StudyofMakeShiftAutomobileManufacturingProcessinIndiaUsingSimulation (1)

The document discusses a study on the makeshift automobile manufacturing process in India, focusing on a company called ABC Auto. It highlights inefficiencies in their production due to outdated technology and poor layout, and presents a simulation model developed using ARENA software to identify and eliminate bottlenecks, ultimately improving production rates. The study concludes that simulation can effectively analyze and enhance manufacturing processes in makeshift technology-based firms.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

StudyofMakeShiftAutomobileManufacturingProcessinIndiaUsingSimulation (1)

The document discusses a study on the makeshift automobile manufacturing process in India, focusing on a company called ABC Auto. It highlights inefficiencies in their production due to outdated technology and poor layout, and presents a simulation model developed using ARENA software to identify and eliminate bottlenecks, ultimately improving production rates. The study concludes that simulation can effectively analyze and enhance manufacturing processes in makeshift technology-based firms.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/343961865

Study of Make Shift Automobile Manufacturing Process in India Using


Simulation

Article · January 2015

CITATIONS READS

2 584

4 authors, including:

Lokesh Singh
JIT Jaipur
6 PUBLICATIONS 29 CITATIONS

SEE PROFILE

All content following this page was uploaded by Lokesh Singh on 29 August 2020.

The user has requested enhancement of the downloaded file.


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

Study of Make Shift Automobile Manufacturing Process in


India Using Simulation
Upendra Kumar Rajat Butola Lokesh Singh
Amity University, Haryana Amity University, Haryana
Amity University, Haryana

Sparsh Pratik*
Amity University, Haryana

Abstract: Most of the makeshift auto manufacturers lack in the technology; as a consequence the
manufacturer cannot satisfy the market demand at right time and right cost. Currently they are
following the traditional manufacturing (Jugaad) technology. Improper layout, uncontrolled process,
inefficient due date management, non-standardized transportation of semi-finished goods all
together, less automation, uncertain demand, lack of training of workers, leads to ineffective and
delayed production or prolonged production time. The above scenario was studied using a three
wheeler manufacturing company of Kanpur called “ABC Auto”. Time and motion study was
conducted in their manufacturing plant to quantify their process. The resulting model of ABC Auto
was simulated with the help of ARENA. Using the results from simulation, the capacity of
manufacturing plant was calculated and developed the benchmark for the company. Process analysis
was conducted and bottlenecks were removed. Through the elimination of the bottlenecks, plant
capacity was increased.

Keywords: Makeshift, Simulation, Arena, Manufacturing Process.

Introduction: Indian automotive industry was born in the early 1942 when Hindustan Motors was
set up.Since then it has evolved technologically and econolmically.Hindustan Motors, which
produced the first car, The Land master upgraded the version and later branded it as ‘Ambassador’
[Export Import Bank of India, 2008]. Indian auto component industry is emerging as a global
manufacturing hub for auto component manufacture. The Auto components industry is
predominantly divided into the following segments: Engine parts: 31%, Drive Transmission &
Steering Parts: 19%, Suspension & Brake Parts: 12%, Electrical Parts: 9%, Body and chassis: 12%,
Equipments: 10%, others: 7%. Indian auto component industry is one of the front runners for
grabbing the global auto component outsourcing market, estimated to be worth US$700 billion by
2015. This study is based on small and medium- sized automobile manufacturing firms in India. The
major problem of such manufacturing processes is the ever increasing expenses of manufacturing. In
India there is a significant demand for three wheelers; popularly known as auto rickshaw or autos. In
India there are few manufacturers who make variants of auto rickshaws by using makeshift
technology. They procure some components from other manufactures and produce some component
82 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik
International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

themselves. Then they assemble all those components and make the end product, which is the auto
rickshaw or just auto. These small automobile industries do not have proper assembly line for
manufacturing. These small automobile industries work on makeshift technology, which depend on
the man- machine combination, where human still dominates. Every company that works using the
makeshift technology has the following type of situation: Planning of manufacturing process is not
scheduled, Less skilled labour, Inefficient equipment, Less automation, Inappropriate plant layout,
Substandard equipment, Transportation of semi-finished goods is not standardized, Data
management is inefficient, Lack of training for labour. Due to all this above mentioned factors such
manufacturing processes are very inefficient, which result in very low manufacturing rate of the
automobile. So in order to fulfil their demand, they need to work overtime which increases their
expenses. For study the manufacturing process, we took five major component of auto and found
their process flow. Every component has their own process flow, for collecting the data we did the
time and motion study for every component, in this we recorded the time taken by the component at
different process.

