The Monthly Progress Report No. 54 for the Design and Construction of Gishen Junction -Km 14 road project indicates that as of December 2024, only 14.24% of the work has been completed, significantly lagging behind the elapsed time of 102.89%. The project, originally scheduled for completion in November 2024, has faced delays due to issues such as design holdups and mobilization challenges. Financially, the total estimated contract amount has increased to ETB 1,420,078,845.39, with variation orders adding ETB 103,378,845.39 to the original contract price.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views13 pages

STATUS 54 Dec 2024

The Monthly Progress Report No. 54 for the Design and Construction of Gishen Junction -Km 14 road project indicates that as of December 2024, only 14.24% of the work has been completed, significantly lagging behind the elapsed time of 102.89%. The project, originally scheduled for completion in November 2024, has faced delays due to issues such as design holdups and mobilization challenges. Financially, the total estimated contract amount has increased to ETB 1,420,078,845.39, with variation orders adding ETB 103,378,845.39 to the original contract price.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project

Monthly Progress Report No.54/December 2024

MONTHLY PROGRESS REPORT OF DECEMBER 2024

Project: Design and Construction of Gishen Junction Km 14 road Project


Reporting Period: from November 26, 2024 – December 25, 2024
To: Ethiopian Roads Administration,
Kombolcha Area Construction Projects Management Office

1. EXECUTIVE SUMMARY

1.1 BASIC CONTRACT DATA


A/ Works Contract

Project Name Construction Supervision of Gishen Junction -Km 14

Project Location Amhara Regional National State, South Wello Zone

Project Length (as per the


14 km
conceptual design)

Project length (Final) 18.743 km

Type of work Design and Build

Types of Contract Lump sum

Funded by Federal Government of Ethiopia

Employer Ethiopian Roads Administration

Contractor Ethiopian Construction works Corporation

Letter of Acceptance issued 20thFebruary 2020.

Date of Signing of Contract 16th April, 2020.

Date of Commencement 27th May ,2020

Time for Contractor’s


4 months
Mobilization

Time for Construction 915 Calendar Days (including 4 months mobilization period)

Defects Liability Period 365 Calendar Days from the issue of the taking Over Certificate

Original Contract Completion


After 30 months
Date

Approved extended calendar


712 Calendar Days
days

Final Revised Completion date 8th November 2024

Elapsed time to date 1672

Original Total Contract lump ETB 1,316, 700, 000.00 [including VAT]
Page 1
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024

sum Price

Value of Variation Orders to date ETB 103,378,845.39including 15% VAT

Value of Claims Approved to


None
date

Total Price Adjustment to date ETB 118,013,244.00

Estimated final contract Amount ETB 1,420,078,845.39 including 15% VAT

Currency Local Currency

Exchange Rate 1

ETB 32,920,950.00 (including 15% VAT) With conditional advance


guarantee
Advance payment issued so far 98,752,500.00. (including 15% VAT)With unconditional guarantee
122,527,352.29(including 15% VAT)With unconditional guarantee

Start Repayment of Advance After Certification of 30% of the Contract Price including price
Payment adjustment

Repayment amortization 40% of the amount of monthly Interim Payment Certificates

Minimum Amount of Interim


Birr 5,000,000.00
Payment

5% of Interim payment certificates, up to a maximum of 5% of the


Percentage of Retention Money
contract price

Amount of Liquidated Damages 0.1% of the value of the remaining works per day

Limit of Liquidated Damages 10% of the value of the remaining works

B/ Insurance and Guarantee Bond

Performance security bond amount ETB 131,670,000.00

Expiry date of performance security


After 1261 Calendar days
Guarantee

Advance payment Amount ETB 263,340,000 (including 15% VAT)

Expiry date of Advance payment


354 Calendar days
guarantee

Insurance for Works (CAR), as per


NA
sub clause 18.2

Expiry date of CAR Insurance Bond NA

Page 2
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024

Professional Indemnity Insurance, as


ETB -
per Sub Clause 18.1

Expiry date for PI insurance -

Insurance for Workmen and


-
equipment

C/ Supervision Service Contract

Supervision Consultant Prominent Engineering Solutions

Date of Contract signature 07th February 2020

Original Contract Amount ETB 23,939,921.45

Type of Contract Time base

Commencement date 25th February 2020

Contract period 30 months for construction supervision plus 1-year defect liability

1.2 PROGRESS STATUS BRIEFING


This Monthly Progress Report No 54 of December 2024 covers the work progress of the contractor and
the tasks performed by the Employer’s Representative for the period November 26, 2023–December 25,
2024.

