feed-in_limitation_application_note
feed-in_limitation_application_note
Export Limitation
Version 2.9
January 2025
Version 2.9, January 2025
Table of Contents
Disclaimers ................................................................................................................................ 4
Important Notice ....................................................................................................................... 4
FCC Compliance ....................................................................................................................... 4
Emission Compliance ................................................................................................................ 5
Revision History ......................................................................................................................... 5
Chapter 1: Introducing Export Limitation .................................................................................. 6
Terminology .............................................................................................................................. 6
Chapter 2: Connection Options ................................................................................................. 7
Meter Types and Installation Considerations ........................................................................... 8
Single Inverter System .............................................................................................................. 9
Multiple Inverter System .......................................................................................................... 10
Multiple Inverter System with RS485 Meter ........................................................................... 10
Multiple Inverter System with Inline Meter Connected via SolarEdge Home Network ........... 11
EV Charging and Storage Systems .......................................................................................... 11
Export Limitation Response Time ............................................................................................. 11
Chapter 3: Export Limitation Configuration ............................................................................ 12
Configuring Export Limitation .................................................................................................. 13
Configuring Using SetApp ....................................................................................................... 13
Configuring Using the Device Display .................................................................................... 14
Verifying Export Limitation ...................................................................................................... 15
Verifying Using SetApp ........................................................................................................... 15
Verifying Using the Device Display ......................................................................................... 16
Verifying Using MySolarEdge .................................................................................................. 17
Appendix A: Monitoring Platform - Meter Data ....................................................................... 17
Appendix B: Actual Zero Export Limitation Use Cases ........................................................... 19
Introducing Zero Export Limitation .......................................................................................... 19
Theory of Operation ................................................................................................................ 19
Example 1 - Periodic Energy Export Limit .............................................................................. 20
Example 2 - Export Power Convergence Time Limit .............................................................. 21
Example 3 - Sample Commercial Site Monthly Export Log ................................................... 22
Appendix C: Examples of Total and Per Phase Export Limitation ......................................... 24
Example 1 - Single Phase, Zero Export Limit, Total Limit Mode ............................................ 25
Scenario A ............................................................................................................................... 25
Scenario B ............................................................................................................................... 26
Example 2 - Three-Phase, 70% Export Limit, Total Limit Mode ............................................ 26
Scenario A ................................................................................................................................ 27
Scenario B ............................................................................................................................... 28
Scenario C ............................................................................................................................... 28
Scenario D ............................................................................................................................... 29
Example 3 - Three Phase, Zero Export Limit, Per Phase Limit Mode .................................... 30
Scenario A ............................................................................................................................... 30
Scenario B ................................................................................................................................ 31
Example 4 - Three Phase, 3kW Export Limit, Per Phase Limit Mode .................................... 32
Scenario A ............................................................................................................................... 32
Scenario B ............................................................................................................................... 33
Scenario C ............................................................................................................................... 34
Appendix D: Minimum Import ................................................................................................. 35
Configuring minimum import using SetApp ........................................................................... 35
Configuring minimum import using the device display ......................................................... 35
Appendix E: Regional Considerations .................................................................................... 36
Hawaii ...................................................................................................................................... 36
Disclaimers
Important Notice
Copyright © SolarEdge Inc. All rights reserved.
The material furnished in this document is believed to be accurate and reliable. However,
SolarEdge assumes no responsibility for the use of this material. SolarEdge reserves the
right to make changes to the material at any time and without notice. You may refer to the
SolarEdge web site (www.solaredge.com) for the most updated version.
The material furnished in this document is believed to be accurate and reliable. However,
SolarEdge assumes no responsibility for the use of this material. SolarEdge reserves the
right to make changes to the material at any time and without notice. You may refer to the
SolarEdge web site (https://www.solaredge.com/us/) for the most updated version.
All company and brand products and service names are trademarks or registered
trademarks of their respective holders.
U.S. https://www.solaredge.com/us/patent
The content of these documents is continually reviewed and amended, where necessary.
However, discrepancies cannot be excluded. No guarantee is made for the completeness of
these documents.
Please note: This product is intended to provide remote shutdown of the SolarEdge PV
harvesting system, to enable safer access to a building in the event of fire. This product
DOES NOT reduce the risk of fire or protect firefighters or others accessing a building in the
event of a fire.