Literature Review: Indian industries are presently on fast track development. Especially Indian
automobile industry has improved indigenous technology and as well as importing modern
technology to improve the manufacturing process, so that cheap and reliable vehicles can be
manufactured for Indian population. The strength of Indian industries has to be identified in terms of
development of indigenous technology as well as in the acquisition adaptation of its own technology
[1]. Some authors have studied the application of simulation model to identify optimal production,
specifically in heavy rolling mill system and in steel making industry [2]. Methodology of modelling
and the study of final process of automobile manufacturing and to develop efficient model which
provide maximum throughput or ensure the targeted throughput [3]. Initial efforts of implementing
the simulation model with help of visual management and analysis tool at automotive foundry plant
that is manufacturing engine block is studied in [4]. Virtual simulation of a design of a production
line for a mechanically assembled product is given in [5]. Real world manufacturing problem can be
modelled with the help of simulation and that can be used as an optimization tool for most of the
manufacturing process, [6], used simulation for complex production lines in order to minimize
product lead times and maximize throughput. They explained meta model simulation based
optimization and applied it to a multi objection real world manufacturing system. Depending upon
the field of assembly planning and different objectives, the simulation analysis can be classified into
four hierarchy classes of assembly shop, cells, station, and component [7]. Simulation is a very
helpful tool for manufacturing. It can be used in different industrial field, for the analysis of the
system’s behaviour and to test the system output. Simulation provides low cost, and fast analysis tool
[8].Survival of any industry in today’s competitive market place depends on the response time,
production cost and flexibility in the manufacturing process. From analyzing the literature, it is quite
evident that research in the field of Indian Jugaad auto manufacturers are lacking. Especially no
studies are available in the base of simulation as a tool to study the processes of much industry and

83 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

improve them. Capacity benchmarking, utilization, and desired layout are the major issues playing
such industries in India, which can very well be studied using simulation.

Factory Layout: ABC Auto is an old experienced auto manufacturer, providing autos to major cities
in India and as well as overseas. Its major function is to assemble the equipments and vehicle part to
provide the finished product. Most of the parts of the auto are in-house items. For implementing all
those process ABC Auto has following department/shops: Machine shop, Welding shop, Press shop,
Cutting Shop, Phosphating Shop, Painting shop, Assembly shop, Inventory & Store Room, Front
show department. Factory layout is shown in the Fig 1.

Figure1: Factory layout of ABC Auto

84 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

Overview of the Problem: The focus of ABC Auto is to restrict the level of production with
increase in production time. The current layout plan of the plant is not properly planned and random
as per the olden days. It has not been modified to fit to the modern production plan. Due to this the
in-house transport of semi-finished goods take little bit greater time and thus results in reduced
efficiency. Also as these parts are being moved from one part of plant to the other, the wear and tear
of the material during the transportation occurs, which results in depreciation in the quality factor.
The current layout plan of the plant is shown in the Fig 1.

Simulation Modelling in Arena Simulator: The model of the process was developed using
ARENA software shown in the Fig 2. To begin the experiments, all the values are taken as constant.
The processing time in the departments is constant with the average value of processing time from
time study was used. Every resource is fixed with a quantity of one each. The simulation is first
carried out with constant system, for which the bottleneck was noted and removed or eliminated by
increasing the number of resources. An optimal number of resources were worked out for achieving
the rate of auto manufacturing of 3.36 autos per hour. After achieving the set of fixed optimal
resources the variability was introduced in the system to simulate the real life scenario. The
distributions are applied to the various section or machines in a sequential manner and again
bottlenecks are noted and removed or eliminated by increasing the number of resources. An optimal
number of resources worked out for achieving the rate of auto manufacturing of 3.36 autos per hours.
In this work basically the 5 components, chassis, front show, plane furse, and mudguard and rear
wheel tube is taken.

Process Flow of Component: Input components and their process flow are shown in Table 1. Here
every component has different process flow for manufacturing the component.

