exam question 1

The document contains a series of questions and answers related to project management, specifically focusing on risk management, stakeholder analysis, procurement processes, and quality assurance. It addresses various phases of project management and the methods used for forecasting and training. An answer key is provided at the end for reference.

Uploaded by

ahmed.nabil.fx
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views2 pages

exam question 1

The document contains a series of questions and answers related to project management, specifically focusing on risk management, stakeholder analysis, procurement processes, and quality assurance. It addresses various phases of project management and the methods used for forecasting and training. An answer key is provided at the end for reference.

Uploaded by

ahmed.nabil.fx
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

1. A project audit team discovered that a project did 6.

Various forecasting methods are used to predict


not have a risk register. Which phase under the Risk future project performance. Which of these methods
Management knowledge area has likely been missed out use the assumption that it is possible to identify
or improperly done? the underlying factors that might influence the
a. Identify Risks variable that is being forecasted?
b. Perform Risk Assessment a. Econometric methods
c. Plan Risk Responses b. Probabilistic forecasting
d. Plan Risk Management c. Time series model
d. Judgmental methods
2. Lois is a project manager managing a town-
development project. She has set up a series of 7. A project manager has scheduled a number of
interviews with various stakeholders to gather some training programs for his team. However, he was
experiential (i.e., personal experience) and aware that apart from planned training, unplanned
historical information on risks. Which phase is this training also took place in a number of ways. Which
likely to happen in? of these is not one of the ways in which unplanned
a. Perform Qualitative Risk Analysis training can happen?
b. Plan Risk Responses a. Classroom
c. Understand Risks b. Observation
d. Perform Quantitative Risk Analysis c. Project performance appraisals
d. Conversation
3. Which of the following models describes stakeholders
based on their power, urgency, and legitimacy? 8. As part of the procurement process, the procuring
a. Influence / Impact Grid organization elected to have an estimate of costs
b. Power / Influence Grid prepared by an outside professional estimator. The
estimator came up with an estimate of 500,000.
c. Power / Interest Grid
However, the cost estimates prepared by the
d. Salience Model prospective sellers were in the range of 200,000.
How can this be best interpreted?
4. A project was awarded based on a competitive a. The procurement statement of work was deficient
proposal. Management made a commitment that a few and ambiguous.
key team members would be assigned to the project. b. The professional estimator has inflated the
When such assignment happens, they are termed as: estimate of costs.
a. Bargaining agreements c. The prospective sellers do not have the required
b. Pre-project assignments skills to do the project.
c. Planned assignments d. Prospective sellers are trying to underbid and
d. Pre-assignments win the project.

5. The Direct and Manage Project Execution phase 9. A project manager is working on the Perform QA
requires implementation of approved changes covering phase of a project. He is looking for an
all the following except: interactive means to improve quality and eliminate
a. Defect repair activities that do not add value. Which of the
following will help him do this?
b. Corrective action
a. Quality control measurements
c. Preventive action
b. Quality checklist
d. Acceptance criteria
c. Continuous process improvement
d. Process improvement plan

10. For projects that have a product as a deliverable,


it is very effective to perform product analysis.
Which of these tools is not a product analysis
technique?
a. System breakdown
b. System analysis
c. Systems engineering
d. Requirements analysis

Click Here For More Free PMP Certification Practice Exam Questions
Answer Key

Please check your answers using the listing below.

Question 1 = A;
Question 2 = D;
Question 3 = D;
Question 4 = D;
Question 5 = D;
Question 6 = A;
Question 7 = A;
Question 8 = A;
Question 9 = C;
Question 10 = A;