If the RS485 communication between the firefighter gateway and the SolarEdge inverter(s)
is disconnected for any reason (including fire), the firefighter gateway LCD will display "No
Communication" or "Partial Com.". In this case, the firefighter gateway cannot be relied upon
to disconnect the SolarEdge PV harvesting system.
The images contained in this document are for illustrative purposes only and may vary
depending on product models.
FCC Compliance
This equipment has been tested and found to comply with the limits for a Class A digital
device, pursuant to part 15 of the FCC Rules.
Emission Compliance
This equipment has been tested and found to comply with the limits applied by the local
regulations.
These limits are designed to provide reasonable protection against harmful interference.
This equipment generates, uses and can radiate radio frequency energy and, if not
installed and used in accordance with the instructions, may cause harmful interference
to radio communications. However, there is no guarantee that interference will not occur
in a particular installation. If this equipment does cause harmful interference to radio or
television reception, which can be determined by turning the equipment off and on, you are
encouraged to try to correct the interference by one or more of the following measures:
Changes or modifications not expressly approved by the party responsible for compliance
may void the user’s authority to operate the equipment.
NOTE
Interference may occur when the Wi-Fi Plug-in and Repeater are installed near other
2.4 GHz emitting devices (such as dual technology PIR detectors used in alarm
systems, microwave ovens, etc.). This might degrade/disable the gateway/repeater
operation. If possible, avoid installation nearby such devices, or consider these
interferences when troubleshooting.
Revision History
2.9 January 2025 Consumption meters are not supported in export limitation
use cases.
2.8 March 2022 "SolarEdge Energy Net" was renamed "SolarEdge Home
Network".
2.7 October 2021 Excluding use of Smart Energy Manager (SEM) on follower
inverters in multiple-inverter systems.
For export limitation, a SolarEdge device - an inverter or a CCG (Control & Communication
Gateway) - dynamically adjusts the PV power production in order to ensure that exported
power does not exceed a preconfigured limit. To enable this functionality, an energy meter
that measures export or consumption must be installed at the site.
This document describes system setup considerations and how to configure the system for
export limitation.
Terminology
The following terms are used in this document:
• Export/Import meter: A meter that is installed at the grid connection point and measures
the energy/power exported/imported to/from the grid.
• Consumption: The power consumed at the site. Consumption power is calculated as the
sum of self-consumption power and import power.
• Consumption meter: A meter that is installed at the load consumption point and measures
the energy/power consumed by the site.
• Self-consumption: The PV power consumed by the site and not fed into the grid.
• Production meter: A meter that is installed at the inverter output or site AC connection,
or inside the inverter (a built-in revenue grade meter), and measures the energy/power
produced by the PV system or site.
• External production meter: A meter that is used for production metering of 3rd party
generators, or for AC coupling with non-SolarEdge inverters.
• Site production meter: A meter that is installed at a SolarEdge inverter output, and reads
the energy produced by all the inverters at the site.
• Site limit: The power level (in kW) that the inverter falls back to once an export limit event
is triggered.
• Wye: In a Wye ("Y") configuration, all three phases are connected at a single neutral point.
Wye systems utilize five wires - three hot, one neutral and one ground.
• Delta: In a Delta configuration, the three phases are connected in a triangle. Delta systems
utilize four wires - three hot and one ground.
The following sections describe common export limitation connection scenarios and
response times.
• Meters with an RS485 interface, which are connected to the RS485 port of an inverter/
Commercial Gateway
RS485-Interface meters and SolarEdge Home Network meters can be installed in the
following locations:
NOTE
The meter should measure all grid phases . When a single-phase inverter is connected to a
three-phase grid - a three phase meter is required.
For SolarEdge meter installation, refer to the meter installation guide, available on the
SolarEdge website at:
North America:
http://www.solaredge.com/files/pdfs/solaredge-meter-installation-guide-na.pdf.
Rest of World:
http://www.solaredge.com/files/pdfs/solaredge-meter-installation-guide.pdf
For Inepro meter installation (Inepro meter firmware version 1.18 only), refer to
the application note at https://www.solaredge.com/sites/default/files/connecting-revenue-
grade-meter-to-solaredge-devices.pdf.
