KCV 27090

The document is an Asset Integrity Assessment Form for the FM-200 system at Katara Cultural Village, detailing project and asset identification, assessment observations, and performance results. Key findings include satisfactory visual inspection and functional tests, but several alarm circuit issues and a recommendation to adjust the manual pull station delay to 0 seconds. Overall, the FM200 system's functionality is deemed satisfactory despite some non-compliance in alarm circuits.

Uploaded by

amine.cha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views3 pages

KCV 27090

The document is an Asset Integrity Assessment Form for the FM-200 system at Katara Cultural Village, detailing project and asset identification, assessment observations, and performance results. Key findings include satisfactory visual inspection and functional tests, but several alarm circuit issues and a recommendation to adjust the manual pull station delay to 0 seconds. Overall, the FM200 system's functionality is deemed satisfactory despite some non-compliance in alarm circuits.

Uploaded by

amine.cha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

High Priority

Medium Priority

Low Priority

ASSET INTEGRITY ASSESMENT FORM

1. Project Details
Project Asset Integrity Assessment of Critical Systems
Client Katara Cultural Village FMS Mosanada

2. Asset Identification Details


Barcode KCV-027090 Asset Code KCV-027090
Description FM- 200 Sys Building Children Mall Location 3rd Floor ELV
Room

3. Asset Details
Make: Secutron Model Type FECP
Serial Number: Rating Mfg year 2017

4. Assessment Observations / Results

Extinguishing Panel Information FM 200 Cylinder Information


Manufacturer Secutron Manufacturer LPG
Model Serial No 12520054/12520031
Type Agent Weight LBS 13/13
Voltage 239 VAC Tare Weight LBS 19.4/19.4
Battery 3.6 VDC (low) Total Weight LBS 32.8/32.6
Program Actuator Validity
Location Outside the protected Room Validated Date 20-9-24
Tag Validated in Kgs 34.4/32.6

No. Items Check Change Test Remarks


1 Gauge Pressure Level √
2 Physical Condition √
3 Bracket
4 Tagged √
5 Collar √
6 Safety Cap √
7 Flexible Hose
8 Solenoid Valve 60 sec
9 Nozzle
10 Zone 1 – Smoke Detector x
11 Zone 2 – Smoke Detector x
12 Alarm Notification
13 Manual Pull Station √ 20 sec
14 Abort Switch √ 60 sec
15 Physical condition of Agent cylinder √
16 Piping visual inspection √

Page 1 of 3
ASSET INTEGRITY ASSESMENT FORM
17 Signages √

System Function Summary & Test


Alarm Panel Supervisory Functions
Function Description Test Result
Panel AC Power Loss Loss of AC power to the alarm panel is detected by the OK
alarm system
Panel Sec Power Loss Loss of Secondary power to the alarm panel is detected OK
by the alarm system.
Open Alarm Circuits Electrical opens in initiating and indicating circuits are OK
detected
Short Alarm Circuits Electrical shorts in initiating and indicating circuits are Not OK
detected.
Panel to Panel Circuits Integrity of single or multiple circuits providing interface Not OK
between two or more control panels verified
Ground Faults Ground faults in alarm and power circuits are detected Not OK
Detected

System Function Summary & Test


Alarm Functions - Chemical Suppression
Function Description Test Result
1st Alarm A single initiating zone shows alarm OK
2nd Alarm A 2nd initiating zone shows alarm OK
Time Delay Delay between 2nd alarm and agent discharge 60 sec
Discharge Alarm Audible alarm upon agent discharge OK
Agent discharge Actual discharge of chemical fire suppression agent Not OK
Abort Switch Switch prevents discharge of chemical fire suppression 60 sec
agent.

Panel Inspection
System was in operation upon arrival?_ Yes
Panel and surrounding equipment, conduit and wiring well secured and in good condition_ Yes
Are all lamps and displays operating correctly?_ Yes
Primary power supply operates properly under full load? _ No
Are drawings and wiring diagrams available at the panel?_ No
Are operating instructions posted or available at the panel?_ No
Are zones labelled and identified?_ No

Page 2 of 3
ASSET INTEGRITY ASSESMENT FORM

5. Performance Assessment Summary


Parameter Actual Requirement
Result Remarks
Observation Min. Max.
1. Visual Inspection As mentioned Acceptable OK
in Clause 4.
2. Functional Test As mentioned Activation & Acceptable OK
in Clause 4. Sequence of
Operation as Per
QCDD
6. Conclusion & Recommendation
The above mentioned FM200 system has been assessed and the functionality is satisfactory:

Notes & Recommendations:


• Manual Pull station delay should be 0 sec.

Page 3 of 3