Table 1: Input component and their process flow

S/No. Component Process flow (order wise)


1 Chassis Cuttingmachine1welding m/c 1phosphating shoppainting m/c
2 Front show Shearingpress m/cmilling m/cspot weldingphosphating
shoppainting m/c
3 Plane furse Shearing press m/c millingspot welding m/cphosphating
shoppainting m/c
4 Rear wheel Machine 2welding m/c 2phosphating shoppainting m/c
tube
5 Mudguard Shearing milling m/cspot welding m/cphosphating shop
painting m/c

85 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

Final Arena Simulation Model Shown Below of ABC Auto:

Figure 2: Simulation model for manufacturing process of ABC Auto

Result and Analysis: Here the model is considered from starting and problem is analyzed, means
finding the bottleneck, which is removed by analyzing the system, and repeated this process until we
achieved our required manufacturing rate of auto. In this model we took the rate of incoming of
material/ entity is 3.36 auto per hour, and by proposed model we got rate of auto manufacturing is

86 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

3.365 auto per hour. Fig 3 and Fig 4 shown the utilization of the proposed machine is less which can
be further deduced the proposed model’s waiting time is less.

Utilization of Machine

Figure 3 and Figure 4 show the machine utilization graph for current model and for proposed
simulated model respectively

Current Simulation Model

Figure 3: Utilization Graph of Current Simulation Model

Proposed Simulation Model

Figure 4: Utilization Graph of Proposed Simulation Model

87 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik


International Journal of Engineering Technology, Management and Applied Sciences

www.ijetmas.com January 2015, Volume 3 Issue 1, ISSN 2349-4476

Conclusion: In this work study of makeshift automobile manufacturing in India is done, for study of
Indian scenario of manufacturing, one auto manufacturing firm ABC Auto is considered and their
problem is studied. ABC Auto has very less auto manufacturing rate, so due to which they are unable
to fulfil their target in 8 hours shift so for achieving the target they do the 4-5 hours overtime
everyday which increases their expense. So for solving this problem, time motion study has been
conducted in their plant and real time data is collected, and for the analysis of their system simulated
model of the manufacturing process is made. So with the help of this model, bench mark of the
system is found means it is found that where is the problem in the system. In the ABC Auto, three
bottleneck were found, machine which is 100% utilized, due to this they created the large number of
queue so this queuing processes their overall manufacturing process getting delay. By the use of
simulation model the entire bottleneck has been removed one by one by increase the resources, and
the process is known as shifting of bottleneck. So, finally required manufacturing rate of auto has
been achieved, better utilization of machine, queue length of entity decreased. So this study shows
with the help of simulation, problem in manufacturing process can be found and can be analyze for
any manufacturing system. This simulation method can help lot in makeshift technology based
automobile firm for improving their process and for analyzing the system. This method can be used
in other industry also.

References:
[1] SikkaPawan,’ Technology Innovation by SME’s in India’ Technovation 19 (1999) 317–321, 1998
[2] Azadeh, M.A, ‘optimization of heavy continuous rolling mill system via simulation’ Proceeding of the seventh
international conference on Industrial Engineering and Engineering Management, 2000, Guangzhou, China pp 378-
384

[3] Patel, V,J, Ashby, and J, Ma 2002. Discrete event simulation in automotive final process system, Proceeding of the
2002 Winter Simulation Conferences, ed, E, Yucesan, C, H, Chen, J. L. Snowdon, and J.M. Charnes, pp. 1030-
1034, San Diego, California

[4] Choi, S.D., A.R. Kumar, and A. Houshyar., ‘A simulation study of an automotive foundary plant manufacturing
engine blocks’ Proceeding of the 2002 Winter Simulation Conference, ed. E.Yucesan, C.H. Chen, J.L. Snowdon,
and J.M. Charnes, 2002 san Diego, California, pp. 1035-1040
[5] Kibira, D., McLean C., ‘Virtual reality simulation of a mechanicalassembly production line’ Proceedings of the 2002
Winter SimulationConference, ed. E. Yücesan, C. H. Chen, J. L. Snowdon, and J. M.Charnes, 2002, San Diego,
California pp. 1130-1137
[6] Altiparmak, F., B. Dengiz, and A. A. Bulgak., ‘Optimization of buffersizes in assembly systems using intelligent
techniques.’ Proceedings ofthe 2002 Winter Simulation Conference, ed. E. Yücesan, C.H. Chen, J.L. Snowdon, and
J.M. Charnes, 2002, San Diego, California pp. 1157-1162
[7] Wiendahl, H., Garlichs R., Zeugtraeger K., ‘Modeling and simulation of assembly systems’ CIRP Annals 1991,
40(2), pp. 577-585
[8] Hosseinpour, F and Hajihosseini, H. World Academy of Science, Engineering and Technology 51 2009

88 Upendra Kumar, Rajat Butola, Lokesh Singh, Sparsh Pratik