NOTE
If your inverter has a built-in RGM (Revenue Grade Meter), you can connect an external
meter for export limitation using one of the following methods:
• For inverters with a display, connect both the RGM and the external meter to the RS485
port.
• For inverters using SetApp, the external meter can be connected to the second RS485
port.
In the event of a communications loss between the inverter and the meter, the inverter's
power level falls back to the site limit.
NOTE
The above figure single phase inverter connection. For three phase inverters, 3 CTs
are required.
The figure shows a system with a meter measuring export levels, but the meter is also
applicable to systems with meters measuring consumption levels.
Figure: Single-inverter connection with inline meter over SolarEdge Home Network
NOTE
The figure shows a system with a meter measuring export levels, but the meter is also
applicable to systems with meters measuring consumption levels.
When using an RS485 meter for multiple inverter export limitation, two options are available:
• Option 1: The meter is connected to the RS485 port of the leader inverter, as shown in
the figure below. The leader inverter serves as the smart energy manager. If your inverter
has a built-in RGM (Revenue Grade Meter), you can connect an external meter for export
limitation using one of the following methods:
• For inverters with a display, connect the meter using the RS485 Expansion Kit (available
from SolarEdge).
• For inverters using SetApp, you can connect both meters to the RS485 port configured
as multi-device.
In the event of a communications loss between the inverter and the meter, the multiple
inverter system power level falls back to the site limit.
• Option 2: The meter is connected to one of the RS485 ports of a Commercial Gateway,
as shown in the figure below. The Commercial Gateway is the smart energy manager.
The Commercial Gateway’s second RS485 port can be used to create an RS485 bus for
communication between the inverters.
In the event of a communications loss between the Commercial Gateway and the meter,
the multiple inverter system power level falls back to the site limit.
Multiple Inverter System with Inline Meter Connected via SolarEdge Home Network
When using SolarEdge Home Network to connect an inline meter in a multiple inverter export
limitation scenario, the inverter serving as the smart energy manager connects to the meter
wirelessly over SolarEdge Home Network.
In the event of a communications loss between the inverter serving as the smart energy
manager and the meter, the multiple inverter system power level falls back to the site limit.
(1) Assumes that all inverters produce power at the same level. SetApp inverters can
support up to 63 inverters (connected either using 2 RS485 buses or over SolarEdge Home
Network).
(2) Nested RS-485 buses are applicable only for display inverters.
(3) The virtual meter provides calculated power/energy values based on actual meter
measurements.
In a multi-inverter system, the limit is configured in the Smart Energy Manager (the inverter
or Commercial Gateway that is connected directly to the meter).
NOTE
The Smart Energy Manager (SEM) is the device connected to the meter. The SEM is
required to be the communication leader.
NOTE
1. From the Commissioning page, select Power Control > Energy Manager > Limit Control
> Control Mode > Export Control.
2. Select Site Limit and enter the limit value at the connection point, in kW. The default
value is none (-), which means that the system is not limited.
NOTE
The value you enter here is the overall limit to which the site export will be
restricted, whether you use the Total or Per Phase limit control modes (as
explained in the next step).
NOTE
NOTE
3. In the Limit Control menu, select Limit Mode. Select one of the limit modes displayed
below:
• Total: The Site Limit is the total export power (the combined production minus the
combined consumption) on all the phases combined. Reverse current on one phase
will count as negative power and can compensate for another phase.
• Per Phase: For three phase inverter connections, the inverter sets the limit on each
phase to 1/3 of the total site limit. Use this mode if there is a limit on each individual
phase.
To configure export limitation in the SolarEdge device using the device display:
1. Enter Setup mode, and select Power Control > Energy Manager > Limit Control > Control
Mode > Export Ctrl.
2. Select Site Limit and enter the limit value at the connection point, in kW. The default
value is none (-), which means that the system is not limited
NOTE
The value you enter here is the overall limit to which the site export will be
restricted, whether you use the Total or Per Phase limit control modes (as
explained in the next step).
NOTE
NOTE
3. In the Limit Control menu, select Limit Mode. Select one of the limit modes displayed
below:
• Total: The Site Limit is the total export power (the combined production minus the
combined consumption) on all the phases combined. Reverse current on one phase
will count as negative power and can compensate for another phase.
• Per Phase: For three phase inverter connections, the inverter sets the limit on each
phase to 1/3 of the total site limit. Use this mode if there is a limit on each individual
phase.
