SPSE ICB User Guide for Vendor
SPSE ICB User Guide for Vendor
1
June 2016
June 2016
Table of Contents
1 Introduction .................................................................................................................... 4
1.1 Regular Consultant Selection .................................................................................. 4
2 Scope and Intention of the User Guide .......................................................................... 5
3 Regular Consultant Selection (RCS) ............................... Error! Bookmark not defined.
3.1. Vendor’s User ID Registration ............................................................................. 6
3.2. Steps in Regular Consultant Selection (RCS) Process. ..................................... 10
2
Abbreviation
3
1 Introduction
The Government of Indonesia through Presidential Decree No 54/2010 regarding Public
Procurement of Good/Service, in Article 131 Paragraph (1) regulates that on Year 2012
all Indonesian Government’s Ministries/Agencies/Institutions are required (mandatory)
to implement electronic good/service procurement for partially/all procurement
packages. It was also stipulated on Perpres No 54/2010 that Electronic Procurement
Service Unit (LPSE) will be responsible for the e-procurement system implementation.
Operational technical provision for LPSE was regulated in the Chairman of LKPP
Regulation No. 2/2010 and need to abide by Government entities. LPSE in
implementing electronic good/service procurement service system is compulsory to
follow the provision as stated in the Act No. 11/2008 regarding information and
electronic transaction.
Regular Consultant Selection (RCS) is a system within SPSE which can be used
to select consultant firm to participate in bidding for Asian Development Bank
(ADB) funded Project in MPWH. RCS adopted shortlist consultant system and
follows ADB Procurement Guidelines.
Example of the SPSE LKPP for ADB’s Projects in MPWH covered in the RCS
system:
1. Flood Management in Selected River Basin (FMSRB).
2. Accelerating Infrastructure Delivery through Better Engineering Services
Project or ESP (Non Panel Selection)
This User Guide did not cover elaboration regarding selection method available for
ESP Panel Consultant System using SPSE in MPWH. This User Guide will only
focus on how to guide prospecting/ interested vendors in using SPSE system
(particularly RCS) to participate in Projects funded by ADB in MPWH.
4
REOI for ADB Projects which included in Regular Consultant Selection (RCS) will
also be posted on ADB’s Consulting Services Recruitment Notice (CSRN) and
website of MPWH’s SPSE.
a) International vendors in this case, will refer to all consultant firms (vendors)
incorporated outside Indonesia and has not been legally operated in Indonesia.
b) National vendors will refer to consultant firms which legally incorporated in
Indonesia.
Note: Please follow step by step instruction given in this User Guide. Each action will be elaborated
with screen shot images from live system for easier view. Please notice that signs or shapes on the
images and read the elaboration of the project and the system in the Introduction section for better
clarification.
5
3.1. Vendor’s User ID Registration
This image below is the Home Page of SPSE MPWH site which is dedicated for ADB. In
order to participate in the bidding via this system (SPSE), vendor must register via online to
acquire user ID for login into the system (please refer to Image 2)
Please click link “Register as Vendor” in order to access registration page. You will be
directed to the following page where vendor will fill the form.
Image 2
Image 2
If you happen to click “Login as Vendor” button, you may also Please click link “Register
as Vendor” in order to access registration page. You will be directed to the following page
where you can fill the form. The line marked by asterisk is mandatory (please refer to Image
4)
Image 3
6
Image 4
Please notice red box and arrow which means that the following registration form need to be
filled, particularly for the * (mandatory). Upon completion you may click Register button
(please refer to blue arrow).
Vendors need to pay attention to following remarks:
In Vendor Type, vendor must choose between International or
National Vendor by clicking the dropdown.
Definition of International Vendor refers to any vendors which has
not possessed legal permit to operate business from Government of
Indonesia.
Definition of National Vendor refers to any vendors which obtain
legal permit to operate business from Government of Indonesia.
User ID, refers to name code that will be used to login into SPSE
application. Please use term which is easy to remember as user ID.
Password, refers to password that will be used to login into SPSE
application. Please create a password which includes series of
alphabet and numeric for security reason.
Password (Verification), need to be fill in order to ensure the
password filled was matching with what previously typed
(consistency).
Company’s name, refers to name of company which register as
vendor.
Company’s address, refers to address of company appropriate
with tax ID.
7
Tax ID number, It refers to tax ID number of the company
registering as vendor in the country where it legally incorporated.
Phone, refers to telephone number of company which register as
vendor.
