SWMS_Tiles cutting & Fixing work

This Safe Work Method Statement outlines the procedures, hazards, risks, and control measures for tile cutting and fixing work at HILTI Manufacturing India Pvt. Ltd. It emphasizes the importance of worker training, proper supervision, and the use of personal protective equipment (PPE) to ensure safety on site. The document also includes details about the responsibilities of supervisors and the necessary legislative compliance for the project.

Uploaded by

NAGARJUNA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views9 pages

SWMS_Tiles cutting & Fixing work

This Safe Work Method Statement outlines the procedures, hazards, risks, and control measures for tile cutting and fixing work at HILTI Manufacturing India Pvt. Ltd. It emphasizes the importance of worker training, proper supervision, and the use of personal protective equipment (PPE) to ensure safety on site. The document also includes details about the responsibilities of supervisors and the necessary legislative compliance for the project.

Uploaded by

NAGARJUNA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 9

Safe Work Method Statement

Project Name: HILTI MANUFACTURING INDIA PVT. LTD. Address: Savli, Gujarat
Company Name: SCON Projects Private Limited Activity/Work:- Tiles cutting & fixing work
Address: Samarth House Sr. No. 116, Hissa No. 3/1,3/3, 3/10, Pune Bangalore Highway, Near Shell Petrol Pump, Warje, Pune-411058
Office Contact No: 020-25286425
PM/Supervisor Name Mr. Sachin Khairnar Contact No.: 9657002698
Person who
Procedure (in steps) Possible Hazards Risk Control Measures
will ensure
(Break the job down into (Identify the hazards associated with Rating (Describe what action or procedure will be taken to eliminate or minimize
the risk of injury or damage. Use the Hierarchy of Controls below as a this happens
steps. Each step should each step. Examine each to find (See
accomplish some major possibilities that could lead to an below) guide
tasks and be in logical accident or potential harm arising.) 1. Eliminate the Hazard
sequence.) 2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE

Prepared by Reviewed by Reviewed by Reviewed by Approved by


SCON HSE SCON Project Manager JLL HSE HILTI HSE HILTI Project Manager
1) All workers Medical Fitness Certificate to be submitted before
entering the site. Project
Manager/
2) Safety induction training will be conducted for all workers.
Admin/
3) It will be ensured that all workers have valid gate pass before Safety
enter in site. Officer
H
4) Tool box talk will be conducted every day before start of the work.
5) SOP's & Safe Work method Statement's will be briefed to workers
 Unskilled, Untrained M before starting the work.
1 Mobilization new Manpower,
manpower 6) Job specific trainings will be conducted for workers.
 Unaware about workplace
7) Only authorized, medically fit and trained workers will be
deployed for the work.
8) Proper supervision will be provided.
9) It will be insured that Mandatory PPE's & Job specific PPE's are
being provided and worn by workers while working.

Area
1) RCCB/ ELCB in main supply board to be there. Supervisor
M and
2) Use of good insulation electrical cable.
Engineer
 Electric shock M 3) Joint free cables shall be used. No loose connections allowed for the
work
2 Electrical Connection
 Short circuit
4) Electrical Cable inspection shall be done by Authorized Electrician.
M
 Fire
5) Remove all flammable & combustible material from work area.
6) Fire extinguisher / Fire point available on working area.
M 1) Ensure all power tools shall be good condition and inspected by Area
Tiles Cutting activity Safety dept with respective checklist. Supervisor
 Un inspected cutting machine
M and
2) Ensure defective tools not allowed to work. Engineer
 Flying chips
3) Work area shall be clear and free from any obstruction
M
 Cleaning of burr on blade 4) Use small metal stick to remove of burr.
3 5) Workmen should be having safety goggle, nose mask , hand gloves
along with all mandatory PPE’s
6) Area shall be barricade along with safety poster’s
7) Ensure Proper supervision will be provided.
8) Ensure height work permit taken by Engineer and verified by safety
officer prior to work.

