Subcontracting
Subcontracting
Subcontracting info record will be created for final product and vendor combination. ➢
Go to T. code- ME11.
➢ Give vendor.
➢ Give material.
➢ Give plant.
Select info category→ Subcontracting enter→ System will copy date from vendor if
required edit the information and save the info record.
Step 1) Create a standard purchase order for the material that has a BOM maintained.
On the component screen, enter storage location from which the components should
be issued.
I have created a fake BoM for our material (we sure can’t create LCD TV 40″ from two
components called semiconductors and plastics), but it’s enough to serve the purpose
(you can create a BoM in CS01 transaction if you don’t have it for your test material).
Step 3) In stock monitoring transaction, we will provide the components for vendor.
1. Select the components (click the boxes next to components material numbers).
2. Post goods issue.
Just confirm the right storage location and quantity. Do that for all of the components.
Step 6) You should see this kind of screen confirming that your PGI was done
successfully for 2 items.
You can see that there is a material document for the components, with movement
type 541.
Or
The next step is the issuing the components to the subcontractor. This is
done via MIGO. Select transfer posting against the purchase order. Even
though the goods are issued to the subcontractor, the ownership of the
stock is still lying with the manufacturer because the actual stock
consumption will happen only when manufacturer receives the finished
goods. Due to this, there is no accounting document created for this
material document. This issued stock will be shown in the MMBE as stock
issued to the vendor. This is a special stock in SAP and called as parts
provided to the vendor.
Step 8) Goods receipt. (MIGO)
In this step, the manufacturer will receive the finished goods from the
vendor. When the finished goods are received from the subcontracting
vendor that means that the components are consumed at the vendor
premise for making the finished goods.
You can post a goods receipt against a purchase order to receive the finished goods
from the vendor.
Now you have issued the components to subcontractor, received the finished product.
9. Invoice verification.
The baking team in the accounts payable department will do the vendor
payment.(SAP T code- F-53)