Email address, refers to official company email address that
register as vendor.
Website, refers to official website address of company that
registered as vendor.
Next step vendor will be sent an email notification regarding confirmation of registration
(Please refer to Image 5)
Dear,
Donald Management
Thank you for registering in the ESP's SPSE. Your account name is Donald Management.
To complete your registration, please do the following: Open the link below by clicking on it:
Click here
Email copy of your firm's article of incorporation and tax identification document as issued in the country of incorporation
[email protected]
to [email protected] and [email protected]. The document should be in pdf format. The email should have the
subject line "ESP Registration for Donald Management".
Sincerely,
LPSE Administrator
Image 5
Sincerely,
When vendor click on the sign “Click here” on the Image 5, then confirmation screen will
LPSEappear
Administrator
(Please refer to Image 6):
Image 6
Vendor may click “Back to main page” in order to access Home Page. There is no further
step at this stage.
8
After registration with SPSE has been approved by the Committee, there will be an email
sent to the vendor notifying that registration has been approved. (Please refer to Image 7):
Dear,
Donald Management
Your registration with SPSE has been approved. Details of your registration are as follows:
• Your User ID : DONALDMGM
• Company Name: Donald Management
• Address: South East 14th
Sincerely,
LPSE Administrator
Image 7
9
3.2. STEPS IN REGULAR CONSULTANT SELECTION PROCESS
The next step after being registered in the system, vendor may start entering bidding in
Regular Consultant Selection (RCS) if interested.Vendor can find out bidding package by
accessing MPWH LPSE website: lpse.pu.go.id/eproc-esp (Please refer to Image 8). In
RCS process there are several steps which need to be conducted prior having chance to be
properly analyzed and decided as winner in the bidding.
Image 8
Steps or phases in the Regular Consultant Selection Process (RCS) are described as follow:
1. Announcement Stage
Image 9
In the main page, vendor might find the “Package Name” in the middle of the website screen
(Please refer to Image 9). Vendor can click on the “Package Name” and will be directed on
the screen as appeared in Image 10. Vendor might click “REOI Summary” (refer to red
10
circle) to view and information summary contained in the REOI and then vendor can click on
“Submit EOI” (refer to blue circle) if interested to participate.
Image 10
Next step vendor will be directed to login screen (please refer to Image 11). You may use
your user ID and Password (refer to red circle) and then click “Login” button (blue circle).
Image 11
11
Vendor will be directed the screen below. After carefully reading the information presented
on the page, you may click “Accept and Submit EOI” (please refer to Image 12).
Image 12
Upon completion on previous step, following screen will appear. Please notice there is a
confirmation sign on the green banner (Please refer to Image 13)
Image 13
12
Vendor will able to view schedules and stages in RCS process in the Package by clicking
“View” button (Please refer to Image 14).
Bidding Schedule
Image 14
2. Submission of EOI
In order to enter the Shortlist, vendor needs to complete several steps including submitting
proposal. The next step will be to go to Dashboard or login to the system (Please refer to
Image 15).
Image 15
13
Upon entering the system, the screen should automatically display the Dashboard section of
the website and vendor can click on the package or blue circle (please refer to Image 16).
Image 16
Next step vendor will see the screen on the image below. Vendor can upload EOI and other
Supporting document by clicking “Choose File” (refer to red arrow) and then continue with
“Upload” (refer to blue arrow).
Image 17
After completing steps above, “Submit EOI” button will appear (refer to Image 18). Please
click on “Submit EOI” in order to move to the next step (refer to Image 19).
14
Image 18
Image 19
15
For the next step, a confirmation page will appear after completion on the above step.
Please notice sign on the green banner (Please refer to Image 20)
Image 20
Vendor will also automatically receive an email notification as seen below (Please refer to
Image 21):
Image 21
The next step after submitting EOI, vendor will wait for further process and assessment from
Tender Committee. In the event that vendor eligible/ pass the assessment then the status of
that vendor will be changed into Shortlisted. Vendor can view their status by login to the
system using their valid user ID and go to the Dashboard.
16
Image 22
As previously mentioned above, in the Dashboard section vendor can see the status
(please refer to red circle in Image 23)
Image 23
17
Apart from viewing status at the Dashboard, vendor will also receive email notification from Tender
Committee (please refer to Image 24).
Image 24
In the event that Tender Committee upload RFP document or any other supporting
document, vendor will automatically receive notification email as appeared in Image 25.