M 1) Ensure only inducted person should be deployed at work place. Area


 Untrained person
Tiles Fixing activity Supervisor
M 2) Workmen should be having nose mask, rubber hand gloves, safety and
 Improper Handling goggle, along with all required PPEs
4
Engineer
3) Ensure do not use defective hand tools during fixing tiles.
4) Area shall be barricade along with safety poster’s

Area
1) Ensure proper illumination during dark hours.(100 lux) Supervisor
and
2) Route shall be illuminated.
Engineer
3) Ensure close supervision will be done while working at night work.
H
 Darkness 4) Job specific training has been conducted to all worker’s
5 Work during dark hours
 Fall of person , materials
H
Personnel Summary

SUPERVISOR’S DETAILS
Supervisors Name & Qualifications: Name: Mr. Umesh Prajapati
Experience: 10 Years
Qualifications: BE (Civil)
Supervisor’s Responsibilities: In addition to the above, the supervisor is to provide training in the use of this SWMS, issue PPE and
provide training in the same, supervise the work, ensure conformity with this SWMS, amend the SWMS
when additional hazards are found (and if applicable, ensure all workers receive a tool-box talk to discuss
the control measures for the additional hazards).

DESCRIPTION OF TRAINING THAT HAS BEEN GIVEN TO PEOPLE INVOLVED WITH THE WORK

H&S GENERAL INDUCTION: General Safety Induction Yes

WORK ACTIVITY TRAINING:

SITE INDUCTION: Site safety induction, Yes

OTHER: (List other training undertaken by workers):

TICKETS, PERMITS or LICENCES REQUIRED undertaking this work (ie. Certificates of Competency, Confined Spaces etc):

Vehicle Insurance, PUC, Driver License

LEGISLATION, CODES OF PRACTICE and GUIDELINES applicable to this work

BOCW ACT 1996 & RULES 2003, GUJARAT BUILDING AND OTHER CONSTRUCTION WORKERS (REGULATION OF EMPLOYMENT AND CONDITIONS OF
SERVICE).
Additional Codes and Standards applicable to this trade:
Equipment & Material Summary
PLANT and EQUIPMENT USED and MAINTENANCE FREQUENCY :

Serial Plant/Equipment Contractor Work cover Plant Maintenance/service records and log books
Registration Hazards sighted by Principal Contractor prior to
No (if identified equipment being used on site?
applicable) and
controlle Yes No Sign Date
d within
SWMS?
1
2

ELECTRICAL EQUIPMENT USED DURING THE WORKS (Attach Electrical Equipment Register if applicable):
Item Tag/ Testers Name License Test Result Test Result
Item & Signature Number Date Date
Number
____
____ /___
/____ _
/____ /___
_
____
____ /___
/____ _
/____ /___
_
HAZARDOUS SUBSTANCES or DANGEROUS GOODS USED IN THE WORKS and anticipated volumes (Attach MSDS if
applicable):
Purpose Location & MSDS
Date MSD
(i.e. Volume Controls Attache
Date on Site Left Product Name S
Applicatio Used on (& PPE to be worn) d
Site Date
n on site) Site (Y/N)
/ / / / Cement / /
/ / / / / /
N.B. - All workers must be trained in the safe use of all chemicals and provided with the PPE required when using and storing these chemicals. Disposal
is to be as per the waste disposal methods in the MSDS. Spillage and leaks are to be cleaned up as per the spill/leak procedures identified in the MSDS.
We agree that we have been consulted in the hazards and control measures and agree to complete the work in accordance with our Safe Work
Method Statement (SWMS).
We have been provided with training in all tasks outlined in our SWMS and in the Codes of Practice applicable to our work.

Sr. No. Employee / Worker Signature Date


1. / /
2. / /
3. / /
4. / /
5. / /
6. / /
Any changes, additions or deletions made to this SWMS are to be covered with the above personnel and the Principal Contractors representative at a
Toolbox meeting (Record date and time of Toolbox meeting below):

Date: Time:
Comments:

A copy of the Toolbox Meeting must be attached to this SWMS.