 So far, 1672 calendar days (i.e102.89% of the contract period) have elapsed and the estimated to
date accomplishment is 14.24% of the total workload. This is equivalent to a weighted average
of 2.67km.
 During the reporting period of the month December 2024, the contractor’s actual estimated
accomplishment is 0.06% (0.01km) of the contract amount.
The following table shows the financial and physical progress of the works up to the end of the reporting
period:

Table: 1.2:- Financial and Physical progress (for the reporting month and to date)

Up to Previous
Description
Month This Month To date

%age Km %age Km %age Km

plan 22.18 4.16 4.76 0.89 26.94 5.05

Actual 14.17 2.66 0.06 0.01 14.24 2.67

Page 3
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024

Actual Vs plan 63.90 1.35 52.85

Up to Previous
Description
Month This Month To date

%age METB %age METB %age METB

plan 22.18 253.93 4.76 54.50 26.94 308.42

Actual 14.17 162.27 0.06 0.74 14.24 163.01

Actual Vs plan 63.90 1.35 52.85

Page 4
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

To end of this reporting period, the overall accomplishment of the project is 14.24%(2.67km) while the to
date planned work is 26.94%( 5.05Km) and the time elapsed to date is 102.89% (1672Days) Cal Days)

It also shows the accomplishment is much less with respect to time elapsed; while the progress is 14.24%of
time elapsed to date and this shows that the accomplishment is lagging from time.

This fiscal year’s actual progress is also 0.86 %( 0.15km) In addition; the reporting period monthly
progress is0.06%( 0.01km).

Physical progress for Main item of works

The cumulative physical status of each bill item shown below with respect to the planned length (km) or
(percentage) and the actual accomplishment.

Table 1.4: Major Work Items (bill group) of the Works Contract accomplishment with respect to the
Action Plan for 2017 EFY

Up to previous
This Month To date Amount
month
Weighted Plan Actual Plan Actual Plan Actual
Bill
Description Average
No.
(%)
% % % % % %

Survey, Investigation and


1 2.00% 1.61% 1.54% 0.03% 0.00% 1.63% 1.54%
Design

Series 1000/Division 1400


2 Project/Employer's 4.00% 2.25% 2.07% 0.07% 0.00% 2.32% 2.07%
Representative Facilities

Series 1000/Division
3 1500/Detour and Traffic 1.50% 0.89% 0.78% 0.04% 0.00% 0.92% 0.78%
Management

Series 2000 and 4000/Site


4 31.50% 14.34% 9.52% 2.20% 0.06% 16.54% 9.58%
Clearance and Earthwork

5 Series 5000/Subbase 5.00% 0.38% 0.01% 0.20% 0.00% 0.58% 0.01%

6 Series 5000/Base Course 10.00% 0.61% 0.00% 0.38% 0.00% 0.99% 0.00%

Page 5
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

Series 6000/Bituminous
7 30.50% 0.78% 0.00% 1.28% 0.00% 2.06% 0.00%
Surface

Series 3000, Series 8000 and


Series 9000/Bridge, Culvert,
8 11.00% 1.29% 0.26% 0.52% 0.00% 1.81% 0.26%
Drainage and Protection
Work

Series 9000, Series 1000 and


9 Series 2000/Road Furniture 4.50% 0.04% 0.00% 0.04% 0.00% 0.08% 0.00%
and Environmental Works

14.24
Total 100.00% 22.18% 14.17% 4.76% 0.06% 26.94%
%

Accomplishment with respect to Plan 63.90% 1.35% 52.85%

Note:

The Planned amount up to end of this reporting period is as per the Contractor’s Action plan for 2017 EFY

1.2.1 BILL NO. 1: SURVEY, INVESTIGATION AND DESIGN


The progress of works with respect to assessments and selection of routes, survey, investigation and design
works are presented below.