• Site Limit: The limit that was defined for the site.
• Site Export: The power that is fed into the grid. This line is displayed only if the control
mode is "Export Control".
• Self-consume: The PV power consumed by the site. This line is displayed only if the
control mode is "Export Control".
• Local - The power is controlled locally (e.g. by a fixed limit), or this inverter limits the
PV power production to its relative portion of the export power limit, as a result of
disconnected communication with the smart energy manager. If this status appears,
check the communication to the smart energy manager or the communication to the
meter.
• PWR Limit: The inverter maximum output power set by the smart energy manager
1. Press the Enter button or the LCD external button until reaching the Smart Energy
Manager status screen, showing the site-level data. View the site-level data on the Smart
Energy Manager screen.
Site Limit: The limit that was defined for the site.
Site Export: The power that is fed into the grid. This line is displayed only if the control
mode is "Export Ctrl".
Self-consume: The PV power consumed by the site. This line is displayed only if the
control mode is "Export Ctrl".
• LOCAL - The power is controlled locally (e.g. by a fixed limit), or this inverter limits
the PV power production to its relative portion of the export power limit, as a result of
disconnected communication with the smart energy manager. If this status appears, check
the communication to the smart energy manager or the communication to the meter.
PWR Limit: The inverter maximum output power set by the smart energy manager
• Select Inverter Status > Advanced Installer View > View detailed inverter status to
display inverter status details. Check the value of the Power Limit field.
No meter installed:
Production (inverter/site) ✓ ✓
Consumption X X
Self-consumption X X
Export X X
Import X X
Export meter:
Production (inverter/site) ✓ ✓
Export X ✓
Import X ✓
This appendix describes the use cases of zero export limitation and shows examples of
system behavior when configured as a zero-export system. However, the same principles
apply for non-zero export limitation use-cases. Actual method of configuration can be found
in Export Limitation Guide application note.
Theory of Operation
“Zero export” term can be misleading at times as one may think that export to the grid is
always avoided. In fact, “zero export” mode is expected to export some energy to the grid in
some edge cases. The solar systems strives to produce as much power as possible for the
site consumption, however, load change events constantly occur. The zero export-regulated
system tries to match production-power and load-consumption- power at all times. During
the transition periods, some export power is inevitable.
In a balanced zero-export system, the inverter maintains export power to zero by regulating
production power PP [W] to match PC [W]. So at the beginning of the above example PP =
PC. At a sudden load power decrease (shedding), the previous instantaneous power (PC) is
changing to PC’ (the new instantaneous consumption power). The inverter should abruptly
reduce its production power to match the new consumption power (PC’): PP’ = PC’.
During the duration it takes the inverter to reduce its power, energy is temporarily exported
to the grid. The energy level exported is a direct result of the following factors:
The blue line in the figure below shows an example of system response times in the case of
PC changing from PMAX to PC’ = 0.33PMAX load shedding with one or more inverters (at T1).
The red line represents a single inverter response to the abovementioned load shedding,
moving from PP (=PC) to PP’ (PC’).The area between the blue line and red lines (illustrated by
the dashed lines) represents the energy exported to the grid during this duration (T3-T1).
The green line represents multiple inverter response to the abovementioned load shedding.
The green line will exhibits similar behavior to a single inverter use-case, but will take
slightly longer duration (T4-T1) due to the inverters communication latencies.
Color Measurement
• T2-T1 ≅1 sec
The expected energy export for a single inverter use case is ~1.25X/3600 [Wh]. The
expected energy export for multiple inverters use case is ~1.5X/3600 [Wh].
In the figure below, we can see how a few events contribute to the exported energy level.
Color Measurement
The user turns on 2kW load at T1, and 3kW load at T2. Each time, the inverter regulates
its production to match load consumption. Once the user switches OFF the 2kW load at T3,
the inverter responds within ~1 second to regulate the power. During this period, energy is
exported to the grid (the blue dashed triangle) is ~0.28 Wh. Similarly, once the user switches
OFF the 3kW load at T4, the inverter regulates the power within ~2 seconds and the energy
exported to the grid (the green dashed triangle) is ~0.83 Wh.
Note: a typical household will generate on average 5 load shedding events per active hour.
