalt


Excavator ✓ ✓
Breaker ✓
End loader/backhoel ✓ ✓ ✓
Borepile Mechine ✓
Dump Truck ✓ ✓ ✓ ✓
Mobile Crane ✓ ✓ ✓
Stamper / Plate ✓ ✓ ✓
Concrete Ready Mixer √ ✓
Mixer (Molen) ✓ ✓ √
Concrete Vibrator ✓ ✓
Water Tank Truck ✓ ✓ ✓ ✓
Iron bender and cuter √ ✓ ✓
Welding machine √ ✓ √
Scaffolding ✓ √
Dewatering Pump √ ✓ √
Generator √ √ ✓ ✓
Electrical carpentry √ √ ✓ ✓
Hand Power Tools ✓ ✓ ✓ ✓
Asphalt Mixing Plant ✓
Concrete Batching Plant ✓ ✓
Vibratory Roller ✓ ✓ ✓
Bulldozer. ✓ ✓

E. HOURS OF WORK

It is anticipated that the core working hours for construction will be set out as follows:
· 08.00 – 18.00 hours
Weekdays;
· Working on Sunday will be subject to reasonable notice.
All work outside these hours will be subject to prior agreement, and/or reasonable notice to the
Engineer, who may impose certain restrictions. Although night time working will not normally be
undertaken, it is expected that some deliveries will take place at night and that certain works may have
to be undertaken during this period.
F. PROPOSED CONSTRUCTION METHODOLOGY

PREPARATION

Approximately of area are expected to be site cleared generated during preparation and excavation of
the foundation works.

Before the work starts the access points to the site shall be identified and while performing
construction we must maintain good environmental condition to prevent any incident.

Site cleaning proper will commence once access into the project site can be provided. The
construction access/egress to the project site will be provided by the construction of temporary access
road, which will subsequently be incorporated within the permanent works. We anticipate that this
could be completed within one weeks, to allow truck access to the project site for the disposal of site
cleaning/excavation foundation material and also can use for delivery of construction material.

The construction of site office and material storage will be done together with site cleaning. As the site
cleaning is made the project sign board and installed in a place that easily seen by including project
data, project value, time of implementation, etc.
❑ EXCAVATION WORKS include DEMOLISH LINE
STONE AREA LOCATION
This stage will take the construction as close as possible to the works access with the exact position
dependent on the agreed location for the works access and detailed analysis of the ground conditions.
During excavations, detailed monitoring of existing services and the like will be required, like:

1. Construction Method
• Submission of Shop Drawings
• Excavation of Unsuitable materials and surplus materials
• Disposing of materials excavated
2. Tools, Equipment and Machineries
• Excavator
• Bracker
• Fron end loader/backhole
• Dump Trucks
• Water Tank Truck
• Level Instrument
• Tool
3. Workmen List
• Site Engineer 1 job
• Site Supervisor 1 job
• Workers 5 jobs
• Driver and Operators 5 jobs

4. Safety

• Development of construction method and procedure and thoroughness of publicity to the


workers
• Enforcement of check before commencing work
• Communication of safety instruction particular
• Execution of toolbox meeting prior to commencing work
• All persons with safety protective equipment, helmet, and shoes.

❑ STONE MASONRY WALL

1. Construction Method

• Submission of materials testing and Shop Drawings


• Layout and Excavation for Slope protection to design elevations
• Compaction of base bedding for structure
• Installation of Boulder bedding and pouring of lean concrete for stone masonry walls
• Construction of batter boards
• Construction of Retaining slope protections
• Embankment of Backfill Materials and compaction
2. Tools, Equipment and
Machineries

• Excavator
• Bracker
• Fron end loader/backhole
• Dump Trucks
• Water Tank Truck
• Concrete Mixers 1 Bagger
• Hand Roller or Stamper
• Level Instrument
• Tools

3. Workmen List

• Site Engineer 1 job


• Site Supervisor 1 job
• Workers 10 jobs
• Driver and Operators 5 jobs

4. Safety

• Development of construction method and procedure and


thoroughness of publicity to the workers
• Enforcement of check before commencing work
• Communication of safety instruction particular
• Execution of toolbox meeting prior to commencing work
• All persons with safety protective equipment's, helmet, and shoes.