Survey, Investigation and Design works have 2% of weight from the total project values. Work planned
according to contractor’s Action plan, to end of this reporting month is1.63% (with respect to total
project cost), however, contractor’s accomplishment to date is 1.54%.
Page 6
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 81.65% 77.00% 5.54%

%age from total project cost 1.63% 1.54% 5.54%

1.2.2 BILL NO. 2: GENERAL


The General item have5.50% weight from the total Project Values. Work planned to end of this reporting
month was 5.50% (with respect to total project cost), and contractor’s accomplishment to date is2.85%.

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 59.00% 51.82% 12.03%

%age from total project cost 3.25% 2.85% 12.03%

1.2.3 BILL NO. 4: SITE CLEARANCE AND EARTHWORK


This work comprises clearing and grubbing, roadbed preparation and treatment of expansive, soil cut &
borrow to fill and cut to waste.

This item of work has 31.5% weight from the total project values. Work planned to end of this reporting
month was 16.54% (with respect to total project cost), and contractor’s accomplishment to date is
9.58%.

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 55.52% 30.41% 42.11%

%age from total project cost 16.54% 9.58% 42.11%

1.2.4 BILL NO. 5: SUBASE, ROADBASE AND GRAVEL WEARING COURSE


This work comprises sub base production, hauling and placing of Sub base material. This item of works has
5% weight from the total project values.

Description Planned Actual slippage

Page 7
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

Accomplishment Accomplishment

% age from item of work 6.12% 0 100%

%age from total project cost 0.61% 0 100%

1.2.5 BILL NO. 5: BASE COURSE


This work comprises sub base production, hauling and placing of Sub base material. This item of
works has 10% weight from the total project values.

Planned Actual
Description slippage
Accomplishment Accomplishment

% Age from item of work 2.56% 0 1000%

%Age from total project cost 0.78% 0 100%

1.2.6 BILL NO. 7: BITUMINOUS SURFACING


This work comprises prime coat application for carriageway, Asphalt Surface aggregate production and
construction.

This item of works has 30.5 % weight from the total project values.

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 2.56% 0% 100%

%age from total project cost 0.78% 0 100%

1.2.7 BILL NO. 8: BRIDGE, CULVERT, DRAINAGE AND PROTECTION WORKS


This work comprises Bridge construction, Slab/Box and slab culvert construction, Roadside drainage and
protection works.

This item of works has 11% weight from the total project values.
The cumulative progress of the item to date with respect to its bill amount and total project cost presented
hereunder

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 11.71% 2.33% 80.12%

Page 8
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

%age from total project cost 1.29% 0.26% 80.12%

1.2.8 BILL NO. 9: ROAD FURNITURE AND ENVIRONMENTAL PROTECTION WORKS


This work comprises mainly road furniture works and Environmental protection works as the title
indicated.

This item of works has 3% weight from the total project values. The cumulative progress of the item to
date with respect to its bill amount and total project cost presented hereunder

Planned Actual
Description slippage
Accomplishment Accomplishment

% age from item of work 0.81% 0 100%

% age from total project cost 0.04% 0 100%

1.3 ENCOUNTERED PROBLEMS

1.3.1 PROBLEMS FROM PREVIOUS MONTHS

 Delay on design of the project road.


 Delay on mobilization of the required material resource, machinery and equipment and sufficient
man power.
 Delay in the arrangement of the permanent facility, vehicle and laboratory equipment for the
engineer.
 Shortage of construction materials including fuel and cement

 Slow action of the contractor to engage in permanent works.


 Slow action in requesting removal of row obstacles and on arranging required facilities to identify
obstacles for the row committee and the engineer.
 The contractor has continued on unauthorized works ignoring consultants’ advice regarding west
disposal.

1.3.2 PROBLEMS IN THIS MONTH

 Delay on finalizing design of the project road.


 Delay on mobilization of the required material resource, machinery and equipment and sufficient
man power.
 Delay in the arrangement of the permanent facility, vehicle and laboratory equipment for the
engineer.
 Shortage of construction materials.

 Slow action of the contractor to engage in permanent works.

Page 9
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

 Slow action in requesting removal of row obstacles and provide clear information to the ER.

