This document is a checklist for the final erection inspection of steel structures related to the East West Piperack-1 project. It outlines various activities and their compliance with safety and structural standards, including the condition of materials and permissible deviations. The report is dated December 29, 2024, and includes sections for contractor and client acceptance signatures.

Uploaded by

Veeramathavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1 views

ITR-5_SECL

This document is a checklist for the final erection inspection of steel structures related to the East West Piperack-1 project. It outlines various activities and their compliance with safety and structural standards, including the condition of materials and permissible deviations. The report is dated December 29, 2024, and includes sections for contractor and client acceptance signatures.

Uploaded by

Veeramathavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ITR No.

: C-0505S
BOC-1971 - Grid Substation (GSS) Civil Works
Report No.:
Date : 29-12-2024
STEEL STRUCTURE ERECTION CHECK-LIST
RFI No.: 1971-YAM-CS-CPF1-0080
Final Erection Inspection for WO # 18, EW Pipe Support Near
Drg. No.: PPP-CP1-KBR-CG-4017-1019-002
PPP-CP1-KBR-CS-2358-1022-001.
&
Job Description: East West Piperack-1 (Elevation-MPS-19, MPS-20 & MPS-21).
Inspection Result
Sl. Activity Description Remarks
(Acc. / Rej.)
Safety Requirements, Scaffoldings, Lifting, Equipment’s, Skilled Labors
1 & Technicians to execute the Jobs are approved by a Method of
Statement.

Prior to Erection, fabricated parts of Structures transported Safely to


2 the Yard for Installation. To check for visible abrasion, distortion,
bending, buckling or any other damage to structural member.

External Painting/Coating System over Structure is in Good Conditions.


3 Incase Damaged Sections Identified, to be marked and Shop/Field
Repair to be Proposed by Contractor.

Installation of Anchor Rods, Foundation Bolts & Concrete Pedestals are


4 in Plan, Projection & Position. (Post Installation Survey Report to attach
for acceptance).

Position Permissible deviation of the erected Columns & Post ± 5mm to


5
its specified position/grid center on horizontal axis.

Liner Dimension Permissible deviation from specified length or width ±


6
5mm per 10 m of length.

Plumb Permissible deviation from Vertical at every 15 m of Height ± 5


7
mm per 15 m of length.

Levels Permissible deviation between the specified level & that of


8
erected member ± 3mm on Vertical Axis.

Filler Shims/Steel Packing Plates/Levelling Nuts are available as per


9 Specifications/AFC /Shop Drawings in position under Bearing & Base
Plates.

Columns Plumb Line through the base Working Point for an individual
10 column is in precise location ± 6mm on Tolerance on location of
Working Point at Base.

11 Check Bolt Tightening found Satisfactory.

Notes / Remarks:

Report Acceptance CONTRACTOR (AL YAMAMA - QC) CLIENT (KBR - QC)

Name

Signature

Date