❑ EMBANKMENT WORKS/SOIL FILLING


1.
Cons
truct
ion
Met
hod
• Submission of Shop Drawings
• Embankment material from the excavation in location
transported using Dump Truck for common embankment and
take from quarry for selected materials
• Embankment material that was poured by Dump Truck are
paved and levelled using Wheel Loader
• The Material is compacted using Vibratory Roller assisted by
water tank truck to get the optimum compaction moisture
content. During the compaction a group of workers will be
smooth the heap edges and level using tools
• Measurement of all area elevation with survey equipment,
when not in accordance with the plans and specification
related instructed by the supervisory directors, carried
reworking
• Embankment Works/ Soil Filling is Completed

2. Tools, Equipment and Machineries

• Excavator
• Loader
• Dump Trucks
• Vibratory Roller
• Hand Roller or stamper
• Level Instrument
• Tools

3. Workmen List

• Site Engineer 1 job


• Site Supervisor 1 job
• Skilled Workers 1 job
• Workers 10 jobs
• Driver and Operators 5 jobs

4. Safety

• Development of construction method and procedure and


thoroughness of
• publicity to the workers
• Enforcement of check before commencing work
• Communication of safety instruction particular
• Execution of toolbox meeting prior to commencing work
• All persons with safety protective equipment's, helmet, and shoes.

3. COMMISSIONING AND HANDOVER


On completion of all works, the buildings shall be subjected to statutory
inspections before finally being handed over to the Construction Road

a. SITE LOGISITICS
Site logistics will form a significant part of the pre-appointment meetings for
Project Manager and that regular coordination meetings will be held
throughout the construction phase of the project. The principles of the logistics
plan will be detailed in all stages and brochures or mill certificate or other
documents issued from suppliers will submitted to Engineer for approval.

b. Site Accommodation
As shown in the schedule it would be construct temporary building as project
office and welfare accommodation. This would mean any external space
which can be agreed with the Engineer could be used solely for
loading/temporary storage.
The site accommodation will be relocated towards the end of the project and
main pedestrian entrance would be right alongside the accommodation area so
would heighten security and ease Health and Safety concerns.

c. Personnel Access
The proposed site personnel access is anticipated to be located at the main
gate. All personnel will be issued with access cards and a ‘no card, no entry’
principle will be applied. It also allows site management to quickly and easily
track what resources are on site on a day to day basis. It is good practice from
both a Health & Safety and logistics perspective to keep the pedestrian access
and vehicular access for deliveries completely segregated.

d. Deliveries
All deliveries will need to be kept off the main streets; it could have a ‘roll in
roll out’ system meaning that the delivery trucks must follow the flow of the
traffic. This will reduce disturbance to the neighbours and the general public
and ensure that there is no on-street loading or unloading which has clear
safety and traffic management benefits for all involved. Delivery arrangements
will of course need to be agreed with the Engineers.
G. MOBILIZATION SCHEDULE1. . EQUIPMENTS SCHEDULE

Monthly
No. Equipm
ent 1 2 3 4 5 6 7 8 9 10 11 12

1 Excavator 10 1 1 1 1 10 10 1 1 1 1 1
0 0 0 0 0 0 0 0 0
2 Breaker - 4 4 4 - - - - - - - -

3 End loader/backhoel 4 4 4 4 4 4 4 4 4 4 4 4

4 Borepile Mechine - 1 1 - - - - - - - - -
5 Dump Truck 24 24 24 24 24 24 24 24 24 24 24
24

6 Mobile Crane
4 4 4 4 4 4 4 4 4 4 4 4
7 Stamper / Plate Compactor 2 2 2 2 2 1
2 2 2 2 2 2
8 Concrete Ready Mixer 4 4 4 4 4 4 4 - -
- - 4
9 Mixer (Molen) 10 1 1 1 10 10 1 1 1 1 1
-
0 0 0 0 0 0 0 0
10 Concrete Vibrator 4 4 4 4 4 4 4 4 4 4 4
-
12 Water Tank Truck 3 3 3 3 3 3 3 3 3 3
- 3
13 Iron bender and cuter 2 2 2 2 2 2 2 - - - -
2
14 Welding machine 4 4 4 4 4 2 4 4 4 4 4 2

15 Scaffolding 2 2 2 2 2
- 2 2 2 2 2
16 Dewatering Pump
- 4 1 1 1 1 1 1 1 - - -

17 Generator 1 1 1 1 1 1 1 1 1 1 1 1

18 Electrical carpentry tools 1 1 1 1 1 1 1 1 1 1 1 1

19 Hand Power Tools 2 2 2 2 2 2


2 2 2 2 2 2
20 End loader/backhoe loader 4 4 4 4
4 4 4 4 4
21 Mobile Crane 2 2 2 2 2 2
2 2 2 2 2 2
22 Welding machine 2 2 2 2 2 2
2 2 2 2 2 2
23 Bar bending Machine 2 2 2 2 2 2
2 2 2 2 2 2
24 Scaffolding 5 5 50 50 5 5
50
0 0 0 0
25 Stamper / Plate 3 3 3 3 3 3
3 3 3 3

