Method Statement for Chasing Ceiling for New Location of Light Points and Junction Box

This document outlines a method statement for chasing ceilings to accommodate new light points and junction boxes, detailing the scope, purpose, materials, manpower, and equipment required. It emphasizes safety measures, quality control, and the proper methodology for executing the work, including preparation, chasing, and application of repair materials. Responsibilities for implementation and adherence to safety protocols are also specified to ensure compliance with project standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views7 pages

Method Statement for Chasing Ceiling for New Location of Light Points and Junction Box

This document outlines a method statement for chasing ceilings to accommodate new light points and junction boxes, detailing the scope, purpose, materials, manpower, and equipment required. It emphasizes safety measures, quality control, and the proper methodology for executing the work, including preparation, chasing, and application of repair materials. Responsibilities for implementation and adherence to safety protocols are also specified to ensure compliance with project standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Method Statement for Chasing

Ceiling for New Location of Light


Points and Junction Box
By Noel MadesPosted on October 6, 2017In Method Statement (MEP)3 Comments

Share1Save

If the design drawing for the electrical layout changed after pouring
concrete on the slab, then that would be a problem, so, in order to
resolve the said problem, you have to discuss with the engineer or
consultant at the earliest possible time.

The engineer most probably will ask the “method statement or


procedure” on how to resolve it. And the method statement below is
the one you can propose as this was what we’ve proposed too.

Here is the method statement for chasing ceiling for the new location
of light points and junction box.

1. Scope of Work
The purpose of this method statement is to describe the measures
and ways of rectification works for chasing ceiling as per project
specification and project quality plan.
2. Field of Application
This method statement would be used to make sure the proper way of
chasing the ceiling on the new line of conduits to the light points for all
the flats of first floor Block-A of this project.

3. Purpose
The purpose of this method is to define the specific tasks to be
performed by Company relating the chasing ceiling works and to make
sure quality of the output including the safety of the works.

4. Reference
• Design Layout Drawing / Shop Drawing
• Specification Section 00000 Concrete Works
• Material Approval for repair material

5. Material
• Cement Mortar (Premix approved by Engineer for repairing concrete)

6. Manpower
• Construction Manager
• Site Engineer
• QAQC engineer
• Safety officer
• Scaffolder
• Foreman
• Helpers
• Carpenters

7. Equipment & Tools


• Scaffolding
• Handheld concrete cutter/grinder
• Chisel
• Hand tools consisting of hammer, steel tape, suitable grouting tools
etc.
• Personal Protective Equipment

8. Work Methodology
8.1 Preparation prior to start chasing ceiling

Read also: Method Statement for Dewatering

8.1.1 The line of the PT duct would be marked onto the ceiling by the
Post Tension subcontractor representative to avoid clashing to the
new location of the light points/junction box. The line of new conduits,
junction box, and new light points would also be marked.

8.1.2 Clearance to be given by PT engineer, whenever necessary.

8.1.3 Inspection would be raised to the engineer for the marked PT


and MEP lines prior to proceed chasing work.

8.2 Chasing of Ceiling


8.2.1 Working platform would be provided by the use of scaffolding or
movable scaffold, it would be erected below the working zone by the
certified scaffolder. Barrication would be provided during work
commencing.

8.2.2 Erected scaffold shall be inspected and green tag would be


placed before the operatives can do the work.

8.2.3 Chasing would commence only after the approval of the marked
location of the conduits, junction box and light points.

8.2.4 The new marked location of the junction box and light points
shall be cut via hand-held cutting machine. Sizes of the cut shall be
wider than the size of junction box and light points to allow placement
of concrete repair material.
8.2.5 The new marked line of PVC conduit shall also be cut by
handheld machine.

8.2.6 The depth of the chased concrete shall not exceed the required
depth. The foreman and site charge-hand shall monitor the chasing
work in order to avoid inaccuracy.

8.2.7 Ensure that the operatives involved in the chasing of the ceiling
should wear appropriate PPE in order to avoid injuries.

8.2.8 Proper lighting would be provided whenever necessary.

8.2.9 Inspection would be raised for approval of the engineer prior to


MEP installations.

Read also: Method Statement for Pouring Concrete on Slab on Grade

8.3 Application of FRS Cement Mortar over installed


PVC conduits and sides of Junction Box and light
points
8.3.1 The approved material cement mortar (Fibre Reinforced
Shrinkage Mortar) shall be used for closing and repairing the chased
area.

8.3.2 Cleaning would be done prior to filling the area and


unsatisfactory conditions shall be removed before proceeding any
grout applications.

8.3.3 Priming: FRSCM must be applied before the bonding agent dries
while it is still tacky to achieve a better bond between the fresh and
cured section.

8.3.4 Mixing: For mixing process, a slow speed drill (200 – 250rpm)
fitted with a suitable paddle is recommended. Place (4.0 liters of cold
clean water in the mixing bucket. With the drill and operation, add the
entire content of the 25kg bag of FRSCM while mixing continuously till
a lump uniform consistency mix is achieved. Powder must be always
added to water.

8.3.5 Allow the obtained mix to stand for about 3 minutes and then
remix before application. Under no circumstances should partial
mixing be considered.

8.3.6 Application: Apply the FRS cement mortar manually with a


trowel or a spatula with full compaction, to the primed substrate while
it is still tacky.

8.3.7 The minimum applicable coat thickness is 10mm and the


maximum thickness shall be 50 mm for vertical and 25 mm for
overhead sections. For small horizontal sections, thickness should be
from 10mm up to 100mm. Application thickness is dependent on
repair size and granulometry. High build applications can be achieved
through temporary formwork.

8.3.8 If the application of the second coat is necessary the previous


layer should be cross-hatched and allowed to take up initial set before
applying the next coat.

8.3.9 Use trowel or sponge for the finishing touch.

Read also: Method Statement for Elevator Installation

8.3.10 The repaired area shall be cured in accordance with good


concrete curing practice and protected by drying winds. A water curing
shall be used by spraying. Curing should begin as soon as final finish
is achieved.

8.3.11 Application and further methodology shall be as per Material


Technical Data Sheet recommended by the manufacturer.

8.4 Application of Spray Plaster


8.4.1 Grinding would be made prior to application of spray plaster
course on the joints, if necessary.

8.4.2 Application of the succeeding spray plaster paint shall be done


as per approved paint system. Ensure that the paint system is
followed as per the manufacturer’s recommendation or technical data
sheet.

8.4.3 Final paint application would be inspected for engineer’s


approval.

8.4.4 Mock-up to be provided prior to proceed succeeding works.

9. Responsibilities
• Company Construction Manager shall be responsible for the overall
implementation of this method statement.

• Company Safety officers shall ensure implementation of all safety


procedures & safety measures related to the nature of works being
carried out and in accordance with the project HSE plan.

• Company site QA/QC Engineer is responsible for implementing the


related QA/QC Works as detailed in a quality plan.

10. Quality
• Company QA/QC staff shall monitor and ensure that documents
such as Method Statement shall be approved before commencing
chasing ceiling work.
11. Safety
• All works shall comply with the safety instruction/procedure as set
out in the approved project HSE plan and all safety recommendations
of local authorities shall be followed.
• All works should comply with safety procedure / instruction as set out
in project safety plan.

• Basic PPE to be worn by all staff.

• Sufficient lighting would be arranged during the works when required