Assuming the house is active for 6 hours a day and assuming each event exports ~1Wh to
the grid; the overall monthly energy exported is ~0.9kWh, which is ~10% of the average
inverter nameplate (7.6 kVA).
In the example depicted below, the first zero export event takes (t2-t1) seconds to reach zero
export. According to the regulation requirement, the duration must comply with (t2-t1) ≤ TExp.
Similarly, the next event must also comply with (t4-t3) ≤ TExp.
All SolarEdge inverters comply with the above mentioned regulation. Here is an example:
Color Measurement
NOTE
The above mentioned example is valid for both single inverter and multi- inverter
cases.
NOTE
1 224 2
2 448 4
3 558 5
4 1,052 8
5 642 5
6 1,144 9
7 754 6
8 1,246 10
9 884 7
10 966 8
11 708 6
12 230 2
13 410 3
14 318 3
15 794 7
16 1,030 8
17 876 7
18 910 8
19 1,312 11
20 1,216 10
21 1,042 8
22 312 3
23 1,338 11
24 1,276 10
25 1,204 10
26 1,282 10
27 1,088 9
28 1,280 10
29 984 8
30 96 1
31 776 7
The overall system exported energy daily levels depends on the number of inverters. The
more inverters, the more energy exported. As mentioned above, the number of events may
vary based on user behavior and site characteristics. A factory facility where heavy loads
are being switched ON/OFF regularly will exhibit a wide variance of events, while an office
building might show a more consistent behavior.
• Total: The Total site limit is the total export power on all the phases combined, that is,
the combined production minus the combined consumption, as represented in the formula
below. Reverse current on one phase will count as negative power and can compensate
for another phase.
• Per Phase (for three phase inverters): Each phase will be limited to 1/3 of the configured
site limit, that is, the export power is the sum of the production minus the consumption of
each phase, as represented in the formula below. The division of the limit into the three
phases is performed internally; the user enters the total site limit.
In the example, the Site Limit and Limit Mode configuration is detailed. The example includes
production and consumption scenarios and details how the export, consumption and import
power values are influenced by the conditions. The tables in each scenario detail the
following values:
• Potential PV Production
• Consumption (load)
• Production
• Export power
• Self-consumption
• Import power
In addition, the Smart Energy Management status screen is presented with the values
applicable to each scenario.
The example system has a single-phase inverter with a maximum AC power of 7.6 kW.
NOTE
For detailed guidelines on configuring export limitations settings, refer to the chapter,
Export Limitation Configuration [12]).
Scenario A
Potential PV 7 7
Production
Consumption (load) 4 4
Production 4 4
Self-consume 4.0 kW
Scenario B
The loads are powered from the PV and from the grid.
Potential PV 4 4
Production
Consumption (load) 7 7
Production 4 4
Self-consume 4.0 kW
The system export power limit is set to 70% of max DC power, that is, to 70% x 12kW =
8.4kW, and the Total Limit Mode is used.
NOTE
Systems in Germany complying with the EEG2012 70% limitation would be configured
using the Total option.
NOTE
For detailed guidelines on configuring export limitations settings, refer to the chapter,
Export Limitation Configuration [12]).
Scenario A
PV potential is greater than the loads, which are not distributed evenly across the 3 phases.
The loads are powered from the PV only, and the excess PV power is fed into grid.
PV production is not limited, because the export power is lower than the limit.
Consumption (load) 3 3 0 6
Self-consume 6.0 kW
Scenario B
PV potential is equal to the loads, which are not balanced across the 3 phases.
Although on phase 1 the consumption is greater than the production, the difference is
compensated for by phase 3, where the production is greater than the consumption.
Therefore, PV production is not limited, because there is no export power.
Potential PV 2 2 2 6
Production
Consumption (load) 3 2 1 6
Production 2 2 2 6
Self-consume 6.0 kW
Scenario C
PV potential is lower than the loads, which are not balanced across the 3 phases.
The loads are powered from the PV and from the grid.
Consumption (load) 3 2 1 6
Self-consume 5.0 kW
Scenario D
PV potential is greater than the loads, which are not balanced across the three phases.
The loads are powered from the PV only, and the excess PV power is fed into grid. In
addition, PV production is limited to maintain the export limit.
