STATUS 54 Dec 2024
STATUS 54 Dec 2024
1. EXECUTIVE SUMMARY
Time for Construction 915 Calendar Days (including 4 months mobilization period)
Defects Liability Period 365 Calendar Days from the issue of the taking Over Certificate
Original Total Contract lump ETB 1,316, 700, 000.00 [including VAT]
Page 1
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024
sum Price
Exchange Rate 1
Start Repayment of Advance After Certification of 30% of the Contract Price including price
Payment adjustment
Amount of Liquidated Damages 0.1% of the value of the remaining works per day
Page 2
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024
Contract period 30 months for construction supervision plus 1-year defect liability
So far, 1672 calendar days (i.e102.89% of the contract period) have elapsed and the estimated to
date accomplishment is 14.24% of the total workload. This is equivalent to a weighted average
of 2.67km.
During the reporting period of the month December 2024, the contractor’s actual estimated
accomplishment is 0.06% (0.01km) of the contract amount.
The following table shows the financial and physical progress of the works up to the end of the reporting
period:
Table: 1.2:- Financial and Physical progress (for the reporting month and to date)
Up to Previous
Description
Month This Month To date
Page 3
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No.54/December 2024
Up to Previous
Description
Month This Month To date
Page 4
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
To end of this reporting period, the overall accomplishment of the project is 14.24%(2.67km) while the to
date planned work is 26.94%( 5.05Km) and the time elapsed to date is 102.89% (1672Days) Cal Days)
It also shows the accomplishment is much less with respect to time elapsed; while the progress is 14.24%of
time elapsed to date and this shows that the accomplishment is lagging from time.
This fiscal year’s actual progress is also 0.86 %( 0.15km) In addition; the reporting period monthly
progress is0.06%( 0.01km).
The cumulative physical status of each bill item shown below with respect to the planned length (km) or
(percentage) and the actual accomplishment.
Table 1.4: Major Work Items (bill group) of the Works Contract accomplishment with respect to the
Action Plan for 2017 EFY
Up to previous
This Month To date Amount
month
Weighted Plan Actual Plan Actual Plan Actual
Bill
Description Average
No.
(%)
% % % % % %
Series 1000/Division
3 1500/Detour and Traffic 1.50% 0.89% 0.78% 0.04% 0.00% 0.92% 0.78%
Management
6 Series 5000/Base Course 10.00% 0.61% 0.00% 0.38% 0.00% 0.99% 0.00%
Page 5
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Series 6000/Bituminous
7 30.50% 0.78% 0.00% 1.28% 0.00% 2.06% 0.00%
Surface
14.24
Total 100.00% 22.18% 14.17% 4.76% 0.06% 26.94%
%
Note:
The Planned amount up to end of this reporting period is as per the Contractor’s Action plan for 2017 EFY
Survey, Investigation and Design works have 2% of weight from the total project values. Work planned
according to contractor’s Action plan, to end of this reporting month is1.63% (with respect to total
project cost), however, contractor’s accomplishment to date is 1.54%.
Page 6
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Planned Actual
Description slippage
Accomplishment Accomplishment
Planned Actual
Description slippage
Accomplishment Accomplishment
This item of work has 31.5% weight from the total project values. Work planned to end of this reporting
month was 16.54% (with respect to total project cost), and contractor’s accomplishment to date is
9.58%.
Planned Actual
Description slippage
Accomplishment Accomplishment
Page 7
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Accomplishment Accomplishment
Planned Actual
Description slippage
Accomplishment Accomplishment
This item of works has 30.5 % weight from the total project values.
Planned Actual
Description slippage
Accomplishment Accomplishment
This item of works has 11% weight from the total project values.
The cumulative progress of the item to date with respect to its bill amount and total project cost presented
hereunder
Planned Actual
Description slippage
Accomplishment Accomplishment
Page 8
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
This item of works has 3% weight from the total project values. The cumulative progress of the item to
date with respect to its bill amount and total project cost presented hereunder
Planned Actual
Description slippage
Accomplishment Accomplishment
Page 9
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Slow action in requesting removal of row obstacles and provide clear information to the ER.
The consultant has produced letters and forwarded to the contractor and arrange bilateral and
tripartite meeting to solve the project issues
The Consultant has done lots of discussions with the Contractor including Design consultant
regarding the design issues and also has written notice on delay of Design deliverables.
The Contractor is frequently reminded to arrange temporary facility for the engineer, though no
satisfactory action taken so far.
The contractor has not shown preparatory works except earth work. Even though the contractor
mobilized additional pipe moulds and cement in the reporting period, structural works are not
proceeding as per the plan.
Description Dozer Grade Exc Paver Rol. D.T Loader W. Fuel W.Drill Mobile Crusher
r T Crane
T.
Total 4 1 4 - 2 11 3 2 1 - - 1
Avail. no
Working 3 - 3 - 1 7 1 2 1 - - -
on avrg.
1 Guarantee
Page 10
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
354
Advance Oromia
1.2 2,534,647.5 11/6/2020 Calendar Expired
Payment insurance
days
Unconditiona
1.2. Global 131,670,000.0 17/06/202
18/06/2024 l bank
1 bank 0 5
guarantee
SINQEE Unconditiona
131,670,000.0 05/06/202
BANK 06/06/2023 l bank
0 4
S.C. guarantee
1.3 Retention
2 Insurances
Insurance for
Design Not
2.1
(Professional Submitted
Indemnity)
Insurance for
Works,
2.2 expired
equipment and
plant (CAR)
Third Party
2.3 Coverage,
Commented
sub clause 18.3
Insurance for
2.4 Workmen, sub Commented
clause 18.4
Page 11
Design and Construction of Gishen Junction -km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Variation Order No.1 Amounting ETB 103,378,845.39 (Ethiopian birr One Hundred Three Million
Three Hundred Seventy-Eight Thousand Eight Hundred Forty-Five and 39/100) including 15% VAT
as per Clause 14: [Variations] of the General condition of the works contract issued for the Emergency
Maintenance Works of Tenta-Gashena: Contract 1, Tenta Junction-Wogeltena-Kurba (Km31+500-
65+000) road project.
The contractor substantiates a claim for extension of time for completion and cost reimbursement. Accordingly,
the submitted document reviewed by the Employer’s representative and the employer in line with the contract
document and relevant articles of FDRE Civil code and the forwarded recommendation via letter PES/GJ-Km
14p/459/22 dated November 28, 2022 and also the Employer forwarded his determination via letter A51/69/7-
236 dated March,03,2023. Cost claim number one is under review by the ER: the contractor provided
contemporary records and resubmitted the cost claim on the reporting period.
The contractor substantiates a claim for extension of time for completion and cost reimbursement.
Accordingly, the submitted document reviewed by the Employer’s representative and the employer and a
time extension granted for 712 calendar days. The contractor EoT 4 has been requested and the ER is
carrying out his assessment.
employer.
Page 12
Design and Construction of Gishen Junction km 14 Ethiopian Roads Administration Road Project
Monthly Progress Report No. 54/December 2024
Work opportunity created by the project during the month of December 2024 for the Contractor’s Employees is not yet reported attached here under.
N Projec Employme Total No. of No. of Disabled Employment & Gender based Youth and above Gender based …. Remar
o. t nt Employment Employees Report k
Name by Skill based on Gender Permanent Contract Age ≤29 Age ≥30
Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot Fema Mal Tot
le e al le e al le e al le e al le e al le e al
1 skilled
CONSTRUCTION PROJECT
GISHEN JUNCTION-KM.14
ROAD DESIGN AND
semi-
skilled
unskilled
total