Module 3 - Project Management Fundamentals-1
Module 3 - Project Management Fundamentals-1
A project manager
juggles numerous
activities
The Process of Identifying and
Selecting IS Development Projects
• Top-down source are projects
identified by top management or by a
diverse steering committee.
• Bottom-up source are project
initiatives stemming from managers,
business units, or the development
group.
• The process varies substantially
across organizations.
Project Management
Fundamentals
• Project initiation
• Determining project feasibility
• Activity planning and control
• Project scheduling
• Managing systems analysis team
members
Project Initiation
• Defining objectives
• Determining resources
• Operationally
• Technically
• Economically
The Three Key Elements of Feasibility Include
Technical, Economic, and Operational Feasibility
Technical Feasibility
• Planning includes:
• Selecting a systems analysis team
• Estimating time required to complete each task
• Scheduling the project
• Control includes:
• Comparing the plan for the project with its actual
evolution
• Taking appropriate action to expedite or
reschedule activities
Estimating Time
• Gantt Charts
• Simple
• Lends itself to end user communication
• Drawn to scale
• PERT diagrams
• Useful when activities can be done in
parallel
Using a Two-Dimensional Gantt Chart for
Planning Activities that Can Be Accomplished in
Parallel
PERT Diagram
C o n d u c t In te rv ie w s
Q u e stio n n a ire s
R e a d R e p o rts
A n a ly ze D a ta F lo w s
In tr o d u ce P r o to ty p e s
O b se rv e R e a c tio n s
P e r fo r m C o st/B e n e fit
P r e p a re P r o p o sa l
P r e se n t P ro p o sa l
1 5 10 15 20
C urrent W eek W eeks
PERT Diagram
I P r e s e n t P ro p o s a l H 2
20
A, 3 B, 4
C, 4 D, 8 G, 3 H, 2 I, 2
10 30 50 60 70 80
E, 5 F, 3
40
PERT Exercise
Gantt Chart
C A 2
D B 5
E D 3
F A 4
G C 3
H E, F 5
I G 6
J D 2
K H, I 2
L H, I 4
M J 3
N K 1
O L 2
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
A ctivity P re d e ce sso r D u ra tio n
A none 2
PERT
B A 3
C A 2
D B 5
E D 3
F A 4
G C 3
H E, F 5
I G 6
J D 2
K H, I 2
L H, I 4
M J 3
N K 1
O L 2
Paths
Paths Days
10-20-40-70-90-120 15
10-20-40-70-50-80-100-120 21
10-20-40-70-50-80-110-120 24
10-20-50-80-100-120 14
10-20-50-80-110-120 17
10-20-30-60-80-100-120 16
10-20-30-60-80-110-120 19
10-20-40-70-50-80-110-120
24
1. How many possible paths are there from the start to the end of the project?
2. Which tasks are on the critical path of the PERT chart above?
3. What is the slack time for tasks C, D and G?
4. The person working on task C tells the project manager he can't start work
until one day after the scheduled starting date. What impact would this
have on the completion date of the project? Why?
5. Task A will be delayed by 2 days because some equipment has arrived
late. If the project manager still wants to finish the project within the original
time frame, he will need to shorten the time for one or more of the tasks.
What steps can he take to reduce the number of days allocated to a task?
6. The project manager decides to reduce the time needed for tasks D and F
by one day each. How effective will this reduction be in achieving his aim of
maintaining the original finish time for the project?