Consumption (load) 1 0 0 1
Self-consume 1.0 kW
Example 3 - Three Phase, Zero Export Limit, Per Phase Limit Mode
In this example, the system has 12kW DC power connected to a three-phase inverter with a
maximum AC power of 10kW.
The system export power limit is set to 0W – no power is fed into the grid, and the Per Phase
Limit Mode is used.
NOTE
Systems in Australia complying with zero export regulations would be configured with
a Site Limit of 0 and using the Total option.
NOTE
For detailed guidelines on configuring export limitations settings, refer to the chapter,
Export Limitation Configuration [12]).
Scenario A
PV potential is lower than the loads, which are distributed evenly across the 3 phases.
The loads are powered from the PV and from the grid.
Consumption (load) 4 4 4 12
Export 0 0 0 0
Self-consume 10.0 kW
Scenario B
PV potential is greater than the loads, which are not balanced across the 3 phases.
To maintain a 0W export limit for each phase individually, the production on phase 3 must be
limited. Since the three phase inverter is always phase-balanced, the production on phases 1
and 2 is limited accordingly.
Consumption (load) 4 3 1 8
Production 1 1 1 3
Export 0 0 0 0
Self-consumption 1 1 1 3
Self-consume 3.0 kW
Example 4 - Three Phase, 3kW Export Limit, Per Phase Limit Mode
In this example, the system has 12kW DC power connected to a three-phase inverter with a
maximum AC power of 10kW.
The system export power limit is set to 3kW, and the Per Phase Limit Mode is used. This
means that exporting power on each phase is limited to 1kW.
NOTE
NOTE
For detailed guidelines on configuring export limitations settings, refer to the chapter,
Export Limitation Configuration [12]).
Scenario A
PV potential is lower than the loads, which are distributed evenly across the 3 phases.
The loads are powered from the PV and from the grid.
Consumption (load) 4 4 4 12
Export 0 0 0 0
Self-consume 10.0 kW
Scenario B
PV potential is greater than the loads, which are not balanced across the 3 phases.
To maintain a 1kW export limit for each phase individually, the production on phase 3 must
be limited. Since the three phase inverter is always phase-balanced, the production on
phases 1 and 2 is limited accordingly.
Consumption (load) 4 3 1 8
Production 2 2 2 6
Export 0 0 1 1
Self-consumption 2 2 1 5
Self-consume 5.0 kW
Scenario C
PV potential is greater than the loads, which are not balanced across the 3 phases.
To maintain a 1kW export limit for each phase individually, the production on phase 3 must
be limited. Since the three phase inverter is always phase-balanced, the production on
phases 1 and 2 is limited accordingly.
In this scenario, despite the system production being limited as in the previous scenario,
the limitation is less severe because the loads are more balanced, and this allows increased
self-consumption.
Consumption (load) 3 2 2 7
Production 3 3 3 9
Export 0 1 1 2
Self-consumption 3 2 2 7
Self-consume 7.0 kW
1. Enter 0.0 in the Set Site Limit screen (refer to the chapter, Export Limitation
Configuration [12]
2. Select Power Control > Energy Manager > Limit Control > Control Mode > Min Import Ctrl
3. Enter the minimum amount of power to be purchased in the Min Import Ctrl screen.
NOTE
The minimum import function for inverters with a display requires CPU version 3.18xx
or above.
1. Enter 0.0 in the Set Site Limit screen (refer to the chapter, Export Limitation
Configuration [12]).
2. Select Power Control > Energy Manager > Limit Control > Control Mode > Min Import Ctrl
3. Enter the minimum amount of power to be purchased in the Min Import Ctrl screen.
Hawaii
When using the SolarEdge EV Charging Single Phase Inverter, the Excess Solar mode (non-
scheduled, solar-only charging) functionality is subject to variations when the inverter is set
to one of the Hawaii country settings.
Excess Solar mode operation is available only to homeowners with Smart Export tariffs. It
will not be available for those with Zero Export tariffs.
During the day, homeowners with either tariff program (Smart Export or Zero Export) will be
able to maximize their charging using available solar power combined with grid power priced
at Hawaii's lowest retail rates.
To offset the nighttime consumption of electricity priced at Hawaii's high retail rate, it is
recommended to set a daytime daily schedule (usually from 10AM to 5PM), and use the Full
Power (combined solar and grid charging) mode to charge during non-scheduled periods.