0% found this document useful (0 votes)
4 views2 pages

012125-mrf

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views2 pages

012125-mrf

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Republic of the Philippines Province

of Pampanga
SAN SIMON
PURPOSE OF VISIT: Monitoring of the Construction of Central MRF with DILG, LPMC, MEO and
MPDO
DATE: January 21, 2025
PLACE: San Agustin, San Simon, Pampanga

I. HIGHLIGHT:
 The Construction of the Central MRF should be completed on or before April 18, 2025, as per MC
No. 2024-006. The project timeline is 12 months from the date of issuance from the regional
office.
 The LGU should request a letter from the COMELEC for the exemption of the project prior to the
election ban.
 The MEO should submit to DILG-MLGOO a geotagged photo for the update on the backfilling of
the road leading to the construction site.
 The MEO should submit a new schedule of work in accordance with the MC No. 2024-006 project
deadline.

II. ISSUES, CONCERNS, RESPONSES, AND AGREEMENTS:


ISSUES/CONCERNS RESPONSES/AGREEMENTS
None None

III. REFERENCES:
Letter from the DILG dated January 17, 2025, RE: “Implementation of Construction of Central MRF
project funded under FY 2023 SGLGIF.”
Prepared by: Attested by:

AGNES Y. MACAPAGAL KIMBERLY P. CUNANAN


Admin Aide 1 OIC-MPDC/LDRRMO IV