Method Statement for Chasing Ceiling for New Location of Light Points and Junction Box
Method Statement for Chasing Ceiling for New Location of Light Points and Junction Box
Share1Save
If the design drawing for the electrical layout changed after pouring
concrete on the slab, then that would be a problem, so, in order to
resolve the said problem, you have to discuss with the engineer or
consultant at the earliest possible time.
Here is the method statement for chasing ceiling for the new location
of light points and junction box.
1. Scope of Work
The purpose of this method statement is to describe the measures
and ways of rectification works for chasing ceiling as per project
specification and project quality plan.
2. Field of Application
This method statement would be used to make sure the proper way of
chasing the ceiling on the new line of conduits to the light points for all
the flats of first floor Block-A of this project.
3. Purpose
The purpose of this method is to define the specific tasks to be
performed by Company relating the chasing ceiling works and to make
sure quality of the output including the safety of the works.
4. Reference
• Design Layout Drawing / Shop Drawing
• Specification Section 00000 Concrete Works
• Material Approval for repair material
5. Material
• Cement Mortar (Premix approved by Engineer for repairing concrete)
6. Manpower
• Construction Manager
• Site Engineer
• QAQC engineer
• Safety officer
• Scaffolder
• Foreman
• Helpers
• Carpenters
8. Work Methodology
8.1 Preparation prior to start chasing ceiling
8.1.1 The line of the PT duct would be marked onto the ceiling by the
Post Tension subcontractor representative to avoid clashing to the
new location of the light points/junction box. The line of new conduits,
junction box, and new light points would also be marked.
8.2.3 Chasing would commence only after the approval of the marked
location of the conduits, junction box and light points.
8.2.4 The new marked location of the junction box and light points
shall be cut via hand-held cutting machine. Sizes of the cut shall be
wider than the size of junction box and light points to allow placement
of concrete repair material.
8.2.5 The new marked line of PVC conduit shall also be cut by
handheld machine.
8.2.6 The depth of the chased concrete shall not exceed the required
depth. The foreman and site charge-hand shall monitor the chasing
work in order to avoid inaccuracy.
8.2.7 Ensure that the operatives involved in the chasing of the ceiling
should wear appropriate PPE in order to avoid injuries.
8.3.3 Priming: FRSCM must be applied before the bonding agent dries
while it is still tacky to achieve a better bond between the fresh and
cured section.
8.3.4 Mixing: For mixing process, a slow speed drill (200 – 250rpm)
fitted with a suitable paddle is recommended. Place (4.0 liters of cold
clean water in the mixing bucket. With the drill and operation, add the
entire content of the 25kg bag of FRSCM while mixing continuously till
a lump uniform consistency mix is achieved. Powder must be always
added to water.
8.3.5 Allow the obtained mix to stand for about 3 minutes and then
remix before application. Under no circumstances should partial
mixing be considered.
9. Responsibilities
• Company Construction Manager shall be responsible for the overall
implementation of this method statement.
10. Quality
• Company QA/QC staff shall monitor and ensure that documents
such as Method Statement shall be approved before commencing
chasing ceiling work.
11. Safety
• All works shall comply with the safety instruction/procedure as set
out in the approved project HSE plan and all safety recommendations
of local authorities shall be followed.
• All works should comply with safety procedure / instruction as set out
in project safety plan.