Image 25
Vendor can view the aforementioned RFP / other uploaded document from Committee by login into
the system (Please refer to Image 26 in the next page) and see from the Bidding Information section
after login in to the system (Please refer to blue circle in Image 27)
18
Image 26
Image 27
19
Image 28
4. Preproposal Forum
The next step will be Preproposal Forum / Clarification Forum. In this phase vendor can asks
questions pertaining content of documents and other technical issues related with bidding. Vendor
can ask questions by login into the system (Please refer to Image 29 in the next page) and
continue by clicking “Ask for Clarification” button (Please refer to Image 30).
20
Image 29
After conducting previous step (asking question by clicking “Ask for Clarification” as in the Image
30) and then continuing with clicking “Send Question” (please refer to Image 31). Vendor can also
upload attachment / document to support question being asked if considered necessary by clicking
“Choose File” and then continue by click “Submit” (Please refer to Image 32).
Image 30
21
Image 31
Image 32
All questions asked by vendors will be stored into designated database within the system.
Vendor who enter the bidding may view the questions as well as response from Tender
Committee (Please refer to Image 33 and 34. In the image 34 please notice the Participant
Questions section to see the questions and Bidding Committee Clarification to see
response from the Committee.
22
Image 33
Image 34
23
5. Submission of Technical and Financial Proposals
In this stage vendor will submit technical and financial proposals required to enter the bidding.
First step vendor will be needed to login to the system by accessing the Home Website
lpse.pu.go.id/eproc-esp/ (Please refer to Image 35) and continue by login using designated user
ID and password (refer to Image 36).
Image 35
Image 36
24
After login in, vendor will be required to upload technical proposals in accordance with bidding
package by click “Choose File” to upload technical proposal and click “ Upload” (refer to Image 37);
and then followed by uploading Financial Proposals by clicking “Choose File” and “Upload” (refer to
Image 38). Financial Proposals must be in the following format: pdf and xlxs or xlx.
Image 37
Image 38
25
Vendor which already uploaded technical and financial proposals need read the terms and condition
and click on the checkmark button (Please refer to red circle in Image 39) prior continuing to the next
step. After properly reading the terms and click on the checkmark then “Submit Proposal” button will
appear and vendor can click it to move on to the next step (Please refer to blue circle in the Image 40)
Image 39
Image 40
26
After submitting proposals, there will be a green banner sign appeared in the Dashboard (Please
notice the green banner sign on the Image 41). At the very same time the vendor will also
automatically receive a notification email on the system. The email consists of information regarding
documents name being submitted along with submission date and time (Please refer to Image 42)
Image 41
Image 42
27
6. Evaluation of Technical Proposals
Vendors who pass the technical proposal stage will receive an email containing
information that the particular vendor has met the minimum requirements for technical
proposals from the Committee (Please refer to Image 43).
Vendor may also view the status: “Pass technical evaluation” (Please refer to red circle
in Image 45) by login using registered user ID (refer to Image 44).
Image 43
Image 44
28
Image 45
All qualified vendors will be invited to send their representatives to attend/witness opening
financial proposal which will be conducted online (using computer) in certain designated time
and venue (which will be stipulated in the invitation letter to qualified vendors). Whether all
qualified vendors send the representatives to witness the opening of financial proposal or not
the event will still be implemented at the designated time and venue.
Vendor who passed technical proposal stage will receive an email containing information
that financial proposal have been opened by the Committee after the opening financial
proposals event take place (Please refer to Image 46).
Image 46
29
8. Evaluation of Financial Proposals, Combined Evaluation Final Ranking
For vendors who passed the financial proposal and combined evaluation stage, status in
the dashboard will show as: “Pass technical evaluation” (Please refer to Image 47).
Image 47
9. Contract Negotiation
In this stage, vendor will conduct contract negotiation process. Vendor will receive an
invitation through email (Please refer to Image 48). The email contained information
regarding time, location and implementation of contract negotiation.
Image 48
Vendor who complete the price negotiation process will receive email notification which
includes information that the company has been declared as winner of the bidding
(Please refer to Image 49).
30
Image 49
Vendor who declared as winner of the bid will see the status in their Dashboard as:
“Awarded” (Please refer to Image 51). Vendor will need to login first using their
designated user ID and Password (Please refer to Image 50). Upon login to the system,
vendor will be taken straight to the Dashboard screen.
Image 50
Image 51
31