1.4 ACTIONS TAKEN /PROPOSED SOLUTION.

 The consultant has produced letters and forwarded to the contractor and arrange bilateral and
tripartite meeting to solve the project issues
 The Consultant has done lots of discussions with the Contractor including Design consultant
regarding the design issues and also has written notice on delay of Design deliverables.
 The Contractor is frequently reminded to arrange temporary facility for the engineer, though no
satisfactory action taken so far.

1.5 PREPARATORY WORKS

 The contractor has not shown preparatory works except earth work. Even though the contractor
mobilized additional pipe moulds and cement in the reporting period, structural works are not
proceeding as per the plan.

1.6 AVAILABILITY OF KEY EQUIPMENT IN THE REPORTING MONTH

Availability of Key Equipment during the month is shown below.

Description Dozer Grade Exc Paver Rol. D.T Loader W. Fuel W.Drill Mobile Crusher
r T Crane
T.

Total 4 1 4 - 2 11 3 2 1 - - 1
Avail. no

Working 3 - 3 - 1 7 1 2 1 - - -
on avrg.

1.7 STATUS OF INSURANCES AND BONDS


The current status of insurance and Bonds to end of this month is shown below: -

No. Description Source Amount Valid requirement Expiry Status


date

1 Guarantee

1.1 Performance Ethiopian 131,670,000.00 18/8/2023 17/8/2025 Expired and


Security bond Insurance on process of
Corporatio renewal

Page 10
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

354
Advance Oromia
1.2 2,534,647.5 11/6/2020 Calendar Expired
Payment insurance
days
Unconditiona
1.2. Global 131,670,000.0 17/06/202
18/06/2024 l bank
1 bank 0 5
guarantee

SINQEE Unconditiona
131,670,000.0 05/06/202
BANK 06/06/2023 l bank
0 4
S.C. guarantee

1.3 Retention

2 Insurances

Insurance for
Design Not
2.1
(Professional Submitted
Indemnity)

Insurance for
Works,
2.2 expired
equipment and
plant (CAR)

Third Party
2.3 Coverage,
Commented
sub clause 18.3

Insurance for
2.4 Workmen, sub Commented
clause 18.4

Page 11
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

1.8 DETAILS OF VARIATION ORDER

Variation Order No.1 Amounting ETB 103,378,845.39 (Ethiopian birr One Hundred Three Million
Three Hundred Seventy-Eight Thousand Eight Hundred Forty-Five and 39/100) including 15% VAT
as per Clause 14: [Variations] of the General condition of the works contract issued for the Emergency
Maintenance Works of Tenta-Gashena: Contract 1, Tenta Junction-Wogeltena-Kurba (Km31+500-
65+000) road project.

1.9 CLAIMS STATUS

The contractor substantiates a claim for extension of time for completion and cost reimbursement. Accordingly,
the submitted document reviewed by the Employer’s representative and the employer in line with the contract
document and relevant articles of FDRE Civil code and the forwarded recommendation via letter PES/GJ-Km
14p/459/22 dated November 28, 2022 and also the Employer forwarded his determination via letter A51/69/7-
236 dated March,03,2023. Cost claim number one is under review by the ER: the contractor provided
contemporary records and resubmitted the cost claim on the reporting period.

1.10 EOT STATUS

The contractor substantiates a claim for extension of time for completion and cost reimbursement.
Accordingly, the submitted document reviewed by the Employer’s representative and the employer and a
time extension granted for 712 calendar days. The contractor EoT 4 has been requested and the ER is
carrying out his assessment.

employer.

Page 12
Design and Construction of Gishen Junction km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024

1.11 JOB OPPORTUNITY


One of the positive impacts of any project is creating Job Opportunity for the local community. Accordingly, the following are the records obtained from the
respective Human resource department showing the subject under discussion:

Work opportunity created by the project during the month of December 2024 for the Contractor’s Employees is not yet reported attached here under.

N Projec Employme Total No. of No. of Disabled Employment & Gender based Youth and above Gender based …. Remar
o. t nt Employment Employees Report k
Name by Skill based on Gender Permanent Contract Age ≤29 Age ≥30
Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot
le e al le e al le e al le e al le e al le e al
1 skilled
CONSTRUCTION PROJECT
GISHEN JUNCTION-KM.14
ROAD DESIGN AND

semi-
skilled

unskilled

total

Page 13