Module-A211-04
Module-A211-04
Process cost systems are used to apply costs to similar products that are mass
produced in a continuous fashion, such as the production of ice cream, steel or soft
drinks. In comparison, costs in a job order cost system are assigned to a specific job,
such as the construction of a customized home, the making of a motion picture, or the
manufacturing of a specialized machine.
Suppose that a furniture company has the following processes involved in building its
products: machining and assembly. In the Machining Department, the raw materials are
shaped, honed, and drilled. In the Assembly Department, the parts are assembled and
packaged.
Materials, labor, and manufacturing overhead can be added in both the Machining and
Assembly Departments. When the Machining Department finishes its work, the partially
completed units are transferred to the Assembly Department. In the Assembly
Department, the goods are finished and are then transferred to the finished goods
inventory. Upon sale, the goods are removed from the finished goods inventory.
All raw materials issued for production are a materials cost to the producing department.
Materials requisition slips may be used in a process cost system, but fewer requisitions
are generally required than in a job order cost system, because the materials are used
for processes rather than for specific jobs. The entry to record the materials used is:
Time tickets may be used in determining the cost of labor assignable to the production
departments. The labor cost chargeable to a process can be obtained from the payroll
register or departmental payroll summaries. All labor costs incurred within a producing
department are a cost of processing the raw materials. The entry to assign the labor
costs is:
The basis for allocating the overhead costs to the production departments in an objective
and equitable manner is the activity that “drives” or causes the costs. A primary driver of
overhead costs in continuous manufacturing operations is machine time used, not direct
labor. Thus, machine hours are widely used in allocating manufacturing overhead costs.
The entry to allocate overhead is:
At the end of the period, the following transfer entries are needed:
Equivalent Units
A major step in process cost accounting is the calculation of equivalent units. Equivalent
units of production measure the work done during the period, expressed in fully
completed units. This concept is used to determine the cost per unit of completed
product.
The formula to compute equivalent units of production under the weighted average
method is as follows:
The method of computing equivalent units here is referred to as the weighted average
method. It considers the degree if completion (weighting) of the units completed and
transferred out and the ending work in process. A lesser used method, called the FIFO
method, is discussed in Appendix 1.
To illustrate the computation of equivalent units using the weighted average method,
A production cost report is the key document used by management to understand the
activities in a department because it shows the production quantity and cost data related
to that department. In order to be ready to complete a production cost report, the
company must perform four steps:
a. Compute the physical unit flow.
b. Compute the equivalent units of production.
c. Compute unit production costs.
d. Prepare a cost reconciliation schedule.
In the example above, the total units to be accounted for and the units accounted
for are both equal to 7,000 units for Skopje Company.
In computing unit costs, production costs are expressed in terms of equivalent units of
production. When equivalent units are different for materials and conversion costs, the
formulas for computing unit costs are as follows:
The cost reconciliation schedule shows that the total costs accounted for equal the
total costs to be accounted for as follows:
The Skopje Company’s Processing Department Production Cost Report at the end of the
period is as follows:
Operations Costing
Companies often use a combination of a process cost and a job order cost system,
called operations costing. Operations costing is similar to process costing in that
standardized methods are used to manufacture the product. At the same time, the
product may have some customized, individual features that require the use of a job
order cost system.
The equivalent units for material costs of the Processing Department under the FIFO
method are computed as follows:
The equivalent units for conversion costs of the Processing Department under the FIFO
method are computed as follows:
Assume the Processing Department of the Skopje Company has the following additional
cost information:
The Skopje Company’s Processing Department Production Cost Report at the end of the
period using the FIFO method is as follows:
All Wood is considering switching from one overhead rate based on labor hours to
activity-based costing.
Instructions
Perform the following analyses for these two components of overhead:
a. Compute total machine setups and inspection costs assigned to each product, using
a single overhead rate.
b. Compute total machine setups and inspection costs assigned to each product, using
activity-based costing.
EXERCISE 2
1. Write down a summary about process costing.
Sources:
Cabrera & Cabrera / Management Accounting Concepts and Application, 2017 Edition
Hilton / Managerial Accounting, 9th Edition
IMA / Standards of Ethical Conduct for Management Accountants,
https://www.accountingverse.com/managerial-accounting/introduction/code-of-ethics.html
Kieso & Waygandt / Managerial Accounting, 4th Edition
Roque, Rogelio S. / Reviewer in Management Advisory Services, 2016 Edition
End of Week 4