2. . MANPOWER SCHEDULE
Monthly
No. Man Power
1 2 3 4 5 6 7 8 9 10 11 12

1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1
2 Pavement Highway Engineer 1 1 1 1 1 1 1 1 1 1 1 1
3 Bridge Engineer 1 1 1 1 1 1 1 1 1 1 1 1
4 Quality Assurance / Material
Engineer 1 1 1 1 1 1 1 1 1 1 1 1
5 Quality Surveyor Engineer 1 1 1 1 1 1 1 1 1 1 1 1
6 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1
7 Environmental / Officer 1 1 1 1 1 1 1 1 1 1 1 1
8 Site Engineer 2 2 2 2 2 2 2 2 2 2 2 2
9 Site Supervisor 4 4 4 4 4 4 4 4 4 4 3 3
10 Surveyor 6 6 6 6 6 6 6 6 6 6 6 6
11 Quality Engineer/Laboratorio 4 4 4 4 4 4 4 4 4 4 4 4

Key-Responsibility for Management and Organization Structure

The contractor must maintain and organizational structure acceptable to the Owner and ensure that all
employers must have the necessary skills, knowledge, tools and equipment to implement the project base
on specification, Drawing and Bill of Quantities. The Minimum requirements of the Key- Responsibility
are following:
1. Director of Company
The Director is responsible for overall management of the project, controlling and monitoring
build progress and ensuring the project will be implemented base on work plan,
ensuring the quality of the project base on specifications, Drawing and Bill of
Quantities.

2. Project Manager / Site Construction Manager


The Contractor will be providing the professionals site/manager construction with a minimum
7 Year general work experience and 5 years similar work experience in construction area (see
CV attach on Key-Personal). The Site / Construction Manager is responsible for overall
management of the project, controlling and monitoring build progress and ensuring
the project will be implemented base on work plan, ensuring the quality of the
project base on specifications, Drawing and Bill of Quantities. The site/construction
Manager will be controlling and divided the work to the Site Engineer, Architect,
Electrical Engineer and reporting all the activity to the director of contractor.

3. Site Civil Engineer


The Contractor will be providing the professionals Site Civil Engineer with a minimum 5 Year
general work experience and 3 years similar work experience in construction area (see CV attach on
Key-Personal). The Site Engineer is responsible for ensuring all activities on site are carried out
accordance with the schedule and the construction drawing and make direct instruction to
Supervisor if necessary direct to the foreman to apply appropriate action for the smooth execution of
the work base on the specifications, Drawing and Bill of Quantities. The Site engineer also
responsibility for controlling and monitoring the supervisor for build progress and ensuring the
project will be implemented base on work plan, Drawing and Bill of Quantities. And the Site
engineer will be reporting progress of works to the Site Construction manager.

4. Site Supervisor
The Contractor will be providing the professionals Site Supervisor with good work experience on
construction area (see CV attach on Key-Personal). The Site supervisor responsible for ensuring all
activities on site are carried out accordance with the schedule and the construction drawing and
make direct instruction to the foreman to apply appropriate action for the smooth execution of the
work base on the specifications, Drawing and Bill of Quantities. The Supervisor also
responsibility for controlling and monitoring the foreman for build the work base on specifications,
Drawing and Bill of Quantities. And the supervisor will be reporting progress of works to the Site
engineer, Electrical engineer, Architect Engineer.

5. Site Surveyor
The Contractor will be providing the professionals Site Surveyor with good work experience on
construction area (see CV attach on Key-Personal). The Site Surveyor responsible for ensuring
all activities on site are carried out to Mapping section distribuition GIP &B POLY Pipe that
installation for STA – STA accordance with the schedule and the construction drawing and make
direct instruction to the foreman to apply appropriate action for the smooth execution of the work base
on the AS BUILD DRAWING MAPPING TRACKING specifications, Drawing and Bill of
Quantities. The SURveyor also responsibility for controlling and monitoring the foreman for build
the work base on specifications, Drawing and Bill of Quantities. And the SURveyor will be reporting
progress of works to the Site engineer,
Other Supporting staff like: Administration, Finances, Logistic, ect., will be support the Key-Staff for
managing all materials construction, equipment, Safety and health, environmental issues and all
administration work related items for the purpose of implementation of the project.

Name: Mario Gamboa


In the capacity of Authorized Representative

Signed…………………………………………………………………………………………………
Duly authorized to sign the Bid for and on behalf of BQ Corperation Unip Lda
Date: January 29, 2025